Circle, LLC ( 2015 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Circle, LLC                                   )      
    ASBCA No. 58575
    )
    Under Contract No. W912P8-04-C-0004           )
    APPEARANCES FOR THE APPELLANT:                       Thomas F. Gardner, Esq.
    Douglas A. Kewley, Esq.
    W. Lee Kohler, Esq.
    Gardner & Kewley, APLC
    Metairie, LA
    APPEARANCES FOR THE GOVERNMENT:                      Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    William G. Meiners, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, New Orleans
    OPINION BY ADMINISTRATIVE JUDGE SCOTT
    ON CROSS-MOTIONS FOR SUMMARY JUDGMENT
    AND APPELLANT'S MOTIONS TO STRIKE
    Circle, LLC (Circle) appealed under the Contract Disputes Act (CDA), 
    41 U.S.C. §§ 7101-7109
    , from the contracting officer's (CO's) final decision denying its
    $1,652,739.64 claim based upon the U.S. Army Corps of Engineers' (Corps') alleged
    constructive change to the subject contract involving a canal improvement project in
    Louisiana. The parties filed cross-motions for summary judgment on liability. Circle
    also moved to strike portions of declarations the Corps submitted and of its statement of
    genuine issues of material fact. For the reasons stated below, we deny Circle's motions
    and we grant the Corps' cross-motion for summary judgment.
    APPELLANT'S MOTIONS TO STRIKE
    Preliminarily, we resolve Circle's motion to strike certain paragraphs in declarations
    submitted by the Corps. Circle contends that they are inadmissible under FED. R. Crv. P.
    56(c)(4) and FED. R. Evro. 602. Rule 56(c)(4) states that:
    An affidavit or declaration used to support or oppose a
    motion must be made on personal knowledge, set out facts
    that would be admissible in evidence, and show that the
    affiant or declarant is competent to testify on the matters
    stated.
    FED. R. Evm. 602 states in pertinent part that:
    A witness may testify to a matter only if evidence is
    introduced sufficient to support a finding that the witness has
    personal knowledge of the matter. Evidence to prove
    personal knowledge may consist of the witness's own
    testimony.
    Circle complains about statements such as the declarant has no personal knowledge, no
    knowledge, or no recollection of a specific meeting, submittal, submittal rejection, or
    direction by the Corps that Circle alleges occurred at the meeting. Circle also contends
    that many of the alleged factual disputes in the Corps' Statement of Genuine Issues of
    Material Fact should be stricken because they are either based upon inadmissible
    averments in the Corps' declarations or upon mere denials, which are insufficient to
    defeat summary judgment.
    The Corps responds that Circle has misinterpreted the cited Rules and that a
    declarant's statement about the declarant's lack of knowledge or recollection of a matter
    is a statement necessarily founded upon the declarant' s own personal knowledge. The
    Corps asserts that the declarations are in direct response to Circle's allegations that three
    of the Corps' declarants attended a specific meeting, referred to by Circle as the
    "Expectations Meeting" (app. mot., vol. 2, tab D (hereafter O'Brien aff.) ii 8), at which
    two of them required Circle to use a particular computer program for design work. The
    Corps contends that the declarations establish that Circle's allegations that the events
    occurred are uncorroborated. The Corps cites to several cases, including Thai Hai,
    
    ASBCA No. 53375
    , 02-2 BCA ii 3 L971, recon. denied, 03-I BCA iJ 32,130, afj"d, Thai
    Hai v. Brownlee, 
    82 F. App'x 226
     (Fed. Cir. 2003) (unpublished), in which it alleges that
    a witness's lack of recollection was treated as admissible evidence. Circle argues that the
    cases are distinguishable.
    The Corps also opposes Circle's motion to strike much of its Statement of
    Genuine Issues of Material Fact. The Corps contends that the issues are based upon the
    documentary record, or upon a lack of documentation to support Circle's claim, in
    addition to the Corps' declarations. The Corps cites to FED. R. CIV. P. 56(c)(l)(A) and
    (B), which state:
    (1) Supporting Factual Positions. A party asserting that a
    fact cannot be or is genuinely disputed must support the
    assertion by:
    2
    (A) citing to particular parts of materials in the record,
    including ... documents, ... affidavits or
    declarations, .. .interrogatory answers, or other materials; or
    (B) showing that the materials cited do not establish
    the absence or presence of a genuine dispute, or that an
    adverse party cannot produce admissible evidence to support
    the fact.
    Circle counters, inter alia, that the lack of documentation is not necessarily relevant
    because the Corps has admitted to having lost some records in Hurricane Katrina.
    The Federal Rules of Civil Procedure do not apply to the Board as an
    administrative tribunal but we may look to them for guidance, particularly in areas our
    rules do not specifically address. Thai Hai. 02-2 BCA ii 3 L971 at 157,920. Similarly,
    Board Rule IO(c) (addressing hearings) notes the fact that the Federal Rules of Evidence
    are not binding upon the Board but they may guide the Board's rulings. Board Rule 7
    provides that, in deciding motions for summary judgment, we look to FED. R. C1v. P. 56
    for guidance. Regarding the admissibility of proffered evidence, it is up to the Board in
    its sound discretion to determine what evidence is admissible and the weight to be given
    it. Laguna Construction Co., 
    ASBCA No. 58324
    , 14-1 BCA ii 35,748 at 174,949
    (addressing appellant's motion to strike); see Board Rules IO(c), l l(d), 13(d).
    The Corps' declarants include the administrative contracting officer (ACO), who
    averred that he was unaware of the alleged Expectations Meeting or of any
    documentation about it, and the three Corps employees alleged by Circle to have attended
    the meeting. The declarants do not deny that there were meetings with Circle involving
    its submittals; they deny knowledge or recollection of a specific meeting on or about the
    date alleged by Circle and Circle's contentions as to what occurred at the meeting.
    Indeed, one of the two Circle affiants said to have attended the meeting averred that he
    did not recall the exact date of the meeting, but he named a date based upon the best of
    his recollection (O'Brien aff. iJ 8).
    The alleged Expectations Meeting, submittal, submittal rejection, and Corps
    direction, and other disputed matters referred to by Circle and the Corps in connection
    with Circle's motions to strike, are pertinent to the Board's analysis of Circle's claim.
    We deny Circle's motions to strike the disputed portions of the Corps' declarations and of
    its Statement of Genuine Issues of Material Fact.
    3
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE
    SUMMARY JUDGMENT MOTIONS
    The parties have submitted affidavits or declarations in support of their motions.
    The following facts, derived from those submittals and the proposed facts alleged by the
    parties and the portions of the record to which they refer, are undisputed or
    uncontroverted unless otherwise indicated.
    1. On 15 January 2003 the Corps issued a sealed bid solicitation for Phase 1 of a
    Southeast Louisiana (SELA) urban flood control project involving improvements to the
    Two Mile Canal in Jefferson Parish, Louisiana (R4, tab 4 at 3). The work included, inter
    alia, constructing a concrete flume in the canal. The contractor was required to install a
    Temporary Retaining Structure (TRS), consisting of temporary sheet pile, to stabilize the
    canal while the flume was being constructed. It was the contractor's responsibility to
    design the TRS and select sheet pile capable of satisfying certain minimum performance
    criteria in specification section 02252. (R4, tab 1 at 2, ii 1; app. statement of undisputed
    facts (AUF) iii\ 2-5; gov't resp. to app's proposed facts (GRF) iii! 2-5)
    2. The solicitation and eventual contract contained the following provisions:
    a. Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (AUG 1987), which
    provides in pertinent part:
    (a) The [CO] may, at any time, ... by written order designated
    or indicated to be a change order, make changes in the work
    within the general scope of the contract, including changes-
    ( 1) In the specifications (including drawings and designs);
    (2) In the method or manner of performance of the work;
    (b) Any other written or oral order (which, as used in this
    paragraph (b ), includes direction, instruction, interpretation,
    or determination) from the [CO] that causes a change shall be
    treated as a change order under this clause; provided that the
    Contractor gives the [CO] written notice stating
    (1) the date, circumstances, and source of the order and
    (2) that the Contractor regards the order as a change order.
