Shea v. Az Registrar ( 2020 )


Menu:
  •                       NOTICE: NOT FOR OFFICIAL PUBLICATION.
    UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL
    AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.
    IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    SHEA CONNELLY DEVELOPMENT LLC, Plaintiff/Appellant,
    v.
    ARIZONA REGISTRAR OF CONTRACTORS, et al., Defendants/Appellees.
    No. 1 CA-CV 19-0718
    FILED 11-3-2020
    Appeal from the Superior Court in Maricopa County
    No. LC2019-000048-001
    The Honorable Douglas Gerlach, Judge
    AFFIRMED
    COUNSEL
    DKL Law PLLC, Tempe
    By David W. Lunn
    Counsel for Plaintiff/Appellant
    Arizona Attorney General’s Office, Phoenix
    By John R. Tellier
    Counsel for Defendant/Appellee AZ Registrar
    Fidelis V. Garcia Attorney at Law, Chandler
    By Fidelis V. Garcia
    Counsel for Defendant/Appellee Revive
    SHEA v. AZ REGISTRAR, et al.
    Decision of the Court
    MEMORANDUM DECISION
    Presiding Judge Randall M. Howe delivered the decision of the Court, in
    which Judge Kent E. Cattani and Judge Cynthia J. Bailey joined.
    H O W E, Judge:
    ¶1            Shea-Connelly Development, LLC (“SCD”) appeals the
    Arizona Registrar of Contractor’s (“ROC”) suspension of SCD’s
    contractor’s license for violations of Arizona’s Prompt Pay Act and
    associated statutes, namely A.R.S. § 32–1183.1 SCD argues that the
    administrative law judge (“ALJ”) was required to consider offset, accord
    and satisfaction, and recoupment in making its disciplinary determination
    to the ROC. For the foregoing reasons, we affirm.
    FACTS AND PROCEDURAL HISTORY
    ¶2             SCD and Revive Construction and Cleaning, LLC (“Revive”)
    entered construction subcontracts for two different large-scale construction
    projects. In one, SCD subcontracted Revive to frame the Morningstar
    Glendale Project (“Glendale Project”) in Glendale. In the other, SCD hired
    Revive to fix the framing done by a prior sub-contractor at two buildings at
    the Park Place I Project located in Fountain Hills, Arizona (the “Park Place
    Project”) The Glendale Project subcontract provided that if Revive
    defaulted on any contract or subcontract with SCD, it would be deemed to
    have defaulted on all contracts or subcontracts with SCD. In anticipation of
    its work at the Glendale Project, Revive submitted an application for
    payment, SCD paid Revive $58,641.57, and Revive signed a “Conditional
    Waiver and Release on Progress Payment.” Revive did not, however,
    perform any work at the Glendale Project.
    ¶3           The relationship between SCD and Revive deteriorated due
    to Revive’s work on the Park Place Project. What was initially a $300,000
    bid by Revive, turned into invoices totaling over $800,000. SCD sent
    superintendents to review Revive’s work since Revive was well over
    budget and the work failed inspections. SCD continued to pay Revive’s
    weekly invoices until late January, when Revive submitted an invoice for
    1     The operative statutes have been redesignated and renumbered
    from A.R.S. §§ 32–1129 to 32–1129.07 as A.R.S. §§ 32–1181 to 32–1188.
    2
    SHEA v. AZ REGISTRAR, et al.
    Decision of the Court
    work done solely on things that failed inspection. SCD did not object to that
    invoice or any subsequent invoices in writing but considered both the Park
    Place and Glendale Projects subcontracts terminated. At the time of
    termination, SCD owed Revive for four outstanding invoices from the Park
    Place Project, #97, #100, #101, and #102, totaling $68,783.25.
    ¶4            Revive filed a complaint with the ROC claiming SCD owed
    $68,783.25 for the outstanding invoices. The ROC notified SCD that a
    complaint had been filed against it, explaining that SCD was “free to raise
    any issues or affirmative defenses to this complaint . . . .” SCD timely replied
    that it did not owe Revive because it had made an accord and satisfaction
    with Revive that mitigated Revive’s damages.
