Northrop Grumman Corporation ( 2018 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Northrop Grumman Corporation                   )     
    ASBCA No. 60190
    )
    Under Contract No. N68936-05-C-0059            )
    APPEARANCES FOR THE APPELLANT:                       Terry L. Albertson, Esq.
    Stephen J. McBrady, Esq.
    Crowell & Moring LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                      E. Michael Chiaparas, Esq.
    DCMA Chief Trial Attorney
    Robert L. Duecaster, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Chantilly, VA
    OPINION BY ADMINISTRATIVE JUDGE PEACOCK
    ON THE GOVERNMENT'S MOTION FOR RECONSIDERATION
    The government has moved for reconsideration of our opinion in Northrop
    Grumman Corporation, 
    ASBCA No. 60190
    , 17-1 BCA ~ 36,800 (hereinafter referenced
    as "quantum decision"). 1 In its Motion for Reconsideration (Motion), the government
    continues to maintain that Northrop Grumman Corporation (NGC) should have incurred,
    and in fact was required "by operation of law" to "incur" $253 million more than the
    Post-Retirement Benefits (PRB) costs actually incurred by its PRB Plan during the
    pre-transition years, commensurately increasing the costs of its flexibly-priced contracts,
    including major weapons systems purchased from NGC. Because appellant failed to
    incur/accrue, assign, and fund or claim the amount disallowed in the pre-transition years,
    the government, without any factual support or proof, alleges that the unfunded,
    disallowed amount was "incurred by operation of law," somehow was included in the
    "transition obligation" and that appellant has been "claiming" the disallowed costs as part
    of the annual amortization of that obligation since 2007 in the "post-transition" years.
    The government primarily relies on alleged "inconsistencies" among the quantum
    decision and earlier "Entitlement Phase" decisions. Northrop Grumman Corporation,
    
    ASBCA No. 57625
    , 14-1BCA~35,501, aff'd on recon., 14-1BCA~35,743 (hereinafter
    the "entitlement decisions"). It asserts that the holdings of the entitlement decisions
    1
    The government motion also requests that this appeal be referred to the Board's Senior
    Deciding Group. The Board's Chairman has denied that request.
    became the "law of the case" which the Board failed to follow in the quantum decision.
    Briefing related to the motion was concluded on 15 November 2017. 2
    Upon reconsideration, we affirm the quantum decision. There are no
    inconsistencies among the quantum decision and the Board's earlier entitlement
    decisions. The government's assertions that the Board contradicted the "law of the case,"
    i.e., the entitlement decisions, are based on the government's untimely raised and
    unreasonable "interpretation" of the entitlement decisions. Moreover, the government has
    ignored the quantum remedy for noncompliance established in FAR 31.201-2(c). In
    addition, it has misapplied fundamental concepts of cost "incurrence" and "disallowance."
    The government's initial brief supporting its Motion focused on what it
    alleges are differences in the purported "philosophy" and "intent" of the quantum
    decision vis-a-vis the entitlement decisions. 3 The "philosophy" and "intent" of a Board
    decision are best derived from its language. The basic holding of the entitlement
    decisions was that appellant failed to comply with the FAS 106 PRB cost accrual
    methodology in the pre-transition years. The quantum decision addressed the monetary
    consequences of that noncompliance. In particular, nothing in the entitlement decisions
    considered, much less condoned, the central premise of the government's quantum
    position, i.e., that NGC was required to, and thus actually did, "incur" $253 million
    more PRB costs "by operation of law" in the pre-transition period and that, somehow in
    2
    The Board's previous entitlement decision "conclude[d] that FAR 31.205-6(o)
    supports the government's disallowance of unfunded [PRB] costs" and
    remand[ ed the appeal] to the parties to determine quantum." Northrop
    Grumman, 14-1BCA~35,501 at 174,025, ajf'd on recon., Northrop Grumman,
    14-1BCA~35,743. After the parties were unable to resolve quantum, the
    Board heard "the 'quantum phase' of the parties' disputes regarding
    a government disallowance, totaling $253,361,512, of [PRB] costs associated
    with the 'transition' of [appellant] from its 'pre-transition' accrual methodology
    to the methodology prescribed in FAR 31.205-6(0)." Northrop Grumman,
    17-1BCA~36,800 at 179,363. The Board held there that the government's
    disallowance of this sum was incorrect, and "that the government suffered no
    damages as a consequence of appellant's use of the DEFRA methodology during
    the pre-transition years." This was because the contractor had "specifically and
    expressly executed a 'negative' Plan amendment" in 2006 which "ensured that
    NGC would never incur the costs disallowed and effectively mooted allowability
    issues associated with the transition obligation and the change in NGC's cost
    accounting practices related to PRB costs." 