    4
    (c) Except as provided in this clause, no order, statement, or
    conduct of the [CO] shall be treated as a change under this
    clause or entitle the Contractor to an equitable adjustment.
    (d) If any change under this clause causes an increase or
    decrease in the Contractor's cost of, or the time required for,
    the performance of any part of the work under this
    contract, ... the CO shall make an equitable adjustment ....
    However, except for an adjustment based on defective
    specifications, no adjustment for any change under paragraph
    (b) of this clause shall be made for any costs incurred more
    than 20 days before the Contractor gives written notice as
    required ....
    (e) The Contractor must assert its right to an adjustment under
    this clause within 30 days after
    ... (2) the furnishing of a written notice under paragraph (b) of
    this clause, by submitting to the [CO] a written statement
    describing the general nature and amount of the proposal,
    unless this period is extended by the Government.
    (R4, vol. II, app'x at 77-78)
    b. Defense Federal Acquisition Regulation Supplement (DFARS) 252.201-7000,
    CONTRACTING OFFICER'S REPRESENTATIVE (DEC 1991), which states:
    (a) "Definition. Contracting officer's representative" means
    an individual designated in accordance with subsection
    201.602-2 of the [DFARS] and authorized in writing by the
    [CO] to perform specific technical or administrative
    functions.
    (b) If the [CO] designates a [CO's] representative (COR), the
    Contractor will receive a copy of the written designation. It
    will specify the extent of the COR's authority to act on behalf
    of the [CO]. The COR is not authorized to make any
    commitments or changes that will affect price, quality,
    quantity, delivery, or any other term or condition of the
    contract.
    (R4, vol. II, app 'x at 94)
    5
    c. Specification section 00010, Bidding Schedule, Note 2, which states that
    "[w]ithin seven (7) days after issuance of the NTP [notice to proceed], the Contractor
    shall initiate a meeting to discuss the submittal process with the Area or Resident
    Engineer or his authorized representative" (R4, vol. II, app'x at 00010-5).
    d. Specification section 02252, TRSs, which states in part:
    1.1 SCOPE
    This work shall consist of designing, furnishing,
    installing, maintaining, and subsequently removing all
    [TRSs] required to complete this project. The Contractor
    shall be solely responsible for the design, layout,
    construction, maintenance, and subsequent removal and
    disposal of all elements of the [TRSs].
    1.3 SUB MITTALS
    Submittals shall be in accordance with Section 01330-
    "SUBMITTAL PROCEDURES". No work shall proceed
    until the submittals have been reviewed and approved by
    the [CO]. ...
    ( 1) Design calculations.
    (2) Shop Drawings .... These shop drawings shall bear
    the stamp and signature of the Registered Professional
    Engineer. These drawings shall clearly show:
    (b) Material grade, weight, length and designation
    of steel sheet pile section( s) used.
    1.4 DESIGN CALCULATIONS
    1.4.1 Design Procedures
    6
    The Contractor shall follow design procedures using the
    method of developing soil pressure for estimating the
    external forces, set forth in "Steel Sheet Piling Design
    Manual" excluding [various methods]. The design
    performed by the Contractor must evaluate the overall
    stability and sizing of the sheet piling and other structural
    elements for the [TRSs]. The Contractor shall use and
    rely upon the soil borings, design sheer strength profile(s)
    and unit weight data presented in the plans and/or in the
    figure(s) attached ... for its design. The structure shall
    meet all the requirements of Corps of Engineers Safety
    Manual EM 385-1-1 for fall protection and ingress and
    egress.
    1.4.3 Sheet Pile Wall Design
    The design of the sheet pile walls shall be developed
    using a method of analysis indicated in paragraph
    1.4.1.. ..
    (R4, vol. II, app'x at 02252-1 to -2)
    3. The parties agree that, as part of Circle's bid preparation, Mr. Minor Hines, a
    Circle project manager, prepared a hand sketch depicting Circle's proposed TRS design,
    which was based upon the use of AZ18x60 sheet piles (app. mot., vol. 1, attach. A
    (hereafter Cavalier aff.), ex. 1, attach. B (hereafter Duong aff.) ii 2; AUF iii! 11, 12; GRF
    iii! 11, 12). The government contends that this TRS design did not comply with contract
    requirements (GRF ii 12). Mr. Ivy Cavalier, currently a Circle equipment manager, who
    assisted in bid preparation in August 2003, states in his affidavit that the sketch was
    prepared after Mr. Hines consulted with Mr. J. Michael Dixon, P.E., Circle's engineering
    consultant. Mr. Co Duong, a Circle estimator from 1994 to 2006, similarly states in his
    affidavit, as does Circle's president, Mr. M. J. Wolfe, Jr. (Cavalier aff. iii! 1-3; Duong
    aff. iii! 1, 4, 5; app. mot., vol. 1, tab V, attach. C (hereafter Wolfe aff.) iii! 1, 4, 6; AUF
    ii 11) Mr. Dixon died in 2004 (app. mot. at 16). Mr. Hines did not submit an affidavit.
    For lack of knowledge, the Corps disputes that the sketch was prepared after consultation
    with Mr. Dixon (GRF ii 11).
    4. Mr. Cavalier prepared an AutoCad drawing, based upon Mr. Hines' hand
    sketch, depicting Circle's planned TRS design, using AZ18x60 sheet piles. On
    22 August 2003 Mr. Cavalier faxed a copy of his AutoCad drawing, depicting Circle's
    planned TRS design, to Mr. Dixon for his review and approval. On 25 and 26 August
    7
    2003 Mr. Hines faxed to Mr. Dixon solicitation pages containing soil data related to the
    project. (Cavalier aff., 5, ex. 2; Duong aff., 7, exs. 3, 4; AUF ,, 13-16; GRF ,, 13-16)
    5. Circle contends that "[a]fter performing design calculations to verify Circle's
    planned TRS design, Mr. Dixon reported back to Circle that AZ 18x60 sheet piles would
    work for the TRS" (AUF, 17). Circle cites to Mr. Cavalier's statement that:
    Mr. Dixon performed design calculations based on the [TRS]
    depicted in Exhibit No. 2. Mr. Dixon reported back to Circle
    that Circle's proposed [TRS], using AZ18x60 sheet piling,
    would meet the requirements of project specifications.
    (Cavalier aff., 6) Mr. Cavalier does not identify to whom Mr. Dixon reported or when
    and there is no contemporaneous documentary evidence of record of Mr. Dixon's
    calculations. The Corps disputes Circle's contention on the ground that the Corps has not
    seen, and has no knowledge, that Mr. Dixon performed the calculations or that the TRS
    design complied with the contract (GRF, 17).
    6. Circle contends that, only after consulting with Mr. Dixon, and obtaining his
    assurance that a TRS constructed with AZ18x60 sheet piles "would have complied with
    the Project specifications," did it base its bid upon the use of those sheet piles (AUF
    , 18). The Corps disputes Circle's contention on the ground that it has not seen, and has
    no knowledge, of what, if any, consultation occurred between Mr. Dixon and Circle prior
    to Circle's decision to use AZ l 8x60 sheet piles for its TRS or that the TRS design
    allegedly approved by Mr. Dixon complied with the contract (GRF , 18).
    7. Sheet pile cost is based upon a unit price per pound of steel used. Larger sheet
    piles are more expensive than smaller ones. (AUF , 20; GRF , 20) On 27 August 2003
    Circle received a proposal from Skyline Steel (Skyline) to sell AZ18x60 sheet piles.
    Circle prepared its bid for the TRS work based upon the use of AZ 18x60 sheet piles. It
    based its material cost estimate upon Skyline's quotation. It based its estimated labor and
    equipment costs upon its historical production rates associated with AZ 18x60 sheet piles.
    (Duong aff. ,, 12-13, exs. 9-12; AUF ,, 24-26; GRF ,, 24-26)
    8. Circle's bid preparation worksheets, bid summary, and pre-construction budget
    reflect that its estimated TRS costs included, among other things, purchasing AZ 18 sheet
    piles and installing two levels of bracing (Duong aff. ,, 13-15, exs. 9, 10; AUF ,, 27-30;
    GRF ,, 27-30).
