Sw Fabrication v. Phoenix ( 2019 )


Menu:
  •                       NOTICE: NOT FOR OFFICIAL PUBLICATION.
    UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL
    AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.
    IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    SOUTHWEST FABRICATION LLC, Plaintiff/Appellant,
    v.
    CITY OF PHOENIX, et al, Defendants/Appellees.
    No. 1 CA-CV 18-0588
    FILED 12-17-2019
    Appeal from the Superior Court in Maricopa County
    No. CV 2017-008552
    The Honorable Kerstin G. LeMaire, Judge
    AFFIRMED
    COUNSEL
    Zeitlin v. Zeitlin PC, Phoenix
    By Dale S. Zeitlin
    Counsel for Plaintiff/Appellant
    Sanders & Parks PC, Phoenix
    By Shanks Leonhardt
    Counsel for Defendants/Appellees
    Gaona Law Firm, Phoenix
    By David F. Gaona
    Counsel for Defendant/Appellee, TALIS Construction, Co.
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    MEMORANDUM DECISION
    Judge Michael J. Brown delivered the decision of the Court, in which
    Presiding Judge Jennifer B. Campbell and Judge Lawrence F. Winthrop
    joined.
    B R O W N, Judge:
    ¶1             Southwest Fabrication, LLC, (“SWF”) appeals the superior
    court’s orders (1) granting summary judgment on SWF’s special action
    complaint filed against the City of Phoenix and members of the city council
    (collectively, “the City”) and TALIS Construction Corporation (“TALIS”);
    (2) denying SWF’s motion for relief from judgment; and (3) awarding the
    City and TALIS attorneys’ fees under A.R.S. § 12-341.01. For the following
    reasons, we affirm.
    BACKGROUND
    ¶2            On October 28, 2016, the City issued an invitation for bids
    (“IFB”) for bus stop enhancements. SWF and TALIS were the only bidders.
    Among other things, the IFB required that bids include a pre-approved
    solar-powered operating electrical system to light the bus shelters. City
    staff approved the proposed electrical systems submitted by SWF and
    TALIS.
    ¶3             SWF’s bid price was $10,165,446 and TALIS’s bid price was
    $9,512,975. In January 2017, City staff recommended that the contract be
    awarded to TALIS as the lowest responsive, responsible bidder. SWF filed
    a protest, asserting in part that (1) TALIS was not a responsible bidder
    because it did not meet the IFB’s work-experience requirements, and (2)
    TALIS’s bid was not responsive because it did not comply with the
    electrical-system requirements. City staff denied SWF’s protest and SWF
    appealed. Following an evidentiary hearing, a hearing officer
    recommended denying SWF’s appeal. The city manager adopted the
    hearing officer’s findings and denied the appeal. The city council executed
    the contract with TALIS on May 10, 2017.
    ¶4           SWF filed a special action complaint in the superior court on
    May 25, 2017, reiterating the allegations raised at the bid-protest hearing
    and asking the court to issue a preliminary injunction, rescind the contract
    2
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    award to TALIS, and award the contract to SWF. That same day, TALIS
    met with City staff and agreed to prepare three different prototypes of bus
    shelter configurations and refurbishments. On May 31, TALIS began
    performing the services outlined in the contract. By June 15, TALIS had
    performed work on 66 bus shelters.
    ¶5             In response to SWF’s complaint, the City filed a motion for
    summary judgment, in which TALIS joined. On June 19, SWF filed an
    application for preliminary injunction and request to consolidate with the
    trial on the merits. After oral argument, by minute entry dated September
    13, 2017, the superior court denied SWF’s application for preliminary
    injunction, finding in part that its claims were barred by laches and were
    moot. SWF did not seek to appeal that order.
    ¶6            After allowing the parties to engage in limited discovery and
    conducting oral argument, the court granted summary judgment in favor
    of the City and TALIS, affirming its prior rulings. The court also awarded
    attorneys’ fees to the City and TALIS under § 12-341.01.               SWF
    unsuccessfully sought post-judgment relief, and this timely appeal
    followed.