    ¶5            At the subsequent administrative hearing, SCD’s owner, Bart
    Shea testified that SCD had terminated the Park Place Project subcontract
    because of Revive’s inadequate workmanship, which SCD deemed a
    material default. Because of the cross-default provision in the Glendale
    Project subcontract, SCD considered Revive in default on the Glendale
    Project and terminated that subcontract as well. SCD then requested Revive
    return the Glendale Project payment. Revive refused, and Shea considered
    those funds payment for the outstanding invoices from January and
    February in the Park Place Project. Shea further testified that to make the
    Park Place Project pass inspection, SCD hired another subcontractor to fix
    Revive’s work. Shea argued that any amount required to fix Revive’s work
    would offset, or be deducted from, the invoice amount. Therefore, SCD did
    not owe Revive, but Revive owed SCD.
    ¶6           Revive’s witness, Rogelio Vazquez, declined to answer
    questions about the Glendale Project. He did, however, verify the contracts
    and the unpaid Park Place Project invoices. He further testified that SCD
    notified Revive that it would not pay the invoices but did not provide any
    written explanation.
    ¶7            The ALJ found that SCD provided no written evidence that it
    paid invoices #97, #100, #101, and #102. She further found that SCD
    provided no authority to establish that the Registrar considers offsets when
    assessing whether a contractor has violated the Prompt Pay Act. She made
    no findings, however, whether she found any witnesses credible, nor any
    other finding related to offset, recoupment, or accord and satisfaction. The
    ALJ consequently found that SCD violated both A.R.S. § 32–1154(A)(10)
    and Arizona’s Prompt Pay Act. Pursuant to A.R.S. § 32–1154(B)(3), the ALJ
    recommended the ROC suspend SCD’s license until it paid Revive the
    amount of the invoices it owed, and the ROC adopted the recommendation.
    3
    SHEA v. AZ REGISTRAR, et al.
    Decision of the Court
    The superior court affirmed the ROC determination on factual grounds,
    inferring the material facts at issue to affirm the ALJ. SCD timely appealed.
    DISCUSSION
    ¶8            SCD appeals the suspension of its license under A.R.S. 32–
    1154(B)(3), arguing that the ALJ’s recommendation and ROC’s
    determination improperly precluded evidence of offset, recoupment, and
    accord and satisfaction. We review an administrative action based on an
    interpretation of law de novo. See Forest Guardians v. Wells, 
    201 Ariz. 255
    , 259
    ¶9 (2001).
    ¶9            We interpret statutes to give effect to the legislature's intent,
    looking first to the statutory language itself. Baker v. Univ. Physicians
    Healthcare, 
    231 Ariz. 379
    , 383 ¶ 8 (2013). When the language is clear and
    unambiguous, and thus subject to only one reasonable meaning, we apply
    the language without using other means of statutory construction. State v.
    Gomez, 
    212 Ariz. 55
    , 57 ¶ 11 (2006). Specifically, “[s]tatutory construction
    requires that provisions of a statute be read and construed in the context of
    related provisions and in light of its place in the statutory scheme.”
    Id. at 176.
    In doing so, we give effect to all provisions of a statute and harmonize
    those provisions. Sw. Gas Corp. v. Indus. Comm'n, 
    200 Ariz. 292
    , 297 ¶ 16
    (App. 2001).
    I.     The ALJ did not abuse her discretion when she rejected SCD’s
    claim that it had an accord and satisfaction with Revive.
    ¶10           SCD argues that the ALJ abused her discretion when she did
    not consider evidence that it had an accord and satisfaction agreement with
    Revive that constituted payment of the invoices at issue. SCD cannot rely
    on accord and satisfaction here, however.
    ¶11           The Prompt Pay Act requires a contractor to pay the full
    amount of an invoice for work done and material supplied within seven
    days of the invoice being certified and approved. A.R.S. §§ 32–1183(A), (B);
    see also A.R.S. § 32–1182(A), (D). An invoice is deemed certified and
    approved 14 days after the contractor receives the invoice if the contractor
    does not prepare and issue a written statement detailing the reasons for
    withholding payment. A.R.S. §§ 32–1183(A), (B), (E); see also A.R.S. § 32–
    1182(A), (D). SCD concedes that it did not provide written objections to the
    invoices as A.R.S. § 32–1183(E) required, and the invoices were duly
    deemed certified. SCD was therefore required to pay the invoices.
    4
    SHEA v. AZ REGISTRAR, et al.
