Dabrowski v. Bartlett , 246 Ariz. 504 ( 2019 )


Menu:
  •                                   IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    BOGDAN DABROWSKI, et al., Plaintiffs/Counter-
    Defendants/Appellants/Cross-Appellees,
    v.
    DAVID C. BARTLETT, Defendant/Counter-Claimant/Appellee/Cross-
    Appellant.
    No. 1 CA-CV 17-0380
    FILED 5-7-2019
    Appeal from the Superior Court in Maricopa County
    No. CV2013-008944
    The Honorable Lori Horn Bustamante, Judge
    AFFIRMED IN PART; REVERSED IN PART; JURISDICTION
    ACCEPTED/RELIEF GRANTED IN PART AND REMANDED
    WITH INSTRUCTIONS
    COUNSEL
    MacQueen & Gottlieb PLC, Phoenix
    By Benjamin L. Gottlieb (argued), Patrick R. MacQueen
    Counsel for Plaintiffs/Counter-Defendants/Appellants/Cross-Appellees
    Radix Law, PLC, Scottsdale
    By Donald R. Alvarez
    Counsel for Defendant/Counter-Claimant/Appellee/Cross-Appellant
    DABROWSKI v. BARTLETT
    Opinion of the Court
    OPINION
    Judge Paul J. McMurdie delivered the opinion of the Court, in which
    Presiding Judge Jennifer B. Campbell and Judge Kent E. Cattani joined.
    M c M U R D I E, Judge:
    ¶1             Bogdan and Jolanta Dabrowski appeal from a judgment
    granting David C. Bartlett a private way of necessity (“private
    condemnation”) over the Dabrowskis’ property. Bartlett cross-appeals,
    contending he was entitled to either express easement rights or an easement
    by implied way of necessity. For the reasons set forth below, we hold that:
    (1) an unactivated easement is subject to a merger; (2) a common law
    easement by implied way of necessity does not exist if the severance of the
    parcel did not cause the lot to lack a reasonable outlet; (3) unity of
    ownership for a merger may occur even if the parties are technically
    different; (4) in a private condemnation action, a finding that a more
    reasonable route exists through the subject property constitutes “bad faith,
    oppression, or abuse of power” under Solana Land Co. v. Murphey, 
    69 Ariz. 117
    , 125 (1949), precluding the condemnor from condemning its selected
    route; and (5) a private condemnation judgment must be satisfied before a
    final order of condemnation can issue and an easement recorded.
    Accordingly, we affirm the judgment on the easement claims and remand
    for the court to determine the route, scope, and cost of the private
    condemnation.
    FACTS AND PROCEDURAL BACKGROUND
    ¶2              The parties dispute whether Bartlett should have access to his
    five-acre lot in Cave Creek over the Dabrowskis’ adjacent lot. Both lots were
    part of a larger parcel that was split into three lots in 1999, then identified
    as Parcels A, B, and C. In 2002, Parcel A was divided into three separate lots
    of approximately five acres each, which include the lots now owned by the
    Dabrowskis (“Lot 1”) and Bartlett (“Lot 2”) (collectively the “Lots”).
    2
    DABROWSKI v. BARTLETT
    Opinion of the Court
    ¶3           Until 2007, Rockaway Hills Drive (the “access road”) was the
    only road on the land.
    Figure 1
    On March 2, 2000, Jack Lewis, the owner of Parcels A and B, declared an
    easement that reached Lot 2 through Lot 1 (the “2000 Express Easement”)
    and then sold the Lots in Parcel A.
    Figure 2
    ¶4              In April 2001, Lewis conveyed Parcel B to Andrew C. Jacob in
    his capacity as trustee of the ACJ [Andrew C. Jacob] Declaration of Trust
    (“Jacob Trust”). On September 18, 2001, Lewis reacquired the Lots via a
    trustee’s sale.
    ¶5             On September 18, 2002, the Town of Cave Creek approved a
    lot split (“2002 Lot Split”), which established the Lots as they currently
    appear. The survey that accompanied the 2002 Lot Split was prepared for
    Jacob and reflected an ingress, egress, and utility easement over Parcel B for
    the benefit of Lot 1, similar to the 2000 Express Easement, but did not extend
    to Lot 2. The month after the 2002 Lot Split was approved, Lewis conveyed
    Lots 1 and 2 to Jacob and his wife.
    ¶6            Cave Creek approved a second lot split of Parcel A on April
    11, 2003, based on a separate survey (“2003 Lot Split”) also prepared for
    3
    DABROWSKI v. BARTLETT
    Opinion of the Court
    Jacob. The 2003 Lot Split was recorded on April 12, 2003. The survey,
    depicted below, showed an easement over Parcel B reaching the midpoint
    of the eastern border of the Lots and did not encumber Lot 1 for the benefit
    of Lot 2.
    Figure 3
    ¶7            The next month, Jacob and his wife sold the Lots to Bartlett
    (“Jacob-Bartlett conveyance”). In 2005, Bartlett conveyed Lot 1 to Michael
    Hiltner and Julie Mahon but retained Lot 2 in his capacity as a trustee of the
    JoshuaBleu Trust (“Bartlett-Hiltner conveyance”). Bartlett did not record an
    express easement in connection with the conveyance. The Jacob Trust sold
    Parcel B to Bryan Anderson in June 2005.
    ¶8              In 2007, Hiltner completed construction of a house and
    driveway located on Lot 1. Anderson began construction of his house on
    Parcel B in 2006, which was completed in 2014. The Dabrowskis acquired
    the house and property comprising Lot 1 via a trustee’s sale in January 2012.