    9. On 6 October 2003 Circle submitted its project bid in the amount of
    $12,075,806.13. The portion of the price attributable to the TRS scope of work was
    $2,456,773.99. Circle's estimated cost (excluding markup) for the TRS work, as
    8
    reflected in its bid worksheets and pre-construction budget, was $2,305,468.99. (Duong
    aff. 't!'t! 13-15; Wolfe aff. 't! 7; AUF 't!'t! 32-34; GRF 't!'t! 32-34)
    10. On 22 October 2003 the Corps awarded the contract to Circle (R4, tab 5).
    Circle then negotiated further with Skyline for the TRS sheet piles. Mr. Matt O'Brien, a
    Circle project manager from 2003 to 2013, states that he requested 58-foot sheet pile as a
    ruse, knowing that Skyline would provide stock-length 60-foot pile for the price of the
    shorter ones, rather than custom fabricate. Circle received a revised proposal from
    Skyline for AZ18x58 sheet pile and ordered it on 7 November 2003. (App. supp. R4,
    tabs 7, 8; O'Brien aff. 't!'il 4, 7; AUF 't!'il 36-38, 41-42; GRF 't!'il 36-37, 41-42) Circle has
    not provided evidence of whether Skyline actually delivered 60-foot pile. The Corps
    disputes the "ruse" claim for lack of knowledge or information (GRF 't! 38).
    11. On 3 November 2003 Circle acknowledged receipt of the CO's 22 October
    2003 letter to Mr. Steve Hinkamp, resident engineer for the Corps' Southeast
    Louisiana-Jefferson Parish Resident Office (SELA-J), appointing him as the contract's
    ACO. The letter advised that the authority was not redelegable; as ACO, Mr. Hinkamp
    could modify construction contracts within the contract scope under the Changes and
    other named clauses provided that no individual contract action under the clauses could
    exceed $100,000; and he was to record all actions he took in administering the contract,
    in accordance with applicable regulations. (R4, tab 8 at 5-6; gov't mot. and opp'n, tab D
    (hereafter Hinkamp dee!.) 't!'il 1, 2)
    12. On 5 November 2003 Circle and the Corps held a submittals meeting, per
    contract section 00010, Bidding Schedule, Note 2, to discuss the submittal process. The
    Corps informed Circle that additional submittal meetings could be arranged at its
    discretion to expedite the submittal review process for certain work components,
    including the TRS. (R4, vol. II, app'x at 00010-5; app. supp. R4, tabs 30, 31)
    13. The Corps held the Pre-Construction Conference on 18 November 2003.
    ACO Hinkamp avers in his declaration that, at the meeting, he informed Circle that the
    only two persons authorized to make changes to the contract were the CO and himself as
    ACO and that, if Circle believed that any instructions given to it by any other person
    constituted a change to the contract, the matter should be brought to his attention. (R4,
    tab 9; Hinkamp dee!. 't! 3, ex. 1; AUF 't! 43; GRF 't! 43) Mr. Hinkamp's 12 January 2004
    minutes of the pre-construction conference state:
    I pointed out that Diane Pecoul is the [CO], and that I
    am the [ACO] and SELA Resident Engineer. Ms. Pecoul and
    myself are the only two people who have the authority to
    make changes to the contract. Instructions given to you by
    anyone else should be brought to my attention if you consider
    them to be a change to the contract.
    9
    (R4, tab 9 at 6) The minutes record that Messrs. O'Brien, Duong and others attended for
    Circle. On 15 January 2004 Mr. O'Brien signed an acknowledgment to the Corps that he
    concurred with the minutes, without exception. (R4, tab 9 at 2, 12) Circle agrees with
    the foregoing (app. resp. to gov't proposed additional facts (ARF), iii! 129-31).
    14. Mr. O'Brien avers in his affidavit:
    8. After the Pre-Construction Conference, which was
    held on November 18, 2003, I took the Corps'
    recommendation and scheduled an informal meeting with the
    Corps to discuss the Corps' expectations regarding the TRS
    submittals process ("Expectations Meeting"). I do not recall
    the exact date on which the Expectations Meeting occurred.
    However, to the best of my recollection, the Expectations
    Meeting occurred on the Thursday following the
    Pre-Construction Conference, i.e., November 20, 2003.
    9. On or about November 20, 2003, I attended the
    Expectations Meeting with the Corps to informally discuss
    the Corps' expectations regarding the TRS submittals.
    The Expectations Meeting was held in the morning at the
    SELA offices in the Joseph Yenni Building in Harahan,
    Louisiana. Mr. Co Duong and Mr. J. Michael Dixon also
    attended the Expectations Meeting on behalf of Circle.
    Mr. Robert Guillot, Mr. Frederick Young and Mr. Shung
    Chiu attended the Expectations Meeting on behalf of the
    Corps.
    10. Mr. Dixon brought with him to the Expectations
    Meeting copies of his TRS design and his TRS hand
    calculations. Mr. Dixon's TRS design was based on the use
    of AZ l 8x60 sheet piles and two levels of bracing. Mr. Dixon
    presented copies of his TRS design and hand calculations to
    Mr. Young and Mr. Chiu.
    11. During the Expectations Meeting, Mr. Young and
    Mr. Chiu reviewed and discussed Mr. Dixon's original TRS
    design and hand calculations. However Mr. Young and
    Mr. Chiu refused to accept Mr. Dixon's original TRS design
    and hand calculations for an official review.
    10
    12. During the Expectations Meeting, Mr. Young and
    Mr. Chiu advised Circle that Circle would need to submit new
    TRS calculations which had to be performed using the Corps'
    proprietary CWALSHT software program. Mr. Young and
    Mr. Chiu explained that the TRS design calculations needed
    to be performed using CWALSHT because the Corps
    intended to use CWAL SHT to conduct its review of Circle's
    TRS design calculations.
    Mr. O'Brien does not allege that the CO or the ACO was present at the alleged
    Expectations Meeting or at any other meeting at which any Corps employee is said to
    have instructed Circle that its TRS calculations must be performed using CWALSHT.
    15. Mr. Duong avers in his affidavit:
    16. On or about November 20, 2003, I attended a
    meeting with the Corps to discuss the Corps' expectations
    regarding Circle's TRS submittals ("'Expectations Meeting").
    The Expectations Meeting was held in the morning at the
    SELA offices in the Joseph Yenni Building in Harahan,
    Louisiana. Mr. Matt O'Brien and Mr. J. Michael Dixon also
    attended the Expectations Meeting on behalf of Circle.
    Mr. Robert Guillot, Mr. Frederick Young and Mr. Shung
    Chiu attended the Expectations Meeting on behalf of the
    Corps.
    17. Mr. Dixon brought with him to the Expectations
    Meeting copies of his TRS design and his TRS hand
    calculations. Mr. Dixon's TRS design was based on the use
    of AZ18x60 sheet piles. Mr. Dixon presented copies [of] his
    TRS design and hand calculations to Mr. Guillot, Mr. Young
    and Mr. Chiu. Mr. Guillot, Mr. Young and Mr. Chiu refused
    to accept Mr. Dixon's TRS design and hand calculations for
    an official review. Mr. Guillot, Mr. Young and Mr. Chiu
    advised that Circle would need to submit new TRS
    calculations.
    Mr. Duong does not allege that the CO or the ACO was present at the alleged
    Expectations Meeting or at any other meeting at which any Corps employee is said to
    have instructed Circle that its TRS calculations must be performed using CWALSHT.
    Mr. Duong does not allege that any of the Corps personnel attending the meeting
    instructed or directed the contractor or its design consultant that Circle must use the
    Corps' CWALSHT program for its TRS design.
    11
    16. ACO Hinkamp avers in his declaration:
    4. I have no knowledge or recollection of an
    "expectations meeting" that is alleged to have occurred on or
    about November 20, 2003 between representatives of Circle
    and the [Corps], nor am I aware of any documentation
    indicating that such a meeting did take place.
    5. I am aware of allegations made by Circle that, at a
    meeting on or about November 20, 2003, two Corps
    employees, Frederick Young and Shung Chiu, structural
    engineer and geotechnical engineer, respectively, instructed
    or directed Circle that it was required to use the CWALSHT
    computer program to design its [TRS].
