Southwest v. Burns ( 2014 )


Menu:
  •                                NOTICE: NOT FOR PUBLICATION.
    UNDER ARIZ. R. SUP. CT. 111(c), THIS DECISION DOES NOT CREATE LEGAL PRECEDENT
    AND MAY NOT BE CITED EXCEPT AS AUTHORIZED.
    IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    SOUTHWEST FARM SERVICES, LTD. PARTNERSHIP, an Arizona
    limited partnership Plaintiff/Appellee,
    v.
    ROBERT BURNS and JEANNE BURNS, husband and wife dba ROBERT
    BURNS ARCHITECTS, INC., Defendants/Appellants.
    No. 1 CA-CV 12-0808
    FILED 3-27-2014
    Appeal from the Superior Court in Maricopa County
    No. CV2010-092562
    The Honorable Emmet J. Ronan, Judge
    AFFIRMED
    COUNSEL
    Grant & Vaughn, P.C., Phoenix
    By Kenneth B. Vaughn, Sharon R. Sprague
    Counsel for Plaintiff/Appellee
    Jeffrey M. Zurbriggen, P.C., Phoenix
    By Jeffrey M. Zurbriggen
    Counsel for Defendants/Appellants
    SOUTHWEST v. BURNS
    Decision of the Court
    MEMORANDUM DECISION
    Judge Lawrence F. Winthrop delivered the decision of the Court, in which
    Presiding Judge Patricia A. Orozco and Judge Kenton D. Jones joined.
    W I N T H R O P, Judge:
    ¶1             Robert and Jeanne Burns, doing business as Robert Burns
    Architects, Incorporated, appeal from a judgment and award of attorneys’
    fees in favor of Southwest Farm Services, Limited Partnership on a breach
    of contract claim. For the reasons stated below, we affirm.
    FACTUAL AND PROCEDURAL BACKGROUND
    ¶2           Southwest       Farm      Services,   Limited     Partnership
    (“Southwest”) is a hay brokering business. In August 2006, Southwest
    contracted with Robert Burns Architects, Incorporated, 1 for the
    development of a preliminary project site plan to develop property owned
    by Southwest and intended for business operations (the “Preliminary Site
    Plan Contract”). The price of services in the Preliminary Site Plan
    Contract was $5,600. In October 2006, Southwest contracted with Burns to
    provide more comprehensive architectural and engineering services
    related to the construction of buildings (the “Construction Design
    Contract”). In this contract, Southwest hired Burns to design and provide
    construction documents and engineering services for several buildings, a
    gate entry, and walls on the property. The price of services in the
    Construction Design Contract was $182,950, payable in six payments
    pursuant to a schedule set forth in the contract.
    ¶3          Southwest paid Burns $165,970.51 through June 2009. This
    included approximately $5,600 Southwest paid Burns on the Preliminary
    Site Plan Contract prior to signing the Construction Design Contract.
    Although Burns furnished preliminary site plans and later revised those
    1      Robert Burns entered the contract doing business as Robert Burns
    Architects, Inc. Southwest later learned the corporation had been
    dissolved in 2002 and filed an amended complaint alleging that Robert
    Burns and the marital community were personally liable for the breach of
    contract. We refer to the defendants collectively as “Burns.”
    2
    SOUTHWEST v. BURNS
    Decision of the Court
    site plans, Burns never delivered to Southwest final, signed, and sealed
    construction documents under the Construction Design Contract. Robert
    Burns testified that he would have delivered signed and sealed documents
    upon receipt of the final payment, which never occurred.
    ¶4           In October 2009, Southwest notified Burns that it considered
    Burns to be in material breach and demanded delivery of final
    construction documents in exchange for payment of the $10,959.49 balance
    due on the contract or a refund of the money Southwest paid Burns.
    Burns did not respond. Southwest made a second identical demand in
    March 2010, to which Burns also did not respond.
    ¶5            Southwest then filed a complaint for breach of contract.
    Burns answered and counterclaimed for breach of contract, bad faith, and
    unjust enrichment. At a one-day bench trial, the trial court received
    evidence of Burns’ invoices to Southwest and payment from Southwest to
    Burns. The court also heard testimony from Michael Perez, Southwest’s
    limited partner and manager, and Robert Burns. The trial court ruled that
    final payment to Burns on the Construction Design Contract was not due
    until there was “100% completion of the construction documents and
    submitt[al] to Maricopa County and approval of the building permit by
    Maricopa County.” The trial court found that no final, signed, and sealed
    plans had been submitted and there was no approved building permit.