    DISCUSSION
    ¶7            To prevail on claims raised in a special action complaint, a
    plaintiff must demonstrate: (1) “the defendant has failed to exercise
    discretion which he has a duty to exercise; or to perform a duty required by
    law as to which he has no discretion”; (2) “the defendant has proceeded or
    is threatening to proceed without or in excess of jurisdiction or legal
    authority”; or (3) a “determination was arbitrary and capricious or an abuse
    of discretion.” Ariz. R.P. Spec. Act. 3. As a threshold matter, however, a
    court may deny special action relief if the plaintiff fails to pursue its claims
    in a timely manner. See ASH, Inc. v. Mesa Unified Sch. Dist. No. 4, 
    138 Ariz. 190
    , 192 (App. 1983); Western Sun Contractors Co. v. Super. Ct., 
    159 Ariz. 223
    ,
    227 (App. 1988).
    A.     Laches
    ¶8            SWF argues its claims are not barred by laches because it
    timely sought to preserve the status quo, the contract is severable, and the
    City and TALIS have unclean hands. We review the superior court’s
    finding on laches for abuse of discretion. Korte v. Bayless, 
    199 Ariz. 173
    , 174,
    ¶ 3 (2001). An abuse of discretion occurs if the record lacks substantial
    evidence supporting the court’s conclusion. Rash v. Town of Mammoth, 
    233 Ariz. 577
    , 583, ¶ 17 (App. 2013). We review de novo the court’s legal
    3
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    conclusions. Flying Diamond Airpark, LLC v. Meienberg, 
    215 Ariz. 44
    , 47, ¶ 9
    (App. 2007).
    ¶9            The laches doctrine is an equitable defense “designed to
    discourage dilatory conduct.” Sotomayor v. Burns, 
    199 Ariz. 81
    , 82–83, ¶ 6
    (2000). “Laches will generally bar a claim when the delay is unreasonable
    and results in prejudice to the opposing party.” 
    Id. at 83, ¶ 6
    . To determine
    whether delay was unreasonable, we consider the justification for the delay,
    the extent of the plaintiff’s advance knowledge of the basis for the
    challenge, and whether the plaintiff exercised diligence in preparing and
    advancing his case. See Harris v. Purcell, 
    193 Ariz. 409
    , 412, ¶ 16 (1998). “The
    unreasonable delay must also cause prejudice to either the opposing party
    or the administration of justice, ‘which may be demonstrated by showing
    injury or a change in position as a result of the delay.’” Rash, 233 Ariz. at
    583, ¶ 18.
    ¶10           Two cases are helpful in assessing whether the superior court
    erred in finding that SWF’s claims were barred by laches. In ASH, 
    138 Ariz. at
    191–92, a school bus supplier (“ASH”) whose bid was unsuccessful
    sought to invalidate a contract between a school district and the successful
    bidder and to compel the district to award the contract to ASH. 
    Id.
     The
    superior court denied relief, but before briefing was complete for the
    ensuing appeal, the buses were paid for and delivered. 
    Id.
     We held that
    because the contract had been performed, the relief ASH sought would be
    futile and therefore the case was moot. 
    Id.
     We reasoned that “[b]y failing
    to obtain any interlocutory stay or injunction to enjoin performance of the
    disputed contract, ASH did not protect the status quo,” and that failing to
    stay the contract’s performance “made the issue of its propriety moot.” 
    Id. at 192
    .1
    ¶11           By contrast, in Western Sun, 
    159 Ariz. at 225, 227
    , we found
    that laches did not bar Western Sun Contractors Company’s (“Western
    Sun”) action because it took steps to preserve the status quo throughout the
    litigation. A city awarded a construction contract to Pipe Tech, Inc. (“Pipe
    Tech”) because it determined that Pipe Tech was the lowest bidder. 
    Id.
     at
    1       Cases involving mootness are often instructive in analyzing whether
    laches applies because they share the common thread that a party may lose
    the right to have its claims heard on the merits if it does not timely seek
    relief or take steps to preserve the status quo. See e.g., Korte, 
    199 Ariz. at 174, ¶ 3
    ; Harris, 
    193 Ariz. at 412, ¶ 16
    ; Mathieu v. Mahoney, 
    174 Ariz. 456
    , 458
    (1993); Prutch v. Town of Quartzsite, 
    231 Ariz. 431
    , 435, ¶ 13 (App. 2013), as
    amended (Feb. 26, 2013).
