Capy Machine Shop, Inc. ( 2015 )


Menu:
  •               ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                  )
    )
    Capy Machine Shop, Inc.                      )      ASBCA No. 59085
    )
    Under Contract No. SPE4A6-13-M-S227          )
    APPEARANCE FOR THE APPELLANT:                       Mr. Salvatore Capacchione
    President
    APPEARANCES FOR THE GOVERNMENT:                     Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Edward R. Murray, Esq.
    Adrienne D. Bolton, Esq.
    Trial Attorneys
    DLA Aviation
    Richmond, VA
    OPINION BY ADMINISTRATIVE JUDGE TUNKS
    This is an appeal from the default termination of a contract to supply aircraft
    fairings. The parties have elected to submit the appeal on the record pursuant to Board
    Rule 11.
    FINDINGS OF FACT
    1. On 25 September 2013, Mr. John Vlachos, general manager of Capy
    Machine Shop, Inc. (Capy), accepted Order No. SPE4A6-13-M-S227 1 (hereinafter the
    contract) in the amount of$37,431.60. The contract required Capy to supply 18
    aircraft fairings 2 to the Defense Logistics Agency Aviation (DLA Aviation or
    government). (R4, tab 1 at 1, 5) The delivery date for the first article was 24 April
    2014 and the remaining 17 units were due on 18 February 2015 (R4, tab 2 at 2).
    2. The contract incorporated FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPL y
    AND SERVICE) (APR 1984), which provided, in part, as follows:
    1
    The contract resulted from a Request for Quotations issued by the government on
    16 August 2013 (R4, tabs 3, 4).
    2
    Statement of Facts~ 1 of our decision on the government's motion for summary
    judgment (Capy Machine Shop, Inc., ASBCA No. 59085, 14-1BCA~35,783),
    erroneously stated that the contract was for 27 splice fairings. The contract was
    for 18 fairings, one of which was a first article. (R4, tab 1)
    (a)(l) The Government may ... terminate this
    contract in whole or in part if the Contractor fails to--
    (i) Deliver the supplies or to perform the services
    within the time specified in this contract or any extension;
    (ii) Makes progress, so as to endanger performance
    of this contract ... ; or
    (iii) Perform any of the other provisions of this
    contract ....
    (R4, tab 1 at 23)
    3. On 18 October 2013, Banner Metalcraft, Inc., Capy's subcontractor, revised
    its quote to Capy adding a one-time tooling charge of $19 ,64 7 to its quotation (app.
    12 March 2015 hr., attachs. 1, 4).
    4. On 7 November 2013, Mr. Vlachos requested a no-cost cancellation of the
    contract, stating as follows:
    Please cancel the above contract at no cost to Capy
    Machine.
    Our forming vendor can't locate his tooling[.]
    (R4, tab 6)
    5. The contracting officer issued the following show cause notice to Capy on
    13 November 2013:
    Because you have indicated in an e-mail dated
    07 NOV 2013 citing an inability to locate tooling on
    contract SPE4A6-13-M-S227 within the time required by
    its terms and thereby requesting termination for
    convenience, the Government is considering terminating
    this contract under the provisions for default. Pending a
    final decision in this matter, it will be necessary to
    determine whether your failure to perforin arose from
    causes beyond your control and without your fault or
    negligence. Accordingly, you are given the opportunity to
    present, in writing, any facts bearing on the question to
    me ... within 10 days after receipt of this notice ....
    2
    If you have any questions, please contact
    Len DuPilka, Contract Administrator....
    (R4, tab 7)
    6. On 26 November 2013, Mr. Vlachos responded to the show cause notice as
    follows:
    The cost of new tooling is $19,647.00 total which wasn't
    included on the quote.
    That is the reason for asking to cancel this contract.
    (R4, tab 8)
    7. On 12 December 2013, Capy's contract was terminated for default pursuant
    to FAR 52.249-8:
    You are hereby notified that contract SPE4A6-13-M-S227
    is terminated for default effective immediately. Your right
    to proceed further with performance of this contract is
    terminated. The termination is based on your failure to
    perform in accordance with the terms and conditions of the
    contract. The terminated supplies may be procured against
    your account and you will be held liable for excess costs.
    (R4, tabs 9-10) How Capy had failed to perform was not explained.
    8. On 19 December 2013, Capy timely appealed the termination of its contract
    to this Board, where it was docketed as ASBCA No. 59085.
    9. The government moved for summary judgment on the ground of
    anticipatory repudiation on 4 April 2014. We denied the motion on 022 October 2014.
    Capy Machine Shop, 14-1 BCA ii 35,783.
    10. The parties have agreed to submit the appeal on the written record pursuant to
    Rule 11. Both parties submitted briefs. The government attached Mr. DuPilka's
    5 March 2015 declaration to its brief as exhibit 3. His declaration states, in part, as
    follows:
    Capy has a history of obtaining awards by quoting low
    prices, then requesting cancellation when they cannot
    perform the contract at that price. I have included as
    Exhibit 1 e-mails from Capy, all received after
    September 24, 2013, requesting cancellation after award on
    3
    13 orders in addition to the two contracts identified
    above ....
    When we cancel a contract, it has an adverse impact on
    DLA Aviation. A buyer and Contracting Officer must start
    the process all over again, by issuing a new solicitation,
    obtaining quotes, and making a new award. This takes
    time. Not only does it increase DLA Aviation's
    administrative costs, it also means we will take longer to
    get the parts to our military customers. In many instances
    it also leads to them going without the parts they need.
    The government also submitted answers to interrogatories propounded to Capy, in
    part, as follows:
    Interrogatory 4: In your January 9, 2014, Complaint you
    state "[We] cannot afford to complete this order." Explain
    what you meant by "cannot afford to complete this order."
    Answer: The cost of tooling exceeded the price of the
    contract therefore making the contract unconscionable.
    Interrogatory 5: Identify the date when you decided you
    could not afford to complete the order.
    Answer: On 11107/13.
    Interrogatory 7: At the time the contract was terminated
    for default, did you intend to fulfill the contract at the
    existing contract price?
    Answer: Due to the circumstance we were unable to fulfill
    the contract.
    4
    DECISION
    A termination for default is "a drastic sanction which should be imposed ... only for
    good grounds and on solid evidence." JD. Hedin Construction Co. v. United States,
    408 F .2d 424, 431 (Ct. Cl. 1969) (citations omitted). The government bears the burden of
    proving that the termination was justified. If the government establishes a prima facie
    case that the termination was proper, the burden of production-or going forward-shifts
    to the contractor. Lisbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 765 (Fed. Cir.
    1987).
    The government argues that its termination for default was justified because
    (1) Capy anticipatorily repudiated the contract; and (2) Capy's routine practice of bidding
    low and requesting no-cost cancellations when it cannot perform adversely impacts
    DLA's ability to supply needed parts to the field and increases its administrative costs.
    Capy argues that the termination was improper because its supplier increased the cost of
    tooling after award, making it unconscionable for Capy to perform at the contract price.
    The government argues that Capy anticipatorily repudiated the contract because it
    requested the CO to cancel the contract after award. We considered and rejected this
    argument in our decision on the government's motion for summary judgment. Capy
    Machine Shop, 14-1BCA~35,783 at 175,042. We held that Capy's request did not
    evince the "positive, definite, unconditional and unequivocal" refusal to perform required
    to prove anticipatory anticipation. While the government has submitted additional
    evidence, including Capy's answers to interrogatories, we are not convinced that such
    responses render its request for a no-cost termination to be a positive, definite,
    unconditional and unequivocal refusal to perform. Capy made a request to which the
    government never really responded, except to terminate for default.
    The government also argues that the termination should be upheld on the basis of
    public policy. In its brief, the government explains as follows:
    Capy routinely asks the Government to cancel its contracts
    after award because it can no longer afford to perform
    them or cannot obtain the part it originally quoted ....
    [T]his ... negatively impacts DLA Aviation.... DLA
    Aviation must essentially start over from scratch and issue
    a new solicitation for the item, review quotes, and make a
    new award, then wait for a new delivery period to pass ....
    Certainly the Government could wait until delivery was
    due for each of Capy's contracts [and] then terminate for
    default...[b]ut that would put the Government even further
    behind in obtaining the parts it needs and hamper its ability
    to effectively prioritize its procurement workload.
    (Gov't br. at 8-9)
    5
    The government has not pointed to any authority justifying a termination for
    default under one contract based upon performance under other contracts. Nor are we
    aware of any. This argument is unpersuasive.
    Federal Rules of Evidence (FRE) 406 3 permits the introduction of evidence of
    routine practices of an organization to prove that on a particular occasion the organization
    acted in accordance with the routine practice. See generally Advisory Committee Notes
    to 1972 Proposed Rules; Handbook of Federal Evidence, 7th ed., vol. 3, § 406; Federal
    Rules of Evidence Manual, 8th ed., vol. 2, § 406. While perhaps the evidence of routine
    practice is sufficient to prove that appellant frequently requests that contracts be
    cancelled, it is not sufficient to prove that it is Capy's routine practice to bid or quote
    with no intention of performing. Indeed, the evidence in this appeal is that pre-existing
    tooling could not be found and would have to be produced at a cost of approximately
    50% of the contract price-a fact unknown to Capy at the time of quotation or award.
    The government has not pointed to any authority justifying a termination for
    default under one contract based upon a history of performance under other contracts.
    Nor are we aware of any. This argument is not persuasive. It is apparent that the
    government is frustrated by the number of times Capy has asked for the cancellation of
    contracts and considers that Capy has a routine practice of receiving awards it does not
    intend to fulfill. That concern is one that perhaps is best addressed in the process of the
    award of contracts, not the termination of contracts once awarded.
    Neither of the grounds relied on by the government justify the termination for
    default and we have no evidence regarding whether a termination for failure to make
    progress was justified.
    The appeal is sustained. The termination for default is converted to a termination
    for the convenience of the government.
    Dated: 8 October 2015
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    3
    The Board uses the FRE as a guide. Board Rule IO(c) (2014).
    6
    I concur                                        I concur
    M
    RICHARD SHACKLEFORD
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 59085, Appeal of Capy
    Machine Shop, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    7
    

Document Info

Docket Number: ASBCA No. 59085

Judges: Tunks

Filed Date: 10/8/2015

Precedential Status: Precedential

Modified Date: 10/19/2015