Goodloe Marine, Inc. ( 2022 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of -                                  )
    )
    Goodloe Marine, Inc.                          ) ASBCA Nos. 62106, 62446
    )
    Under Contract No. W9126G-18-C-0071           )
    APPEARANCES FOR THE APPELLANT:                   Michael H. Payne, Esq.
    Cohen Seglias Pallas Greenhall & Furman PC
    Philadelphia, PA
    Casey J. McKinnon, Esq.
    Cohen Seglias Pallas Greenhall & Furman PC
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                   Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Clark Bartee, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, Galveston
    OPINION BY ADMINISTRATIVE JUDGE MELNICK GRANTING
    THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT
    Appellant, Goodloe Marine, Inc., of Wimauma, Florida (Goodloe), was awarded
    a contract to perform pipeline dredging by the United States Army Corps of Engineers
    (Corps or government). The government eventually terminated Goodloe for default for
    failing to dredge at the required production rate. Goodloe appeals from the default, as
    well as from a denial by the government of its claim for additional time it alleges
    should be recognized due to weather delays. The government has moved for summary
    judgment, which we grant.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    I.       Undisputed Facts
    The following facts have not been shown to be in genuine dispute.
    1. On September 29, 2018, the government awarded the firm fixed-price
    contract identified above to Goodloe. The contract was for pipeline dredging of the
    Gulf Intracoastal Waterway around Galveston, Texas. The contract estimated that
    630,000 cubic yards of material would be removed. (R4, tab 1 at 4-10, tab 2) Among
    the standard Federal Acquisition Regulation (FAR) clauses incorporated by reference
    was FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
    (R4, tab 1 at 16). In addition to that provision, the contract contained section 3.1.3,
    entitled “Default Terms.” It provided that:
    Failure of the Contractor to comply with the requirements
    of the Contract will be grounds for a determination, by the
    Contracting Officer, that the Contractor is not prosecuting
    the work with sufficient diligence to ensure completion
    within the time specified in this Contract. Upon making
    this determination, the Contracting Officer may terminate
    the Contractor’s right to proceed with the work, or
    separable parts of it, in accordance with the default terms
    of the Contract.
    (R4, tab 1 at 173)
    2. The contract required Goodloe to begin performing 10 calendar days after
    receiving a notice to proceed and complete performance 130 calendar days later. The
    government issued the notice to proceed on October 17, 2018, establishing February 24,
    2019, as the contract completion date. (R4, tab 1 at 8, tab 3)
    3. The contract imposed strict capacity requirements upon Goodloe.
    Section 1.15.2 mandated that “[t]he effective production rate of the dredge plant shall
    not be less than 360,000 cubic yards per month” and “[n]o reduction in the capacity of
    the dredge equipment and attendant plant employed to execute the work is to be made
    except by written direction of the Contracting Officer.” The capacity would be
    measured from actual performance. (R4, tab 1 at 133) Dredging 360,000 cubic yards
    per month (30 days) requires an average of 12,000 cubic yards per day.
    4. To achieve the contract’s requirements, Goodloe informed the government
    during a pre-award survey that it intended to use two dredges. One was Bettie G and
    the other was Perseverance. (Gov’t statement of undisputed material facts ¶ 2; app.
    resp. ¶ 2) Goodloe said that Bettie G’s average production rate ranged between 6,000
    and 8,000 cubic yards per day. Goodloe stated that Perseverance could achieve
    between 8,000 and 10,000 cubic yards per day. Goodloe also noted that it had a third
    dredge, Reliable, available to assist if necessary to complete performance on time.
    Goodloe represented that all three dredges were sitting idle at its yard and could be
    moved within days to the project site once it received a notice to proceed. Goodloe
    confirmed that it understood that the minimum amount of material that had to be
    dredged in a month was 360,000 cubic yards. It represented that Bettie G would start
    dredging about 21 days after the notice to proceed and Perseverance would arrive about
    2
    two to three weeks later and dredge concurrently with Bettie G at a rate that would
    achieve the minimum production. (R4, tab 349 at 1409, 1411, tab 350 at 1420)
    5. The record contains a series of forms purporting to be Goodloe’s Contractor
    Quality Control (QCR) Reports. However, no author is identified and their certification
    lines are blank. Beginning with the form dated November 6, 2018, a series of them
    indicate that Goodloe encountered weather delays on a total of 30 different days between
    October 18 and December 29, 2018. Many of the forms attached calendars for October,
    November, and December 2018 that also supposedly show the reported adverse weather.
    The calendars appear to be from an internet weather application (“app”), but Goodloe
    does not identify the source. There is also no indication of the geographical location they
    purport to describe, except the December calendar is marked Bay City, Texas. We
    judicially notice that location is over 70 miles on a straight line from Galveston. 1 (R4,
    tabs 196, 198, 200, 202, 204, 212, 214, 227, 237, 239, 241, 243, 257, 275, 277, 281, 283,
    293, 295, 297, 301, 303, 305, 307)
    6. Goodloe began dredging on December 17, 2018, with Bettie G. (R4,
    tab 220; gov’t statement of undisputed material facts ¶ 15; app. resp. ¶ 15; app. supp.
