Katherine McClerkin v. Rogue Construction, LLC , 2022 Ark. App. 515 ( 2022 )


Menu:
  •                                Cite as 
    2022 Ark. App. 515
    ARKANSAS COURT OF APPEALS
    DIVISION III
    No. CV-22-10
    Opinion Delivered   December 14, 2022
    KATHERINE MCCLERKIN                          APPEAL FROM THE PULASKI
    APPELLANT                 COUNTY CIRCUIT COURT,
    SIXTH DIVISION
    V.                                           [NO. 60CV-18-8522]
    HONORABLE TIMOTHY DAVIS FOX,
    ROGUE CONSTRUCTION, LLC                      JUDGE
    APPELLEE
    REVERSED AND REMANDED
    KENNETH S. HIXSON, Judge
    Appellant Katherine McClerkin appeals from an order of the Pulaski County Circuit
    Court that granted appellee Rogue Construction, LLC’s motion to enforce a settlement
    agreement between the parties. On appeal, McClerkin argues that the circuit court’s finding
    that the parties entered into an enforceable settlement agreement was clearly erroneous. We
    agree, and we reverse and remand.
    I. Facts and Procedural History
    In August 2017, McClerkin entered into a contract with Rogue Construction for
    remodeling work on her house.       Problems arose, resulting in this litigation.    Rogue
    Construction filed a complaint against McClerkin alleging that McClerkin breached the
    contract by failing to pay the amount owed under the contract. Rogue Construction
    requested $25,525.92 in damages. McClerkin answered and asserted a counterclaim for
    breach of contract alleging that she suffered damages in excess of $100,000 when she was
    required to repair Rogue Construction’s allegedly defective work.1
    The parties attempted to negotiate a settlement of their claims in two separate phases. 2
    The first phase began in the summer of 2020, and in June 2020 the parties met for mediation
    but were unable to reach an agreement. The parties continued to negotiate, and on July 1,
    2020, Rogue Construction’s counsel sent an email to the circuit court stating that the parties
    had agreed to a settlement and were working on finalizing the language of the settlement
    agreement. However, on September 2, 2020, McClerkin’s counsel sent an email to the
    circuit court advising the court that unfortunately the parties could not agree on the release
    language to be included in the settlement agreement. McClerkin’s counsel explained that
    proposed language provided by Rogue Construction was unilateral in that it released only
    Rogue Construction from liability but not McClerkin.
    The parties continued to negotiate the terms of the settlement agreement to no avail.
    Finally, on October 20, 2020, Rogue Construction sent a letter to the circuit court advising
    1
    McClerkin later filed an amendment to counterclaim and second amendment to
    counterclaim wherein she raised additional claims for negligence and breach of implied
    warranty and requested additional damages, including consequential damages.
    2
    In the first phase of settlement negotiations, Rogue Construction was represented
    by Jason Davis, and in the second phase, it was represented by G. Spence Fricke, who is
    Rogue Construction’s counsel in this appeal. McClerkin was represented by Jack Wagoner
    in both phases of the settlement negotiations, and in the latter stages of the second phase,
    McClerkin was also represented by John Ogles, who is McClerkin’s counsel in this appeal.
    2
    the court that the parties were ultimately unable to reach a settlement agreement and
    requested the case be placed back on the active trial docket. Rogue Construction explained
    to the court that, although the parties had agreed to a monetary amount for the settlement,
    the parties had not reached an agreement as to which party would pay an outstanding bill of
    $3434.50 owed to subcontractor Ace Glass for installation of a shower door in McClerkin’s
    master bathroom.
    Notwithstanding that the parties had not reached an agreement as to all the material
    terms of a settlement agreement during the first phase of the negotiations, on October 27,
    2020, McClerkin filed a motion to enforce a settlement agreement. Rogue Construction
    opposed the motion. The circuit court initially granted McClerkin’s motion to enforce a
    settlement agreement on February 5, 2021; however, on February 8, the circuit court set
    aside the February 5 order and placed the case back on the docket for litigation of any and
    all issues.