    Decision of the Court
    ¶12           SCD could not use its alleged accord and satisfaction with
    Revive to escape its obligation to pay the certified invoices. A construction
    contract is “a written or oral agreement relating to the construction,
    alteration, repair, maintenance, moving or demolition of any building,
    structure or improvement or relating to the excavation of or other
    development or improvement to land,” A.R.S. § 32–1181(A)(1), and under
    the Prompt Pay Act, a construction contract “shall not alter the rights of any
    contractor, subcontractor or material supplier to receive prompt and timely
    payments as provided under this article,” A.R.S. § 32–1182(P). An “accord
    and satisfaction discharges a contractual obligation or cause of action when
    the parties agree to exchange something of value in resolution of a claim or
    demand and then perform on that agreement.” Abbott v. Banner Health
    Network, 
    239 Ariz. 409
    , 413 ¶ 11 (2016). By definition, an “accord and
    satisfaction” would alter a subcontractor or material supplier’s statutory
    right to receive prompt payment under the Prompt Pay Act. Because
    recognizing an accord and satisfaction between SCD and Revive would
    limit Revive’s ability to receive payment for work done on a construction
    contract in contravention of the express language of A.R.S. § 32–1182(P), the
    ALJ did not abuse her discretion by not considering evidence of an accord
    and satisfaction.
    II.    The ALJ was not required to consider any offsets or the defense of
    recoupment in determining whether the Prompt Pay Act was
    violated.
    ¶13            SCD also argues that the ALJ abused her discretion by not
    considering evidence of an offsetting counterclaim or the equitable defense
    of recoupment in imposing sanctions under A.R.S. § 32–1154 (B)(3). An
    offset is an action or counterclaim a defendant might have brought in a
    separate action against the plaintiff and recovered a judgment. W. J. Kroeger
    Co. v. Travelers Indem. Co., 
    112 Ariz. 285
    , 287 (1975). “[A] recoupment is a
    reduction by the defendant of part of the plaintiff's claim because of a right
    in the defendant arising out of the same transaction.” Morris v. Achen Constr.
    Co., Inc., 
    155 Ariz. 507
    , 510 (App. 1986), rev'd and vacated on other 
    grounds, 155 Ariz. at 512
    .
    ¶14            Neither offset nor recoupment apply in Prompt Pay Act
    proceedings before the ROC. The purpose of the Prompt Pay Act is to
    establish a statutory framework for ensuring timely payments from owners
    and contractors to subcontractors and suppliers, Stonecreek Bldg. Co., Inc. v.
    Shure, 
    216 Ariz. 36
    , 39 ¶ 16 (App. 2007), and proceedings before the ALJ are
    meant to adjudicate whether payments have been timely made or withheld
    for valid statutory objections. The proceedings are not venues for
    5
    SHEA v. AZ REGISTRAR, et al.
    Decision of the Court
    comprehensive litigation over contract rights and obligations. See 
    id., 216 Ariz. at 40
    ¶ 18 (regardless of obligations under the Prompt Pay Act, civil
    remedies for breach of contract or tort claims are unaffected). Allowing a
    contractor to bring a counterclaim or some right outside the Prompt Pay
    Act against a subcontractor or supplier to reduce the amount owed under
    certified invoices would inflate a simple prompt payment proceeding
    before an ALJ to full civil litigation better suited to the superior court.
    ¶15            SCD argues that not allowing it to litigate these matters before
    the ALJ in the prompt pay proceeding violates its due process and is
    judicially inefficient. But due process is not violated when a party has “the
    opportunity to be heard at a meaningful time and in a meaningful manner.”
    See Samiuddin v. Nothwehr, 
    243 Ariz. 204
    , 211 ¶ 20 (2017). SCD can, if it
    chooses, bring any and all claims in civil litigation against Revive. See
    
    Stonecreek, 216 Ariz. at 40
    . SCD argues it may have to pay now only to have
    subsequent relief granted in its favor. But this does not violate due process
    because SCD retains full rights to bring its claim in a court of general
    jurisdiction. Furthermore, the Legislature has weighed any potential
    inefficiency in favor of timely payments to subcontractors and material
    suppliers, and we do not second-guess policy decisions. See Kromko v.
    Arizona Bd. of Regents, 
    216 Ariz. 190
    , 194 ¶ 21 (2007) (we do not substitute
    our “subjective judgment of what is reasonable under all the circumstances
    for that of the . . . Legislature.”).2
    2             SCD requests that this Court award SCD its reasonable
    attorneys’ fees and costs, pursuant to A.R.S. §§ 12-341 and 12-341.01, in
    connection with this appeal. We deny the request because SCD was not
    successful on appeal.
    6
    SHEA v. AZ REGISTRAR, et al.
    Decision of the Court
    CONCLUSION
    ¶16   For the reasons stated, we affirm.
    AMY M. WOOD • Clerk of the Court
    FILED: AA
    7