    6. I have no personal knowledge that Frederick Young
    or Shung Chiu instructed or directed Circle that it was
    required to use the CWALSHT computer program to design
    its TRS. Additionally, no employee of the [Corps] has ever
    informed me that such direction or instruction was ever given
    to Circle by Mr. Young or Mr. Chiu.
    7. The only persons who had authority to modify the
    terms of [the subject contract] were [the CO and the ACO].
    Neither Frederick Young, Shung Chiu, nor Robert Guillot,
    who is also alleged to have attended the purported meeting of
    November 20, 2003, had any authority whatsoever to modify
    the terms and conditions of [the subject contract]. In
    particular, neither Frederick Young, Shung Chiu, nor
    Robert Guillot had any authority to instruct or direct Circle
    that it was required to use the CWALSHT computer program
    to design its TRS.
    8. The first time I became aware of the allegations that
    Corps employees had instructed or directed Circle that it was
    required to use the CWALSHT computer program to design
    its TRS was when Circle submitted its Request for Equitable
    Adjustment ("REA"), dated April 13, 2009 ....
    12
    10. The contractor was required to provide all
    submittals to my attention at the government's resident office
    (SELA-J), on ENG Form 4025. The SELA-J Office would
    distribute the submittal to the appropriate review parties (in-
    house and/or A-E design office as well as to Jefferson Parish,
    the local sponsor). Review comments from appropriate
    offices would be consolidated by the SELA-J Resident Office
    and a signed response would be returned by the ACO to the
    Contractor on the same ENG Form 4025. The contractual
    requirements for submittal procedures are set forth in Section
    013 30 of the contract, entitled "Submittal Procedures".
    11. Frederick Young and Shung Chiu were Corps
    employees and engineers whose duties included reviewing
    and providing comments on TRS submittals provided by
    Circle. Mr. Young and Mr. Chiu provided comments and
    made recommendations to me whether to approve or reject
    TRS submittals, but they had no authority themselves to
    approve or reject submittals. Only the [CO] and [ACO] had
    authority to approve or reject submittals.
    12. Under the process set forth in the contract, and as
    discussed at the submittals meeting of November 5, 2003, all
    official submittals were required to be submitted on ENG
    Form 4025 and the signed response by the ACO was required
    to be returned to the Contractor on this same ENG Form
    4025. This process is established so that the Contractor
    receives only one official response from a properly
    designated government official, in this case, the ACO.
    Circle generally agrees with Mr. Hinkamp's statements in his declaration concerning the
    submittal process. It alleges that the ACO authorized it to meet directly with the
    Engineering Division to expedite the TRS design and submittal review. (ARF ~ 137)
    17. Mr. Guillot, a Corps employee assigned to the SELA Urban Flood Protection
    Resident Office during the project, who oversaw the work of the project engineer and
    construction inspectors on several drainage improvement projects (gov't mot. and opp'n,
    tab E (hereafter Guillot decl.) ~~ 1-3), avers in his declaration:
    4. While I did attend meetings related to the [TRS] for
    [the subject contract], I have no recollection of attending a
    TRS meeting on or about November 20, 2003.
    13
    5. With regard to the TRS meetings that I did attend,
    I have no knowledge or recollection that either
    Frederick Young or Shung Chiu rejected a TRS submittal
    informally provided by Circle.
    6. With regard to the TRS meetings that I did attend,
    I have no knowledge or recollection that either
    Frederick Young or Shung Chiu instructed or directed Circle
    that it was required to use the CWALSHT computer program
    to design its TRS.
    7. With regard to the TRS meetings that I did attend,
    I have no knowledge or recollection that either
    Frederick Young or Shung Chiu instructed or directed Circle
    that if it did not use the CWALSHT computer program to
    design its TRS, its TRS submittal would be rejected.
    8. Neither I, nor Frederick Young, nor Shung Chiu
    had authority to modify [the subject contract].
    9. Neither I, nor Frederick Young, nor Shung Chiu
    had authority to approve or [reject] submittals under [the
    subject contract].
    18. Mr. Young, a Corps structural engineer until 2006, who was assigned to
    review the structural design aspects of Circle's TRS submittals (gov't mot. and opp'n,
    tab F (hereafter Young decl.) iii! 2, 3), avers in his declaration:
    4. While I did attend meetings related to the [TRS] for
    [the subject contract], I do not recall attending a TRS meeting
    on or about November 20, 2003.
    5. I do not recall that, at a meeting on or about
    November 20, 2003, Mr. Michael Dixon, P.E., informally
    submitted a TRS design using ... AZ 18 sheet pilings to me.
    6. With regard to the TRS meetings that I did attend,
    I have no recollection that I, Shung Chiu or anyone else ever
    rejected a TRS submittal informally provided by Circle on
    November 20, 2003.
    7. With regard to the TRS meetings that I did attend,
    I have no knowledge or recollection that I or anyone else
    14
    instructed or directed Circle that it was required to use the
    CWALSHT computer program to design its TRS.
    8. With regard to the TRS meetings that I did attend,
    I never instructed or directed Circle that if it did not use the
    CWALSHT computer program to design its TRS, its TRS
    submittal would be rejected.
    9. I never had authority to modify [the subject
    contract].
    10. My role in the submittals process for [the subject
    contract] was to review TRS submittals on behalf of my
    office, make comments, and forward those comments to
    higher authority.
    11. I did not have authority to approve or reject
    submittals under [the subject contract].
    19. Mr. Chiu, a Corps geotechnical engineer until his retirement in 2012, assigned
    to review the geotechnical design aspects of Circle's TRS submittals (gov't mot. and
    opp'n, tab G (hereafter Chiu decl.) iii! 1-3 ), avers in his declaration:
    4. While I did attend meetings related to the [TRS] for
    [the subject contract], I have no recollection of attending a
    TRS meeting on or about November 20, 2003.
    5. I have no recollection that, at a meeting on or about
    November 20, 2003, Mr. Michael Dixon, P.E., informally
    submitted a TRS design to me or Frederick Young that
    allowed for the use of AZ 18 sheet pilings.
    6. With regard to the TRS meetings that I did attend,
    I have no knowledge or recollection that I, Frederick Young
    or anyone else ever rejected a TRS submittal informally
    provided by Circle.
    7. With regard to the TRS meetings that I did attend,
    I have no knowledge or recollection that I, Frederick Young
    or anyone else instructed or directed Circle that it was
    required to use the CWALSHT computer program to design
    its TRS.
    15
    8. With regard to the TRS meetings that I did attend, I
    have no knowledge or recollection that I, Frederick Young or
    anyone else instructed or directed Circle that if it did not use
    the CWALSHT computer program to design its TRS, its TRS
    submittal would be rejected.
    9. Neither I nor Frederick Young had authority to
    modify [the subject contract].
    10. My role in the submittals process for [the subject
    contract] was to review TRS submittals on behalf of my
    office, make comments, and forward those comments to
    higher authority.
    11. Neither I nor Frederick Young had authority to
    approve or reject submittals under [the subject contract].
    20. The Corps agrees that, after the pre-construction conference, meetings with
    Circle to discuss its TRS submittals occurred (see AUF 144; GRF 144). However, it
    disputes that: (a) a TRS submittals Expectations Meeting occurred on or about
    20 November 2003 and the personnel named by Circle attended; (b) Mr. Dixon brought
    copies of the TRS design submittal package, including his calculations performed by
    hand, and he provided the package to the Corps' technical advisors; (c) Mr. Dixon's TRS
    design used AZ18x60 sheet piles and two levels of bracing; (d) during the meeting Circle
    and the Corps informally reviewed Mr. Dixon's TRS design, his calculations and
    assumptions, and the Corps became aware that Circle had based its bid price upon AZ 18
    sheet piling and that its design included two levels of bracing; and (e) during the meeting
    the Corps refused to accept Circle's TRS design submittal for an official review and
    instructed it and Mr. Dixon to perform new TRS calculations using only the Corps'
    proprietary CWALSHT software program, which the Corps intended to use to review the
    TRS design and Mr. Dixon's calculations (Hinkamp decl. 114-6, 8; Guillot decl. 1i! 4-7;
    Young decl. 1i! 4-8; Chiu decl. iii! 4-8; gov't mot. and opp'n, ex. 5 at 5 (app. resp. to
    interrog. No. 2d.); AUF iii! 45-56; GRF iii! 45-56).
