Buck Town Contractors & Co. ( 2018 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Buck Town Contractors & Co.                   )      
    ASBCA No. 60939
    )
    Under Contract No. W912P8-09-D-0052           )
    APPEARANCES FOR THE APPELLANT:                       W. Lee Kohler, Esq.
    Douglas A. Kewley, Esq.
    Thomas F. Gardner, Esq.
    Gardner & Kewley, APLC
    Metairie, LA
    APPEARANCES FOR THE GOVERNMENT:                      Thomas J. Warren, Esq.
    Acting Engineer Chief Trial Attorney
    William G. Meiners, Esq.
    Stephen S. Bland, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, New Orleans
    OPINION BY ADMINISTRATIVE JUDGED' ALESSANDRIS
    ON APPELLANT'S MOTION FOR PARTIAL SUMMARY JUDGMENT
    The United States Army Corps of Engineers (Corps or government) contracted with
    Buck Town Contractors & Co. (Buck Town) to reconstruct a hurricane protection levee in
    St. Charles Parish, Louisiana. Buck Town subcontracted the work in question to Circle
    LLC (Circle). The contract required placement of a layer of geotextile material at the base
    of the levee, and that the geotextile be provided in continuous machine-direction lengths
    without seams, with all seams and overlaps to be installed perpendicular to the centerline of
    the levee. For reasons of efficiency related to the length of the rolls of geotextile material
    used on the project, every third row of geotextile material on the levee installed by Circle
    consisted of two strips of material joined by an overlap running parallel to the centerline of
    the levee. The Corps objected to this method only after one segment of the levee was
    complete (and the geotextile buried) and another segment had a large part of the geotextile
    installed. Buck Town was required to remedy this situation by the Corps, leading to the
    dispute now before us.
    Buck Town moves for partial summary judgment on an issue of contract
    interpretation, seeking a holding that the contract permitted the use of partial rows of
    geotextile. We deny Buck Town's motion. 1 We find that the plain language of the contract
    does not permit the use of overlaps parallel to the centerline of the levee. 2
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    On 28 September 2009, the Corps awarded to Buck Town under Multiple Award
    Task Order Contract No. W9I2P8-09-D-0052 (the contract), Task Order No. 0004, for
    construction of Reach IA, part of a hurricane protection levee in St. Charles Parish,
    Louisiana (R4, tab 2). Buck Town subcontracted work, including, geotextile placement, to
    Circle (Statement of Genuine Issues (SGI) ii 2). The task order for Reach IA required a
    layer of geotextile material covering an area approximately I20-feet wide by 2,900-feet
    long (R4, tab 79 at I 890).
    The contract's specification for reinforcement geotextile provided, in relevant part:
    .3. I . I Procedure
    The geotextile shall be installed to the lines and grades
    as shown on the contract drawings. Objects, or debris
    that are capable of damaging the geotextile shall be
    removed before the geotextile is placed. At the time of
    installation, the geotextile shall be rejected if it has
    defects, rips, holes, deterioration, or damage which was
    incurred during manufacture, transportation, or storage.
    The geotextile shall be installed with the seams facing
    up to allow for visual inspection. All seams and
    overlaps shall be placed perpendicular to the centerline
    of the levee. Fill shall not be placed on the geotextile
    until the seams or overlaps are within 5 degrees of being
    perpendicular to the levee centerline and all sags and
    wrinkles are removed from the geotextile. The
    Contractor shall take precautions to avoid damaging the
    geotextile during placement.
    1
    The present motion concerns only 
    ASBCA No. 60939
    , which is consolidated with
    ASBCA Nos. 60940 and 6094 I. Buck Town initially filed a second motion for
    summary judgment in 
    ASBCA No. 6094
     I, regarding a dispute as to whether it was
    required to replace certain geotextile based upon testing of the fabric's tensile
    strength. Buck Town withdrew that motion on 2 October 20I 7.