    The second phase of settlement negotiations followed. This phase was documented
    by a series of email exchanges between the parties’ attorneys.         On April 29, 2021,
    McClerkin’s counsel sent an email to Rogue Construction’s counsel stating:
    I think that this case is settled. We will need a release from you as well though. My
    client has instructed me to tell you that she will withdraw her complaint with the
    Contractor’s Board as you have requested. I just want to talk with you and make sure
    we’re on the same page about everything. . . . I hope to get with you and knock this
    one out as soon as we can visit.
    Later that day, Rogue Construction’s counsel evidently had a telephone conversation with
    McClerkin’s counsel, and Rogue Construction’s counsel then sent a follow-up email stating:
    3
    Jack—I’m confirming we have a settlement for $65,000. I will prepare a mutual release
    which will include a mutual confidentiality provision, a non-disparagement provision,
    and an agreement by your client to withdraw her complaint at the Contractor’s
    Licensing Bd, and not re-file it. Please confirm on your end.
    McClerkin’s counsel replied:
    Confirmed. I’ll need to see the release language before we sign. But send it to me
    and I expect we’ll just be signing it and sending it back. I know you as an ethical, very
    talented lawyer. I trust you’ll include release language that takes care of both sides.
    Rogue Construction’s counsel replied, “Understood, and I will try my very best to do that.”
    Rogue Construction’s counsel prepared a “Confidential Settlement Agreement and
    Mutual Release” consisting of eight paragraphs. The proposed agreement provided that for
    consideration of $65,000, McClerkin would release Rogue Construction from any and all
    claims arising out of the design or construction work performed by Rogue Construction.
    The proposed agreement also provided that the lawsuit would be dismissed with prejudice
    in its entirety, and that McClerkin would withdraw her pending complaint against Rogue
    Construction before the Arkansas Contractor’s Licensing Board. There were additional
    provisions covering confidentiality, nondisparagement, mutual release, and no admission of
    liability. On May 6, 2021, Rogue Construction’s counsel sent an email to McClerkin’s
    counsel with an attachment containing the Confidential Settlement Agreement and Mutual
    Release along with the message, “Jack—attached is the release. I have gone over it with my
    client and he will agree to it if your client will agree to sign it.” Thirteen minutes after
    receiving that email, McClerkin’s counsel responded, “I have a couple of questions. Can
    you please call me as soon as you get a chance.”
    4
    A few days passed, and the next correspondence between the parties contained in the
    record occurred on May 11, 2021, when Rogue Construction’s counsel sent an email stating:
    Jack—following is language that my client and I can agree to add to paragraph 7 of the
    release:
    “For the same consideration, McClerkin further agrees that she will be
    responsible for paying any outstanding bills or other indebtedness for work or
    services provided by any subcontractor who worked on, or provided materials
    to, the Construction. To the best of Rogue Construction (formerly Rogue
    Architecture LLC)’s current knowledge, there are no outstanding balances due
    to any subcontractors, with the exception of Ace Glass Company, and
    McClerkin agrees that she will be responsible for, and will pay all sums owed
    to, Ace Glass Company.”
    In that email, Rogue Construction’s counsel apparently introduced yet a new provision and
    stated further, “My client is also interested in adding some statement of assurance to the
    effect that McClerkin will see that there is a final inspection as soon as reasonably possible
    so that we can close out the construction and he can close his currently open construction
    permit.” Rogue Construction’s counsel concluded the email with, “Just let me know if you
    want to discuss.”
    The parties exchanged emails again on June 1, 2021. McClerkin’s counsel sent an
    email to Rogue Construction’s counsel stating:
    I don’t think I have received a new version of the release we discussed a week or two
    ago. If you have sent one, please resend as it must have gotten lost in my spam folder
    or something.