    4
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    225. One day after the contract was executed, Western Sun obtained an
    interlocutory stay to enjoin the city from proceeding with the contract. Id.
    at 226. When the superior court later denied relief, Western Sun filed a
    special action the next day, obtained a stay at the appellate level, and was
    granted an accelerated briefing schedule. Id. We held that Western Sun
    preserved the status quo because it timely obtained an injunction before
    any construction began. Id. at 227. We also concluded that Pipe Tech had
    suffered no significant reasonable change in position or irreparable harm
    because all the steps it took before the injunction was issued were
    preparatory to contract performance. Id. (noting that notifying utilities of
    contemplated construction work, obtaining permits, and ordering supplies
    and equipment were preparatory acts).
    ¶12           Here, SWF failed to timely seek or obtain a preliminary
    injunction or otherwise preserve the status quo throughout litigation. As
    the superior court observed:
    On May 10, 2017, the City of Phoenix and Talis executed the
    contract. On May 26, 2017, Talis began work on the contract
    by meeting with the City of Phoenix and preparing mock ups
    of the shelter projects and refurbishments to other bus
    shelters. On May 31, 2017, Talis began actual performance of
    the contract. By mid-June, Talis had worked on . . . 6[6] bus
    shelters.
    Despite being aware of these developments, SWF did not file its application
    for preliminary injunction until June 19, 2017. When the superior court
    denied the application, SWF did not appeal the ruling, seek a stay, or
    pursue special-action relief in this court. As of the date of the superior
    court’s judgment, TALIS had been performing work under the contract for
    more than ten months.
    ¶13          Read together, ASH and Western Sun make it clear that a party
    must act to preserve the status quo before contract performance begins to
    avoid laches.     SWF unreasonably delayed by waiting until after
    construction was well underway to file its application for preliminary
    injunction. And unlike Western Sun, SWF did not diligently advance its
    case when it failed to appeal the superior court’s order denying its
    application.
    ¶14          SWF urges us to follow Sandy City v. Salt Lake City, 
    827 P.2d 227
     (Utah 1992). That case, however, supports our analysis. Sandy City
    challenged Salt Lake City’s zoning change and grant of a conditional use
    5
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    permit to McDonalds to develop a restaurant on a parcel of land formerly
    zoned as residential. Id. at 229. The Utah Supreme Court ruled that Sandy
    City’s claim was not barred by laches because Sandy City diligently
    pursued its case at each step of the litigation, including seeking an
    injunction before any construction began and appealing when the district
    court denied the injunction. Id. at 230. SWF did none of these things. It
    waited to file its application for preliminary injunction until after
    construction had already begun and then failed to appeal when the superior
    court denied its application. Sandy City is consistent with the rule set forth
    in ASH and Western Sun.
    ¶15           SWF argues that it timely moved to preserve the status quo
    by asking the superior court for a preliminary injunction in its unverified
    complaint and emailing the City and TALIS requesting that they
    voluntarily refrain from entering a formal contract. This fails for at least
    two reasons.
    ¶16            First, a complaint must be verified to allow a plaintiff to
    obtain an injunction on the complaint alone. A.R.S. § 12-1803(B); Barnet v.
    Bd. of Med. Examiners, 
    121 Ariz. 338
    , 340 (1979) (“This statute means that
    relief on the ‘complaint alone’ shall not be granted unless the complaint is
    verified.”). SWF’s complaint was not verified; thus, it could not obtain a
    preliminary injunction on that basis alone.
    ¶17            Second, the email that SWF sent to the City and TALIS was
    insufficient to preserve the status quo. ASH and Western Sun confirm that,
    barring some voluntary agreement, a party seeking to preserve the status
    quo must obtain an injunction or stay to avoid a later finding of laches or
    mootness. See ASH, 
    138 Ariz. at 192
     (“By failing to obtain any interlocutory
    stay or injunction to enjoin performance of the disputed contract, ASH did
    not protect the status quo . . . .”); W. Sun, 
    159 Ariz. at 227
     (“Western Sun
    timely obtained an injunction in this matter before any construction began,
    and thus preserved the status quo.”). SWF knew that the City and TALIS
    executed the contract on May 10, 2017, and were required to begin
    performing work under the contract on May 31, 2017. Emailing the City
    and TALIS to request that they not formalize a contract they had already
    executed and incurred obligations under was insufficient to preserve the
    status quo.