    R4, tab 30 (Native) at 1391 (production rate tab)).
    7. On January 10, 2019, the government sent a letter of concern to Goodloe’s
    president in Florida regarding its ability to timely complete the contract. The
    government indicated that Goodloe’s average dredging rate of 2,011 cubic yards per
    day had placed it three weeks behind schedule and was unacceptable. The government
    directed Goodloe to submit an updated schedule by January 15, 2019. (R4, tab 170)
    8. Goodloe’s president, Ms. Bettie Goodloe, responded to the government on
    January 15, 2019. She indicated that Goodloe had experienced “weather days” and
    “vendor delays” that delayed the arrival of Bettie G and Perseverance to the site. She
    stated that Goodloe had provided documentation of the weather, and expressed the
    belief that the conditions Goodloe encountered justified a later completion date. She
    also represented that Perseverance would arrive on or about January 22, 2019. (R4,
    tab 161)
    9. On February 11, 2019, the contracting officer issued a show cause notice to
    Goodloe notifying it that the government was considering terminating the contract for
    default. The government observed that Bettie G did not start dredging until
    December 17, 2018, 65 days after the notice to proceed. Perseverance did not arrive
    until January 23 and experienced operational problems. Goodloe’s invoice for
    December 15, 2018 through January 23, 2019, showed less than 35,000 cubic yards
    removed, well below the contractual requirement. (R4, tab 101)
    1
    See FED. R. EVID. 201.
    3
    10. Goodloe responded to the show cause letter on February 15, 2019. Goodloe
    stated that it had been delayed by weather since the notice to proceed. It characterized
    the amount of rainfall during the previous several months as unusual, saying anyone who
    lives or works in the area knows that. It explained that the conditions had hampered its
    assembly and placement of pipelines, emphasizing its delays commenced before dredging
    began. Goodloe also represented that other Corps projects in the area had been delayed
    by weather and that the government’s survey party had declined to work on Goodloe’s
    project due to weather on two occasions. It also stated that it had recently been delayed
    for two days by fog. Goodloe did not deny the rate of production indicated by the
    contracting officer. (R4, tab 94)
    11. Goodloe attached to its show cause response more weather app calendars for
    October 2018 through January 2019. This second set appears to be from The Weather
    Company and describes the weather differently for many of the days than the calendars
    Goodloe submitted previously with the purported QCR reports (R4, tabs 94, 237). As
    before, Goodloe did not identify the geographical location the calendars are meant to
    describe, other than to vaguely declare they are “for the area closest to our work.”
    Goodloe claimed it was delayed by weather for 40 days and by an additional lock delay
    caused by the Corps of one and a half days. (R4, tab 94 at 653-56)
    12. Goodloe also provided three purported news articles with its show cause
    response describing another project. The first two look to have come from a website
    called Dredgewire and are dated prior to the award of this contract. One stated that the
    Corps expected to dredge the San Jacinto River’s West Fork the week of September 17,
    2018, weather permitting. The article implied that weather had previously delayed
    commencement of the project. (R4, tab 94 at 658) Another reported that the project
    actually began September 21, repeating the reference to prior weather delays (id. at 660).
    The third “article,” dated November 5, 2018, is just text with no indication that it was
    published anywhere. It repeated that the San Jacinto river project began on September 21
    after experiencing the weather delays. (Id. at 662)
    13. Goodloe’s show cause response also admitted that Perseverance was
    delayed arriving on site because of continuing dry dock repairs that Goodloe started
    after the dredge was sunk by Hurricane Harvey. We judicially notice that storm struck
    Texas and Louisiana in August 2017, over a year before this contract was awarded.
    Goodloe blamed its insurance company and a hydraulic expert for overlooking damage
    requiring significant time to repair. (R4, tab 94)
    14. Goodloe continued to dredge after the February 24, 2019 period of
    performance expired. Perseverance began dredging on either March 6 or 7, 2019.