    This case is giving me anxiety. I need to get this release deal either resolved or we
    have to pick the case back up and start moving forward with it. I don’t want to have
    to do that when the case was settled. We are giving you a full release. My client has
    agreed to a release and the $65,000, pay the contractor bill to Ace Glass, and assume
    5
    responsibility for any outstanding bills to subcontractors. Rogue affirms that it is not
    aware of any unpaid subcontractor bills except for Ace Glass.
    Can we get on the phone or in person and knock this out? This case stands out
    among my cases because of the position it is in right now. I feel like I need to get the
    release situation resolved asap.
    Rogue Construction’s counsel responded:
    Jack I am out of the office right now on vacation. I return to the office next Monday.
    I do believe I sent you the final version of the release agreement, but by copy of this
    email I’m asking De’Shae to do that just in case I did not. My client has been very
    busy over the last week or so and wants to review the release one last time. He is
    going to be doing that soon and I anticipate we will have a deal in the very near future.
    Rogue Construction’s counsel subsequently prepared a revised version of the
    Confidential Settlement Agreement and Mutual Release, which contained identical
    language as the former version and added a paragraph providing that McClerkin would be
    responsible for paying any outstanding subcontractor bills. In an email sent on June 8, 2021,
    Rogue Construction’s counsel provided McClerkin’s counsel with a copy of the revised
    version of the proposed agreement along with this message:
    Jack—I have now reviewed the attached final release with my client. My client is
    willing to sign this release if your client is willing. If you will have your client sign
    and return the signature page to me, I will have my client sign as well, and I will order
    the check from Hanover. Please also send me the payee information in terms of how
    the check should be made out as well as a W-9. Just let me know if you want to
    discuss.
    Notably, Rogue Construction never received a response to the above correspondence.
    On June 17, 2021, Rogue Construction sent a follow-up email to McClerkin’s
    counsel, who was then still Jack Wagoner, stating, “Jack—just following up.” Wagoner did
    not respond to that email. However, on June 21, 2021, McClerkin acquired additional
    6
    counsel, John Ogles. Now on board, co-counsel3 Ogles reached out to Rogue Construction’s
    counsel with an email stating, “I just [got] hired to represent Ms. McClerkin. I look forward
    to working with you and getting this case resolved. I will be in touch.”
    On June 30, 2021, Rogue Construction’s counsel sent Ogles an email stating, “John—
    just checking back. Are you available this week for a telephone call? I’d like to get this done
    if we possibly can as soon as we can.” Later that day, Ogles responded, “Sorry, I forgot to
    call you. Let’s touch base this afternoon. Do you think we have to mediate again?” Rogue
    Construction’s counsel replied:
    Sure. What’s a good time for you? I’ll give you a call. I’m not going to eliminate all
    possibilities of mediation, but Jack [Wagoner] and I had reached an agreement on the
    amount of money to be paid, $65,000, and we were working on the terms of the
    release, and I thought we had basically gotten agreements on that although no one
    had signed anything. Do you need to see the latest release that I sent Jack?
    Ogles then responded, “No. I have seen it. I will not stand in the way of a settlement but I
    think she has changed her mind.”
    Apparently dissatisfied, or perhaps confused, with the response from the new co-
    counsel, John Ogles, Rogue Construction’s counsel turned around and emailed McClerkin’s
    existing co-counsel, Jack Wagoner, stating:
    Jack—I have talked to John Ogles and he said he would not stand in the way of a
    settlement agreement. I thought we had one or at least were very near one. I am
    resending you again the final release with language that you requested. My client is
    anxious to settle this and get it done. Please let me hear from you.
    3
    While we have referred to Jack Wagoner and John Ogles as “co-counsel,” we do not
    intend to imply any legal relationship between the attorneys except they were both apparently
    now representing McClerkin going forward.
    7
    In response to that email, Wagoner sent Rogue Construction’s counsel an email clearly
    stating that “[w]e don’t have an agreement.” Among other things, Wagoner stated in the
    email that there was no agreement because “you keep sending me releases that are not
    completely mutual.” Wagoner stated that there was no settlement and indicated that
    McClerkin was moving forward with trying the case. This email from Wagoner wherein he
    confirmed there was no settlement agreement is the last correspondence between the parties
    contained in the record.
