ABC Data Entry Systems, Inc. ( 2016 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    ABC Data Entry Systems, Inc.                  )       ASBCA No. 59865
    )
    Under Contract No. GS-03F-0148V               )
    Delivery Order No. W912P6-13-F-0008          )
    APPEARANCE FOR THE APPELLANT:                            Ms. Dorothy Powell
    Vice President
    APPEARANCES FOR THE GOVERNMENT:                          Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    Kevin J. Jerbi, Esq.
    James L. Roth, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Chicago
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    Appellant complains that the government negligently estimated the amount of
    work to be performed under an indefinite-quantity contract. The parties agreed to
    submit the appeal on the record pursuant to Board Rule 11.
    FINDINGS OF FACT
    On 5 November 2009, the General Services Administration (GSA) and appellant,
    ABC Data Entry Systems, Inc. (ABC), entered into Schedule Contract No. GS-03F-0148V,
    for scanning and other document conversion services (R4, tab 11 ). As the parties stipulate
    (R4, tab 12, ~~ 3-5), the schedule contract includes (1) Federal Acquisition Regulation
    (FAR) clause 52.216-22, INDEFINITE QUANTITY (DEVIATION I-JAN 1994); (2) a
    "Guaranteed Minimum" clause providing that "[t]he minimum that the Government agrees
    to order during the period ofthis contact is $2,500"; and (3) FAR 52.211-16, VARIATION
    IN QUANTITY (APR 1984), which (as set forth in the schedule contract) provides, at
    paragraph (a):
    A variation in the quantity of any item called for by this
    contract will not be accepted unless the variation has been
    caused by conditions of loading, shipping, or packing, or
    allowances in manufacturing processes, and then only to
    the extent, if any, specified in paragraph (b) below.
    (Id. at 15, 24, 134of146)
    On 8 July 2013, ABC and the U.S. Army Corps of Engineers (government) entered
    into Delivery Order No. W912P6-13-F-0008, for a total award amount of$50,375 (R4,
    tab 1 at 1). The delivery order recites that the schedule contract applies to the delivery
    order, and lists line items, quantities, and unit prices for document scanning (id. at 1, 3-6).
    The parties stipulate that, according to the bid schedule, the government estimated that
    900,500 pages would be scanned (R4, tab 12, ~ 12). The parties further stipulate that,
    ultimately, the government provided a total of 454,608 pages to be scanned (id.,~ 13), and
    that the government paid ABC $13,692.31 for scanning (id.,~ 14).
    On 25 November 2014, ABC presented to the contracting officer a claim for
    $36,250, alleging that the government "failed to provide the required number of
    documents to be scanned" (R4, tab 8 at 1, 7). ABC alleged that "[t]he contract...was
    for [the processing of] 900,500 images," and that "[t]he reduced quantity [sic] 453,000
    of documents actually processed ... was 50% smaller," which "increased our overhead
    and other costs and will put us in a loss situation unless the claim is approved" (id.
    at 1-3). The claim does not use the term "breach" (id. at 1-3). The contracting officer
    denied the claim on 10 February 2015 (R4, tab 6). ABC timely appealed on 3 March 2015.
    DECISION
    In its 23 June 2016 brief to the Board, ABC asserted that the government
    breached the contract by violating FAR 52.211-16, and by negligently estimating the
    number of pages to be scanned. On 27 June 2016, we asked the parties how the
    pertinence of GSA schedule contract provisions to the dispute might affect our
    jurisdiction in view of Sharp Electronics Corporation v. McHugh, 
    707 F.3d 1367
    (Fed.
    Cir. 2013). In response, (1) the government asserted that the Board did not have
    jurisdiction to entertain any "breach of contract or negligent estimate claims" (21 July
    2016 filing at 2), and (2) ABC abandoned its reliance upon FAR 52.211-16, asserting
    that "given the harm caused by the [government's] negligent estimate, [the] appeal
    should still be granted" (23 September 2016 filing at 2).
    Because ABC has abandoned its reliance upon FAR 52.211-16, the only
    question before us is whether the government breached the contract by negligently
    estimating the work. Ifthere is no dispute regarding the meaning of GSA schedule
    contract provisions that are relevant to an appeal, we may apply those provisions to the
    relevant facts; however, if resolving the dispute requires us to interpret any provision
    of a schedule contract, we do not have jurisdiction to entertain the appeal. Sharp
    