    2
    The Corps did not cross-move for summary judgment, so we deny Buck Town's motion,
    but do not enter summary judgment in favor of the Corps.
    2
    3.3.1 Seams
    Geotextile panels shall be sewn along the selvedged
    edges so that seams run parallel with the machine
    direction to produce geotextile pieces that are wider than
    the weaving machine produces. Geotextiles shall be
    supplied in continuous machine direction lengths
    without seams. All seams shall be made with thread that
    meets the requirements for plastic yam, as specified in
    paragraph GEOTEXTILE REQUIREMENTS. The
    Contractor is responsible for choosing the sewing
    machine, thread, stitch type, number of stitches per inch
    and any other particulars that are required to achieve the
    seam strength that is specified in Table 1.
    3 .3 .1. 1 Damaged Seams
    Rips in seams that occur as a result of placement, and
    which are less than two feet from the end of the
    geotextile panel do not require repair. Rips that are
    longer than two feet, or of any length that occur at
    locations that are more than two feet from the end of the
    panel, shall be repaired by placing a single layer of
    geotextile of the same strength to cover the entire
    affected seam. The piece of geotextile shall extend a
    minimum of five feet on each side of the damaged seam.
    3.3 .2 Overlaps
    Overlaps may be used at [points of intersection 3] or to
    join pieces of geotextile that become too heavy to handle
    with construction machinery. All overlaps shall run in
    the same direction as the seams. A minimum of two feet
    is required at each overlap.
    (R4, tab 5 at 110-12) In December 2009, Buck Town submitted to the Corps a geotextile
    fabric placement plan with a plan view showing overlapping, full length panels installed
    perpendicular to the centerline of the levee (R4, tab 6).
    In January 2010, Circle placed the geotextile material in Reach IA of the levee (R4,
    tabs 8, 9). Circle used 15' x 300' rolls of geotextile material for the project (R4, tab 11 ).
    To minimize waste from the 300' rolls of geotextile, Circle typically placed two 120',
    3
    A point of intersection is where the centerline of the levee changes direction.
    3
    full-length panels, and one 60', partial-length panel, from each roll. In rows that used two
    partial-length panels, Circle joined the panels with a 2' overlap. (R4, tab 2 at 20; SGI ,-r 6)
    To prevent ultraviolet radiation damage, each day Circle would place the first layer of fill
    over the newly-placed geotextile, covering the overlaps from view (R4, tab 8).
    Several representatives of the Corps, including quality assurance inspectors, were on
    site at various times while Circle placed the geotextile material in Reach IA (R4, tab 8; app.
    supp. R4, tab 33). Buck Town's quality control reports, submitted to the Corps, included the
    statement that "2' overlapping was applied at every ?djoining new roll of geotextile" (R4,
    tab 8; app. supp. R4, tabs 9, 11, 13, 21, 23, 25, 27, 29, 31, 33, 35). The Corps' quality
    assurance inspectors did not raise any issues with Circle's geotextile placement (R4, tab 9;
    app. supp. R4, tabs 10, 12, 14, 22, 24, 26, 28, 30, 32, 34, 36). During February and
    March, 2010, Circle continued to place embankment fill over the geotextile (comp I. ,-i 121,
    answer ,-i 121). By 24 March 2010, Circle had placed roughly seven feet of embankment fill
    along the entire levee crest covering the geotextile (app. supp. R4, tab 129).
    Under a different task order, Task Order No. 0005, Buck Town and Circle constructed
    a second reach of the same levee, referred to as Reach 2A (app. supp. R4, tab 5). On I 0
    March 2010, during the Reach 2A Geotextile Preparatory Phase Meeting, Buck Town and
    Circle discussed with Mr. Otho Barnes, P.E., a Corps engineer, that, the "material for two (2)
    rows will be installed in complete/whole 90' sections. Every third row/panel an overlap will
    be required at the parallel seam/lap." (App. supp. R4, tab 47) 4 From 16-24 March 2010,
    Circle placed roughly 40 percent of the geotextile on the Reach 2A project, including some
    geotextile rows with overlaps joining two partial-length panels (compl. ,-i,-i 143, 148, answer
    ,-r,-r 143, 148).