    A dispute arose shortly thereafter between the Dabrowskis and Bartlett
    regarding Bartlett’s access to Lot 2, leading to the Dabrowskis filing suit to
    quiet title in 2013. Bartlett counterclaimed, alleging that he was entitled to
    an implied way of necessity, an implied easement of necessity, or in the
    alternative, a private condemnation across Lot 1. Bartlett later added a
    counterclaim alleging that he had express access rights via the 2000 Express
    Easement. At the time of trial, the land appeared as follows:
    4
    DABROWSKI v. BARTLETT
    Opinion of the Court
    Figure 4
    ¶9            The superior court granted summary judgment to the
    Dabrowskis on Bartlett’s express easement claim, finding that the 2000
    Express Easement had terminated by a merger. The parties proceeded to a
    bench trial on the remaining claims. Following the trial, the court ruled that:
    [T]he 2003 Lot Split did not create a valid easement, there is
    no express easement, and there is no implied easement at this
    time over the Dabrowski property in favor of the Bartlett lot.
    The court further finds there is no other adequate alternative
    access to Bartlett’s property. Accordingly, [Arizona Revised
    Statutes (“A.R.S.”) section] 12-1202 allows a [private
    condemnation] under the circumstances presented in this
    case.
    The court allowed Bartlett to “select the route location and nature of the
    [private condemnation] ensuring the greatest amount of deference to the
    privacy and concerns of the Dabrowskis,” ordered Bartlett to “compensate
    the Dabrowskis for the easement over their property,” and requested
    simultaneous briefing regarding the values of the available routes, stating
    that it could not “provide a value based upon the testimony provided at the
    hearing.”
    ¶10            In the post-trial briefing, the Dabrowskis submitted affidavits
    from a real estate appraiser, their trial expert, and Bogdan Dabrowski. They
    sought compensation ranging from $96,000 to $433,250 depending on
    Bartlett’s choice of route. Bartlett objected, contending the affidavits had not
    been disclosed or offered at trial. The court overruled his objection and
    determined compensation for three potential routes as follows:
    “Graham #1” Easement = $37,200
    “Graham #2” Easement = $36,000
    5
    DABROWSKI v. BARTLETT
    Opinion of the Court
    “Slyder” Easement = $96,250
    The considerably higher value assigned to the Slyder Easement reflected
    the increased burden the easement posed on the Dabrowskis’ property. On
    Bartlett’s motion for reconsideration, the court allowed him to present
    rebuttal evidence concerning value but affirmed its compensation
    determinations.
    ¶11           Bartlett submitted a proposed form of judgment. The
    Dabrowskis objected to the proposed judgment and asked the court to
    order Bartlett to compensate them when the easement was recorded, and to
    impose several new requirements on Bartlett, including: (1) indemnifying
    them for any liability resulting from construction; (2) repairing and
    maintaining their driveway following construction; (3) preserving
    unspoiled nature beyond 20 feet of the easement width; and (4) requiring
    Bartlett and his successors and assignees to equally share in future costs of
    the maintenance and repair of the shared roadway. The court rejected the
    Dabrowskis’ requests and entered a partial final judgment ordering Bartlett
    to choose either the Graham #2 or Slyder Easement and to compensate the
    Dabrowskis before “constructing a roadway . . . or by June 1, 2017,
    whichever is earliest.” The judgment is silent on the timing of the recording.
    The court also ordered the parties to bear their attorney’s fees and costs,
    ruling that Bartlett’s statement of costs was untimely.
    ¶12          The Dabrowskis timely appealed, and Bartlett timely
    cross-appealed.
    DISCUSSION
    A.     We Have Appellate Jurisdiction Over Some of the Claims Raised
    by the Parties and We Exercise Special Action Jurisdiction to
    Decide the Remaining Claims.
    ¶13            Although neither party has raised the issue, we have an
    independent obligation to determine whether we have appellate
    jurisdiction, Robinson v. Kay, 
    225 Ariz. 191
    , 192, ¶ 4 (App. 2010), and we
    must dismiss an appeal over which we lack jurisdiction, Davis v. Cessna
    Aircraft Corp., 
    168 Ariz. 301
    , 304 (App. 1991). Because “[p]ublic policy is
    against deciding cases piecemeal,” our jurisdiction over appeals generally
    is “limited to final judgments which dispose of all claims and all parties.”
    Musa v. Adrian, 
    130 Ariz. 311
    , 312 (1981); see also A.R.S. § 12-2101. However,
    Arizona Rule of Civil Procedure 54(b) permits the superior court to enter
    an appealable final judgment on fewer than all claims in a case, Garza v.
    Swift Transp. Co., 
    222 Ariz. 281
    , 284, ¶ 13 (2009), when the judgment
    6
    DABROWSKI v. BARTLETT
    Opinion of the Court
    “dispose[s] of at least one separate claim of a multi-claim action,” 
    Davis, 168 Ariz. at 304
    . We review de novo whether the superior court has
    appropriately certified a judgment as final and appealable under Rule 54(b).
    
    Davis, 168 Ariz. at 304
    .
    ¶14            Here, the superior court included language from Rule 54(b) in
    the judgment, indicating portions of the judgment were not final but did
    not note which parts. The parties appealed and briefed the judgment in its
    entirety. “Certification under Rule 54(b), however, ‘does not give this court
    jurisdiction to decide an appeal if the judgment in fact is not final, i.e., did
    not dispose of at least one separate claim of a multi-claim action.’” Grand v.
    Nacchio, 
    214 Ariz. 9
    , 16, ¶ 17 (App. 2006) (quoting 
    Davis, 168 Ariz. at 304
    ).
    “[A] claim is separable from others remaining to be adjudicated when the
    nature of the claim already determined is ‘such that no appellate court
    would have to decide the same issues more than once even if there are
    subsequent appeals.’” Cont’l Cas. v. Superior Court, 
    130 Ariz. 189
    , 191 (1981)
    (quoting Curtiss-Wright Corp. v. Gen. Elec. Co., 
    446 U.S. 1
    , 8 (1980)). Here, the
    quiet title action and the private condemnation action are severable. The
    judgment regarding the Dabrowskis’ quiet title action and Bartlett’s claims
    of an equitable interest through Lot 1 are final. Thus, we have appellate
    jurisdiction to review the quiet-title judgment.