    On August 4, 2021, Rogue Construction filed a motion to enforce settlement. In its
    motion, Rogue Construction alleged that after several years of litigation, the parties agreed
    to settle their claims for payment of a specific monetary amount and execution of a
    settlement agreement providing certain terms. Rogue Construction alleged that the parties
    exchanged various drafts of the agreement and reached an accord on all material terms.
    Rogue Construction asked the circuit court to order McClerkin to stand by the agreement
    she negotiated and enter an order enforcing the parties’ settlement agreement. Rogue
    Construction also asked that, in enforcing the settlement, the circuit court dismiss Rogue
    Construction’s claim and McClerkin’s counterclaim with prejudice.4
    On August 23, 2021, McClerkin filed a response to Rogue Construction’s motion to
    enforce settlement, asking that it be denied. McClerkin argued that there was no enforceable
    4
    Rogue Construction also filed a separate motion to dismiss McClerkin’s second
    amended counterclaim. Rogue Construction never specifically asked to dismiss McClerkin’s
    first amended counterclaim.
    8
    settlement agreement because there was no meeting of the minds or mutual agreement on
    all material terms.
    On November 4, 2021, the circuit court entered an order granting Rogue
    Construction’s motion to enforce settlement agreement. The circuit court ordered the
    parties to execute releases and pay money within thirty days, and the circuit court dismissed
    the complaint and counterclaim with prejudice. The circuit court denied as moot Rogue
    Construction’s motion to dismiss McClerkin’s second amended counterclaim. 5
    II. Discussion
    In this appeal, McClerkin argues that the circuit court’s November 2021 order should
    be reversed because the circuit court clearly erred in finding that the parties entered into an
    enforceable settlement agreement. McClerkin argues that the parties did not reach a full
    and complete settlement because the parties never reached a mutual agreement as to the
    language of the releases to be executed by both parties, which was a material part of the
    agreement.6 McClerkin argues that there was no binding agreement reached but rather an
    5
    We observe that there can be no issue as to the finality or appealability of the circuit
    court’s order because in McClerkin’s notice of appeal she stated that she abandoned any
    pending but unresolved claims as required by Rule 3(d)(vi) of the Arkansas Rules of
    Appellate Procedure–Civil.
    6
    In her brief, McClerkin also cites Terra Land Services, Inc. v. McIntyre, 
    2019 Ark. App. 118
    , 
    572 S.W.3d 424
    , where we stated that an attorney may not compromise his client’s
    cause of action without permission. However, McClerkin does not appear to argue on appeal
    that her attorney did not have permission or lacked authority to negotiate or enter into an
    agreement on her behalf, and at any rate, such argument would not be preserved because it
    was not raised below. See Chastain v. Chastain, 
    2012 Ark. App. 73
    , 
    388 S.W.3d 495
     (stating
    9
    agreement to engage in continuing negotiations. We agree with McClerkin’s argument, and
    we reverse and remand.
    The law favors amicable settlement of controversies, and courts have a duty to
    encourage rather than discourage compromise as a method of resolving conflicting claims.
    Williams v. Davis, 
    9 Ark. App. 323
    , 
    659 S.W.2d 514
     (1983). Nevertheless, a settlement is
    contractual in nature, and in order to be legally valid, it must possess the essential elements
    of a contract. 
    Id.
     The essential elements of a contract include (1) competent parties, (2)
    subject matter, (3) legal consideration, (4) mutual agreement, and (5) mutual obligations.