    Id. at 179,372
    . Familiarity with
    these decisions is presumed.
    3 Presumably, the government refers to the alleged "philosophy" and "intent" of the two
    judges participating in the "entitlement decisions" who retired before issuance of
    the "quantum" decision. The third judge participated in all decisions.
    2
    a manner never detailed or proved, the government-fabricated "costs" thus "incurred"
    found their way into the transition obligation to be amortized in the post-transition years.
    On 12 October 2017, the government filed a "Reply in Support of the
    Government's Motion for Reconsideration" (gov't reply), wherein the government
    alleged that the entitlement decisions definitively held that the disallowed costs were
    included in the "transition obligation." To the Board's knowledge, this is the first
    instance where government counsel expressed such an interpretation of the entitlement
    decisions from the filing of the quantum appeal in September 2015 to October 2017.
    When notified by the gov't reply of its "interpretation," the Board issued an Order
    seeking additional briefing and answers to a series of questions to the parties for further
    clarification on 17 October 2017. In accordance with the schedule prescribed in the
    Board's 17 October 2017 Order, the government filed its response on 1November2017
    (gov't answers) and appellant on 15 November 2017. We have reviewed the parties'
    respective responses. Among other things, the Board specifically asked the government
    where its current pivotal interpretation of the Board's entitlement decisions was asserted
    in the post-hearing quantum briefs. The answer, as appellant succinctly emphasizes, is
    "nowhere." We consider that the late-asserted issue and "interpretation" has been
    waived by the government. Moreover, ifthe Board had reached such a critical
    conclusion in the entitlement decisions, it would have effectively disposed of the central
    and dispositive issue of the entire quantum phase of the proceedings. There would have
    been no need for the quantum phase ifthe Board's entitlement holding resolved all
    issues associated with the computation of the "transition obligation." As the government
    admits, '"theoretically" there would not have been any need to prepare and proffer at trial
    the government's expert opinion expressing for the first time the government's "cost
    incurrence by operation of law" theory, nor any need for further evidence, argumentation
    and briefing of those issues. (Gov't answers at 4) Indeed, the matter would have been
    resolvable by summary judgment disposing of the quantum phase issues without more
    than two years of litigation centered on the composition of the transition obligation. The
    only "inconsistency" is between the government's position advocated by counsel for the
    first two years of this litigation and its "interpretation" first advanced in October 2017 in
    the gov't reply, supplementing its Motion.
    Not only is the government's late-asserted interpretation untimely, it is also
    patently unreasonable. Again, boiled down to its essence, the government now
    maintains that the entire quantum phase "theoretically" was superfluous and
    unnecessary. To the contrary, the entitlement decisions consistently emphasized the
    lack of critical quantum details in the entitlement record that would be required to
    intelligently evaluate issues associated with the "transition obligation." The entitlement
    decisions expressly acknowledged that these did not address NGC's argument that, as a
    result of the PRB plan change in 2006, the disallowed costs "will not be incurred and as
    such, the government has no reason to disallow them." The entitlement decisions,
    noting the paucity of quantum details generally, also expressly and specifically stated
    3
    that the Board required "a better developed record to address" whether the costs had
    been incurred or would be incurred and claimed in the post-transition years as part of
    the amortized "transition obligation." Thus, the quantum phase proceedings.
    All "quantum" issues were before the Board in the "Quantum Phase" proceedings.
    Among other things, the entitlement decisions do not address, much less express approval
    of, the quantum details supporting the government's computation and extraordinary
    "disallowance" of unincurred, unclaimed and unreimbursed costs. All details regarding
    the quantum consequences of noncompliance with the FAS 106 methodology and
    computation of any government remedy were remanded to the parties. There is no
    inconsistency among the decisions.