    ¶15             Conversely, Bartlett’s cross-claim for a private condemnation
    is not final. The final route has not yet been determined, the Dabrowskis
    have not been compensated, and the court has not entered the final order
    of condemnation. Therefore, we do not have appellate jurisdiction over
    those claims. See 
    Nacchio, 214 Ariz. at 16
    , ¶ 17. However, when parties
    mistakenly raise issues from a non-appealable order, we have the discretion
    to sua sponte accept special action jurisdiction and consider the merits of the
    claims. See State v. Bayardi, 
    230 Ariz. 195
    , 197–98, ¶ 7 (App. 2012) (appeal
    treated as a special action when parties appealed from a superior court
    minute entry); Danielson v. Evans, 
    201 Ariz. 401
    , 411, ¶ 35 (App. 2001) (after
    finding appellate jurisdiction lacking, court sua sponte accepted special
    action jurisdiction); see also A.R.S. § 12-120.21(A)(4); Ariz. R.P. Spec. Act.
    1(a). We accept special action jurisdiction here because the parties have
    fully briefed and argued the issues, the superior court has ruled on the
    claims, and the non-final issues would likely be raised on appeal after a
    final judgment. We also accept special action jurisdiction because the
    judge’s order raises questions of first impression—which are particularly
    appropriate for special action review—concerning the application of Article
    2, § 17 of the Arizona Constitution and A.R.S. § 12-1126(B). See Chartone, Inc.
    v. Bernini, 
    207 Ariz. 162
    , 165–66, ¶¶ 8–9 (App. 2004).
    7
    DABROWSKI v. BARTLETT
    Opinion of the Court
    B.     In the Quiet Title Action, the Court Did Not Abuse Its Discretion
    by Finding the Dabrowskis Proved That There Was Not an
    Easement Over Their Property—Either Express or Implied.
    ¶16          The Dabrowskis initially brought an action for quiet title
    under A.R.S. § 12-1101(A):
    An action to determine and quiet title to real property may be
    brought by any one having or claiming an interest therein,
    whether in or out of possession, against any person . . . when
    such person . . . claims an estate or interest in the real
    property which is adverse to the party bringing the action.
    Bartlett’s counterclaim asserted that he was entitled to either (1) an express
    easement; (2) an easement of implied necessity; or (3) an implied easement
    by way of necessity.
    ¶17             We review a grant of summary judgment de novo, viewing the
    facts in the light most favorable to the non-moving party. BMO Harris Bank,
    N.A. v. Wildwood Creek Ranch, LLC, 
    236 Ariz. 363
    , 365, ¶ 7 (2015). For issues
    resolved at trial, we consider the evidence presented in the light most
    favorable to upholding the court’s rulings. Town of Marana v. Pima County,
    
    230 Ariz. 142
    , 152, ¶ 46 (App. 2012). But we review the court’s conclusions
    of law de novo and may draw legal conclusions from facts found or inferred
    from the judgment. FL Receivables Tr. 2002-A v. Ariz. Mills, L.L.C., 
    230 Ariz. 160
    , 166, ¶ 24 (App. 2012); In re Estate of Musgrove, 
    144 Ariz. 168
    , 170 (App.
    1985). To the extent the superior court’s decision was based on an
    interpretation and application of the law, we review its decision de novo.
    Freeman v. Sorchych, 
    226 Ariz. 242
    , 247, ¶ 11 (App. 2011).
    1.     The Court Did Not Err by Finding the 2000 Express
    Easement Terminated as to the Lots.
    ¶18            Bartlett claims the court erred by finding he did not have an
    express easement through Lot 1 via the 2000 Express Easement. The
    superior court determined that the 2000 Express Easement merged when
    the Lots came under common ownership between 2001 and 2003.
    Specifically, the superior court found that the Lots were under common
    ownership on three occasions: (1) under Lewis in 2001; (2) under Jacob in
    2002; and (3) under Bartlett from 2003 until he sold Lot 1.
    ¶19           Merger applies, and an easement terminates, when one party
    obtains both the greater and the lesser interest in the same property without
    any intermediate interests in other hands. Flood Control Dist. of Maricopa
    8
    DABROWSKI v. BARTLETT
    Opinion of the Court
    County v. Paloma Inv. Ltd. P’ship, 
    230 Ariz. 29
    , 41, ¶ 39 (App. 2012). In such
    cases, the lesser interest is extinguished. 
    Id. ¶20 While
    Bartlett recognizes the general proposition, he argues
    that an express easement is not “activated” until the parcels are severed,
    and—as to portion of the easement granting Lot 2 access through Lot 1—the
    express easement did not merge because the Lots were not commonly
    owned at any time after the Bartlett-Hiltner conveyance that severed the
    parcels. He cites no authority, however, for the proposition that easements
    that have not been activated are not subject to a merger, and we decline to
    so hold.
    ¶21           As there is no Arizona authority directly on point, we look to
    the Restatement (Third) of Property (Servitudes) (“Restatement (Third)”).
    See Paxson v. Glovitz, 
    203 Ariz. 63
    , 67, ¶ 21, n.3 (App. 2002) (“In the absence
    of contrary precedent, Arizona courts look to the Restatement.”). The
    Restatement (Third) does not exempt easements that have not been
    activated by separate ownership from the merger. The comments instead
    provide that merger applies “when the burdens and benefits are united in
    a single person, or group of persons” because “the servitude ceases to serve
    any function” and “no one else has an interest in enforcing the servitude.”
    Restatement (Third) § 7.5 cmt. a.
    ¶22           The benefits and burdens of the 2000 Express Easement were
    unified during the three periods in which the superior court found common
    ownership. The fact that those benefits and burdens were later severed in
    subsequent conveyances did not by itself activate or recreate the easement.
    See Restatement (Third) § 7.5 cmt. b (“A subsequent conveyance of the
    property that results in separate ownership of the previously dominant and
    servient estates raises the question whether the parties can re-create the
    servitude that previously existed on the property without complying with
    the requirements set forth in Chapter 2. Under the rule stated in this section
    they cannot.”). Indeed, an express easement could not have been
    reestablished without a writing that complied with the statute of frauds.