    21. Circle has not controverted the Corps' asserted fact that no documentary
    evidence exists to corroborate Circle's statement that an "Expectations Meeting"
    occurred on or about 20 November 2003. Although Circle deems the point to be
    irrelevant, it "agrees that it has been unable to locate any contemporaneous
    documentation to corroborate the affidavit testimony of Matt O'Brien and Co Duong that
    the Expectations Meeting occurred." (ARF iJ 116)
    22. Circle acknowledges the following of the Corps' asserted facts, although it
    deems them irrelevant: (a) no Corps representative whom Circle alleges to have attended
    16
    an Expectations Meeting on or about 20 November 2003 recalls having attended such a
    meeting and Circle has no information with which to dispute their professed lack of
    recollection (but Circle asserts that Messrs. O'Brien's and Duong's affidavit testimony
    establishes that the Corps personnel were there) (ARF if 117); (b) Circle does not have
    proposed TRS design documents, including calculations and Mr. Dixon's original pre-bid
    design, said to have been submitted by him to the Corps in November 2003 (gov't mot.
    and opp'n, ex. 6 at 4 (app. resp. to doc. prod. req. No. 20); ARF if 118); and (c) Circle has
    no documentation to confirm that Mr. Dixon's original TRS design was provided to the
    Corps personnel at the alleged Expectations Meeting (gov't mot. and opp'n, ex. 6 at 3
    (app. resp. to interrog. No. 13(e)); ARF if 135).
    23. Circle contends that it is irrelevant (ARF if 122), but it admits that Mr. Duong:
    [R]ecalls that the Corps rejected Mr. Dixon's hand
    calculations which were brought to the Expectations Meeting,
    but has no recollection of the reason the Corps rejected
    Dixon's hand calculations. Mr. Duong also has no
    recollection of the discussion of the use of CWALSHT
    software during the Expectations Meeting.
    (Gov't mot. and opp'n, ex. 5 at 5 (app. resp. to interrog. No. 2d.))
    24. Subject to an objection that it is a conclusory statement of law, Circle admits
    that Messrs. Young, Chiu and Guillot were not given express authority under the contract
    to modify it. However, Circle contends that Messrs. Young and Chiu "'were cloaked with
    implied authority to effect constructive changes to the Contract." (ARF if 128) Circle
    also "admits that Mr. Young and Mr. Chiu did not have express authority under the
    contract to approve or reject Circle's TRS submittals" (ARF if 138). However, Circle
    contends that the Corps' Engineering Division made the ultimate determination whether
    Circle's TRS submittals complied with project specifications and the ACO was merely a
    conduit for delivering the Division's comments to Circle (id.). The Corps replies that the
    authority matter is not a conclusory legal statement but is based upon the factual record
    (gov't reply to app. resp. to gov't proposed additional facts if 128).
    25. CWALSHT is a proprietary software program created and owned by the
    Corps. It is intended to be used to perform the design and analysis of a cantilevered
    (unbraced) or anchored (single-braced) sheet pile retaining wall. It is not intended to be
    used to perform the design and analysis of a sheet pile retaining wall with multiple levels
    of bracing. (AUF iii! 57-59; GRF iii! 57-59)
    26. On 1 and 2 December 2003 Mr. Dixon performed TRS design calculations,
    relying exclusively upon CWALSHT, including for construction stages that had two
    braces in the TRS (O'Brien aff., ex. 4; AUF iii! 61-64; GRF iii! 61-64). Circle contends
    17
    that these CWALSHT-based calculations determined controlling maximum moments that
    greatly exceeded the capacity of the AZ 18 sheet piles contained in its original TRS
    design and required it to use AZ26x66 sheet piling. The Corps does not dispute this but it
    denies that evidence exists to establish that Circle's alleged original TRS design complied
    with contract requirements. (AUF if 65; GRF if 65)
    27. On 4 December 2003 Circle issued a revised purchase order to Skyline for
    AZ26x66 sheet piling (O'Brien aff., ex. 6; AUF iii! 67-68; GRF iii! 67-68).
    28. Circle states that, on 23 December 2003, Mr. Dixon's new TRS design and
    CWALSHT-based TRS calculations were part ofTRS Submittal No. M14 (O'Brien aff.,
    ex. 7; AUF if 69). The Corps disputes this on the ground that the document is unsigned
    and the record reflects that the date of Circle's first TRS submittal, No. M14, was
    13 January 2004 (R4, tab 11; Hinkamp decl. if 13; Guillot decl. if 11; GRF if 69).
    29. A TRS submittal meeting occurred on 30 December 2003. The Corps
    disagrees with Circle's characterization of any documents presented at the meeting as a
    "submittal." (R4, tab 1 at 5, if 8 n.4, tab 10; AUF if 70; GRF if 70) The Corps agrees that,
    during the 30 December 2003 submittal discussion, it never advised Mr. Dixon that he
    should not have used CWALSHT to perform calculations for construction stages that
    included two levels of bracing in the TRS or that the use of CWALSHT to analyze a
    multi-braced TRS would calculate incorrect, materially greater moments on the TRS than
    would have been calculated using the methods authorized by the specifications. The
    Corps notes its continuing disagreement with any implication that use of CWALSHT to
    design the TRS was not permitted by the contract. (AUF if 72; GRF if 72)
    30. On 31 December 2003 Mr. Dixon performed design calculations, using
    CWALSHT, to address comments by the Corps during the 30 December 2003 meeting.
    He used CWALSHT for all new TRS design calculations, including for stages that
    included two levels of bracing in the TRS, and identified the maximum moment on the
    sheet pile for each construction stage. (O'Brien aff., ex. 11 at 15311; AUF iii! 73-76;
    GRF iii! 73-76)
    31. Circle contends that Mr. Dixon's 31 December 2003 revised TRS design and
    CWALSHT-based design calculations again determined controlling maximum moments
    that greatly exceeded the moment capacity of the AZ 18 sheet piles contained in its
    original TRS design. The Corps disputes any implication that Circle's alleged original
    design complied with contract requirements, stating that it has never seen that TRS
    design and cannot comment upon its content. (AUF if 77; GRF if 77)
    32. A TRS design meeting was held on 13 January 2004 (AUF if 79; GRF if 79).
    The parties dispute whether Circle's TRS Submittal No. M14, submitted and discussed at
    the meeting, was a supplemental submittal or the first TRS submittal received by the
    18
    Corps (AUF ,, 78-81; GRF ,, 78-81). On 30 January 2014 the Corps rejected TRS
    Submittal No. M14, with comments and instructions to re-submit (O'Brien aff., ex. 16;
    AUF, 83; GRF, 83). The Corps agrees that it never advised Mr. Dixon, including when
    it eventually approved Circle's submittal, that he should not have used CWALSHT to
    perform calculations for construction stages that had two levels of bracing in the TRS or
    that the use of CWALSHT to analyze a multi-braced TRS would calculate incorrect,
    materially greater moments on the TRS than would have been calculated using the
    methods authorized by the specifications. (AUF ,, 82, 84, 93; GRF ,, 82, 84, 93)
    33. On 26 and 27 February 2004, using CWALSHT, Mr. Dixon performed new
    TRS calculations to support the revisions to his TRS design prompted by the Corps'
    comments upon TRS Submittal No. M14. He included calculations for three construction
    stages at two different locations in the canal and for the maximum moment on the sheet
    pile at each construction stage. At each location, the calculations for Stages 2 and 3
    involved construction stages that included two levels of bracing in the TRS. Mr. Dixon's
    TRS design and calculations also determined a controlling maximum moment that
    exceeded the capacity of an AZ 18 sheet pile. His calculations were part of Circle's TRS
    Submittal No. Ml4A, submitted on 2 March 2004. (O'Brien aff., exs. 19, 20; AUF ,,
    85-90; GRF ,, 85-90) On 24 March 2004 the Corps approved submittal No. Ml4A, with
    exceptions (O'Brien aff., ex. 21; AUF, 92; GRF, 92).
