American Boys Construction Company ( 2017 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    American Boys Construction Company             )      ASBCA No. 60515
    )
    Under Contract No. W56SGK-16-C-0013            )
    APPEARANCE FOR THE APPELLANT:                         Mr. Nadeem Alamyar
    President
    APPEARANCES FOR THE GOVERNMENT:                       Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ Bruce L. Mayeaux, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE PROUTY
    This appeal is about the compensation due to appellant, American Boys
    Construction Company (ABC), for the government's terminating the above-captioned
    contract (the contract) for convenience. ABC alleges 1 that in the nine days between
    contract award and a government stop-work order, it incurred $67,793 in compensable
    costs under the contract- primarily for supplies that it obtained in preparation for
    contract performance, but also for stand-by labor costs (app. hr. at 2; app. reply br.;
    see also R4, tab 10 at 4). 2 Because we find that ABC's purchase of the materials for
    which it now seeks compensation was unreasonably premature and that the amounts
    sought for stand-by labor costs have not been substantiated, we deny this appeal,
    although we would have been open to some stand-by labor costs if only ABC had
    presented evidence of such costs.
    1
    After initially requesting that this appeal proceed via a hearing, appellant ultimately
    elected to proceed under the auspices of Board Rule 11, in which the appeal is
    decided exclusively upon the written record.
    2
    ABC's briefs do not specify the amount of money sought in this appeal, nor does its
    complaint or any other filing made with the Board, except that its reply brief
    stated that it was seeking the amount requested by the termination settlement
    proposal it submitted to the contracting officer (app. reply hr. at 4). That
    amount was $67,793 (R4, tab 10 at 4).
    FINDINGS OF FACT
    On 14 February 2016, the government's Regional Contracting Center- Capital
    in Kabul, Afghanistan (RCC), awarded the contract at issue in this appeal to ABC (R4,
    tab 1 at 1-2). This firm-fixed-price contract in the amount of$120,801 ($113,301 for
    the actual performance; $7,500 (estimated) for Defense Base Act Insurance) was for
    the installation of a "sniper screen" at a base in Kabul (id. at 3). The contract's 60-day
    period of performance was set to begin on 28 February 2016 and conclude on 29 April
    2016. ABC was required to commence work within 5 days of receiving the notice to
    proceed from the government. (Id. at 6)
    On 17 February 2016, ABC's project manager, Mr. Walusimbi John, emailed
    Sergeant First Class (SFC) Brandon Cooper, the contracting specialist assigned to
    provide administrative support on the contract (app. supp. R4, tab 1 at 2)3 • Mr. John
    said that he had "attached [a] list of suppliers for the project." SFC Cooper responded
    by informing Mr. John that he was looking forward to working with him again, but that
    the email included no attachment (id. at 3). The record does not indicate whether ABC
    responded with a re-sent attachment, and, given the email sent by ABC to SFC Cooper
    three days later (discussed below), we think it unlikely that it did.
    On 18 February 2016, four days after contract award, the government held a
    preconstruction conference as provided for by the contract (see R4, tab 1 at 15
    (contractual provision incorporating Federal Acquisition Regulation (FAR) 52.236-26,
    PRECONSTRUCTION CONFERENCE (FEB 1995) into the contract), tab 2 (signed
    memorandum detailing conference)). According to a memorandum describing the
    conference that was signed by both government and ABC representatives, among
    other matters discussed, ABC was informed of the contractual requirement to tender
    material submittals to the government on a specified form, the Air Force Form 3000
    (R4, tab 2 at 2-3). Government representatives who attended this meeting included
    Major (MAJ) Joseph Cederstrom (the contracting officer (CO)), SFC Cooper,
    and First Lieutenant (lLT) David Morin (the CO's technical representative) (R4,
    tabs 14-16). SFC Cooper provided written testimony that, although he did not
    specifically recall the discussion held during this meeting, the standard practice at all
    such meetings he attended in Afghanistan was to follow the agenda set forth in the
    3
    ABC submitted to the Board, on 14 February 2017, a number of documents to act as
    its supplement to the Rule 4 file. After the first page, entitled, "Supplement,"
    the pages are sequentially numbered through page 6, followed by a two-page
    declaration by ABC's president, Mr. Nadeem Alamyar. There were no tabs
    delimiting any groups of the documents, but we will consider all of the
    documents up to the declaration to be in tab 1 of ABC's supplement to the
    Rule 4 file, with Mr. Alamyar's declaration to constitute tab 2 to ABC's
    supplement to the Rule 4 file.