    The trial court concluded that Southwest did not breach the Construction
    Design Contract because the final payment was not yet due. The court
    rejected Burns’ claim that its nonperformance was justified as well as
    Burns’ claim for unjust enrichment on the Construction Design Contract,
    finding that Southwest could no longer use the work performed by Burns.
    However, the trial court implicitly found that Burns had completed the
    Preliminary Site Plan Contract by reducing Southwest’s claimed damages
    by the value paid for services under that contract.
    ¶6             The court awarded Southwest a judgment of $160,330.85,
    $65,467.70 in prejudgment interest, and $48,431.90 in attorneys’ fees.
    Burns filed a timely notice of appeal. We have appellate jurisdiction
    pursuant to Arizona Revised Statutes (“A.R.S.”) section 12-2101(A)(1)
    (West 2014). 2
    2      We cite the current Westlaw version of the applicable statutes and
    rules unless revisions material to this decision have since occurred.
    3
    SOUTHWEST v. BURNS
    Decision of the Court
    DISCUSSION
    I.     Breach of Contract
    ¶7            Burns argues the trial court erred when it concluded that
    Burns breached the Construction Design Contract by failing to submit
    final plans to Maricopa County and by failing to obtain an approved
    building permit. 3 Interpretation of a contract is a question of law to be
    decided de novo. Polk v. Koerner, 
    111 Ariz. 493
    , 495, 
    533 P.2d 660
    , 662
    (1975). On appeal, we view the evidence in the light most favorable to
    supporting the judgment and will accept the trial court’s findings of fact
    absent clear error. 
    Id. at 494,
    533 P.2d at 661.
    ¶8             Arizona courts strive to enforce contracts according to the
    parties’ intent. Taylor v. State Farm Mut. Auto. Ins. Co., 
    175 Ariz. 148
    , 152,
    
    854 P.2d 1134
    , 1138 (1993). “In ascertaining the parties’ intent, the court
    will look to the plain meaning of the words as viewed in the context of the
    contract as a whole.” United Cal. Bank v. Prudential Ins. Co. of America, 
    140 Ariz. 238
    , 259, 
    681 P.2d 390
    , 411 (App. 1983).
    ¶9            Burns contends that the scope of work detailed in the
    Construction Design Contract did not require it to submit final plans to
    Maricopa County or obtain an approved building permit. The contract’s
    compensation and payment schedule, however, states that Southwest
    shall make its fifth payment “[u]pon 100% completion of the construction
    documents and Submittal to Maricopa County” and the final payment
    “[u]pon approval of the building permit by Maricopa County.” Burns
    contends that these provisions only triggered payments and did not
    require Burns to submit final plans or obtain a building permit. Our
    adoption of Burns’ interpretation of the scope of work language contained
    within the contract would render the language in the compensation and
    payment schedule meaningless. The payments are dependent upon Burns
    completing the items listed in the schedule. If Burns was not obligated to
    provide these services, this language would be superfluous.
    ¶10           Burns also argues it was not obligated to submit final plans
    or obtain a building permit because the parties had orally modified the
    Construction Design Contract and a valid novation occurred. The contract
    required that all requests for changes to the contract “shall be in writing,”
    3    It is undisputed that Burns never delivered final construction
    documents or a building permit approved by Maricopa County.
    4
    SOUTHWEST v. BURNS
    Decision of the Court
    and Burns admitted there was no written modification of the contract.
    Likewise, there was no evidence of any other agreement between the
    parties supporting any claim for novation. Thus, these arguments fail.
    ¶11            Burns also contends the parties extended his time to perform
    under the Construction Design Contract when Southwest asked Burns to
    obtain an agriculture exemption for the property. However, Southwest’s
    Perez testified the property had the agriculture exemption when he
    purchased it in 2004. Although Burns testified to the contrary, the trial
    court explicitly rejected Burns’ testimony as not credible, accepting
    instead Perez’s testimony that the property always had an agriculture
    exemption. We defer to the judgment of the trial court on this matter. See
    Estate of Reinen v. N. Ariz. Orthopedics, Ltd., 
    198 Ariz. 283
    , 287, ¶ 12, 
    9 P.3d 314
    , 318 (2000) (citations omitted) (stating the “credibility of a witness’
    testimony and the weight it should be given are issues particularly within
    the province of the” finder of fact). 4
    ¶12         For these reasons, we affirm the trial court’s conclusion that
    Burns breached the contract.