    During a 24 March 2010 site visit, Mr. Barnes informed Circle that "reinforcement
    geotextile may be installed incorrectly, and that no seam splicing should occur, when being
    placed" (app. supp. R4, tab 58). An unsigned copy of the Corps' 24 March 2010 quality
    assurance report5 states:
    Circle ... had been installing the fabric where when the end of
    the, usually 300' roll of fabric came, the next roll was
    overlapped 2' with a seam running parallel to levee centerline
    and the installing of fabric continued. What should have
    occurred is that no pieces or panels of fabric should have been
    installed if they were less than 90' wide. That's the distance
    across the bottom of the degraded levee. If done in that
    manner, no parallel to centerline seams would have occurred .
    4
    .       Reach 2A was 90' across whereas Reach IA was 120'.
    5
    A signed copy of the 24 March 2010 quality assurance report, apparently provided
    contemporaneously to Circle, does not contain the cited language (app. supp. R4,
    tab 57).
    4
    (R4, tab I I) Circle removed and replaced the geotextile that had been incorrectly placed
    on Reach 2A (R4, tab 2 at 5). On 25 March 20 I 0, the Corps issued Contract Deficiency
    Notice No. I on the Reach IA Project contending that Buck Town was in "violation of
    specification section 3 I 05 I 9 .05 I 2, paragraph 3. I. I by installing reinforcement geotextile
    overlaps parallel to the centerline of the levee" (R4, tab I2).
    On I9 November 20IO, the administrative contracting officer,Mr. Jeffrey Falati,
    ordered Buck Town to reconstruct the Reach IA levee (R4, tab 33). On 28 December
    2010, Buck Town submitted a Notice of Claim for Constructive Change. On 24 January
    20I I, Buck Town submitted a Request for Equitable Adjustment. On 7 February 20I I, the
    contracting officer rejected Buck Town's Request for Equitable Adjustment. (R4, tab 2 at
    13) Buck Town submitted a claim on 22 March 20I6 that was denied by the Corps'
    contracting officer on 20 September 20I6 (R4, tab 2 at 18, 30). This appeal followed.
    DECISION
    Board Rule 7(c)(2) provides that we look to FED. R. CIV. P. 56 for guidance in
    deciding motions for summary judgment. We will grant summary judgment only ifthere is
    no genuine issue as to any material fact, and the moving party is entitled to judgment as a
    matter oflaw. Celotex Corp. v. Catrett, 477 U.S. 3I7, 322 (1986). A material fact is one
    that may affect the outcome of the decision. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248-49 (I986). The moving party bears the burden of establishing the absence of any
    genuine issue of material fact, and all significant doubt over factual issues must be resolved
    in favor of the party opposing summary judgment. Mingus Constructors, Inc. v. United
    States, 
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987). Once the moving party has met its
    burden of establishing the absence of disputed material facts, then the non-moving party
    must set forth specific facts, not conclusory statements or bare assertions, to defeat the
    motion. Pure Gold, Inc. v. Syntex (US.A.), Inc., 
    739 F.2d 624
    , 626-27 (Fed. Cir. 1984).
    Buck Town asserts that the plain meaning of the contract permitted it to place the
    geotextile across the levee with non-full-length pieces so long as the material was properly
    overlapped. Buck Town's interpretation relies upon its asserted "plain meaning" of the
    term "placed" as "to put in a particular position." Thus, Buck Town argues that it satisfied
    the contractual requirement of "placing" the material perpendicular to the centerline of the
    levee because it unrolled the geotextile in a direction that was perpendicular to the levee.
    (App. br. at l I-15) The government asserts that the plain meaning of the contract prohibits
    the use of partial-length pieces of geotextile because it creates an overlap that is not
    perpendicular to the centerline of the levee (gov't br. at 4-5).