    2
    memorandum discussed above. This included informing the contractor that it was not
    to begin work prior to a notice to proceed issued by the CO and that materials needed
    to be approved by the CO via the Air Force Form 3000 "prior to installation" (R4,
    tab 15 at 2).
    At some point around the time of the preconstruction meeting, government
    contracting personnel were alerted to the possibility that ABC might be the subject of
    security concerns that would preclude it from being permitted access to the base where
    the sniper screen was to be installed. lLT Morin's testimony suggests that this
    knowledge came about just before this meeting (see R4, tab 16 at 3); SFC Cooper's
    testimony implies that those concerns arose just after that meeting (R4, tab 15 at 2-3 ).
    The exact timing of when contracting officials obtained this knowledge need not be
    resolved here.
    Two days after the preconstruction meeting, on 20 February 2016, ABC's
    project manager, Mr. John, emailed the material submittals to SFC Cooper with an
    attached Air Force Form 3000. Mr. John copied MAJ Cederstrom and lLT Morin on
    the message. (R4, tab 3) MAJ Cederstrom, the CO, testified that he never approved
    ABC's submittals (R4, tab 14 at 4). SFC Cooper and lLT Morin also deny knowledge
    of any approval of the material submittals (R4, tab 15 at 3, tab 16 at 4-5).
    ABC alleges, in Mr. Alamyar's declaration, that Mr. John spoke with
    lLT Morin on 14 February 2016 about the materials needed for the project and that,
    due to their scarcity, lLT Morin had given him the "green light" to purchase these
    materials at that time (R4, tab 12 at 3). We find that this allegation is, more likely than
    not, incorrect, and conclude that no such approval was ever given. Mr. Alamyar's
    declaration regarding Mr. John's discussions with lLT Morin is, of course,
    double hearsay. Although we do not have any rule preventing the consideration
    of hearsay, see Board Rule 1 l(d) (permitting the weight of the evidence to rest
    within the discretion of the Board), the further the written testimony strays from
    the first-hand knowledge of the declarant, the less persuasive it becomes. In contrast,
    lLT Morin specifically denied engaging in any such conversation in his declaration
    (R4, tab 16 at 4). This denial by lLT Morin is made particularly persuasive by its
    consistency with his usual practice of disclaiming his authority to make contractual
    decisions that were reserved for the CO. It is further buttressed by the evidence that,
    contrary to ABC's allegations, the materials needed for the job did not appear to be
    scarce (id. at 4-5).
    In any event, shortly after the preconstruction meeting, the government's
    security concerns about ABC ripened, and, on 23 February 2016, SFC Cooper emailed
    a stop-work order to ABC on behalf of the CO (R4, tabs 5, 14 at 4, tab 15 at 3). The
    stop-work order directed ABC to suspend all work on the contract and to cease its
    3
    efforts to obtain Defense Base Act insurance or any other materials needed for the
    performance of the contract (R4, tab 5).