    II.    Burns’ Waiver Defense
    ¶13           On appeal, Burns argues Southwest’s conduct waived any
    obligation Burns had to provide final, signed, and sealed documents,
    because Southwest paid Burns in full through June 2009, purposefully
    delayed the project due to the bad economy, and actually used the
    construction design plans for the current buildings ultimately constructed
    on the subject property after Burns was discharged from the project.
    Under Arizona Rule of Civil Procedure 8(c), “In pleading to a preceding
    pleading, a party shall set forth affirmatively . . . waiver[] and any other
    matter constituting an avoidance or affirmative defense.” Having failed to
    plead this defense in its answer or specifically allege a waiver within its
    4      It is unclear from the briefing whether Burns is really contending
    that its efforts helped Southwest preserve the existing agriculture
    exemption. However, this alternate reading of Burns’ confusing argument
    is not material to our evaluation. The uncontested facts are: (1)
    Southwest made repeated demands on Burns to provide final, sealed
    plans under the Construction Design Contract, (2) these demands were
    ignored, and (3) no such plans were ever provided. As a result, the
    evidence at trial more than supports the verdict and judgment as to
    breach.
    5
    SOUTHWEST v. BURNS
    Decision of the Court
    counterclaim, Burns is precluded from raising the defense of waiver on
    appeal. See Parks v. Am. Cas. Co. of Reading, Pa., 
    117 Ariz. 339
    , 342, 
    572 P.2d 801
    , 804 (1977), disapproved on other grounds in Darner Motor Sales, Inc. v.
    Universal Underwriters Ins. Co., 
    140 Ariz. 383
    , 387-88, 
    682 P.2d 388
    , 392-93
    (1984). We therefore decline to reach the merits of Burns’ waiver defense.
    III.   Burns’ Counterclaim for Unjust Enrichment
    ¶14           Burns counterclaimed asserting unjust enrichment, arguing
    that it was entitled to compensation for the services it provided prior to
    any breach.
    Unjust enrichment occurs when one party has and retains
    money or benefits that in justice and equity belong to
    another. . . . To recover on a claim for unjust enrichment, a
    claimant must show (1) an enrichment, (2) an
    impoverishment, (3) a connection between the two, (4) the
    absence of justification for the enrichment and
    impoverishment and (5) the absence of any remedy at law.
    Loiselle v. Cosas Mgmt. Grp., LLC, 
    224 Ariz. 207
    , 210, ¶ 9, 
    228 P.3d 943
    , 946
    (App. 2010) (quotations and citations omitted).
    ¶15            Citing Trustmark Ins. Co. v. Bank One, Ariz. NA, 
    202 Ariz. 535
    ,
    542, ¶ 34, 
    48 P.3d 485
    , 492 (App. 2002), Southwest contends that Burns
    cannot pursue a counterclaim for unjust enrichment because the doctrine
    of unjust enrichment is not available where there is a specific contract
    governing the parties. However, we find the immediate case consonant
    with Adelman v. Christy, 
    90 F. Supp. 2d 1034
    (D. Ariz. 2000) where the
    litigant asserted unjust enrichment as an alternative theory of recovery in
    the event it was deemed the breaching party. See 
    Adelman, 90 F. Supp. 2d at 1045
    . Thus, we will consider the trial court’s denial of Burns’ unjust
    enrichment counterclaim.
    ¶16           The trial court found Southwest did not receive any benefit
    from the work Burns performed on the Construction Design Contract
    because that work was of no use to Southwest without the final, signed,
    and sealed documents. On appeal, we view the evidence in the light most
    favorable to supporting the judgment and will accept the trial court’s
    findings of fact absent clear error. Polk, 111 Ariz. at 
    494, 533 P.2d at 661
    .