    In fact, a principle mandate of the entitlement decisions required the parties
    to evaluate in the quantum phase whether the $253 million was included in the
    transition obligation or eliminated by the 2006 Plan amendment. Perforce, ifthe
    Entitlement panel had adopted the government's position regarding the "incurrence" of
    those costs "by operation of law" in the pre-transition years there would have been no
    need for quantum phase proceedings. The entitlement decisions essentially instructed
    the parties to resolve a primarily actuarial question requiring them to delve into the
    details of the computation of the ''transition obligation" and the consequences of the
    2006 PRB Plan amendment. Only appellant constructively responded to that primary
    directive and issue. Appellant provided the only persuasive evidence, including expert,
    testimony conclusively establishing as a fact that the Plan did not include any pre-
    transition year PRB costs, calculated pursuant to the FAS 106 methodology, in the
    transition obligation. The government failed to sustain its burden of proving otherwise.
    The Board at the time of the entitlement decisions had never even been presented with
    the government's "cost incurrence by operation oflaw" theory, much less a cogent
    explanation of how such "costs" found their way into NGC's transition obligation.
    Obviously, it could have drawn no definitive conclusions regarding the government's
    theories that had never been developed until the quantum phase proceedings.
    The gravamen of this dispute has always been whether the government was
    damaged, i.e., in the words, of FAR 31.201-2(c) whether the contractor claimed
    (or the government paid) any disallowable "excess" PRB costs as a consequence of
    appellant's noncompliance. The ultimate overriding fact is that the government did not
    pay any "excess." It cannot overcome that basic fact that there was no "excess" by
    parsing through the entitlement decisions trying to find "inconsistencies," actual or
    implied in the supposed "philosophy and intent" of those decisions. The Board
    emphasized that it had virtually no quantum facts and left all quantum issues to be
    decided on a full record. The pertinent "law of the case" is that the entitlement
    decisions specifically and expressly refrained from drawing any quantum conclusions
    until it had a fully-developed record. The quantum phase proceedings clearly
    established that the contractor did not claim any excess. The government attempts to
    4
    absolve itself of this failure of proof by focusing on alleged "inconsistencies" between
    the entitlement decisions and the quantum decision. There are no such inconsistencies.
    The thrust of those decisions was always to leave the ultimate quantum questions open
    for full examination and scrutiny on a fully developed quantum record. The entitlement
    decisions contained no pre-judgment of quantum or any quantum-related issue. Any
    reading of the language of those decisions to the contrary is simply disingenuous and
    incorrect. Even ifthe entitlement decisions somehow could reasonably be construed to
    be inconsistent, it does not change the fundamental fact that the contractor has never
    claimed, and will never seek reimbursement of the costs and the government has never
    and will never pay the amount disallowed. Regardless of any possible inconsistency,
    fundamental fairness requires that those quantum phase conclusions would necessarily
    be dispositive and controlling.
    The government position disregards, and is also inconsistent with, the
    FAR-prescribed remedy for noncompliance. The government has declined to address
    the Board's discussion of the overall status and quantum impact ofFAR 3 l.201-2(c) on
    cost allowability generally. As emphasized in the "quantum decision," the latter
    provision places the current dispute in context and perspective. It provides the
    government with a general remedy in the event of a non-compliance with more specific
    cost principles. The government arguments fail to meaningfully consider that remedy.
    Only the "excess" is unallowable. There are no "excess" NGC PRB costs to disallow in
    this case.
    One express mention of an arguably "quantum-focused" issue in the "entitlement
    decisions" occurred in the Board's discussion of a "ceiling" on allowability of PRB
    costs in its reconsideration of the entitlement decisions. However, the Board merely
    observed that there was no express mention of a "ceiling" in FAR 31.205-6(o). The
    Board expressed no opinion on the impact of FAR 31.201-2(c) on the quantum
    consequences of non-compliance and the limits of the government remedy reflected in
    the latter provision. FAR 31.205-6(o) must be analyzed and interpreted in the overall
    context of the cost allowability provisions generally. The interrelation of that provision
    with FAR 31.202-2(c) is critical. The "ceiling" is created by reading the two provisions
    together. The former establishes allowability criteria and the latter prescribes the
    government's "quantum" remedy for noncompliance therewith.
