Parsons Evergreene, LLC ( 2018 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Parsons Evergreene, LLC                        )      
    ASBCA No. 61784
    )
    Under Contract No. FA8903-04-D-8703            )
    APPEARANCES FOR THE APPELLANT:                        Douglas S. Oles, Esq.
    James F. Nagle, Esq.
    Adam K. Lasky, Esq.
    Howard W. Roth III, Esq.
    Oles Morrison Rinker & Baker LLP
    Seattle, WA
    APPEARANCES FOR THE GOVERNMENT:                       Jeffrey P. Hildebrant, Esq.
    Air Force Deputy Chief Trial Attorney
    Michelle D. Coleman, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE PROUTY
    REGARDING ALLEGEDLY TARDY REQUESTS FOR PAYROLL RECORDS
    As stated in footnote 1 of the majority opinion for 
    ASBCA No. 58634
     and in
    our order issued today on the matter, for reasons of clarity and judicial efficiency,
    we *issue this separate opinion under a new appeal number upon the subject of
    appellant, Parsons Evergreene, LLC's (PE's), demand for compensation of costs
    associated with the Air Force's (AF's) allegedly tardy requests for payroll records.
    Judge Clarke, who presided over the hearing in this matter, believes, for those
    reasons set forth in his dissent, that the AF's failure to engage in a "prompt" investigation
    of the payroll matter should entitle PE to compensation pursuant to Federal Acquisition
    Regulation (FAR) 22.406-1. As we explain below, although we adopt the material
    findings of fact made by Judge Clarke's majority opinion in 
    ASBCA No. 58634
    ,
    concurrently filed today, PE's appeal based upon FAR 22.406-1 is denied.
    * Because the two judges who reviewed Judge Clarke's original opinion in 
    ASBCA No. 58634
     (Judges Shackleford and Prouty) came to a different conclusion than
    Judge Clarke on the payroll review issue, the remaining two judges from
    Judge Clarke's division were asked to consider it, consistent with Board practice and
    procedure. As reflected below, they concurred with Judges Shackleford and Prouty.
    We deny this appeal because FAR 22.406-1 does not provide a remedy to a
    contractor for the government's untimely investigation of complaints relating to labor
    standards. Under longstanding law:
    In order for a private contractor to bring suit against
    the Government for violation of a regulation, that
    regulation must exist for the benefit of the private
    contractor.
    Freightliner Corp. v. Caldera, 
    225 F.3d 1361
    , 1365 (Fed. Cir. 2000) (citing Cessna
    Aircraft Co. v. Dalton, 
    126 F.3d 1442
    , 1451 (Fed. Cir. 1997); and Rough Diamond Co.
    v. United States, 351 F .2d 636, 640-42 (Ct. Cl. 1965)). Cessna was particularly clear:
    The primary intent of a statute or regulation must be to
    protect or benefit a class of persons in order for that class
    to be able to bring suit against the government for violating
    the statue or regulation.
    126 F.3d at 1451 (citing Rough Diamond, 351 F.2d at 640, 642). To be sure, a regulation
    may be intended to benefit more than one class of persons, see, e.g., Todd Cons tr., L.P. v.
    United States, 
    656 F.3d 1306
    , 1314 (Fed. Cir. 2011) (performance evaluation regulation
    meant to benefit both government and contractor), but Freightliner and Cessna make
    clear that the operative test is not that application of the regulation merely be to the
    benefit of the contractor in the particular controversy for which it is bringing suit, but that
    the contractor has been an intended beneficiary all along.
    With this in mind, we tum to the text of FAR 22.406-1. That FAR provision is
    entitled, "Policy," which underscores, to us, that the section is meant as a broad explanation
    of later FAR provisions as well as an instruction for contracting agencies about the goals of
    their labor standards programs. Subsection (a) of FAR 22.406-1 provides, in full:
    General. Contracting agencies are responsible for
    ensuring the full and impartial enforcement of labor
    standards in the administration of construction contracts.
    Contracting agencies shall maintain an effective program
    that shall include -
    (I) Ensuring that contractors and subcontractors are
    informed, before commencement of work, of their
    obligations under the labor standards clauses of the
    contract;
    2
    (2) Adequate payroll reviews, on-site inspections,
    and employee interviews to determine compliance by the
    contractor and the subcontractors, and prompt initiation of
    corrective action when required;
    (3) Prompt investigation and disposition of
    complaints; and
    (4) Prompt submission of all reports required by
    this subpart.
    The remainder of FAR 22.406-1, subsection (b), directs the issuance ofpreconstruction
    letters and the arrangement of preconstruction conferences with contractors.