    34. Circle alleges that the Corps' instruction that it use CWALSHT necessitated
    its use of AZ26x66 sheet piles, which were longer, thicker, heavier and more expensive
    than AZ l 8x60 sheet piles, and required more time to drive and remove than it had
    estimated in its bid. The Corps denies any such instruction and disputes the extra time
    claim based upon lack of knowledge. (Hinkamp decl. ,, 6, 7; Guillot decl. ,, 6, 7;
    Young decl. ,, 7, 8; Chiu decl. ,, 7, 8; AUF ,, 94-96; GRF ,, 94-96)
    35. By letter to ACO Hinkamp of 14 October 2004, Circle challenged a
    "conservative" vibration threshold in the specifications said to have caused it to upgrade
    its vibratory hammer. It also stated that it was "experiencing a very delayed process in
    removing [the TRS] sheet pile." (R4, tab 14 at 1) Circle alleged:
    In addition to the capital outlay for new equipment, we will
    continue to encounter the additional costs associated with
    slowed production. The successful hammer referenced
    above, will remove the sheeting, but at a much slower pace
    than originally anticipated, as the approved wall thickness and
    length of steel sheet pile drastically exceeds our bid day
    intent.
    Circle ... and their TRS design consultant contend that
    demands to achieve approved TRS design exceeded the
    19
    requirements of specification section 02252 expressly Steel
    Sheet Pile Design Manual, November 1987.
    (Id. at 2) Circle noted that it expected to receive equitable restitution and reserved its
    right to file a claim. It also suggested that, to prevent further delays, damages and
    impacts, the TRS design presently approved might be re-evaluated by the Corps' chief
    design engineer. (Id.) Circle contends that this satisfied the Changes clause's notice
    requirements concerning alleged contract changes (see R4, tab 17; app. mot. at 20-23).
    36. The project was completed on 7 July 2007 (AUF if 98; GRF if 98).
    3 7. On 13 April 2009 Circle submitted an REA to the ACO in the amount of
    $1,652, 740, alleging that Corps structural review criteria exceeded specification
    requirements, causing extra costs for additional and heavier materials, and additional
    equipment and labor to install and remove the TRS. Circle included a 3 April 2009
    report by Grecon Construction Engineers, Inc. (Grecon), which concluded that the Corps
    required the use of the wrong calculation method, CWALSHT, which applies to anchored
    structures, not braced structures. Grecon stated that this reduced the limits of the stress
    allowed by the specifications, causing the sheet pile used for the TRS to be longer than
    required by the specifications, with a greater section modulus than could have been
    anticipated at the time of bid. (R4, tab 17)
    38. On or about 14 July 2009, the CO denied the REA, stating that Corps records
    showed that Circle had ordered 66-foot long AZ26 sheet piles prior to providing any TRS
    submittal. Also, its first submittal included calculations by Mr. Dixon dated 1 December
    2003, nearly a month before the first TRS meeting, in which he had recommended
    66-foot long AZ26 sheet pile based upon a design using CWALSHT. The CO contended
    that this was contrary to Circle's contention that it was forced into using that sheet pile.
    The CO also disagreed with most ofGrecon's assertions. (R4, tab 18)
    39. In a 5 August 2009 letter to the CO, Circle stated that it was not until its
    engineer's 8 January 2004 calculations implementing the 30 December 2003 meeting
    requirements that it was determined that an enhanced modulus and length would be
    required and Circle revised its sheet pile order (R4, tab 19). By letter to Circle on or
    about 21August2009, and subsequently, the CO requested documentation and a
    summary of how and when Circle's design changed based upon discussion with the
    Corps (R4, tabs 20-22). On 18 June 2010 Circle provided the Corps with records that it
    had originally placed an order for AZ 18 sheet piles with Skyline and had later requested
    AZ26 sheet piles (O'Brien aff. if 41, ex. 29; AUF if 103; GRF if 103).
    40. During a 21 July 2010 meeting with the Corps to discuss the REA, Circle
    advised that, due to Mr. Dixon's death, its original TRS design and hand calculations were
    no longer available (R4, tab 23; O'Brien aff. if 42; AUF iii! 104-05; GRF iii! 104-05). The
    20
    Corps asked it for calculations supporting its contention that, had it used calculations
    similar to those it had submitted on past Corps projects, not using CWALSHT, it would not
    have had to upsize the sheet pile from AZ l 8x60 to AZ26x66. The Corps suggested that the
    calculations should be available because the REA was based upon this contention and
    Grecon had referred to the calculations. (R4, tab 23)
    41. The Corps agrees with Circle's statements that, on 13 September 2011, the
    Corps approved Circle's TRS design and calculations on the Two Mile Canal, Phase II
    project, which involved a separate canal reach, abutting that involved in this appeal.
    Circle's design for Phase II used AZ18x60 sheet piles for the TRS. The CO was the
    same one who denied Circle's claim at issue here and the ACO was again Mr. Hinkamp.
    (AUF ~~ 107-10; GRF ~~ 107-10) However, the Corps states that it:
    [D]isputes the implication that, because Circle's TRS design
    using AZ 18 sheet pilings was approved on a different project,
    8 years later, and at a different location along the same canal,
    Circle should have been allowed to construct its TRS for the
    subject project using AZ18 sheet pilings. The first TRS
    design that Circle submitted to the Corps for review on the
    instant contract did not propose the use of AZ 18 sheet pilings,
    but AZ26 sheet pilings.... Further, differing soil conditions
    and differing requirements at different locations along the
    canal could easily explain why a TRS constructed of AZ 18
    sheet pilings would be acceptable at one location, but not
    another. [Citations omitted]
    (GRF ~ 108; see also Hink.amp decl.   ~~   13, 14; Guillot decl.   ~   11)
    42. Circle and the Corps exchanged correspondence concerning Grecon's
    calculations and Circle's REA from December 2010 to 2012 (R4, tabs 24-28). By letter
    to Circle dated 23 January 2012, 1 which she characterized as in response to Circle's
    request for reconsideration of its REA, the CO asserted:
    After reviewing numerous documents, submittals and
    discussions with the Government and AIE employees, I found
    no evidence indicating that you were forced into using the
    Government's program. Further, Circle claimed it bid the job
    based on another method besides CWALSHT, although no
    partial calculations were ever provided to support this claim.
    1
    As with other Corps correspondence, there is no clear date on the Board's copy of this
    letter, but the Corps' index to its Rule 4 file and Circle's 24 February 2012
    response to the letter (R4, tab 28) indicate that it was dated 23 January 2012.
    21
    I allowed you to complete a design as you originally intended
    to support the contention that the sheet pile could have been
    lighter and shorter.
    On December 21, 2010 you submitted your design.
    While the design methodology was supported by the contract
    specifications, the submittal contained errors and did not
    properly factor the soil strength. When these corrections
    were made, your originally intended design did not result in a
    shorter or lighter sheet pile section. On April 21, 2011 you
    were notified of these findings.
    On November 17, 2011, rather than correcting the
    December 21, 2010 design; you submitted another design
    method.... I believe the Government has been quite liberal in
    allowing you to resubmit a different design methodology even
    [though] there is no evidence to suggest that you were forced to
    use CWALSHT .... At this point in time, it is not reasonable to
    believe that the latest iteration of your design method .. .is the
    one which you intended to use over eight years ago.
    (R4, tab 27) The CO denied Circle's request for reconsideration (id.).
    43. By letter of 24 February 2012, Circle disputed the CO's determinations and
    sought a final decision. On 20 June 2012, Circle submitted a certification that contained
    the elements required by the CDA. (R4, tabs 3, 28-29) On 29 November 2012 the CO
    issued her final decision denying Circle's claim for $1,652,739.64. The CO asserted that:
    1. ... The flaw in your argument is that no Government
    representative directed you, or your design consultant, to use the
    CWALSHT program. At the pre-submittal meetings attended
    by your design consultant, it is entirely possible that a
    Government representative advised both you and your design
    consultant that the CWALSHT program was available to help a
    contractor prepare a design that incorporated steel sheet pile.
