HK&S Construction Holding Corp. ( 2016 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    HK&S Construction Holding Corp.                )      
    ASBCA No. 60164
    )
    Under Contract No. W912WJ-14-C-0020            )
    APPEARANCES FOR THE APPELLANT:                        John A. Dorsey, Esq.
    W. Mark Russo, Esq.
    Ferrucci Russo P.C.
    Providence, RI
    APPEARANCES FOR THE GOVERNMENT:                       Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    Theresa A. Negron, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, New England
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON THE
    GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION
    INTRODUCTION
    The government moves to dismiss the appeal for lack of jurisdiction because, it
    contends, the appeal is untimely. Appellant contends that the appeal is timely because
    it filed the appeal within 90 days of receiving the hard copy of the decision that the
    government sent by Federal Express. The government has not replied to appellant's
    response. The motion is denied.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    The parties entered into the contract in September 2014 (R4, tab 5 at 1), for
    appellant, Hugo Key & Son Construction Holding Corp. (HK&S) to perform repairs to
    a jetty at Block Island, Rhode Island (R4, tab 2 at 1). On 5 June 2015, the contracting
    officer terminated the contract for default (app. resp., ex. A). At 2:35 p.m. on the same
    day, the contracting officer sent HK&S an email with the following message:
    Please see the attached letter, notifying you that the subject
    contract has been terminated for default. A hardcopy of this
    letter has been sent to you overnight via [Federal Express].
    (Gov't mot., ex. 1)
    Although the email listed as an attachment a "Notice of Termination for
    Default.pdf' (gov't mot., ex. 1), the record does not include the email attachment
    itself. Additionally, the email does not indicate which of the notices (that is, the
    emailed notice or the notice sent by Federal Express) was intended to begin the
    running of the 90-day appeal period pursuant to the Contract Disputes Act (CDA), 
    41 U.S.C. § 7104
    (a) (id.).
    HK&S received the hard copy of the notice of termination for default on 8 June 2015
    (app. resp., ex. B ~ 4), and filed its appeal on 4 September 2015, 91 days after 5 June 2015,
    but only 88 days after 8 June 2015.
    DECISION
    The Board lacks jurisdiction over any appeal filed outside of the appeal period
    set forth in 
    41 U.S.C. § 7104
    (a) of the CDA, which requires a contractor wishing to
    appeal a contracting officer's final decision to the Board to do so within 90 days from
    the date of receipt of the final decision. TTF, LLC, 
    ASBCA No. 59511
     et al., 15-1
    BCA ~ 35,883 at 175,434. Sending multiple copies of a contracting officer's final
    decision without indicating which of them is intended to begin the running of the
    appeal period entitles the contractor to compute the date from receipt of the last copy.
    
    Id. at 175,435
    . However, where an appellant has previously requested to receive
    correspondence by means of a particular medium, an earlier copy of the decision
    received through that medium may start the 90-day appeal clock. 
    Id.
    It is the government's burden to establish the date the final decision was received,
    but the burden of proof is on appellant to establish that its appeal was timely filed. TTF,
    LLC, 15-1 BCA ~ 35,883 at 175,434. Although it appears that the contracting officer
    sent HK&S the notice of termination by email on 5 June 2015 (the record contains the
    email listing the notice of termination as an attachment, but not the attachment itself),
    HK&S received a hard copy of the notice of termination on 8 June 2015. The
    government points to no evidence that HK&S had previously requested to receive
    correspondence by email, and the 5 June 2015 email does not indicate whether the email
    or the hard copy was intended to begin the running of the appeal period. Consequently,
    HK&S was entitled to compute the commencement of the appeal period from its receipt
    of the hard-copy notice of termination on 8 June 2015. Because the notice of appeal was
    filed within 90 days of 8 June 2015, the appeal is timely, and we possess jurisdiction to
    entertain it.
    2
    I
    CONCLUSION
    For these reasons, the government's motion is denied.
    Dated: 25 March 2016
    Administrati Judge
    Armed Services Board
    of Contract Appeals
    I concur                                        I concur
    ~~4¥
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 60164
    , Appeal ofHK&S
    Construction Holding Corp., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    3
    

Document Info

Docket Number: ASBCA No. 60164

Judges: McIlmail

Filed Date: 3/25/2016

Precedential Status: Precedential

Modified Date: 5/9/2016