    (R4, tab 52; app. supp. R4, tab 30 (Native) at 1391 (production rate tab))
    4
    15. In late March 2019, Goodloe issued a payment invoice to the government
    for work performed between February 21 and March 19, 2019. According to the
    government payment estimate (Pay Estimate No. 5) associated with that invoice,
    Goodloe had earned $1,494,873.50 of the $3,782,500 contract price, or 39.5%. (App.
    supp. R4, tab 8)
    16. On March 28, 2019, the contracting officer terminated the contract for default
    on the ground that Goodloe had failed to perform in accordance with the contract
    schedule at a production rate of 360,000 cubic yards per month. He stated that work was
    39.5% complete. (R4, tab 23) In determining whether to terminate, the contracting
    officer considered the factors contained in FAR 49.402-3(f) and documented that review
    in a Termination for Default checklist signed March 28, 2019 (R4, tab 25). The
    checklist noted the work was essential, that Goodloe was given every opportunity to
    complete it, but that it had not maintained the required production rate. The checklist
    observed that Goodloe dredged less than 35,000 cubic yards between December 15,
    2018 and January 23, 2019. Regarding the urgency of the services and the time required
    to obtain them from another source, the checklist stated that the channel to be dredged is
    shallow and requires timely dredging for navigation. The services would be sought in an
    upcoming project to ensure completion during the 2019 fiscal year. An earlier draft of
    the checklist from March 22, 2019, indicated that no market research had been
    performed. (Id.; app. supp. R4, tab 7 at 47)
    17. Goodloe has appealed the termination, which has been docketed as 
    ASBCA No. 62106
    .
    18. After terminating the contract, the government performed a survey that
    showed Goodloe had dredged a total of 268,996 cubic yards of material, which is 43%
    of the 630,000 cubic yards the contract estimated would be removed (R4, tab 1 at 10;
    app. supp. R4, tab 29 at 1385). The survey indicated that between March 20 and
    March 28, 2019, the date of termination, Goodloe dredged 45,000 cubic yards (app.
    supp. R4, tab 29 at 1385). Thus, at the time of termination Goodloe was still not
    achieving a rate equal to 360,000 cubic yards per month. 2 An April 2019 government
    engineer spreadsheet states that Bettie G’s production was 20,388 cubic yards in
    December 2018; 61,462 cubic yards in January 2019; 49,012 in February; and
    94,184 in March. Perseverance only dredged in March 2019, producing 60,233 cubic
    yards. 3 Goodloe’s average monthly production with combined dredges was 128,452
    cubic yards, and its highest monthly production was 154,417. The report presented
    three possible scenarios had performance continued. The most reasonable scenario
    2
    Dividing 8 days into 45,000 cubic yards equals 5,625 cubic yards. As already noted,
    360,000 cubic yards per month requires an average of 12,000 cubic yards per
    day.
    3
    These numbers add up to 285,279 cubic yards.
    5
    was based upon Goodloe’s average production using two dredges, with Goodloe
    dredging 297,146 cubic yards over 71 additional days. In the best case scenario for
    Goodloe, it would maintain its highest reported production rates on both dredges and
    require 60 more days to dredge the same amount. Under the least reasonable scenario,
    Goodloe would only dredge 181,457 cubic yards in 44 days. This last scenario was
    not considered very reasonable because of high shoaling rates and the likely
    requirement that Goodloe would have to re-sweep the area. (App. supp. R4, tab 30
    (Native) at 1391 (survey tab))
    19. The parties engaged in some communications following the termination. An
    April 10, 2019 letter from Goodloe’s surety to the contracting officer claimed that at the
    time of termination the project was approximately 30 days from completion (app. supp.
    R4, tab 12). A June 5, 2019 letter to the contracting officer from the surety’s counsel
    sought Goodloe’s reinstatement. It indicated Goodloe might be able to retain help from
    another contractor and together dredge an average of 6,378.2 cubic yards per day, or
    191,346 per month. This is only slightly more than half of the 360,000 cubic yards the
    contract required. Retreating from the surety’s April prediction that the job could be
    completed in 30 days, the letter said that at this rate the project would finish in 48 days,
    implying that approximately 306,000 cubic yards remained to be dredged. The surety
    provided no details about the capabilities of the second contractor’s dredge and
    conditioned its participation upon scheduling. (App. supp. R4, tab 22 at 180) The
    letter’s next paragraph continued that even if the second contractor did not participate,
    Goodloe could proceed using only Perseverance and achieve an average rate of 3,400
    cubic yards per day, or 102,000 per month. This is obviously far below Goodloe’s prior
    representation that Perseverance could achieve between 8,000 and 10,000 cubic yards
    per day, and is less than a third of the contract’s 360,000 cubic yard monthly requirement.
    Anyway, where the prior paragraph had implied that 306,000 cubic yards remained to be
    dredged, here that number abruptly changed to 198,000 cubic yards. The letter claimed
    that the job could be completed in 74 days, including mobilization and demobilization. 4
    (Id.)
    20. The government concluded that the surety’s proposal was not in the
    government’s best interest. It noted the uncertainty of the surety’s projected completion
    times ranging between 30, 48, and 74 days. (App. supp. R4, tab 33 at 1401)
    21. On December 5, 2019, the contracting officer received a claim from
    Goodloe asserting that it had experienced weather delays performing the contract,
    entitling it to a time extension of 41.5 days (R4, tabs 6, 12).
    4
    According to the letter, 240,000 remaining cubic yards “was discussed” by someone.