    However, I have found no evidence to suggest that a
    Government representative directed you or your design
    consultant to use the CWALSHT program [let] alone use it in
    lieu of the methodology specified in Section 02252, paragraph
    1.4.1 of the Contract specifications. To the extent your design
    consultant elected to use the CWALSHT program as a design
    aid, I find that his choice was entirely voluntary.
    22
    2. Even if a Government representative had directed Circle, or
    its design consultant, to use the CWALSHT program, the
    individual had no authority to direct a change to the contract
    specifications.
    (R4, tab 1 at 10) Circle timely appealed to the Board on 25 February 2013.
    44. In January 2014 Circle engaged Mr. Peter Bowlin, a professional engineer
    employed by Ragland Aderman & Associates, Structural Engineering, to recreate the
    TRS design and hand calculations prepared by Mr. Dixon. The purpose was to
    demonstrate that a TRS complying with project specifications could have been
    constructed using AZl 8x60 sheet pile, which Circle alleges it had originally planned to
    use to construct the TRS. Mr. Bowlin prepared a report dated 25 July 2014, which Circle
    submitted to the Corps on or about 25 September 2014. (App. mot., vol. 3, tab E, iii! 1-4,
    ex. l; AUF iii! 112-14; GRF iii! 112-14) Circle contends that the report's calculations
    demonstrate that a contract-compliant TRS could have been constructed using AZ l 8x60
    sheet piles. The Corps disagrees and alleges that, regardless, they were presented over
    ten years after Circle's obligation to provide a contract-compliant TRS submittal and they
    are not relevant to the TRS design it submitted in 2003 or 2004, which had different
    jobsite conditions, nor to the design upon which it had based its bid. (See Hinkamp decl.
    i! 14; AUF i! 114; GRF i! 114)
    DISCUSSION 2
    The Parties' Positions
    Circle contends that the Corps constructively changed the contract when its
    engineers Young and Chiu allegedly summarily rejected Circle's AZ18x60 TRS design,
    2
    The Board perceived a potential timeliness issue regarding Circle's claim. Although
    the court held in Sikorsky Aircraft Corp. v. United States, 
    773 F.3d 1315
     (Fed.
    Cir. 2014), that the CDA's six-year statute of limitations, 
    41 U.S.C. § 7103
    (a)(4)(A), is not jurisdictional, failure to meet a statute of limitations
    remains an affirmative defense. See FED. R. CIV. P. 8(c). Board Rule 6(b) calls
    for the government to set forth any affirmative defenses in its answer to the
    complaint. Although the Corps contends, and Circle disputes, that Circle did not
    comply with the notice requirements of the Changes clause and took over five
    years to notify the Corps of its alleged constructive contract change, the Corps has
    not alleged that Circle's claim to the CO was time-barred under the CDA. The
    Corps did not assert this affirmative defense in its answer or in response to
    Circle's summary judgment motion and has waived it. See, e.g., Diversey Lever,
    Inc. v. Ecolab, Inc., 191F.3d1350, 1353 (Fed. Cir. 1999).
    23
    even though it complied with the specifications, solely because it had not used the Corps'
    CWALSHT software. Circle alleges that the engineers ordered it to submit new TRS
    design calculations using only CWALSHT, contrary to its plan to use hand calculations;
    this order impermissibly limited its options by prohibiting it from using other design
    methods allowed by the specifications; and it misrepresented that CWALSHT could be
    used to design a TRS that had multiple levels of bracing.
    The Corps contends that it is entitled to summary judgment on either of two
    grounds. First, even assuming, for the sole purpose of the Corps' motion, that two Corps
    employees directed or instructed Circle to use the CWALSHT computer program (which
    the Corps "vigorously denies" (gov't cross-mot. at 3)), there was no constructive change
    to the contract because they lacked express or implied authority to modify it and their
    actions were not ratified by anyone who had such authority. Secondly, Circle must
    demonstrate that it had a contract-compliant TRS design that would have allowed it to
    construct the TRS with AZ 18 sheet piles. There is no credible evidence to establish this.
    Moreover, Circle cannot prove that the alleged Corps action was the cause of its decision
    to construct the TRS with more costly AZ26 sheet piles.
    In opposing Circle's motion for summary judgment, the Corps contends that,
    contrary to the requirements of the Changes clause, Circle did not provide timely notice
    of the alleged constructive change, and that most of the material facts necessary to
    support Circle's claim are in genuine dispute.
    In its opposition to the Corps' cross-motion, on the authority issue, Circle alleges
    that an integral part of the duty assigned to the Corps' two technical personnel, to review
    Circle's TRS design submittals, included giving instructions and directions to Circle
    about its design. Thus, they had the implied authority to do so. Their erroneous
    CWALSHT directions, which were binding upon the Corps, required thicker and longer
    sheet piles than Circle had intended and were a constructive contract change. Circle
    concedes that it does not allege ratification (Circle's reply in support of its objects. and
    mots. to strike, at 3). Regarding the Corps' second contention, Circle alleges that it has
    demonstrated the viability of its AZ18 sheet piling design through its consultant's
    re-creation of Mr. Dixon's original design and because the Corps subsequently allowed
    the design on other project work.
    The Corps replies that Circle has admitted that the employees who allegedly
    instructed it to use CWALSHT to design its TRS did not have the express authority to do
    so (see SOF ~ 24; ARF ~ 128), and there is no genuine issue that they lacked implied
    authority to modify the contract. Circle was directly notified that they lacked such
    authority at the outset of the contract. Lastly, the Corps expands upon its secondary
    contention that Circle has not produced a contemporaneous TRS design using AZ 18 sheet
    piles, not based upon the CWALSHT program, that complied with the contract
    specifications.
    24
    Summary Judgment Standards
    Summary judgment is appropriate only when there are no genuine issues of
    material fact and the movant is entitled to judgment as a matter of law. We resolve any
    significant doubt over factual issues, and draw all reasonable inferences, in favor of the
    party opposing summary judgment. Cross-motions do not necessarily mean that
    summary judgment is appropriate. We evaluate each motion on its own merits. Mingus
    Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987); Free &
    Ben, Inc., 
    ASBCA No. 56129
    , 09-1BCA~34,127 at 168,743. We do not resolve factual
    disputes but ascertain whether there is a genuine issue of material fact, which is one that
    might affect the outcome of the case. There is a genuine issue of material fact ifthe
    evidence is such that a reasonable fact finder could find in favor of the nonmovant.
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986); Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323-25 ( 1986); MIC/CCS, Joint Venture, 
    ASBCA No. 58023
    . 14-1 BCA
    ~[ 35,678 at 174,636; Free & Ben, 09-1 BCA ~] 34,127 at 168,742. Mere denials or
    conclusory statements are insufficient to defeat summary judgment. Mingus
    Constructors, 812 F .2d at 1390-91.
    Appellant's Motion for Partial Summary Judgment
    Circle moves for summary judgment that a compensable constructive contract
    change occurred when Corps engineers Young and Chiu allegedly erroneously ordered it
    to use the Corps' CWALSHT program to design the TRS. which Circle had not intended
    to do, the contract did not require, and which misrepresented that the program was
    appropriate for the design work. A constructive change occurs when a contractor
    performs work beyond the contract requirements, without a formal order under the
    Changes clause, due either to an express or implied informal order from an authorized
    government official or to government fault. Bell/Heery v. United States, 
    739 F.3d 1324
    ,
    1335 (Fed. Cir. 2014); International Data Products Corp. v. United States, 
    492 F.3d 1317
    , 1325 (Fed. Cir. 2007); Versar, Inc., 
    ASBCA No. 56857
     et al., 12-1BCA~35,025
    at 172, 122. To meet its burden to prove that it was subject to a constructive contract
    change on the basis it alleges, Circle must establish that:
    ( 1) [I]t was compelled by the government to perform work
    that was not required by the terms of the contract; (2) the
    person directing the change had contractual authority
    unilaterally to alter the contractor's duties under the contract;
    (3) the contractor's performance requirements were enlarged;
    and (4) the additional work was not volunteered. but was
    directed by a government of1icer.
