Military Aircraft Parts ( 2016 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                    )
    )
    Military Aircraft Parts                         )       ASBCA No. 60739
    )
    Under Contract No. SPM4A7-11-M-T117             )
    APPEARANCE FOR THE APPELLANT:                           Mr. Robert E. Marin
    President
    APPEARANCES FOR THE GOVERNMENT:                         Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Edward R. Murray, Esq.
    Trial Attorney
    DLA Aviation
    Richmond, VA
    OPINION BY ADMINISTRATIVE JUDGE WILSON ON THE
    GOVERNMENT'S MOTION TO DISMISS
    The Defense Logistics Agency (DLA or government) moves to dismiss the appeal
    for lack of jurisdiction alleging that Military Aircraft Parts (MAP or appellant) did not
    file its notice of appeal with the Board within the 90-day appeal period from the date of
    receipt of the contracting officer's final decision (COFD). MAP counters that appeal
    language in the COFD was defective, and thus the 90-day time limit was tolled. We
    grant the motion and dismiss the appeal.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 9 August 2011, DLA awarded Contract No. SPM4A7-11-M-Tl 17 to MAP
    for aircraft parts for a total price of $8,950.00 (comp I. if 6; gov't mot., ex. 1). The
    contract included FAR 59.209-4, FIRST ARTICLE APPROVAL -GOVERNMENT TESTING
    (SEP 1989), which provided in pertinent part:
    (a) The Contractor shall deliver 1 unit (s) of
    Lot/Item ... within 180 calendar days from the date of this
    contract to the Government ....
    (b) Within 120 calendar days after the Government
    receives the first article, the Contracting Officer shall
    notify the Contractor, in writing, of the conditional
    approval, approval, or disapproval of the first article.
    (Gov't mot., ex. 1 at 15)
    2. By letter dated 2 October 2012, the contracting officer (CO) notified
    appellant that its first article submission was disapproved. Appellant was given the
    opportunity to resubmit another first article sample for testing. The CO further
    advised that "[t]he failure to resubmit may result in the termination of this contract for
    default." (Compl., ex. D)
    3. There is nothing in the record which indicates that MAP provided a schedule
    for resubmittal or delivered the required item as requested.
    4. By letter dated 21February2013, the CO issued a ten-day cure notice
    requiring appellant, inter alia, to propose a new delivery date, identify which work still
    needed to be accomplished, and "[p ]ropose appropriate consideration for your
    delinquency" (comp I., ex. H). Appellant responded via email dated 22 March 2013
    stating "We would prefer to cancel this contract if possible, but if a [sic] urgent
    requirement still exists we can provide a new first article sample within 60 days of
    notification" (comp I., ex. I).
    5. On 2 April 2013 the CO issued Modification No. POOOOl, partially
    terminating the contract for default. The modification included the following
    language:
    THIS IS THE FINAL DECISION OF THE
    CONTRACTING OFFICER. YOU MAY APPEAL THIS
    DECISION TO THE ARMED SERVICES BOARD OF
    CONTRACT APPEALS. IF YOU DECIDE TO MAKE
    SUCH AN APPEAL, YOU MUST MAIL OR
    OTHERWISE FURNISH WRITTEN NOTICE THEREOF
    TO THE BOARD WITHIN NINETY DAYS FROM THE
    DATE YOU RECEIVE THIS DECISION .
    ... IN LIEU OF APPEALING TO THE ARMED
    SERVICES BOARD OF CONTRACT APPEALS YOU
    MAY BRING AN ACTION DIRECTLY IN THE U.S.
    COURT OF FEDERAL CLAIMS WITHIN TWELVE
    MONTHS OF THE DATE YOU RECEIVE THIS
    DECISION.
    (Compl., ex. J) We find that this language complies with FAR 33.211 which requires
    essentially the language used by the CO.
    2
    6. On 15 August 2016, MAP filed an appeal with the Board, more than 3 years
    beyond the 90-day appeal period (which appellant concedes was I July 2013) and was
    docketed as ASBCA No. 60739. In its complaint, MAP alleges the following:
    21. As defined in the termination modification, the 90-day
    period for timely submission of appeal before the ASBCA
    was approximately 2 April 2013 to 1 July 2013. The same
    modification, which MAP elected to rely upon, alternately
    states MAP could file an action before the COFC [U.S.
    Court of Federal Claims], approximately between 2 April
    2013 and 2 April 2014.
    22. On 14 January 2014 while developing another COFC
    complaint challenging a DLA termination for
    default...MAP unexpectedly determined COFC Rule
    83.l(a)(3) prohibited MAP from proceedingpro se before
    the COFC; prose litigation was the only option MAP
    could practically afford. Thus MAP had allowed the
    90-day period for appeal before the ASBCA to expire
    while actively researching and engaging in appeal
    litigation intended for the COFC.
    (Compl. at 4)
    DECISION
    DLA moves to dismiss, arguing that as the COFD was issued on 2 April 2013 and
    MAP did not file its appeal with the Board until 15 August 2016, the appeal is well
    beyond the 90-day appeal period and must be dismissed for lack of jurisdiction as
    untimely (gov't mot. at 1). MAP replied that the motion should be denied because the
    CO provided defective appeal rights, specifically that the CO did not advise appellant that
    it could not file a pro se action at the Court of Federal Claims and that it relied on said
    defective appeal rights to its detriment (app. reply at 1; comp I. at 4 ). The government
    replies that detrimental reliance is not relevant because MAP was properly advised of its
    appeal rights. The government contends that appellant is asking the Board to impose an
    additional requirement, that the CO advise appellant of the procedural rules of the Court
    of Federal Claims, something neither the CDA nor FAR 33.211 requires. (Gov't reply
    at 1-2) We agree.
    The Contract Disputes Act of 1978 requires a contractor wishing to appeal a
    COFD to the Board to do so within 90 days from the date of receipt of the final decision.
    41 U.S.C. § 7104(a). It is well-settled that the Board lacks jurisdiction over any appeal
    filed outside of this 90-day period, which is statutory and cannot be waived by the Board.
    TTF, LLC, ASBCA No. 59511 et al., 15-1 BCA ~ 35,883 at 175,434 (citing Frasson
    Lodovico S.r.l., ASBCA No. 58645, 14-1BCA~35,525 at 174,114; AST Anlagen-und
    3
    SanierungstechnikGmbH, ASBCA No. 51854, 04-2 BCA ~ 32,712 at 161,836;
    Mid-Eastern Industries, Inc., ASBCA No. 51287, 98-2 BCA ~ 29,907 at 148,065; Cosmic
    Construction Co. v. United States, 
    697 F.2d 1389
    , 1390 (Fed. Cir. 1982)).
    Here, appellant admits that it filed its appeal well beyond the 90-day filing
    period (SOF ~ 6). The appeal language provided by the CO in the termination
    modification was neither incomplete nor misleading (SOF ~ 5). Accordingly, its
    argument regarding detrimental reliance is not persuasive. Thus, the appeal is
    untimely and we lack jurisdiction over it. TTF, LLC, 15-1BCA~35,883 at 175,434.
    CONCLUSION
    The appeal is dismissed with prejudice.
    Dated: 12 October 2016
    OWEN C. WILSON
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    4lt5;. . ·
    I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 60739, Appeal of Military
    Aircraft Parts, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 60739

Judges: Wilson

Filed Date: 10/12/2016

Precedential Status: Precedential

Modified Date: 10/25/2016