    A.R.S. § 44-101(6) (statute of frauds applies to “an agreement . . . for the sale
    of real property or an interest therein”); Owens v. M.E. Schepp Ltd. P’ship,
    
    218 Ariz. 222
    , 228, ¶ 24 (2008) (“The statute of frauds enacts a clear
    legislative prohibition against enforcement of an oral agreement for the
    conveyance of land.”); Restatement (Third) § 2.7.
    ¶23          Because Bartlett admitted he did not record any document
    creating an easement from the Bartlett-Hiltner conveyance, we conclude
    that the superior court correctly granted summary judgment on Bartlett’s
    9
    DABROWSKI v. BARTLETT
    Opinion of the Court
    express easement claim because Lot 2 did not have access via an express
    easement through Lot 1.
    2.     The Court Did Not Abuse Its Discretion by Finding Bartlett
    Was Not Entitled to an Implied Easement of Necessity
    Through Lot 1.
    ¶24           Lot 2 also does not have an implied easement of necessity
    through Lot 1. An implied easement of necessity requires: (1) a single tract
    of land arranged in a manner where one portion of the land derives a benefit
    from the other; (2) unity of ownership; (3) severance of the land into two or
    more parcels; (4) long, continued, obvious use of the subservient land, to a
    degree which shows permanency—by the dominate land—prior to the
    severance; and (5) the use of the claimed easement must be essential to the
    beneficial enjoyment of the dominate land. See Porter v. Griffith, 25 Ariz.
    App. 300, 302 (1975).
    ¶25            When the Lots were severed in 2005, no road connected Lot 1
    to Lot 2, nor did Lot 1 have a connection to the access road on Parcel B. See
    supra ¶ 3, Figure 1. Thus, Bartlett failed to show that at the time of the
    Bartlett-Hiltner conveyance there was a long, continued, and obvious use
    of Lot 1 for the benefit of Lot 2.
    3.     The Court Did Not Abuse Its Discretion by Finding Bartlett
    Was Not Entitled to an Easement by Implied Way of
    Necessity Through Lot 1.
    ¶26           Bartlett contends that the Bartlett-Hiltner conveyance caused
    his lot to become landlocked, resulting in an easement by implied way of
    necessity. “Under the common law, where land is sold that has no outlet,
    the vendor by implication of the law grants ingress and egress over the
    parcel to which he retains ownership, enabling the purchaser to have access
    to his property.” Bickel v. Hansen, 
    169 Ariz. 371
    , 374 (App. 1991). The
    doctrine derives from the presumption that when a party conveys the
    property, it conveys “whatever is necessary for the beneficial use of that
    10
    DABROWSKI v. BARTLETT
    Opinion of the Court
    property and retains whatever is necessary for the beneficial use of the land
    he still possesses.” 
    Id. 1 ¶27
               Under the common law, to obtain an easement by implied
    way of necessity through Lot 1, Bartlett was required to prove: (1) both
    properties were under common ownership; (2) the properties were then
    severed; (3) there is no reasonable or adequate outlet for one of the
    properties; and (4) the need for reasonable access through the severed
    property existed at the time of severance. See Coll. Book Ctrs., Inc. v. Carefree
    Foothills Homeowners’ Ass’n, 
    225 Ariz. 533
    , 541, ¶ 30 (App. 2010); 
    Bickel, 169 Ariz. at 374
    . If an implied way of necessity exists, it may survive through
    multiple conveyances and is not affected by use or the lack thereof. 
    Bickel, 169 Ariz. at 375
    . As explained below, Bartlett failed to prove that he was
    entitled to the common law easement by implied way of necessity because
    he was unable to show that it was the severance of the Lots that caused his
    property to lack an adequate outlet.
    i.       At the Time of Severance, the Lots Did Not Have an
    Express Easement Through Parcel B.
    ¶28           Bartlett argues that at the time of Bartlett-Hiltner conveyance,
    he had an express easement from Lot 1 through Parcel B to the access
    road—as evidenced by the 2000 Express Easement—giving the Lots a
    reasonable outlet and therefore the severance of the Lots caused his lot to
    lack an outlet. The Dabrowskis contend that the Lots’ access through Parcel
    B terminated through merger when Jacob owned the Lots and Parcel B
    concurrently in 2002. Bartlett maintains that there was no unity of
    ownership because Jacob, as trustee for the Jacob Trust, owned Parcel B,
    while Jacob and his wife jointly owned the Lots.
    ¶29           In 2000, Lewis—the then owner of the Lots and Parcel
    B—recorded an express easement, providing access from Lot 1 through
    Parcel B to the access road. See supra ¶ 3, Figure 2. In March 2000, Jacob, as
    trustee of the Jacob Trust, purchased Parcel B. Jacob and his wife then
    purchased the Lots in December 2002. Before Jacob and his wife purchased
    1      Because neither party raised the issue of whether granting a common
    law easement by implied way of necessity is proper under Article 2, § 17 of
    the Arizona Constitution and the legislature’s prescribed remedy for
    landlocked property in A.R.S. § 12-1202, we assume without deciding that
    a conveyance that causes a property to become landlocked may be entitled
    to an easement by implied way of necessity.
    11
    DABROWSKI v. BARTLETT
    Opinion of the Court
    the Lots, Allan Gray prepared a lot survey for Jacob showing the Lots’
    access through Parcel B, but not following the 2000 Express Easement. Jacob
    applied for and received certification for the 2002 Lot Split, and it was
    recorded. The month before selling the Lots to Bartlett, Jacob obtained
    another lot survey from Gray. Jacob again applied to the Town of Cave
    Creek to certify the 2003 Lot Split, which was done, and the 2003 Lot Split
    was recorded. See supra ¶ 6, Figure 3.