    25
    Mountain Chief Management Services, Inc., 
    ASBCA No. 58725
    , 15-1 BCA il 35,831 at
    175,201 (quoting Northrop Grumman Systems Corp. Space Systems Division, 
    ASBCA No. 54774
    , 10-2 BCA i! 34,517 at 170,242-43 ).
    As our Statement of Facts reflects, there are numerous genuine issues of material
    fact that preclude summary judgment in Circle's favor (see, e.g., SOF iii! 20-24). The key
    question of whether Corps engineers Young and Chiu directed or instructed Circle, at an
    Expectations Meeting, or at any time, that it must use the CWALSHT design program to
    design its TRS is strongly disputed. Circle's related contention that Messrs. Young and
    Chiu constructively changed the contract by misrepresenting the appropriateness of
    CWALSHT for Circle's design needs is inherently fact-based and disputed.
    While the CO suggested in her final decision that, at pre-submittal meetings, it
    was possible that a government representative advised Circle and its design consultant
    that the CWALSHT program was available to help prepare a design that incorporated
    steel sheet pile, she also stated that she had found no evidence to suggest that a
    government representative directed the use ofCWALSHT (SOF ii 43, see also SOF
    ii 42). ACO Hinkamp and Messrs. Guillot, Young and Chiu, have declared that they have
    no knowledge or recollection of any such direction (SOF ilil 16-19). Even if those
    declarations were discounted, as Circle urges. and even if Messrs. Chiu and Young had
    purported to issue the direction Circle assigns to them, at the claimed Expectations
    Meeting or otherwise, the record establishes. and Circle concedes, that they did not have
    the express authority to do so (SOF i1,-i 19-2 L 24, 43 ).
    Further, Circle's broad contentions about the engineers' implied authority lack
    evidentiary support. None of Circle's affiants aver that the engineers had such implied
    authority in their experience and, although discovery has occurred, Circle offers no
    material documentation to support its implied authority allegations. Circle cites to
    ACO Hinkamp's declaration concerning the submittal process for its proposition that he
    "merely acted as a conduit for delivering the Engineering Division's comments to Circle"
    (ARF ii 138). However, the declaration does not suggest that the engineers had implied
    authority to approve or reject Circle's submittals, let alone to direct Circle's design
    process. To the contrary, the ACO declared that Messrs. Young and Chiu "had no
    authority themselves to approve or reject submittals. Only the [CO] and [ACO] had
    authority to approve or reject submittals" and "[t]his process is established so that the
    Contractor receives only one official response from a properly designated government
    official, in this case, the ACO." (SOF ii 16, Hinkamp decl. iiii 11, 12)
    Even Mr. O'Brien, the only Circle affiant who claims the direction to use
    CWALSHT occurred, describes the alleged Expectations Meeting as "informal" (SOF
    ii 14, O'Brien aff. iiii 8, 9). As Circle admits, Mr. Duong, the other testifying attendee
    from Circle, has no recollection concerning any discussion about the use of CWALSHT
    software during the Expectations Meeting (SOF iiii 15, 23).
    26
    Circle acknowledges receipt of the CO's letter to ACO Hinkamp at the contract's
    outset advising that the ACO could modify construction contracts under the Changes and
    other clauses up to $100,000 but that the authority was not redelegable (SOF ~ 11).
    Circle also agrees that the ACO advised it at the pre-construction conference that only the
    ACO and the CO were authorized to make changes to the contract (SOF ~ 13 ).
    The Board addressed the question of constructive changes and contracting
    authority in ECC, International, 
    ASBCA No. 55781
    , 13 BCA ~ 35,207, where the
    contractor contended that the government's construction representative/project engineer
    and its CO Rs had issued directives, including wrongful rejection of submittals, causing
    compensable changes. Citing Winter v. Cath-dr!Balti Joint Venture, 
    497 F.3d 1339
     (Fed.
    Cir. 2007), the Board held that, even if events had occurred as the contractor described
    them, and that they could otherwise constitute constructive contract changes, it was
    barred from recovery because none of the officials alleged to have changed the contract's
    requirements were authorized to modify it. 13 BCA ~ 35,207 at 172,738; see also States
    Roofing Corp., ASBCA Nos. 55500, 55503, 09-1 BCA ,-; 34,036 at 168,348 (appeal
    dismissed 
    333 F. App'x 526
     (2009), to the same effect. The same is true here.
    In Cath, the facts supporting a delegation of authority to modify the contract to a
    government representative other than the CO - in that case, the Navy's Resident Officer
    in Charge of Contracts (RO ICC), who was also the Project Manager - were much
    stronger than here, where the individuals alleged to have had implied contract authority
    were engineers. Nonetheless, the court held that, "[b ]ecause the contract explicitly
    reserved authority to modify the contract to the [CO], the ROICC did not have actual
    express or implied authority to direct the contractor to perform compensable contract
    changes.'' Cath, 497 F .3d at 1341. The court elaborated that:
    To demonstrate entitlement to an equitable adjustment, Cath
    must prove that the contract was modified by someone with
    actual authority. Where a party contracts with the
    government, apparent authority of the government's agent to
    modify the contract is not sufficient; an agent must have
    actual authority to bind the government. Such actual
    authority may be express or implied from the authority
    granted to that agent.
    
    Id. at 1344
     (citation omitted). The court pointed to the Changes and other clauses
    reserving authority to the CO to bind the government to contract modifications. Also,
    among other regulations, the court cited to 48 C.F .R. § 43.102(a) ("Only [COs] acting
    within the scope of their authority are empowered to execute contract modifications on
    behalf of the Government."). It also referred to the contract's DFARS 252.201-7000
    clause, included in the instant contract as welt which provides that a COR '"is not
    27
    authorized to make any commitments or changes that will affect price, quality, quantity,
    delivery, or any other term or condition of the contract" (SOF ~ 2b.).
    Regarding the question of implied authority, the court stated that the Navy had
    some blame for contract confusion and the contractor had dutifully complied with the
    Navy's directions for day-to-day contract administration, but the court concluded:
    The problem is that these Navy directives contradicted the
    clear language of the contract and it is the contract which
    governs. The law and the unambiguous contract terms
    compel the result that we reach.
    Authority to bind the government may be implied
    when it is an integral part of the duties assigned to the
    particular government employee .... Here, the ROICC could
    not have had the implicit authority to authorize contract
    modifications because the contract language and the
    government regulation it incorporates by reference explicitly
    state that only the [CO] had the authority to modify the
    contract. Modifying the contract could not be '·considered to
    be an integral part of [the RO ICC project manager's] duties"
    when the contract explicitly and exclusively assigns this duty
    to the CO. We cannot conclude that the [ROICC project
    manager] had implied authority to direct changes in the
    contract in contravention of the unambiguous contract
    language.
    Cath, 
    497 F.3d at 1346
     (citations omitted). Cath controls here.
    In sum, Circle has not proved, as a matter of fact or law, that engineers Young and
    Chiu had the implied authority to direct it to use the CWALSHT design program, or to
    issue the other alleged directives, even if they had attempted to do so. Accordingly, we
    deny Circle's motion for partial summary judgment on liability.
    The Government's Motion for Summary Judgment
    On the other hand, the foregoing establishes that there is no genuine issue of
    material fact that the Corps· engineers lacked the authority, express or implied, to modify
    Circle's contract. Circle has conceded that they lacked the express authority to do so and
    that it was notified that no one, other than the CO and the ACO (up to a point). had the
    authority to change the contract. Circle's contentions that the engineers were cloaked
    with implied authority are conclusory and unsupported by material evidence. They do
    not rise to the level of a genuine issue of material fact.
    28
    Again, Cath controls and the Corps is entitled to judgment as a matter of law.
    Accordingly, we grant the Corps' motion for summary judgment. 3
    DECISION
    We deny Circle's motions to strike and for partial summary judgment and we
    grant the government's cross-motion for summary judgment. The appeal is denied.
    Dated: 1July2015
    c
    oministrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    1~1,~ 11\
    MARK N. STEMPLER /
    Administrative Judge
    I                 RI~KLEFORD
    Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58575
    , Appeal of Circle,
    LLC, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    3
    In view of our disposition, we do not reach the Corps' contention that Circle failed to
    comply with the notice provisions of the Changes clause.
    29