    ¶18           Further, SWF’s unreasonable delay prejudiced TALIS. Unlike
    the preparatory steps Western Sun took, by the time SWF filed its
    application for preliminary injunction TALIS had begun to perform the
    contract and had already worked on 66 bus stops. Ramsey v. Arizona
    6
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    Registrar of Contractors, 
    241 Ariz. 102
    , 109, ¶ 22 (App. 2016) (“We will not set
    aside the trial court’s factual findings unless they are clearly erroneous.”).
    SWF prejudiced TALIS by waiting until TALIS changed its position before
    moving to preserve the status quo.
    ¶19            SWF asserts that TALIS is not prejudiced and that laches is
    unavailable because the contract between the City and TALIS is severable.
    “A contract may be considered severable when the consideration given is
    not single, but apportioned. When separate consideration is given for a
    portion of a contract, that part of the contract may be considered severable.”
    Verma v. Stuhr, 
    223 Ariz. 144
    , 158 (App. 2009) (internal citations omitted).
    However, this does not end our inquiry. As our supreme court observed in
    Waddell v. White:
    Primarily, the question of whether a contract is entire or
    severable is one of intention, which intention is to be
    determined by the language which the parties have used and
    the subject matter of the agreement. A contract may both in
    its nature and by its terms be severable, and yet rendered
    entire by the intention of the parties. We think that perhaps
    the best test is whether all of the things, as a whole, are of the
    essence of the contract. That is, if it appeared that the purpose
    was to take the whole or none, then the contract would be
    entire; otherwise, it would be severable. The divisibility of
    the subject matter, or the apportionment of the consideration,
    while they are both items to consider in determining whether
    a contract is entire or severable, are not conclusive.
    
    51 Ariz. 526
    , 540–41 (1938) (internal citations omitted).
    ¶20           Here, the parties intended the contract to be entire rather than
    severable. When the City solicited bids, the invitation was to bid on all
    work outlined in the contract, not a portion of it. And when the City
    awarded the contract to TALIS, it awarded the contract based on the price
    of TALIS’s bid for completion of all work outlined in the contract. A
    contract for the building and refurbishment of many individual bus stops
    could be viewed as severable by its nature and terms; however, “[t]he
    divisibility of the subject matter, or the apportionment of the
    consideration . . . , are not conclusive.” 
    Id. at 541
    . The price of the bid to
    complete work on the bus stops, as a whole, is the essence of the contract
    between the City and TALIS, and the basis for the award. When TALIS bid
    on the contract it had two choices: take the whole or take none. The contract
    is not severable.
    7
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    ¶21            Finally, SWF counters that laches does not apply due to the
    doctrine of unclean hands. “It is a cardinal rule of equity that he who comes
    into a court of equity seeking equitable relief must come with clean hands.”
    MacRae v. MacRae, 
    57 Ariz. 157
    , 161 (1941). “[I]t is the moral intent of the
    party seeking relief, and not the actual injury done, that is controlling.”
    Weiner v. Romley, 
    94 Ariz. 40
    , 42–43 (1963). Misconduct that would deprive
    a party of equitable relief must be willful. 
    Id. at 43
    .
    ¶22           SWF argues the City secretly never intended to require TALIS
    to comply with the requirements in its IFB, and the City and TALIS
    conspired to fraudulently conceal from SWF that the bus stops TALIS
    produced, including the electric systems, fall below the IFB requirements.
    Therefore, according to SWF, the City and TALIS cannot rely on the
    equitable defense of laches. SWF’s assertion that the bus stops do not meet
    the IFB requirements is based on the declaration of one of its employees,
    who inspected several of the bus stops TALIS constructed and reported that
    they fall below the standards set out in the IFB.