    ¶30            Arizona courts have not addressed the concept of merger
    relating to the unity of ownership when the parties involved share interests
    but are technically different. In this case, two technically different owners
    were involved: Jacob Trust owned Parcel B while Jacob and his wife owned
    the Lots. Other jurisdictions, however, have applied a control test to
    establish unity of ownership. See Cosmopolitan Nat’l Bank v. Chicago Title &
    Tr. Co., 
    131 N.E.2d 4
    (Ill. 1955); Houston Bellaire, Ltd. v. TCP LB Portfolio I,
    L.P., 
    981 S.W.2d 916
    (Tex. App. 1998).
    ¶31              In Houston Bellaire, the court, looking to Cosmopolitan,
    concluded that although “the ownership of the two lots was technically
    different, . . . ‘[t]here was, in effect, common ownership of both properties
    sufficient to indicate the ability to arrange and adapt the property in a
    manner sufficient to satisfy rules of property in the establishment of
    easement by implication.’” Houston 
    Bellaire, 981 S.W.2d at 920
    –21 (quoting
    
    Cosmopolitan, 131 N.E.2d at 7
    ). The court concluded that the parties “with
    the power to arrange and adapt the properties” did arrange matters in a
    way that created an implied easement. 
    Id. ¶32 As
    an owner of the Lots and the trustee of the trust that owned
    Parcel B, the evidence shows Jacob had the power to arrange and adapt the
    properties. First, Jacob commissioned the 2002 Lot Split when Parcel B was
    owned by Jacob Trust. Jacob and his wife purchased the Lots after the Town
    of Cave Creek approved the lot split, and the survey was recorded. Next,
    Ian Cordwell, the Director of Planning and the Zoning Administrator for
    the Town of Cave Creek, testified that Jacob applied for a building permit
    for Lot 2 on March 11, 2003. The town would not approve a building permit
    unless the owner of the property could show that each lot had access from
    a dedicated public right of way to the parcel itself. At the time of Jacob’s
    application for the building permit, he indicated that Lot 2 lacked access.
    Subsequently, Jacob again commissioned Gray to create the 2003 Lot Split,
    which provided access to Lot 2 without burdening Lot 1. Jacob then applied
    for the lot split, which was approved and recorded. Cordwell, who
    accepted both lot splits, testified that he believed the 2003 Lot Split was
    12
    DABROWSKI v. BARTLETT
    Opinion of the Court
    intended to establish an access point for Lot 2 through Parcel B and served
    as a replacement to the 2002 Lot Split.
    ¶33           Jacob obtained and recorded lot splits that depicted access to
    the Lots through various access points in Parcel B immediately preceding
    Lewis’s sale to Jacob and Jacob’s sale to Bartlett. The 2002 and 2003 Lot
    Splits demonstrated that Jacob, as the trustee, exercised the control over
    Parcel B required to situate the land in a manner that benefited the Lots
    when Jacob and his wife purchased the Lots, and again as the seller of the
    Lots. As the Lots’ seller, Jacob arranged access through Parcel B in a manner
    that was beneficial to the Lots, but detrimental to Parcel B, because of the
    proximity of the shared driveway to the location of the proposed home on
    Parcel B. Such control is sufficient to conclude that there was unity of
    ownership over the Lots and Parcel B. We conclude that Jacob’s concurrent
    ownership extinguished any express easement that existed on Parcel B
    concerning the Lots. There was approximately a quarter mile between Lot
    1’s eastern boundary and the access road, for which the Lots did not have
    legal access—via an express easement—at the time of the Jacob-Bartlett
    conveyance. See supra, ¶ 3, Figure 1. Accordingly, the Lots did not have an
    express easement through Parcel B at the time of severance.
    ii.      Bartlett Failed to Show Sufficient Evidence of the
    Need for Reasonable Access at the Time of the
    Bartlett-Hiltner Conveyance.
    ¶34           Without legal access, Bartlett was required to show that at the
    time of the Bartlett-Hiltner conveyance he lacked reasonable access to his
    property. Bartlett argues that Lot 2 does not have—and never has
    had—access through Parcel B. However, as noted above, immediately
    before selling the Lots to Bartlett, Jacob applied for a building permit
    concerning Lot 2 and recorded the 2003 Lot Split. The 2003 Lot Split was
    recorded before the Jacob-Bartlett conveyance and was listed as an
    exception in Bartlett’s title report for the Jacob-Bartlett conveyance.
    ¶35           Michael Johnson, Bartlett’s and Hiltner’s architectural
    designer, testified that the 2003 Lot Split was provided to him when he
    began designing the Bartlett and Hiltner homes in 2006. He testified that
    there were “a lot of different discussions because of the confusion” of the
    two access points. Johnson stated that at some point Bartlett and Hiltner
    agreed to follow the entrance point through Lot 1 to cut costs and create
    less disturbance by sharing a driveway and utility site. With that plan, most
    of the disturbance fell on Lot 1, allowing Bartlett to build the larger home
    he wanted on Lot 2. Johnson also recalled that he wanted the driveway to
    13
    DABROWSKI v. BARTLETT
    Opinion of the Court
    conform with the 2003 Lot Split, but Bartlett refused. Ultimately, Johnson
    testified that Bartlett and Hiltner could not reach an agreement, and Hiltner
    built his driveway and home without Bartlett’s assistance.
    ¶36           Although Bartlett asserted that he has always understood
    access to Lot 2 would be through Lot 1, he could not point to a recorded
    document to support that understanding. Bartlett insists that it was both his
    and Hiltner’s intent that the shared driveway would follow the 2000
    Express Easement. However, the completed Lot 1 driveway does not
    conform with the 2000 Express Easement; instead, it follows the 2002 Lot
    Split. Moreover, Bartlett failed to record an express easement granting
    access for Lot 2 through Lot 1 at the time of the Bartlett-Hiltner conveyance,
    although he stated that access through Lot 1 was the parties’ intent. Bartlett,
    a mortgage broker at the time, failed to disclose his need for access through
    Lot 1 in the seller property disclosure statement, which he provided in
    connection with the Bartlett-Hiltner conveyance. The placement of the
    driveway and Bartlett’s subsequent actions in connection with the
    Bartlett-Hiltner conveyance do not support Bartlett’s contention that Lot 2’s
    access was intended through the 2000 Express Easement.