    Contract interpretation is a matter of law. See, e.g., ThinkQ, Inc., 
    ASBCA No. 57732
    , 13 BCA if 35,221 at I 72,825. In interpreting a contract, we begin with the plain
    language of the contract. See, e.g., Banknote Corp. ofAmerica, Inc. v. United States, 
    365 F.3d 1345
    , 1353 (Fed. Cir. 2004). An additional canon of contract interpretation is that the
    5
    contract should be read as a whole, harmonizing and giving meaning to all provisions.
    ThinkQ, 13 BCA ~ 35,221 at 172,825 (citing NVT Technologies, Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004)).
    Here, the geotextile specifications clearly provide that "[a]ll seams and overlaps shall
    be placed perpendicular to the centerline of the levee" (R4, tab 5, ~ 3.1.1). Buck Town, in
    arguing the plain meaning of the provisions states that "[i]n lieu of utilizing seams to widen
    the material, as long as the machine-direction axis of the material was oriented
    perpendicular to the centerline of the levee, the Contract allowed Circle to 'join pieces of
    geotextile' by using 2' overlaps of adjacent panels" (app. br. at 14). As an initial point, we
    disagree with Buck Town's proffered interpretation of the contract as permitting overlaps
    parallel to the centerline of the levee so long as the geotextile was unrolled in a direction
    perpendicular to the centerline of the levee. Here Buck Town cites the Oxford dictionary
    definition of the word "placed" as "put in a particular position," supposedly supporting its
    interpretation of the contract that "placed" only governed the means by which it was
    installed (app. br. at 13). We read this definition of placed to indicate where something was
    put, not the direction in which it was installed. This is consistent with the full dictionary
    definition: "put in a particular position: a newspaper had been placed beside my plate."
    NEW OXFORD AMERICAN DICTIONARY (3d ed. 2010). In addition, Buck Town's proffered
    interpretation directly conflicts with~ 3.3.1 "Seams" which provides that "[g]eotextiles
    shall be supplied in continuous machine direction lengths without seams" (R4, tab 5 at 112).
    Thus, we find that the plain meaning of the contract does not support Buck Town's
    interpretation.
    Buck Town additionally argues that the Corps' interpretation of the geotextile
    specifications is internally inconsistent because each overlap is two-dimensional. Thus,
    Buck Town argues, each overlap consists of an overlap perpendicular to the direction of the
    levee centerline and an overlap that is parallel to the levee centerline. (App. br. at 18-21 )6
    However, it is Buck Town's interpretation that creates internal inconsistency. The
    geotextile provisions provide that "Geotextile panels shall be sewn along the selvedgedr 71
    edges so that seams run parallel with the machine direction to produce geotextile pieces
    that are wider than the weaving machine produces. Geotextiles shall be supplied in
    continuous machine direction lengths without seams." (R4, tab 5 at 112) Overlaps can be
    substituted for seams to join pieces of geotextile that become too heavy to handle with
    construction equipment, and must run in the same direction as seams (id.). Thus, the
    "seam" that can be replaced with an overlap is the long seam running in the machine
    direction, not the cut edge across the machine width.
    6
    This interpretation would make the requirement for perpendicular overlapping to be
    meaningless because all such two-dimensional overlaps would contain a
    perpendicular component.
    7
    Selvedge is defined as "an edge produced on woven fabric during manufacture that
    prevents it from unraveling." NEW OXFORD AMERICAN DICTIONARY (3d ed. 2010).