    ¶17          The record supports the trial court’s finding that Southwest
    did not receive any benefit from the work Burns performed on the
    Construction Design Contract. Contrary to Burns’ assertion, the record
    6
    SOUTHWEST v. BURNS
    Decision of the Court
    does not demonstrate Burns obtained the property’s agriculture
    exemption. Burns did not provide Southwest with a set of final plans that
    could be used to obtain bids from contractors and financing from lenders;
    even at trial, Burns failed to offer final plans into evidence. Therefore, the
    work Burns may have done on the Construction Design Contract did not
    benefit Southwest, and Burns’ reliance on Cracchiolo v. Carlucci, 
    62 Ariz. 284
    , 
    157 P.2d 352
    (1945), is misplaced.
    ¶18           Burns also argues Southwest received a benefit from
    “grading and drainage” plans from Burns. Although the Construction
    Design Contract included a $55,600 professional fee for “civil engineering
    for grading and drainage analysis,” the record does not demonstrate
    whether Burns provided that service. Perez testified that Southwest had
    to hire its own contractor to draw up a grading and drainage plan because
    Burns failed to provide one. Perez also testified that Southwest told Burns
    the amount “of dirt that needed to be moved and where, and all he did
    was put it on his paper and send it to the county and got it approved.”
    Because the trial court was in the best position to determine the weight of
    the evidence and the credibility of the witnesses, see Estate of 
    Reinen, 198 Ariz. at 287
    , ¶ 
    12, 9 P.3d at 318
    , we conclude the trial court did not err in
    denying Burns’ counterclaim for unjust enrichment related to grading and
    drainage plans under the Construction Design Contract.
    ¶19          Burns also argues that Southwest relied on Burns’ site plans
    pursuant to the Preliminary Site Plans Contract for the layout of its
    current operations. The record demonstrates Burns provided Southwest
    with preliminary site plans. Burns then revised the site plans twice at
    Southwest’s request because the site plans as originally drafted were
    inconsistent with and would not preserve the preexisting agriculture
    exemption. In mid-October 2007, the revised site plans were accepted by
    the County. As such, Burns did provide Southwest with approved site
    plans for which Southwest paid $5,639.66 under the Preliminary Site Plan
    Contract. Because Burns had provided a discernible benefit to Southwest
    and was entitled to retain the $5,639.66 paid for these services, the trial
    court apparently did not include that amount in the $160,330.85 judgment
    against Burns.
    ¶20           Burns appears to argue that a May 2008 invoice for
    $27,791.68 is evidence of the value of Burns’ work on the revised site
    plans, because the invoice refers to a bill from November 2007
    immediately after Burns completed that work. Although Burns had the
    burden of proof on a claim of unjust enrichment, Burns did not offer the
    November 2007 bill in evidence. See e.g., 
    Loiselle, 224 Ariz. at 210
    , ¶ 9, 228
    7
    SOUTHWEST v. BURNS
    Decision of the Court
    P.3d at 946 (App. 2010) (emphasis added) (“To recover on a claim for
    unjust enrichment, a claimant must show . . . (1) an enrichment [and] (2) an
    impoverishment . . . .” (quotations and citations omitted)).
    ¶21           The missing November 2007 bill presents two problems for
    Burns’ claim of unjust enrichment. First, because only two items on the
    May 2008 invoice reference the November 2007 bill, it is unclear from the
    record whether the entire May 2008 invoice includes the value of the site
    plan revision related to the Preliminary Site Plan Contract or whether the
    invoice includes civil engineering services related to the Construction
    Design Contract. Because the trial court specifically found that Southwest
    received no value from the Construction Design Contract, Burns does not
    have a viable claim of unjust enrichment on any portion of the invoice
    related only to that contract.
    ¶22           Second, although there are two items on the May 2008
    invoice that reference the missing November 2007 bill and total $2,940.49,
    without the November 2007 bill in evidence Burns cannot show these
    items are for revision of the site plans. On this record, we therefore
    conclude that the trial court did not err by finding that Burns was
    adequately paid for services rendered pursuant to the Preliminary Site
    Plan Contract.
    IV.    Community Liability
    ¶23           While Jeanne Burns appeared as a party, Burns contends the
    judgment against the marital community’s property is erroneous because
    there was no evidence regarding the relationship between the corporation
    and the marital community. Burns admits that Robert and Jeanne are
    married and that Robert Burns Architects, Inc. was dissolved in 2002.
    Neither spouse objected to the entry of judgment against both defendants.
    Therefore, we will not consider this argument for the first time on appeal.