    Electronics, 707 F.3d at 1374
    . In the latter case, the dispute must first go to a GSA
    scheduling contracting officer, and then, if the contractor seeks further review, to the
    Civilian Board of Contract Appeals or the United States Court of Federal Claims. See
    
    id. at 1372-47
    & nn.2, 3. Here, now that ABC no longer relies upon FAR 52.211-16,
    the only schedule contract provisions relevant to the dispute are the Indefinite Quantity
    and Guaranteed Minimum clauses; the parties do not dispute the meaning of either,
    2
    and we need not interpret either. Consequently, that the dispute involves schedule
    contract provisions is not a bar to our exercising jurisdiction.
    The government also contends that we do not possess jurisdiction to entertain
    any breach of contract claim here because, it says, ABC did not present a breach claim
    to the contracting officer (gov't br. at 3). The Board has jurisdiction to entertain
    claims that arise from the same operative facts as those presented to the contracting
    officer, claim essentially the same relief, and merely assert differing legal theories for
    that recovery. King Aerospace, Inc., ASBCA No. 57057, 16-1BCAi!36,451
    at 177,651. ABC's claim to the contracting officer includes the assertions that "the
    contract...was for 900,500 images" but that the government "failed to provide the
    required number of documents to be scanned," "provid[ing] 453,000 documents,"
    which "was 50% smaller than specified in the contract." We find that the allegations
    before us that the government breached the contract "based on its negligent estimates
    of required documents to be scanned" (app. br. at 5) are the same operative facts set
    forth in the claim to the contracting officer, and that there is no indication that
    appellant seeks in this appeal anything more than essentially the same relief it sought
    from the contracting officer. Rather, ABC merely asserts a breach theory that it did
    not label as such in its claim to the contracting officer, even though it used there the
    term "failed," which is virtually synonymous with the term "breached." See
    130 BLACK'S LAW DICTIONARY (abr. 6th ed. 1991). Accordingly, we have
    jurisdiction to entertain ABC's negligent-estimate breach claim.
    On the merits of that claim, the parties agree that the GSA schedule contract,
    which applies to the delivery order, includes the Indefinite Quantity clause and a
    guaranteed minimum; indeed, we find no dispute that the contract at issue is of the
    indefinite-quantity type. See generally United Healthcare Partners, Inc., ASB~A
    No. 58123, 16-1 BCA i!.36,374 at 177,320 (explaining characteristics of indefinite
    quantity contracts). The government will not be held liable for a negligent estimate in an
    indefinite-quantity contract. 
    Id. We do
    not examine the reasonableness of the estimates
    in indefinite-quantity contracts, and any reliance on such estimates is misplaced. Crown
    3
    Laundry & Dry Cleaners, Inc., ASBCA No. 39982, 90-3 BCA ~ 22,993 at 115,481, ajf'd,
    
    935 F.2d 281
    (Fed. Cir. 1991) (table). Accordingly, ABC's "negligent estimate" claim
    provides no basis for relief, and the appeal is denied.*
    Dated: 10 November 2016
    Administra ive Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    ~                     /~~/
    £~~-
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in ASBCA No. 59865, Appeal of ABC Data Entry
    Systems, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    * ABC states that the government "was also negligent in estimating the period of
    performance" (app. br. at 5), but that passing, single-sentence reference does not
    sufficiently develop that issue; which is, therefore, waived. See ArcelorMittal
    France v. AK Steel Corp., 
    700 F.3d 1314
    , 1325 n.6 (Fed. Cir. 2012); SmithKline
    Beecham Corp. v. Apotex Corp., 
    439 F.3d 1312
    , 1320 (Fed. Cir. 2006).
    4
    

Document Info

Docket Number: ASBCA No. 59865

Judges: McIlmail

Filed Date: 11/10/2016

Precedential Status: Precedential

Modified Date: 11/28/2016