    Billingsley v. Benton NWA Props., LLC, 
    2015 Ark. 291
    . We keep in mind two legal principles
    in determining whether a valid contract was entered into: (1) a court cannot make a contract
    for the parties but can only construe and enforce the contract that they have made; and if
    there is no meeting of the minds, there is no contract; and (2) it is well settled that in order
    to make a contract there must be a meeting of the minds as to all terms, using objective
    indicators. Alltel Corp. v. Sumner, 
    360 Ark. 573
    , 
    203 S.W.3d 77
     (2005). Whether or not
    there is a meeting of the minds is an issue of fact, and we do not reverse a circuit court’s fact-
    finding unless it is clearly erroneous. DaimlerChrysler Corp. v. Smelser, 
    375 Ark. 216
    , 
    289 S.W.3d 266
     (2008). A finding is clearly erroneous when, although there is evidence to
    support it, the reviewing court on the entire evidence is left with a definite and firm
    conviction that a mistake has been committed. 
    Id.
    the well-settled rule that in order to preserve an argument for appeal, the issue must first be
    raised at the circuit-court level).
    10
    During both the first and second phases of the parties’ settlement negotiations, the
    terms of the release language as to both parties was consistently discussed and, ultimately,
    never mutually agreed upon. In the latter stages of the first phase of negotiations, McClerkin
    sent an email to the circuit court noting the parties’ disagreement as to the content of the
    release language, and after the first phase of negotiations, the circuit court initially ruled that
    an enforceable settlement had been reached but then, correctly, set aside that order and the
    parties’ negotiations continued.
    In the second phase of the parties’ settlement negotiations, McClerkin’s counsel
    advised in an email to Rogue Construction’s counsel that he thought the case was settled
    but that “[w]e will need a release from you as well though.” Rogue Construction’s counsel
    responded by stating he would prepare a mutual release, and McClerkin’s counsel replied,
    “I’ll need to see the release language before we sign.” (Emphasis added.) Several days later, Rogue
    Construction’s counsel sent an email stating that it had drafted a release and would send it
    for McClerkin’s counsel’s review. On the following day, Rogue Construction’s counsel
    emailed the first version of the Confidential Settlement Agreement and Mutual Release that
    he had drafted, and advised, “I have gone over it with my client and he will agree to sign it
    if your client will agree to sign it.” (Emphasis added.) McClerkin’s counsel never assented to
    the initial settlement agreement drafted by Rogue Construction’s counsel; after receiving the
    proposed agreement, McClerkin’s counsel sent an email stating, “I have a couple of
    questions. Can you please call me as soon as you get a chance?”
    11
    Settlement negotiations continued, and two weeks later McClerkin’s counsel sent an
    email stating that “I need to get this release deal either resolved or we have to pick the case
    back up and start moving forward with it. . . . I feel like I need to get the release situation
    resolved asap.” A week later, Rogue Construction’s counsel responded with an email, on
    June 8, 2021, wherein he attached his revised draft of the Confidential Settlement
    Agreement and Mutual Release and stated, “My client is willing to sign this release if your
    client is willing . . . . Just let me know if you want to discuss.” McClerkin’s counsel did not
    respond to that email or communicate any agreement as to the settlement language therein.
    In Rogue Construction’s appellate brief, it posits that the parties’ agreement as to the
    material terms of the settlement were expressed in the final version of the agreement
    circulated between counsel on June 8, 2021. This final draft contained release terms
    applicable to McClerkin as well as a mutual release clause applicable to both parties, as
    follows:
    Release
    1)     That Katherine McClerkin (McClerkin), for and in consideration of the
    payment to her of the sum of $65,000, the receipt and sufficiency of which are
    hereby acknowledged, does hereby compromise, settle with, release, acquit and
    forever discharge Rogue Construction, LLC; Rogue Architecture, LLC;
    Jeremiah Russell; The Hanover Insurance Company; as well as their
    predecessors, affiliated companies, successors, agents, servants, officers,
    directors, employees, partners, insurers, and assigns, and any other person,
    firm, corporation or association in privity with them (Rogue Parties), or any of
    them, of and from any and all actions, claims, demands, and causes of action
    whatsoever, known and unknown, which McClerkin may now have or may
    have in the future arising out of any and all design or construction work done
    by Rogue Construction LLC or Rogue Architecture, LLC on McClerkin’s
    residence located at 11040 Rivercrest Drive, Walton Heights neighborhood,
    12
    Little Rock, AR., (the Construction), said claims being more specifically
    described in those pleadings and other materials filed and of record in the case
    of Rogue Construction, LLC v. McClerkin v. Rogue Construction, LLC,
    Pulaski County Circuit Case Number 60CV-18-8522 (the Lawsuit).