    It says survey information supplied to the surety by Goodloe “suggests that the
    number is approximately 198,000.”
    6
    22. A February 2020 government engineer report notes that there were several
    days when weather delayed government acceptance of surveys, which then delayed
    Goodloe’s advancement to the next dredging section (app. supp. R4, tab 24 at 768).
    23. On March 19, 2020, the contracting officer denied Goodloe’s claim for a
    time extension (R4, tab 6). Goodloe has appealed that decision which was docketed as
    
    ASBCA No. 62446
     and consolidated with 
    ASBCA No. 62106
    .
    24. On September 28, 2020, the government awarded a replacement contract to
    complete the remaining work on the project. The new contractor mobilized to the site
    in November 2020, with completion required by July 13, 2021. (App. supp. R4, tab 33
    at 1398-99)
    II.    Status of the Proceedings
    Goodloe’s amended complaint in 
    ASBCA No. 62106
     alleges that it was
    wrongfully terminated because it experienced delays caused by unforeseeable weather.
    It also maintains that the project was near completion at the time of termination, that
    the government did not properly consider the factors contained in FAR 49.402-3(f),
    and that it failed to consider alternatives to termination. Alternatively, Goodloe
    essentially contends that for the same reasons the government breached the implied
    covenant of good faith and fair dealing. Goodloe’s complaint in 
    ASBCA No. 62446
    seeks a time extension of 41.5 days to account for the weather delays.
    The government moves for summary judgement, claiming that the undisputed
    facts show that its termination for default was justified and Goodloe’s delay was not
    excusable. In its effort to defeat summary judgment, Goodloe provided Ms. Goodloe’s
    declaration. Ms. Goodloe testifies that she was involved with and aware of Goodloe’s
    work. She states that Goodloe “was inhibited by weather-related delays, which delayed
    the arrival of certain Goodloe equipment and prevented Goodloe from proceeding with
    the work as planned.” She does not identify the equipment but elaborates that Goodloe
    encountered “rain, high winds, fog and extremely low tides resulting from high winds.”
    Ms. Goodloe also says that the delays were discussed with the government project
    engineer and Goodloe “documented the weather delays in daily reports with supporting
    documentation from weather station data for the relevant dates.” She adds that
    Goodloe’s quality control reports provided notice to the government of the weather
    delays. Ms. Goodloe explains that dredging projects are susceptible to delays from
    weather-related issues, including, but not limited to, rain, wind, fog and high and low
    tides. (App. resp., ex.)
    7
    DECISION
    I.     Summary Judgments Standards
    Summary judgment before the Board is guided by Federal Rule of Civil
    Procedure 56. Board Rule 7(c)(2). Under Rule 56, summary judgment should be
    granted when there are no genuine issues of material fact and the moving party is
    entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 
    477 U.S. 317
    ,
    322 (1986). A non-movant seeking to defeat the suggestion that there are no genuine
    issues of material fact may not rest upon its pleadings, but “must set forth specific facts
    showing that there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc.,
    
    477 U.S. 242
    , 248 (1986) (quoting First Nat. Bank of Ariz. v. Cities Serv. Co., 
    391 U.S. 253
    , 288 (1968)).
    When ruling upon a summary judgment motion, we must construe the evidence
    in the light most favorable to the non-movant and draw all reasonable inferences in its
    favor. Dairyland Power Co-op. v. United States, 
    16 F.3d 1197
    , 1202 (Fed. Cir. 1994).
    However, summary judgment should be entered “against a party who fails to make a
    showing sufficient to establish the existence of an element essential to that party’s
    case, and on which that party will bear the burden of proof at trial” because “a
    complete failure of proof concerning an essential element of the nonmoving party’s
    case necessarily renders all other facts immaterial.” Celotex, 477 U.S. at 322-23.
    Thus, the moving party need not offer evidence showing the absence of a genuine
    issue of material fact regarding an issue on which the non-moving party bears the
    burden of proof. It must only point out to the Board that there is an absence of such
    evidence to shift the burden to the non-movant to offer evidence establishing a genuine
    issue for trial. Id. at 325; DJ Mfg. Corp. v. United States, 
    86 F.3d 1130
    , 1135 (Fed.
    Cir. 1996); Dairyland Power Co-op., 
    16 F.3d at 1202
    ; Homeland Housewares, LLC v.
    Sorensen Research and Dev. Trust, 581 F. App’x 869, 874 (Fed. Cir. 2014).
    II.    Goodloe’s Unexcused Default
    The government premises its motion for summary judgment upon the fact that
    Goodloe did not meet the requirement that it dredge 360,000 cubic yards per month. It
    also relies upon Goodloe’s failure to complete the project by the contract’s February 24,
    2019, deadline. It contends that either of these grounds support sustaining the
    termination.