    ¶37            There is conflicting evidence in the record regarding the
    intended access point for the Lots at the time of the Jacob-Bartlett
    conveyance. The superior court weighed the credibility of the witnesses
    along with the other evidence and concluded there was no implied way of
    necessity between the Lots. Given that the 2003 Lot Split indicates a
    reasonable access point for both lots, the superior court did not abuse its
    discretion by finding Bartlett failed to establish that Lot 2 lacked reasonable
    access in 2005 at the time of the severance. See Coll. 
    Book, 225 Ariz. at 542
    ,
    ¶ 32 (failing to present evidence to establish a lack of an outlet at the time
    of severance prevents a party from prevailing in an action for an implied
    way of necessity). We defer to the superior court’s resolution of the
    evidence presented. FL Receivables 
    Tr., 230 Ariz. at 166
    , ¶ 24.
    4.     The Dabrowskis Prevailed in the Quiet Title Action.
    ¶38           The Dabrowskis prevailed in the quiet title action because
    they proved title to the property and that Bartlett had neither an express or
    implied easement over the Lot 1. Therefore, the Dabrowskis contend the
    superior court erred by not awarding their attorney’s fees and costs under
    A.R.S. §§ 12-1103(B) and 12-341.01(A). We review the court’s decision
    declining to award fees for an abuse of discretion. Vicari v. Lake Havasu City,
    
    222 Ariz. 218
    , 224, ¶ 23 (App. 2009).
    14
    DABROWSKI v. BARTLETT
    Opinion of the Court
    ¶39           Because the Dabrowskis did not correctly request fees under
    A.R.S. § 12-341.01(A), the superior court did not abuse its discretion by
    refusing to award them. See Ariz. R. Civ. P. 54(g)(1) (“A claim for attorney’s
    fees must be made in the pleadings or in a Rule 12 motion filed before the
    movant’s responsive pleading.”); Klesla v. Wittenberg, 
    240 Ariz. 438
    , 441,
    ¶ 13, n.2 (App. 2016) (“Contractual attorneys’ fees must be pleaded and
    proved like any other contract claim, as part of the proponent’s case in
    chief.”).
    ¶40           However, the superior court found that Bartlett was the
    prevailing party in the quiet title action because “[he] is entitled to an
    easement created by private condemnation.” The court erred. The
    Dabrowskis originally sued for quiet title. The court concluded that Bartlett
    did not have a legal interest in Lot 1; thus, the Dabrowskis prevailed in the
    quiet title action. The Dabrowskis also requested attorney’s fees under
    A.R.S. § 12-1103(B) 2 and complied with the statutory requirements for such
    an award. Accordingly, we vacate the superior court’s conclusion that
    Bartlett was the prevailing party and remand for the court to enter
    judgment for the Dabrowskis in the quiet title action, and—in the court’s
    discretion—it may award attorney’s fees under A.R.S. § 12-1103(B). See also
    Scottsdale Mem’l Health Sys., Inc. v. Clark, 
    164 Ariz. 211
    , 215 (App. 1990)
    (“[T]he trial court may consider the same factors that are considered in
    determining whether to award attorney’s fees pursuant to A.R.S. section
    12-341.01.”).
    C.     The Court’s Ruling that Bartlett Proved the Private Condemnation
    is Supported by the Evidence.
    ¶41             “Arizona law permits a landowner to engage in private
    condemnation when land ‘is so situated with respect to the land of another
    that it is necessary for its proper use and enjoyment to have and maintain a
    2      A.R.S. § 12-1103(B) provides:
    If a party, twenty days prior to bringing the action to quiet
    title to real property, requests the person, other than the state,
    holding an apparent adverse interest or right therein to
    execute a quit claim deed thereto, and also tenders to him five
    dollars for execution and delivery of the deed, and if such
    person refuses or neglects to comply, the filing of a disclaimer
    of interest or right shall not avoid the costs and the court may
    allow plaintiff, in addition to the ordinary costs, an attorney’s
    fee to be fixed by the court.
    15
    DABROWSKI v. BARTLETT
    Opinion of the Court
    way of necessity.’” Siemsen v. Davis, 
    196 Ariz. 411
    , 414, ¶ 9 (App. 2000)
    (quoting A.R.S. § 12-1202(A)). “A landowner seeking to condemn a private
    way of necessity over the lands of another must show a ‘reasonable
    necessity’ for the taking.” 
    Id. ¶42 With
    respect to the private condemnation action, the
    Dabrowskis claim the court erred by: (1) awarding Bartlett private
    condemnation through Lot 1; (2) finding that the Slyder easement was a
    viable easement choice; (3) failing to award the Dabrowskis additional
    compensation for the private condemnation; (4) not requiring that the
    one-time payment for the private condemnation be paid when the easement
    is recorded; and (5) not imposing additional conditions on Bartlett in
    connection with the private condemnation.
    1.     The Court Did Not Abuse Its Discretion by Determining
    Bartlett is Entitled to a Private Condemnation.
    ¶43            The Dabrowskis argue that Bartlett is not entitled to private
    condemnation because the superior court erred by concluding that the 2003
    Lot Split did not constitute an express easement, and the existence of the
    alternative route precludes Bartlett from seeking a private condemnation
    through their lot. We do not need to decide whether the 2003 Lot Split
    evidences a valid easement because the mere fact that an alternate legal
    outlet is available to Bartlett does not, as a matter of law, preclude him from
    condemning a way over Lot 1. See Solana, 
    69 Ariz. 117
    , 125 (1949) (“[T]he
    condemnor need not show an absolute necessity for the taking, a reasonable
    necessity being sufficient.”).