    See Englert v. Carondelet Health Network, 
    199 Ariz. 21
    , 26-27, ¶ 13, 
    13 P.3d 763
    , 768-69 (App. 2000) (issues not raised below are not generally
    considered on appeal).
    V.     Southwest’s Failure to Mitigate Damages
    ¶24           Burns argues that the trial court erred by failing to address
    the issue of damage mitigation. “[W]hether the injured party violated his
    duty to mitigate damages is a question of fact for the trier of fact, when
    there is conflicting evidence on the question.” Fairway Builders, Inc. v.
    Malouf Towers Rental Co., Inc., 
    124 Ariz. 242
    , 256, 
    603 P.2d 513
    , 527 (App.
    1979) (citations omitted). Burns argues Southwest had the burden to
    8
    SOUTHWEST v. BURNS
    Decision of the Court
    mitigate damages. However, as the party in breach, Burns has the burden
    of showing that “mitigation was reasonably possible, but was not
    reasonably attempted.” N. Ariz. Gas Serv., Inc. v. Petrolane Transp., Inc., 
    145 Ariz. 467
    , 477, 
    702 P.2d 696
    , 706 (App. 1984) (citation omitted).
    ¶25           As a threshold matter, Southwest argues Burns waived this
    issue by not including mitigation in the joint pretrial statement or closing
    arguments. However, Burns raised mitigation as an affirmative defense in
    its answer. Burns also questioned Perez about Southwest’s ability to
    obtain financing, and Burns testified that the location of the improvements
    on Southwest’s property followed his site plans. Thus, Burns sufficiently
    raised the mitigation issue at trial, and we do not find waiver.
    ¶26            Burns suggests that Southwest failed to mitigate damages by
    not applying for financing after 2006 and by using the site plans. No
    request for written findings of fact or conclusions of law was made upon
    the trial court pursuant to Arizona Rule of Civil Procedure 52(a).
    Therefore, on appeal, this court “must presume that the trial court found
    every fact necessary to support the judgment.” Berryhill v. Moore, 
    180 Ariz. 77
    , 82, 
    881 P.2d 1182
    , 1187 (App. 1994). Perez testified he could not
    apply for a loan without final, signed, and sealed plans that would allow
    him to obtain a bid from a contractor. This testimony supports the
    implicit conclusion that Southwest did not fail to mitigate damages by not
    applying for a loan. Also, as discussed above, Southwest paid Burns for
    its work on the site plans, thereby mitigating Southwest’s damages and
    any compensable injury attributable to Burns related to its work on the
    site plans.
    VI.    Attorneys’ Fee Awards
    ¶27          Burns argues the trial court erred in awarding attorneys’ fees
    to Southwest as there was no basis in fact or law for the award. Burns’
    argument is premised upon its position that Southwest breached the
    contract. Having affirmed that Burns, not Southwest, was the breaching
    party, we also affirm the award of attorneys’ fees to Southwest pursuant
    to A.R.S. § 12-341.01(A), which authorizes an award of fees to the
    successful party in a contract action.
    ¶28          We also reject Burns’ argument that the award was
    erroneous because the trial court failed to make sufficient findings of fact.
    Southwest requested fees pursuant to A.R.S. § 12-341.01, which does not
    require written findings of fact supporting the award, only that the
    underlying matter arise out of a contract. The parties did not request
    9
    SOUTHWEST v. BURNS
    Decision of the Court
    written findings of fact or conclusions of law pursuant to Arizona Rule of
    Civil Procedure 52. Therefore, the trial court did not err in failing to make
    detailed findings of fact in support of its award of attorneys’ fees to
    Southwest.
    ¶29          Both parties request an award of attorneys’ fees on appeal.
    Southwest was the successful party on appeal in this action arising out of
    a contract. Therefore, we award Southwest its reasonable attorneys’ fees
    and costs upon compliance with ARCAP 21(a). See A.R.S §§ 12-341.01(A)
    and 12-342(A) (authorizing an award of costs on appeal to prevailing
    party).
    CONCLUSION
    ¶30            We affirm the judgment in favor of Southwest on its breach
    of contract claim and the rejection of Burns’ counterclaims. We also affirm
    the award of attorneys’ fees to Southwest and award Southwest its
    reasonable attorneys’ fees and costs on appeal upon compliance with
    ARCAP 21(a).
    :MJT
    10