    The contract’s default clause permitted termination if Goodloe did not complete the
    work on time. FAR 52.249-10(a); see Watts Constructors, LLC, ASBCA Nos. 61518,
    61961, 
    19-1 BCA ¶ 37,382
     at 181,724; see also Truckla Servs., Inc., ASBCA Nos. 57564,
    57752, 
    17-1 BCA ¶ 36,638
     at 178,445 (“Failure to complete the contract work is a prima
    facie basis for a default termination”), aff’d, 730 F. App’x 926 (Fed. Cir. 2018). Having
    8
    shown that Goodloe failed to finish by the contract’s February 24, 2019 deadline, the
    government has established that as a basis for termination (SOF ¶¶ 14, 18). 5
    Regarding the government’s reliance upon Goodloe’s failure to dredge 360,000
    cubic yards per month, section 3.1.3 of the contract permitted the government to terminate
    for default if Goodloe’s performance did not comply with the contract’s requirements
    (SOF ¶ 1). The contract expressly stated that the effective production rate of the dredge
    plant was to be no less than 360,000 cubic yards per month and no reduction to the
    capacity of the dredge equipment and attendant plant employed was to be made except by
    written direction of the contracting officer (SOF ¶ 3). Goodloe commenced dredging on
    December 17, 2018, but only with Bettie G (SOF ¶ 6). Perseverance did not arrive on site
    until January 23, 2019, and it was not operational until early March (SOF ¶¶ 9, 14, 18).
    Bettie G was incapable of dredging 360,000 cubic yards per month and did not do so for
    the more than two months that it was the only operational dredge on site (SOF ¶¶ 4, 7, 9,
    16, 18). Accordingly, the government has carried its burden to establish that Goodloe did
    not meet the contract’s requirement for an effective dredge plant production rate of
    360,000 cubic yards per month. 6
    Goodloe’s failure to comply with the contract’s requirements does not entirely
    end our inquiry because Goodloe’s right to proceed could not be terminated if it was
    delayed due to unforeseeable causes beyond its control and without its fault or
    negligence. FAR 52.249-10(b)(1). One of the express examples of excusable delay
    contained in the default clause is unusually severe weather. FAR 52.249-10(b)(1)(x).
    Goodloe says that during performance it encountered rain, high wind, fog and
    extremely low tides that delayed its work. Goodloe bears the burden to show that its
    nonperformance due to unusually severe weather was excusable. Bell Constr. Co.,
    
    ASBCA No. 23376
    , 
    79-2 BCA ¶ 13,908
     at 68,272. To establish a time extension for
    unusually severe weather, Goodloe must: (1) identify work controlling overall
    completion; (2) show this controlling work was delayed by the weather, and (3) prove
    the weather was unusually severe. Skip Kirchdorfer, Inc., ASBCA Nos. 40515, 43619,
    
    00-1 BCA ¶ 30,622
     at 151,168; Bell Constr. Co., 
    79-2 BCA ¶ 13,908
     at 68,272-73.
    It was not the weather that prevented Goodloe from having a dredge plant
    production capacity of not less than 360,000 cubic yards per month. The record shows
    5
    It does not matter that the termination notice did not specifically refer to late
    completion as its reason. The Board sustains a default if justified by the
    circumstances at the time of termination regardless of whether the government
    removed the contractor for another reason. Empire Energy Mgmt. Sys., Inc. v.
    Roche, 
    362 F.3d 1343
    , 1357 (Fed. Cir. 2004) (quoting Kelso v. Kirk Bros.
    Mech. Contractors, Inc., 
    16 F.3d 1173
    , 1175 (Fed. Cir. 1994)).
    6
    Indeed, even when both dredges were operating at the time of termination, Goodloe
    was still failing to meet the required production rate (SOF ¶ 18).
    9
    that Perseverance failed to dredge prior to March of 2019 because it was undergoing
    continuing repairs necessitated by Hurricane Harvey, followed by operational problems
    on site (SOF ¶¶ 9, 13-14, 18). Perseverance’s delay due to damage caused by a
    hurricane occurring over a year before award is not an excusable weather event. When
    Goodloe assured the government during the pre-award survey that it would meet the
    360,000 cubic yard requirement using Perseverance, which it also said could travel to the
    project site within days of the notice to proceed, it was in fact proposing a damaged,
    inoperable dredge. (SOF ¶¶ 4, 13) Perseverance’s inability to perform was anything but
    unforeseeable. Furthermore, contractors generally assume the risk of providing the
    necessary equipment to perform and equipment breakdowns do not excuse performance
    failure. 7 E.g., Commercial Contractors Equip., Inc., 
    ASBCA No. 52930
     et al.,
    
    03-2 BCA ¶ 32,381
     at 160,262-63; Naughton Energy, Inc., 
    ASBCA No. 33044
    ,
    
    88-2 BCA ¶ 20,800
     at 105,073. Regardless of the weather on site between December of
    2018 and March of 2019, only Bettie G was capable of dredging and it lacked the
    capacity to remove 360,000 cubic yards per month, as required by the contract. Goodloe
    has not shown a nexus between the weather and its default. See TRU & Assocs., Inc.,
    
    ASBCA No. 45263
    , 
    96-2 BCA ¶ 28,389
     at 141,785-86 (finding the default upon a coal
    supply contract not excused for unusually severe weather when the contractor failed to
    show that absent the inclement weather it would have been able to perform); Fox-Sadler
    Co., 
    ASBCA No. 8421
    , 
    1963 BCA ¶ 3768
     at 18,795 (disregarding evidence of unusually
    severe weather when it was not the cause of late performance).