    The government has not challenged the Board's discussion of cost incurrence
    by the contractor except to reassert its central contention that appellant "incurred" the
    $253 million "by operation of law" regardless of what the contemporaneous
    documentation reflects. The most persuasive evidence and indicia of cost incurrence
    are contemporaneously-submitted incurred cost and forward pricing proposals for the
    pre-transition period, none of which contained any portion of the $253 million
    "disallowed." During that period, there was never any contention that appellant had
    actually "incurred" the "disallowed" "costs" in question. The government ignores not
    5
    only NGC's Plan, but all the contemporary core cost/pricing/payment related
    documentation and even its own FAR-prescribed remedy, to calculate and assert this
    disallowance. The "government "disallowed" costs that were never incurred, never
    claimed and never reimbursed. The government developed its current theoretical
    construct in 2015 during the prosecution of the quantum phase appeal divorced from the
    reality of all contemporaneous cost incurrence documentation and related cost
    submissions 10-20 years earlier.
    The concept of cost incurrence "by operation of law" in a government contract
    accounting "allowability" context is indeed novel, extraordinary, unique and
    unprecedented. The government has failed to adduce even one analogous case
    supporting its position. The government contemporaneously exercised common sense
    during the pre-transition years and knowingly, willingly, declined to challenge
    appellant's accounting for its claimed PRB costs that resulted in lower costs to the
    government during the pre-transition years. The "common sense" government position
    in this regard in the pre-transition years comported with FAR 31.201-2(c). The
    government now ignores its own regulatory remedy. In doing so it has created an
    extraordinary new category of costs, incurred not by the contractor's own accounting
    measurement, accrual or assignment methodology, but allegedly "required" to be
    incurred by "operation oflaw," without regard to NGC's accounting procedures. To
    the contrary, the operative "law" in this case is the common remedy prescribed for
    noncompliance in FAR 31.201-2(c ). The government's duty is to evaluate costs
    actually incurred and claimed by the contractor under the pertinent cost principle for
    compliance. If non-compliant, any "excess" is unallowable, not costs that were never
    incurred or claimed by the contractor.
    The sole government defense of its "cost incurrence by operation of law" theory
    is based on general platitudes to the effect that laws and regulations often require the
    incurrence of costs. There is nothing particularly remarkable about that basic truism
    in the abstract. But the question in the specific context of a government contract
    cost "disallowance" dispute is whether the government was damaged, injured, harmed,
    i.e., whether it was charged and paid any "excess" as a consequence of noncompliance
    with a cost principle. Here the regulation itself provides the remedy for the regulatory
    noncompliance. FAR Part 31.201-2(c) provides an express remedy for the FAR
    Part 31.205-6(0) noncompliance. Again, the government's theoretical constructs wholly
    ignore that remedy because the government was never damaged and never has paid any
    "excess" as a consequence of the noncompliance. The government's position only
    makes sense ifthe contractor sought to incur in the future (via the transition obligation
    in this case) and seek reimbursement (via amortization of the transition obligation in the
    "post-transition" years) of costs that properly should have been measured, accrued,
    assigned (and funded in this case) in previous accounting periods. NGC did no such
    thing as detailed in the "quantum decision," as a consequence of the 2006 Plan
    amendment and calculation of the transition obligation.
    6
    A primary purpose of the exercise of computing the transition obligation was to
    reconcile the non-compliant DEFRA methodology with the FAS 106 methodology.
    Because the DEFRA methodology required the incurrence of less costs in the
    pre-transition years than the FAS 106 methodology, the difference could have been
    carried forward into the transition obligation in the reconciliation process for
    amortization in the post-transition years. Thus, the reasonable government concern was
    not that the costs had been "incurred" in the past, i.e., the pre-transition years, but that
    they might be incurred in the future post-transition years. If appellant had carried
    forward such costs into the "transition obligation," they would.first be incurred in the
    future via the amortized annual payments, i.e., during the post-transition years. Unless
    the costs were included in the transition obligation, they never would be incurred, much
    less claimed, at any time. Computation of the transition obligation did not occur until
    2006. The government disregards the actual facts of how that obligation was computed.
    In particular, it has failed to analyze appellant's PRB plan, ignores the 2006 Plan
    amendment, and has failed to rebut appellant's proof of the impact of that amendment
    on the calculation of the transition obligation.