    6
    Buck Town's proffered interpretation is internally inconsistent with the contract
    provisions providing that all seams must be perpendicular to the centerline of the levee and
    that the geotextiles be supplied in "continuous machine direction lengths without seams"
    (R4, tab 5 at 112). Buck Town attempts to avoid the contract language requiring that
    seams be perpendicular to the centerline by arguing that the language applies to seams that
    make the geotextile wider and not other seams (app. reply at 22). Even assuming that Buck
    Town's interpretation is correct, its proposed interpretation still conflicts with the provision
    requiring that the geotextile be supplied in continuous machine direction lengths without
    seams. Buck Town additionally argues that the material was "supplied" in continuous
    lengths because it was delivered from the manufacturer to the job site in continuous
    machine direction without seams (id. at 22-23). The term "supply" means to "make
    (something needed or wanted) available to someone; provide." NEW OXFORD AMERICAN
    DICTIONARY (3d ed. 2010). Here, the geotextile specifications concern the relationship
    between the Corps and Buck Town. Thus, the Corps is the "someone" in the dictionary
    definition that has received the goods. Buck Town did not "supply" continuous rows of
    geotextile without seams to the Corps.
    Buck Town also argues that the Corps' interpretation requires the Board to read into
    the contract language that does not exist. Buck Town asserts that the geotextile
    specifications and contract drawings do not contain any expressed instructions requiring
    geotextile rows "having a continuous, machine-direction length sufficient to span the entire
    distance from the flood side placement limit to the protected side limit," "[p]rohibiting the
    contractor from joining together two less-than-full-length panels of geotextile," or
    prohibiting overlaps parallel to the centerline (app. br. at 22-23). Contrary to Buck Town's
    argument, the geotextile specifications specifically require that "[g]eotextiles shall be
    supplied in continuous machine direction lengths without seams" (R4, tab 5 at 112).
    Moreover, the specification's requirement that "[a]ll seams and overlaps shall be placed
    perpendicular to the centerline of the levee" necessarily prohibits seams and overlaps
    placed parallel to the centerline of the levee. The fact that the Corps could have included
    more explicit language that might have prevented this dispute is of no moment. Further,
    Buck Town's citation to A.A. Conte & Son, Inc., ENG BCA Nos. 6104, 6227, 96-2 BCA
    ii 28,581, is not persuasive because that appeal involved a contract where the Army Corps
    of Engineers Board of Contract Appeals agreed with the appellant's interpretation of the
    plain language of the contract. Here, we find that the contractual language does not
    support the appellant's interpretation.
    Having found that the plain meaning of the contract is not consistent with Buck
    Town's proposed interpretation, we decline to consider Buck Town's extrinsic evidence
    regarding the parties' pre-dispute conduct (app. br. at 25-30). See, e.g., City of Tacoma,
    Dept. of Public Utilities v. United States, 
    31 F.3d 1130
    , 1134 (Fed. Cir. 1994); Banknote
    Corp., 
    365 F.3d at 1353
    . To the extent such a claim is properly before the Board, Buck
    Town may choose to present evidence of pre-dispute conduct at a hearing in support of the
    waiver argument it belatedly raises in its reply brief (app. reply at 38-47). Arguments
    raised for the first time in a reply brief are waived. Raytheon Company, Space & Airborne
    7
    Systems, 
    ASBCA No. 57801
     et al., 15-1BCA~36,024 at 175,960 n.3; see also Systems
    Management and Research Technologies Corp. v. Dept. of Energy, CBCA No. 4068, 16-1
    BCA ~ 36,333 at 177,138 n.7 (citingBannum, Inc. v. United States, 
    121 Fed. Cl. 543
    , 552
    n.6 (2015)). For the same reason, we do not consider Buck Town's argument that the "real
    issue" is the Corps' undisclosed engineering considerations (app. reply at 1-10).
    Additionally, as we do not find the contract to be ambiguous, Buck Town's latent
    ambiguity argument is inapplicable. City of Tacoma, 
    31 F.3d at 1134
    .
    CONCLUSION
    For the reasons stated above, Buck Town's motion for partial summary judgment is
    denied.
    Dated: 11 January 2018
    DA YID D' ALESSANDRIS
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    _____ .-
    I concur                                         I concur
    RICHARD SHACKLEFORD                               J. REID PROUTY
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in 
    ASBCA No. 60939
    , Appeal of Buck Town
    Contractors & Co., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREYD. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    l
    t
    8