    Even if we were to disregard Perseverance’s failure to provide the necessary
    dredge capacity, the government has pointed to an absence of evidence supporting
    Goodloe’s allegation that the project was excusably delayed for 41.5 days due to
    unusually severe weather. Because Goodloe would bear the burden of proving that
    excuse at trial, to defeat summary judgment Goodloe must make a showing
    establishing a genuine issue for trial.
    “Unusually severe weather must be construed to mean adverse weather which
    at the time of year in which it occurred is unusual for the place in which it occurred.”
    Broome Constr., Inc. v. United States, 
    492 F.2d 829
    , 835 (Ct. Cl. 1974). No matter
    how severe or destructive the weather may have been, if it was not unusual for the
    time and place no relief is justified. Bigelow, Inc., 
    ASBCA No. 24376
    , 
    81-2 BCA ¶ 15,300
     at 75,737; see also Cape Ann Granite Co. v. United States, 
    100 Ct. Cl. 53
    ,
    72 (1943) (no relief when work was exposed to severe storms but they were not more
    severe than ordinarily encountered); Aulson Roofing, Inc., 
    ASBCA No. 37677
    ,
    
    91-2 BCA ¶ 23,720
     at 118,730 (“Excusable delay will be found only where the
    weather experienced was unusually severe as compared to the past weather at the same
    7
    It is also worth observing that Goodloe represented to the government that Reliable
    was available to assist if necessary (SOF ¶ 4). Goodloe offers no explanation as
    to why it was not employed in the absence of Perseverance.
    10
    location for the same time of year”). Weather records establish what is normal and
    foreseeable weather. Skip Kirchdorfer, 
    00-1 BCA ¶ 30,622
     at 151,168. Excusable
    delays are then determined by comparing the weather experienced to the historic
    weather. DayDanyon Corp., 
    ASBCA No. 57681
    , 
    15-1 BCA ¶ 36,073
     at 176,151,
    aff’d, 673 F. App’x 997 (Fed. Cir. 2017). Merely offering evidence of a number of
    rainy, windy, foggy, or low tide days proves nothing if it is not shown to exceed a
    historical norm. Assuming Goodloe has made a sufficient showing that it was delayed
    because of severe weather, it has not presented any evidence that it was more severe
    than the norm. 8 It has not provided any evidence of the historic weather for the time
    and place of the project for comparison to what occurred. 9 Accordingly, Goodloe has
    not made a sufficient showing to defeat the government’s motion for summary
    judgment upon its claim that its default is excused (or that it is entitled to extra time)
    due to unusually severe weather.
    8
    It is questionable whether Goodloe has made a showing that it was delayed for over
    40 days due to weather. Ms. Goodloe’s declaration does not expressly state that
    she has first-hand knowledge of the weather Goodloe encountered or witnessed
    herself how it impaired Goodloe’s work on any particular day (app. resp., ex.).
    See FED. R. CIV. P. 56(c)(4) (requiring that an affidavit or declaration used to
    support or oppose a motion for summary judgment must be made on personal
    knowledge, set out facts that would be admissible in evidence, and show that the
    affiant is competent to testify on the matters stated); Raytheon Co., 
    ASBCA No. 61859
    , 
    20-1 BCA ¶ 37,630
     at 182,688. The QCR reports are unsigned and
    Goodloe has failed to otherwise identify an author possessing personal knowledge
    of the information they purport to convey. The first set of Goodloe’s graphical
    weather calendars do not identify their source, and with the exception of the
    December calendar’s mention of a city over 70 miles from the project area, fail to
    identify the place they are describing. (SOF ¶ 5) The second set of calendars
    also fail to identify the relevant location (SOF ¶ 11). Goodloe’s purported
    newspaper articles about a Corps dredging project in the San Jacinto River before
    the award of this contract are irrelevant (SOF ¶ 12). However, Goodloe has
    presented a 2020 government engineer report observing that weather delayed its
    advancement to new dredging sections for some unspecified number of days
    (SOF ¶ 22).