    The term "disallowance" presupposes that the contractor has sought an
    "allowance" for the cost in question, i.e., it has included those costs in contemporaneous
    cost-related filings and claimed, charged or been reimbursed for said costs. Here, the
    government has "disallowed" costs for which the contractor has never sought an
    "allowance." The contractor has not and will never claim the costs in dispute here for
    the reasons detailed in the underlying opinion. The "excess," if any, is to be derived
    from cost/pricing, payment, and reimbursement submissions, including incurred cost
    data transmitted to the government from the contractor. There is no mention in any of
    these foundational, core documents that appellant ever incurred the costs in dispute,
    much less claimed their reimbursement. There was no "excess" to disallow, given our
    factual conclusion, unrebutted by any government evidence, that any "excess" was
    not included in the transition obligation or otherwise amortized in the post-transition
    years. Here, the "excess" which is the subject of the government "disallowance"
    consists solely of phantom costs the government "created" in accordance with its
    theoretical construct that the costs were required to be incurred. Therefore, they
    were incurred "by operation oflaw." The government then "disallows" the "excess"
    government-fabricated "costs" that were never charged by the contractor nor paid by
    the government. The alleged "excess" that the government has disallowed was
    wholly-manufactured by the government in its creation of a heretofore unprecedented,
    in government contract accounting/allowability practice, category of costs that were
    "required" to be "incurred" by the contractor "by operation oflaw."
    We also reemphasize that the "required by operation of law" theory advocated by
    the government in this appeal is unreasonable per se because it shortsightedly would
    "require" NGC to use the FAS 106 calculation and charge the government $253 million
    7
    more than NGC actually charged the government using the DEFRA methodology
    during the pre-transition years. Such a position is patently devoid of common sense.
    The government benefited by buying weapons systems and other major systems at a
    commensurately lower cost to the extent that the $253 million thus saved would have
    been allocable to appellant's flexibly-priced contracts. In essence, the government
    interpretation discourages, rather than encourages contractors to institute cost saving
    measures. Our quantum decision recognized that some contractors maximize cost
    saving measures and increase their price/cost competitiveness rather than be penalized
    for not incurring and claiming the maximum amount allowed by regulation.
    The Board's general mention of "damages" and "injury" in the quantum decision
    were a response to the government's extraordinary quantum theory that ignored basic
    concepts of cost "incurrence," and "disallowance" as well as the FAR Part 31 remedy
    for noncompliance. The Board was attempting to determine how (if at all) the
    government was actually damaged or injured by the noncompliance absent inclusion
    of the costs in question in an incurred cost or forward pricing proposal that could
    serve as the basis for any "disallowance." E.g., Servidone Constr. v. United States,
    
    931 F.2d 860
    , 861 (Fed. Cir. 1991) (a claimant under the CDA must prove liability,
    causation, and injury to recover). In effect, FAR 31.201-2(c) by regulation imposes an
    analogous rule in cost disallowance disputes to prove damages. We remain at a loss to
    understand how the government was damaged or injured by the cost savings accruing to
    it as a consequence of the contractor's use of the DEFRA methodology during the
    pre-transition years. In any event, it is clear beyond cavil on a fully developed
    quantitative record that appellant never has and never will incur and claim the
    disallowed costs and the government never has and never will pay any "excess"
    resulting from the noncompliance. The government failed to prove otherwise. The
    entitlement decisions did not short circuit the requirement that the government was
    required to prove its quantum damages.
    Having reconsidered our decision, it is affirmed.
    Dated: 9 January 2018
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    8
    I concur                                      I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    ~A~
    Administrative Judge
    Acting Chairman                               Acting Vice Chairman
    Armed Services Board                          Armed Services Board
    of Contract Appeals                           of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 60190
    , Appeal of Northrop
    Grumman Corporation, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    9
    

Document Info

Docket Number: ASBCA No. 60190

Judges: Peacock

Filed Date: 1/9/2018

Precedential Status: Precedential

Modified Date: 1/31/2018