    2)     It is the express intention of McClerkin to reserve any rights, claims, or causes
    of action which she may have against any person other than the Rogue Parties,
    but to release the Rogue Parties fully and completely. Therefore, in
    consideration of the above payment, McClerkin agrees to a reduction of the
    damages recoverable against all other tortfeasors to the extent of the prorata
    share of the liability of the Rogue Parties, and further agrees to indemnify,
    protect and hold harmless the Rogue Parties from all judgments, claims, losses
    or expenses arising out of or by reason of any action, claim or demand by any
    person on account of the damages sustained by McClerkin as a result of the
    Construction, or any liability or alleged liability of the Rogue Parties. It is
    specifically intended that the Rogue Parties are and shall be released,
    indemnified and held harmless with respect to any liability or alleged liability
    under act 315 of the Acts of Arkansas of 1941, as amended, being the Uniform
    Contribution Among Tortfeasors Act. This Release does not release
    McClerkin from any claims by the Rogue Parties for contribution or
    indemnity.
    3)     For the same consideration, McClerkin covenants and agrees that this Release
    shall cover, and it does cover and release, any and all claims and demands of
    any kind whatsoever arising from the Construction, including any and all
    consequences thereof that may hereafter develop, as well as those already
    known, developed or that are now apparent that the McClerkin could have
    asserted against the Rogue Parties.
    ....
    7) Mutual Release McClerkin and the Rogue Parties hereby agree that any and all
    claims for contribution, fault, defense, damages, requests to be reimbursed for
    attorney’s fees and defense costs, hold harmless, and indemnity by McClerkin or the
    Rogue Parties against the other are forever released to the extent the defense,
    damages, request to be reimbursed for attorney’s fees, defense costs, hold harmless
    obligation, and indemnity or contribution obligation arise out of, or are in any way
    related to the Construction or the Lawsuit.
    13
    We conclude that Rogue Construction’s argument that this version of the agreement was
    enforceable as to all the material terms is misplaced because, as stated, the record reflects no
    communication from McClerkin’s counsel approving this or any other version that Rogue
    Construction’s counsel had drafted.
    Finally, we find it significant that a few weeks after the June 8, 2021, proposed
    settlement had been communicated without response, McClerkin’s newly acquired counsel,
    John Ogles, sent an email to Rogue Construction’s counsel asking, “Do you think we have
    to mediate again?” Rogue Construction’s counsel responded, “Sure. What’s a good time
    for you? I’ll give you a call.” Rogue Construction’s counsel then stated that he and
    McClerkin’s previous counsel, Jack Wagoner, “had reached an agreement on the amount of
    money to be paid, $65,000, and we were working on the terms of the release, and I thought we
    had basically gotten agreements on that, although no one had signed anything.” (Emphasis
    added.) Later that day when Rogue Construction’s counsel emailed Wagoner, he stated that
    “[m]y client is anxious to settle this and get this done,” and Wagoner responded by
    confirming that “[w]e don’t have any agreement” based in part on the absence of a mutual
    agreement as to the terms of the releases.
    It is well settled that in order to make a contract there must be mutual agreement and
    a meeting of the finds as to all terms. See Alltel Corp., supra. We hold on this record that the
    circuit court clearly erred in finding that the parties reached any mutual agreement as to the
    release language of a settlement and, therefore, that the circuit court’s order enforcing the
    settlement agreement must be reversed and the case remanded for further proceedings.
    14
    Reversed and remanded.
    HARRISON, C.J., and BROWN, J., agree.
    Ogles Law Firm, P.A., by: John Ogles, for appellant.
    Barber Law Firm, PLLC, by: G. Spence Fricke and Jerry D. Garner, for appellee.
    15