    9
    Goodloe’s assertion in response to the government’s show cause order that anyone who
    lives in the area knows the weather had been unusual is unsupported and conclusory
    and is therefore inadequate to overcome summary judgment (SOF ¶ 10). Moore
    U.S.A., Inc. v. Standard Register Co., 
    229 F.3d 1091
    , 1112 (Fed. Cir. 2000); see
    also Raytheon Co., 
    20-1 BCA ¶ 37,630
     at 182,688.
    11
    III.   The Record Does Not Support Goodloe’s Contention That the
    Termination Was Arbitrary, Capricious, or an Abuse of Discretion
    Goodloe next argues that even if it was in default, the government’s motion should
    be denied because it has presented evidence the contracting officer was arbitrary and
    capricious terminating it. It suggests the government was materially in error believing the
    project was only 39.5 percent complete and relying upon Goodloe’s less than 35,000 cubic
    yards of production between December 15, 2018 and January 23, 2019 (SOF ¶¶ 9, 16).
    It stresses that Goodloe dredged 154,417 cubic yards in March and a total of 268,996
    at the time of termination, implying that should have been enough (SOF ¶ 18). It also
    contends the government was wrong to conclude that Goodloe would need 74 more days
    to complete the project. 10 Goodloe says the default was an abuse of discretion because
    only a small amount of work remained, the government failed to conduct market research
    into its alternatives if it terminated, and the government’s statements about the urgency of
    the work are contradicted by its actions. Goodloe argues Darwin Construction Co. v.
    United States, 
    811 F.2d 593
     (Fed. Cir. 1987), supports the conclusion that the totality of
    these facts show bad faith and abuse of discretion by the government.
    A default termination can be set aside if the government abuses its broad
    discretion to terminate. McDonnell Douglas Corp. v. United States, 
    182 F.3d 1319
    ,
    1326 (Fed. Cir. 1999). More specifically, default may not be invoked by the
    government as a pretext for reasons unrelated to performance. 
    Id. at 1329
    . To find
    that a default termination reflects an abuse of discretion because it was based upon
    materially erroneous information normally requires bad faith. This in turn requires a
    showing with convincing clarity of a high probability of personal animus by the
    contracting officer with a specific intent to injure. Watts Constructors, 
    19-1 BCA ¶ 37,382
     at 181,728. Regardless of whether Goodloe’s progress was 39.5, 43, or some
    other percentage, or that it dredged varying amounts of materials in different months,
    it failed to maintain a dredging capacity of 360,000 cubic yards per month and failed
    to complete performance by the contract completion date. There is nothing erroneous
    about these facts, much less anything about them to indicate animus by the
    government with a specific intent to injure Goodloe.
    Goodloe suggests the default was still unsustainable because, had it been
    allowed to continue, it would have consistently dredged 10,000 cubic yards per day
    and finished in 18 days. Goodloe has not supported that contention and has not shown
    10
    The evidence cited by Goodloe does not support its contention that the government
    concluded it would take Goodloe 74 more days to complete the project. It shows
    that the government rejected Goodloe’s proposal (made through its surety’s
    counsel) for reinstatement as not being in its best interest because Goodloe’s
    estimated completion time ranged between 30, 48, and 74 days (app. supp. R4,
    tab 33 at 1400-01).
    12
    that it ever demonstrated that possibility to the contracting officer.11 In fact, through
    counsel, Goodloe’s surety made very different representations on Goodloe’s behalf
    while seeking its reinstatement. After abandoning an initial prediction that Goodloe
    could complete the job in 30 days, it informed the contracting officer the work could
    not be finished in less than either 48 or 74 days. The 48 days were dependent upon the
    uncertain employment of another dredge. Neither scenario had Goodloe dredging the
    contractually required 360,000 cubic yards per month. (SOF ¶ 19) Similarly, the
    government’s post-termination analysis ranged between 44 days under the least
    reasonable scenario and 71 under the most reasonable one (SOF ¶ 18). The
    contracting officer rejected the surety’s request to reinstate Goodloe, noting the
    uncertainty of its projections (SOF ¶ 20). Again we see no indication of error by the
    contracting officer regarding the evidence before him and certainly no animus by him
    with a specific intent to injure Goodloe.
    Goodloe also objects to the answers the contracting officer recorded for two of
    the factors he was to consider under FAR 49.402-3(f) when deciding whether to
    terminate for default. Specifically, in response to FAR 49.402-3(f)(3)-(4)’s inquiry
    into the availability of the contract’s services from others, their urgency, and the
    period of time necessary to obtain them, he said the requirement would be included in
    a future project for completion in the 2019 fiscal year. Goodloe complains that the
    government did not perform any market research that would support these statements
    and it did not compare the time an alternative contractor might take to the time
    Goodloe would need to finish performance.