    Reviewing the full text confirms our view that the FAR' s requiring "prompt
    investigation and disposition of complaints," see FAR 22 .406-1 (a )(3 ), was, at most, for the
    benefit of labor, for whose advantage labor standards are required to be enforced, not for
    the benefit ofthe contractor. See Freightliner, 
    225 F.3d at 1365
    . Moreover, nothing in the
    language of the FAR provision comes close to suggesting that its "primary intent" was to
    "protect or benefit" the contractor class. See Cessna, 126 F.3d at 1451.
    Alternatively, we could conclude that FAR 22 .406-1, in setting out general policies
    for contracting agencies to follow, but not specifics, was meant merely for the benefit of
    the government as a "housekeeping regulation," providing guidance to government
    employees about how to establish their labor standards programs, and thus its violation
    gives no class any enforceable rights. See, e.g., Hartman v. Nicholson, 
    483 F.3d 1311
    ,
    1315-16 (Fed. Cir. 2007). Ultimately, we need not decide between whether labor or the
    government was the intended beneficiary to determine that the subject provision was not
    intended for the benefit of the contractor. Creation of a cause of action against the
    government does not occur by happenstance, and there is not enough here to create one
    anew. Thus, we respectfully disagree with our colleague and deny the portion of PE's
    appeal seeking compensation for the allegedly tardy AF request for payrolls.
    Dated: September 5, 2018
    J .' REID PROUTY
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    3
    I concur                   I concur
    RICHARD SHACKLEFORD        DA YID D' ALESSANDRIS
    Administrative Judge       Administrative Judge
    Acting Chairman            Armed Services Board
    Armed Services Board       of Contract Appeals
    of Contract Appeals
    I concur                   I dissent (see separate opinion)
    ALEXANDER
    Administrative Judge       Administrative Judge
    Armed Services Board       Armed Services Board
    of Contract Appeals        of Contract Appeals
    4
    DISSENTING OPINION BY ADMINISTRATIVE JUDGE CLARKE
    REGARDING ALLEGEDLY TARDY REQUESTS FOR PAYROLL
    I respectfully disagree with my colleagues.
    PE claims $762,130 for the government's violation of FAR 22.406-1 Policy,
    dealing with enforcement of labor standards, in particular payroll reviews. In order for
    a contractor to have a cause of action against the government for violation of a
    regulation, it must prove that the regulation exists for the benefit of the contractor.
    Freightliner Corp. v. Caldera, 
    225 F.3d 1361
    , 1365 (Fed. Cir. 2000).
    FAR 22.406-1 requires that if a problem is found during payroll reviews, on-site
    inspections and employee interviews there will be "prompt initiation of corrective action,"
    "Prompt investigation and disposition of complaints," and "Prompt submission of all reports
    required by this subpart" (finding 201 ).* I infer from this that the payroll reviews themselves
    must also be prompt or the entire regulatory scheme becomes meaningless.
    PE and its subcontractors submitted payrolls commencing in 2005 (finding 203).
    The Air Force (AF) "sampled" payrolls and found no problems until the first labor
    interview on 6 December 2007 (id.). The interview caused the AF to look closer at the
    payrolls. This started the lengthy process of the AF requiring PE to resubmit past payrolls
    and respond to AF questions between 2008 and as late as 2012 (findings 203-07). The
    AF took beneficial occupancy on 11 September 2008 (finding 197). I accept PE's
    position that the AF's waiting to commence interviews and detailed payroll reviews until
    2008, when the contract was almost over, made it much more difficult and expensive for
    PE to comply.
    PE has proven that the government failed to conduct payroll reviews promptly and
    as a result it was much more difficult and expensive for PE to respond. I conclude that
    proof of such direct and predictable harm to a contractor is prima facie evidence that a
    regulation, in this case FAR 22.406-1, exists for the benefit of the contractor. The
    government is then required to come forward with evidence to contest the prima facie
    case. If the government fails to do so, the prima facie case stands uncontroverted and the
    party with the burden of proof will have established its case by a preponderance of the
    evidence. Environmental Safety Consultants, Inc., 
    ASBCA No. 53485
    , 05-1 BCA
    ~ 32.903 at 163,019. In this case. the government presented no evidence or argument on
    the benefit issue. I agree with my colleagues that FAR 22.406-1 also benefits workers,
    *   References to findings are to the companion decision issued simultaneously with this
    decision.
    5
    but it is unlikely workers will ever avail themselves of the cause of action so my
    colleagues concession is academic. I sustained this claim and awarded PE $571,598 for
    the government's violation of FAR 22 .406-1.
    Dated: September 5, 2018
    CRAIG CLJ\E
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 61784
    , Appeal of Parsons
    Evergreene, LLC, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    6