    ¶44            When determining whether a reasonable necessity exists, the
    court looks to whether the proponent of the private condemnation has an
    alternative legal route that is both adequate and reasonable. See, e.g., Tobias
    v. Dailey, 
    196 Ariz. 418
    , 422, ¶ 14 (App. 2000). Because there is sufficient
    evidence in the record to support the superior court’s conclusion that
    “[t]here is no other adequate alternative access” to Lot 2, the court did not
    abuse its discretion by ordering a private condemnation.
    ¶45          The route on the 2003 Lot Split may have been reasonable and
    adequate at the time of the Jacob-Bartlett conveyance. However,
    subsequent events show that it may no longer be a reasonable alternative.
    Anderson testified that at the time he purchased Parcel B, the land only
    contained the access road and a well. After acquiring Parcel B, Anderson
    constructed a home, and the access road now leads to his driveway and
    garage. The Town of Cave Creek requires a road or driveway that services
    16
    DABROWSKI v. BARTLETT
    Opinion of the Court
    more than one single-family residence to be 16 feet wide with shoulders on
    each side that are at least two feet wide. To obtain a building permit from
    the Town of Cave Creek, Bartlett needs a 20-foot-wide easement for the
    entirety of the easement through the Anderson property. The Anderson
    driveway is currently 11–12 feet wide and some portions of the driveway
    have no shoulder at all. Anderson’s utilities are on the west side of the
    driveway, and there is solid rock to the east. In short, the current
    specifications of the driveway do not comply with the Rural/Metro Fire
    Department standards for a roadway servicing more than one residence.
    Civil engineer Christopher Wilson testified that the amount of disturbance
    that would result from building the road following the 2003 Lot Split would
    leave approximately 90 square feet available for the actual home on
    Bartlett’s lot.
    ¶46          These facts support the superior court’s finding that there is
    no other adequate and reasonable alternative access to Lot 2 and its
    conclusion that Bartlett is entitled to a private condemnation.
    i.   Bartlett is Not Required to Seek Alternative Routes.
    ¶47            The Dabrowskis argue that Bartlett is not entitled to a private
    condemnation because Bartlett failed to establish both that “the Town of
    Cave Creek would not allow Bartlett to build a roadway to the west or south
    of Bartlett’s Lot” and that he “could not obtain an easement to the west or
    south of his Lot.” Thus, the Dabrowskis contend, Bartlett failed to show a
    reasonable necessity for the taking. The Dabrowskis do not offer legal
    authority for this contention. Bartlett was not obligated to explore
    alternative outlets for which he did not have legal access. See 
    Solana, 69 Ariz. at 125
    (“There is no merit to defendants’ contention that [the statute
    permitting residents to petition to establish a highway], gives to plaintiff an
    appropriate and expedient method of obtaining a means of ingress and
    egress to its property by petitioning the board of supervisors for the
    establishment of a county highway. . . . [P]roviding for condemnation at the
    instance of a private party the framers of our constitution as well as the
    legislature affirmatively rejected such a contention.”). The court found that
    Bartlett’s potential legal access was inadequate, and thus correctly granted
    him a private condemnation through Lot 1.
    ii.        The Evidence Does Not Show               that   Bartlett
    Voluntarily Landlocked Lot 2.
    ¶48          Finally, the Dabrowskis maintain Bartlett is not entitled to
    private condemnation because Bartlett voluntarily landlocked himself. For
    17
    DABROWSKI v. BARTLETT
    Opinion of the Court
    support, they cite to Gulotta v. Triano, 
    125 Ariz. 144
    (App. 1980). In Gulotta,
    the owners severed their land into parcels, leaving the plot they intended
    to keep landlocked. 
    Id. at 145.
    The owners testified that the buyers would
    not have completed the sale with a permanent easement. 
    Id. The owners
    entered into a contract with the buyers for a temporary easement through
    the property, which would terminate at the earlier of two years or upon the
    completion of a new road. 
    Id. After completion
    of the road, the owners
    sought private condemnation through a neighboring parcel, which would
    grant them access to the new road. 
    Id. The owners
    claimed they were
    landlocked, or alternatively, that even if the easement had not terminated,
    the access through the sellers’ land was “so inadequate as to make the
    private right-of-way they seek reasonably necessary.” 
    Id. This court
    denied
    the private condemnation, stating:
    It is obvious from the terms of the agreement for the sale of
    the delicatessen property that [the owners] appreciated the
    danger of losing access to the property they retained. Whether
    they terminated or merely limited their right of ingress and
    egress in order to complete that sale, they did so voluntarily
    without first obtaining an alternative access way. The
    necessity, if any, for a right-of-way across defendants’
    property was created by their own voluntary act. For that
    reason alone they are not entitled to the extraordinary remedy
    afforded by § 12-1202.
    
    Id. ¶49 The
    Dabrowskis contend Bartlett “successfully maximized
    the marketability for the Dabrowski Lot and reaped the financial benefits
    of a higher purchase price ($440,000), only to thereafter invoke the
    protections of A.R.S. § 12-1202.” They point to the fact that Bartlett did not
    disclose his need for an easement in the seller property disclosure statement
    when conveying Lot 1 to Hiltner. But unlike Gulotta, there is no evidence
    that Bartlett appreciated the danger of losing his access or voluntarily
    relinquished access to seek a private condemnation from the Dabrowskis.
    This is especially true because the 2003 Lot Split indicated a way to the
    access road through Parcel B. Therefore, we cannot say that the superior
    court abused its discretion by awarding Bartlett a private condemnation.
    18
    DABROWSKI v. BARTLETT
    Opinion of the Court
    2.     The Superior Court Must Ultimately Determine the Route
    of a Private Condemnation.
    ¶50            The Dabrowskis argue that the court erred by allowing
    Bartlett to choose among three routes and ordering him to “select the route
    location and nature of the private way of necessity ensuring the greatest
    amount of deference to the privacy and concerns of the Dabrowskis.” After
    a court determines that a reasonable necessity exists, “the condemnor
    makes the initial selection and in the absence of bad faith, oppression or
    abuse of power its selection of route will be upheld by the courts.” 