    The nature of the government’s compliance with FAR 49.402-3(f) may aid our
    inquiry into whether the government has abused its discretion terminating the contract,
    but it confers no rights upon Goodloe and the contracting officer’s failure to consider
    one or more of its factors does not dictate disturbing a default termination. DCX, Inc.
    v. Perry, 
    79 F.3d 132
    , 135 (Fed. Cir. 1996). Goodloe cites no authority stating that the
    contracting officer must perform a market research study to address the relevant
    provisions of FAR 49.402-3(f). Though the answers given by the contracting officer
    to these questions about the government’s options lacked specifics, that does not show
    the termination was a mere pretext.
    Finally, Goodloe contends that Darwin Construction dictates that the totality of
    the evidence presented proves bad faith. In Darwin, the Board found that the
    11
    The best we can discern is that Goodloe is relying upon a government report
    showing that on March 16, 2019, which was one out of the 23 days that its two
    dredges worked, their combined production exceeded 10,000 cubic yards (app.
    supp. R4, tab 30 (Native) at 1391 (production rate tab). This one day does not
    evidence that it would have achieved that rate every day into the future, or that
    it would have completed the dredging in 18 days if it had.
    13
    contractor was not terminated because it failed to timely complete the project, but
    simply to enable the government to be rid of dealing with it. That was held to be
    arbitrary and capricious. The court of appeals affirmed, stressing its conclusion was
    based upon the Board’s finding that the government had used the default as a pretext
    to terminate. Darwin, 
    811 F.2d at 596
    . The court of appeals has since elaborated that
    the lesson of Darwin and related decisions is that a termination for default unrelated to
    contract performance is arbitrary and capricious and therefore an abuse of discretion.
    McDonnell Douglas Corp., 
    182 F.3d at 1326
    . However, there is no abuse of discretion
    when there is no evidence of bad faith by the contracting officer; there is a reasonable,
    contract-related basis for his decision; he has not exceeded his discretion; and he has
    not violated any applicable statutes or regulations. Id.; see also Third Coast Fresh
    Distribution, L.L.C., 
    ASBCA No. 59696
    , 
    16-1 BCA ¶ 36,340
     at 177,194.
    We have already confirmed the contract-related basis for Goodloe’s default
    termination. There is no reason to conclude that it contravenes any statutory or
    regulatory restrictions. Goodloe’s complaints about weather delays, the time
    remaining to finish, and the absence of market research have been rejected and do not
    establish bad faith or abuse of discretion. Still, Goodloe suggests it is the victim of the
    contracting officer’s bad faith because it was terminated and replaced by a contractor
    whose services could not be obtained until after Goodloe might have finished the job
    had it been retained. The undisputed facts belie that contention. Goodloe represented
    to the government that it would use a dredge that it knew was unavailable to perform
    its contractual obligations, then failed to perform as required without an excuse,
    blaming its deficiencies upon unusual weather without evidence. Against this
    backdrop, Goodloe’s suggestion that it was an abuse of discretion not to allow it to
    dredge to completion anyway, after the contract completion date expired, and at a rate
    of its own choosing below the contract’s 360,000 cubic yard per month mandate, is
    unfounded.
    IV.    The Record Does Not Support a Breach of the Covenant of Good Faith
    and Fair Dealing
    Goodloe’s alternative theory suggesting the facts amount to a breach of the
    covenant of good faith and fair dealing does not save it. 12 The duty of good faith and
    fair dealing prohibits “interference with or failure to cooperate in the other party’s
    performance.” LaBatte v. United States, 
    899 F.3d 1373
    , 1379 (Fed. Cir. 2018) (quoting
    RESTATEMENT (SECOND) OF CONTRACTS § 205 cmt. d (1981)). The duty binds each
    party not to act to destroy the reasonable expectations of the other party regarding the
    fruits of the contract. However, the duty does not expand a party’s obligations beyond
    12
    Goodloe contends that the government’s motion for summary judgment is only a
    partial motion that does not encompass its good faith and fair dealing claim.
    Nothing in the motion restricted its scope.
    14
    the contract’s express terms or establish responsibilities inconsistent with the contract’s
    provisions. Thus, a party must undermine a specific promise to breach the duty.
    Dobyns v. United States, 
    915 F.3d 733
    , 739 (Fed. Cir. 2019), cert. denied, 
    140 S. Ct. 1106
     (2020). As already explained, the government was contractually entitled to
    terminate Goodloe when it defaulted upon its obligations. Because none of Goodloe’s
    arguments purporting to excuse its default have merit, or otherwise undercut the
    termination’s validity, there is no basis for concluding the government breached its
    implied obligations by exercising its contractual right to terminate for default.
    CONCLUSION
    The government’s motion for summary judgment is granted. The appeals are
    denied.
    Dated: January 27, 2022
    MARK A. MELNICK
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    RICHARD SHACKLEFORD                                J. REID PROUTY
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    15
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 62106, 62446, Appeals of
    Goodloe Marine, Inc., rendered in conformance with the Board’s Charter.
    Dated: January 27, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    16