    ABC responded to the stop-work order by informing the government, in an
    email sent by Mr. John the same day, that it had already purchased the materials
    (R4, tab 8 at 1). As the email explained, "that was the reason [I] sent you the list of
    Suppliers [a] few days ago" (id.). 4
    On 25 February 2016, the installation commander, in fact, barred ABC
    employees from access to the New Kabul Compound (R4, tab 6). On 13 March 2016
    MAJ Cederstrom, the CO, sent an email to ABC. He attached a letter dated
    26 February 2016 that informed ABC that the contract had been terminated for the
    convenience of the government, effective 28 February 2016 (R4, tab 9). This
    termination for convenience letter stated that the termination was being effected
    pursuant to the terms ofF AR clause 52.249-2, Alt I (id. at 2). 5 The letter further
    directed ABC to submit a termination settlement proposal in accordance with FAR
    52.249-2, Alt I(e) (id.). The letter elaborated about the contents of the settlement
    proposal, stating that, "Materials already purchased specifically for the performance of
    this contract, and any additional costs you can demonstrate stemming directly from
    this termination must be accompanied by supporting documentation to substantiate the
    costs you are requesting" (id. at 4).
    On 21 March 2016, ABC submitted a timely termination settlement proposal to
    the CO (R4, tab 10). The proposal was short on narrative description, but requested a
    total of$67,793 in compensation: $55,893 for supplies; $11,900 for labor costs
    "during stand by" (id. at 4). The proposal also included three pages of what appeared
    to be invoices for materials, written (apparently) in Pashto, but with numbers that
    summed to the $55,893 sought for supplies (id. at 5-7). The proposal included no
    evidence of payment for the labor costs, but did specify that it could be broken down
    as $3,500 for the project manager; $2,000 for the construction manager; $1,000 for
    each of the two "structure engineers"; $1,000 each for two "fence engineers"; and
    $300 for each of eight laborers (id. at 4).
    On 25 March 2016, MAJ Cederstrom issued to ABC a "Settlement by
    Determination .. .in accordance with [FAR] 49.109-7" (R4, tab 11 at 2).
    MAJ Cederstrom's determination was that no costs should be paid to ABC. In
    particular, he wrote that ABC "was aware that the Notice to Proceed was not issued
    4
    This explanation provides further support to our finding that the government never
    approved the purchase of the materials earlier. Had it done so, we would expect
    that Mr. John would have stated as much in this email.
    5
    This clause, dated September 1996, governing the termination of firm-fixed-price
    contracts, is incorporated into the contract by reference (R4, tab 1 at 15).
    4
    on this contract [and the] contractor knew that it was prohibited from incurring any
    cost prior to the Notice to Proceed being issued." (Id.)
    The CO's Determination letter did not inform ABC of any appeal rights
    (see R4, tab 10), but the referenced FAR provision, 49.109-7, provides that such a
    determination is appealable in paragraph (f). On 28 March 2016, ABC submitted its
    timely appeal to this Board.
    From the time of the contract termination to the present, ABC has not,
    apparently sold the materials to other suppliers (app. reply br. at 2-3). 6
    DECISION
    The "entitlement to compensation for costs in a termination for convenience is
    determined by those applicable clauses of the FAR that are incorporated into the
    contract at issue." Rex Systems, Inc., ASBCA No. 59624, 16-1 BCA ~ 36,350 at
    177,217. Relevant to the costs sought by ABC here, the applicable FAR clause in the
    contract, FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
    (FIXED-PRICE), ALTERNA TE I (SEP 1996), provides in paragraph (g)( 1)(i) for
    government payment to the terminated contractor for "the cost of this work" that
    was performed prior to contract termination. This comports with the generalized
    notion that fixed-price contracts terminated for convenience under FAR Part 49
    (as this contract was) are "essentially converted into cost-reimbursement contracts."
    Dellew Corp., ASBCA No. 58538, 15-1BCA~35,975 at 175,783-84. The purpose of
    termination for convenience clauses is '"to make the contractor whole for the costs
    incurred in connection with the terminated work." SWR, Inc., ASBCA No. 56708,
    15-1BCA~35,832 at 175,223 (citations omitted). These termination costs,
    however, must be reasonable, Pro-Built Construction Firm, ASBCA No. 59278,
    17-1BCA~36,774, and they must be proved by ABC. Lisbon Contractors, Inc. v.