    ¶23           The superior court found that (1) the City complied with the
    applicable code and terms when it awarded the contract to TALIS; and (2)
    SWF did not prove the City’s engineer acted improperly when he decided
    that TALIS’s electric system met the IFB requirements. However, even if
    SWF’s allegation that the bus stops TALIS constructed fall below the IFB
    requirements is true, it does not establish that the City secretly did not
    intend to hold TALIS to the terms of the contract, nor does it demonstrate a
    conspiracy between the City and TALIS to conceal that alleged intent from
    SWF. Because SWF has not shown willful misconduct on the part of the
    City or TALIS, its unclean-hands defense fails. In sum, the superior court
    did not abuse its discretion in finding that SWF’s claims were barred by
    laches.2
    B.     Attorneys’ Fees Award
    ¶24            SWF contends that the superior court erred in awarding
    attorneys’ fees to the City and TALIS under A.R.S. § 12-341.01 because this
    action is a challenge to the alleged illegal award of a contract rather than an
    action arising out of a contract. A.R.S. § 12-341.01. SWF does not challenge
    the amount of the fees awarded.
    2     Because we do not disturb the superior court’s laches ruling, we do
    not address the merits of TALIS’s bid challenge or whether the court erred
    in denying SWF’s motion for post-judgment relief.
    8
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    ¶25           As an initial matter, we note SWF requested an award of
    attorneys’ fees under § 12-341.01 in its cross-motion for summary judgment.
    After the court ruled against SWF and stated it was awarding fees to the
    City and TALIS upon submission of affidavits, SWF argued for the first time
    that fees were not recoverable under § 12-341.01. SWF cites no authority
    suggesting a party may properly reverse its position as to fee eligibility after
    the court issues an adverse ruling. Regardless, we are not persuaded by
    SWF’s argument that fees could not be awarded under § 12-341.01.
    ¶26           This court’s decision in ASH, 
    138 Ariz. at 192
    , resolves the
    issue. ASH argued that its lawsuit seeking to invalidate the school district’s
    contract award to a competing bidder did not arise out of a contract but was
    instead a petition to compel Mesa Schools to perform a legal duty. 
    Id.
     We
    disagreed, explaining that our “interpretation [was] consistent with the
    broad statutory language providing for the award of attorneys’ fees ‘in any
    contested action.’” 
    Id.
     We further reasoned that “[b]y focusing on the
    procedural context of th[e] special action . . . ASH ignores its substantive
    nature.” 
    Id.
    ¶27           SWF’s complaint sought to invalidate the City’s contract
    award to TALIS and have the contract awarded to SWF. As in ASH, it is
    the contract that prompted the suit. 
    Id.
     Accordingly, the superior court did
    not err in implicitly finding that the City and TALIS were eligible for an
    award of attorneys’ fees under § 12-341.01.
    ¶28           SWF argues nonetheless that awarding attorneys’ fees in this
    case contravenes public policy, relying on Wistuber v. Paradise Valley Unified
    School District, 
    141 Ariz. 346
    , 347 (1984). However, our supreme court
    expressly distinguished Wistuber from ASH in the same paragraph SWF
    quotes from:
    Moreover, this action differs from the type of contract action
    at issue in Ash. Here, petitioners are challenging the
    constitutionality of the action of a public body. An award of
    attorney’s fees would be contrary to public policy in this case
    because it would have a chilling effect on other parties who
    may wish to question the legitimacy of the actions of public
    officials. Where aggrieved citizens, in good-faith, seek a
    determination of the legitimacy of governmental actions,
    attorney’s fees should not usually be awarded. Courts exist
    to hear such cases; we should encourage resolution of
    constitutional arguments in court rather than on the streets.
    9
    SW FABRICATION v. PHOENIX, et al.
    Decision of the Court
    
    Id. at 350
    . The supreme court clarified that the public policy encouraging
    the determination of the legitimacy of governmental actions in courts
    applies to constitutional questions as specifically distinguished from the
    type of actions at issue in ASH—the same actions at issue here.
    CONCLUSION
    ¶29            We affirm the superior court’s orders (1) granting summary
    judgment in favor of the City and TALIS; (2) denying SWF’s motion for
    relief from judgment; and (3) awarding the City and TALIS their reasonable
    attorneys’ fees and costs. Because SWF has not prevailed on appeal, we
    deny its request for attorneys’ fees and costs. In our discretion, we award
    reasonable attorneys’ fees to the City and TALIS, as well as taxable costs,
    upon compliance with ARCAP 21.
    AMY M. WOOD • Clerk of the Court
    FILED: AA
    10