    Solana, 69 Ariz. at 125
    .
    ¶51             Our courts have not opined on what constitutes “bad faith,
    oppression, or abuse of power” in a private condemnation action. In cases
    of private condemnation, the parties have competing interests, and
    ultimately it is for the court to settle such differences. See also 
    Siemsen, 196 Ariz. at 417
    , ¶ 25 (“Such lawsuits, as we have indicated, engage strong
    competing interests and values. To resolve them calls for delicate judgment
    and a close consideration of all applicable facts.”). We hold that absent an
    agreement, the condemnee may present evidence to the court—including
    evidence regarding the feasibility, cost, and other relevant details of a
    specified route—showing that under the circumstances, a more reasonable
    route exists. If the court determines that the condemnee’s suggested route
    is more reasonable, the condemnee will have made a sufficient showing of
    bad faith, oppression, or abuse of power. Accord A.R.S. § 12-1115(A)
    (eminent domain statute) (“Where land is required for public use, the
    state . . . may survey and locate the land, but it shall be located in the
    manner which will be most compatible with the greatest public good and
    the least private injury.”); Queen Creek Summit, LLC v. Davis, 
    219 Ariz. 576
    ,
    580, ¶ 19 (App. 2008) (condemnor in eminent domain action must show that
    it balanced the “greatest public good” and the “least private injury” when
    choosing the location, and condemnee can rebut the showing by
    establishing that the selection is “unnecessarily injurious”).
    3.     The Judgment Must be Satisfied Before a Final Order of
    Condemnation is Issued and the Easement Recorded.
    ¶52           The Dabrowskis raise several issues relating to the court’s
    order concerning the route, timing of the payment, and terms of the private
    condemnation. The order provided Bartlett with two options and directed
    that payment be made before a specified date or before construction on the
    road begins, “whichever is earliest.” The parties dispute whether the taking
    19
    DABROWSKI v. BARTLETT
    Opinion of the Court
    occurs at the time of judgment, payment, recording, or construction of the
    roadway.
    ¶53            Our constitution is clear: “No private property shall be taken
    or damaged for public or private use without just compensation having first
    been made, paid into court for the owner [or] secured by bond as may be
    fixed by the court . . . .” Ariz. Const. art. 2, § 17 (emphasis added); see also
    A.R.S. § 12-1124 (in an eminent domain proceeding, the court “shall set
    aside and annul the entire proceeding[]” when the condemnee is unable to
    collect payment). “When the final judgment has been satisfied . . . the court
    shall make a final order of condemnation, describing the property
    condemned and the purposes of the condemnation.” A.R.S. § 12-1126(A).
    “The title to the land does not vest in the [condemnor] until ‘the final order
    of condemnation’ is made by the court . . . .” State ex rel. Morrison v. Helm,
    
    86 Ariz. 275
    , 280 (1959) (quoting Pool v. Butler, 
    74 P. 444
    , 446 (Cal. 1903)).
    ¶54            A court’s final judgment of condemnation must include the
    route, decided by the court if contested, and the amount of compensation
    for that route. The valuation of the property is determined as the value at
    the time of the taking. See City of Scottsdale v. CGP-Aberdeen, L.L.C., 
    217 Ariz. 626
    , 634, ¶ 36 (App. 2008) (“[W]hen the condemnee offers evidence of a gap
    in time between the summons date and the date of the taking during which
    the value of the property increased, the court must determine the date of
    the taking and whether the value of the property on that date is the same as
    the value provided for in the statute.”). 3
    ¶55              Only after the judgment is satisfied, and the court issues the
    final order of condemnation, can the condemnor record “[a] copy of the
    order . . . in the office of the county recorder of the county . . . in which the
    property is located, and thereupon the property described shall vest in [the
    condemnor] for the purposes therein specified.” A.R.S. § 12-1126(B).
    Accordingly, Bartlett has no rights to the land until after he compensates
    the Dabrowskis.
    ¶56         Finally, concerning the parties’ contributions for
    maintenance, “the owners of the easement have the shared duty to repair
    and maintain the easement.” 
    Freeman, 226 Ariz. at 247
    , ¶ 13. The parties
    3      Bartlett appeals the court’s allowance of post-trial evidence to
    determine the property’s value. We decline to address the issue because the
    “taking” has not yet occurred and upon remand the court may admit
    additional evidence.
    20
    DABROWSKI v. BARTLETT
    Opinion of the Court
    should work together to agree upon terms for the final order that will
    minimize future litigation. To the extent that the parties cannot agree on the
    details of the private condemnation, Freeman addresses the parties’ rights
    to contribution when neither the document creating the easement nor a
    separate agreement between the parties specifies otherwise. See 
    id. at 250–51,
    ¶ 24.
    ATTORNEY’S FEES AND COSTS ON APPEAL
    ¶57           Both sides request costs and attorney’s fees incurred in this
    appeal and cross-appeal under A.R.S. §§ 12-1103(B) and 12-341.01(A).
    Although we affirmed the superior court’s judgment entitling Bartlett to a
    private condemnation, we denied relief on Bartlett’s cross-appeal and
    reversed the court’s determination of the prevailing party in the quiet title
    action. Therefore, neither party was entirely successful, and we decline to
    award fees or costs to either party.
    CONCLUSION
    ¶58            We affirm the superior court’s judgment that Bartlett is not
    entitled to a common law easement, but reverse and remand for the entry
    of judgment in favor of the Dabrowskis in the quiet title action.
    Accordingly, we vacate the denial of the Dabrowskis’ request for attorney’s
    fees, and remand for the court to reconsider the award of attorney’s fees to
    the Dabrowskis as the prevailing parties. We affirm the superior court’s
    determination that Bartlett is entitled to a private condemnation but vacate
    the portion of the order concerning the route, compensation, terms, and
    scope, and remand for further proceedings consistent with this opinion.
    AMY M. WOOD • Clerk of the Court
    FILED: AA
    21