    United States, 
    828 F.2d 759
    , 767 (Fed. Cir. 1987).
    I.     ABC's Materials Costs Would Not Have Been Incurred by a Reasonable
    Contractor
    The CO advanced the argument, in his final decision, that costs incurred prior
    to the notice to proceed are not compensable (R4, tab 11 at 2). Perhaps recognizing
    this argument to be flawed (the government has identified no clause in the contract that
    precludes ABC from beginning preparatory work prior to receipt of the notice to
    proceed; see also Pro-Built, 17-1 BCA ~ 36, 77 4 (recovery of costs incurred prior to
    6   No direct evidence of this is contained in the Rule 4 file, its supplements, or any
    other evidence provided to the Board, but, under the circumstances, we will
    credit this admission made in appellant's filing.
    5
    notice to proceed)), the government now rests its defense upon the notion that it cannot
    be required to pay for materials obtained before it approved ABC's material submittals
    (gov't br. at 12-13). To the extent that the government is making the argument that, in
    the circumstances presented here, it was unreasonable to purchase the materials prior
    to approval of the submittals, its argument carries the day.
    Under the circumstances presented here, we are not persuaded that ABC's
    actions in incurring the alleged costs for materials were reasonable. We do not go so
    far as to hold that a contractor may not, in any circumstances, be compensated for
    materials purchased before the government's approval of material submissions. Here
    we find only that it was unreasonable for the cqntractor to have made a purchase of
    materials prior to the government's agreement that this would be acceptable. This is
    true here, especially given the fact that the notice to proceed had not yet issued from
    the CO and, thus, ABC was not yet under the time pressure that such a notice would
    impose.
    ABC does not dispute the government's argument that its failure to await the
    government's approval of its submittals would normally preclude recovery. Instead, it
    alleges that it did receive such approval and, in fact, needed to obtain such an early
    approval because of material scarcity (app. reply br. at 2). As noted above, however,
    we find that the record supports contrary factual findings. ABC has not met its
    evidentiary burden of proving the material costs were reasonable; thus, we deny this
    portion of ABC's appeal.
    II.    ABC has Not Proved its Stand-By Labor Costs
    We have previously held that reasonable stand-by labor costs incurred prior
    to the notice to proceed may be recoverable in a termination for convenience. See
    Pro-Built, 17-1BCA~36,774. Nevertheless, we require proof of such costs, see SWR,
    15-1 BCA ~ 35,832 at 175,225, and ABC has simply not provided such evidence.
    This is unfortunate, because we find it highly likely that ABC incurred some
    costs (though perhaps not all that it claimed) prior to the termination, but ABC
    declined to provide any evidence - either to the CO or to us - supporting the amount
    that it requested. We simply may not award a figure based upon speculation. Such
    work-arounds as the "jury verdict" method are unavailable to us when the contractor's
    failure to produce substantiation of damages is not due to a "'justifiable inability" to
    produce such evidence, but is caused by a lack of effort by the contractor. See Dawco
    Constr. Co. v. United States, 
    930 F.2d 872
    , 881 (Fed. Cir. 1991), overruled on other
    grounds by Rejlectone, Inc. v. Dalton, 
    60 F.3d 1572
    (Fed. Cir. 1995) (en bane). Thus,
    we award no damages to ABC for its stand-by labor costs.
    6
    I
    CONCLUSION
    For the reasons stated herein, ABC's appeal is denied.
    Dated: 13 September 201 7
    J. REID PROUTY
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    ~~
    Administrative Judge
    Acting Chairman                                   Armed Services Board
    Armed Services Board                              of Contract Appeals
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 60515, Appeal of
    American Boys Construction Company, rendered in conformance with the Board's
    Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    7
    