DynPort Vaccine Company LLC ( 2015 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    DynPort Vaccine Company LLC                    )      
    ASBCA No. 59298
    )
    Under Contract No. DAMDl 7-98-C-8024           )
    APPEARANCES FOR THE APPELLANT:                        Carl J. Peckinpaugh, Esq.
    Brian F. Wilbourn, Esq.
    Counsel
    Computer Sciences Corporation
    Falls Church, VA
    APPEARANCES FOR THE GOVERNMENT:                       Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    Kyle E. Chadwick, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE JAMES
    ON APPELLANT'S MOTION TO DISMISS COUNT 3
    OF THE GOVERNMENT'S COMPLAINT
    The Board's 15 January 2015 decision denied the government's motion to
    dismiss the captioned appeal for lack of jurisdiction and ordered the government to file
    the complaint on its claim. See DynPort Vaccine Company LLC, 
    ASBCA No. 59298
    ,
    15-1BCAii35,860 at 175,334 (DVC). Familiarity with that decision is assumed.
    Hence we summarize only the facts pertinent to the instant motion.
    The captioned contract incorporated by reference the FAR 52.246-8,
    INSPECTION OF RESEARCH AND DEVELOPMENT-COST-REIMBURSEMENT (APR 1984)
    clause which provided, as pertinent to the instant motion:
    (h) ... [T]he Government may at any time require the
    Contractor to remedy by correction or replacement,
    without cost to the Government, any failure by the
    Contractor to comply with the requirements of this
    contract, if the failure is due to ( 1) fraud, lack of good
    faith, or willful misconduct on the part of the Contractor's
    managerial personnel or (2) the conduct of one or more of
    the Contractor's employees selected or retained by the
    Contractor after any of the Contractor's management
    personnel has reasonable grounds to believe that the
    employee is habitually careless or unqualified.
    (R4, tab 1 at Bates 57)
    After months of debating which party bore the costs resulting from DVC's
    default termination of subcontractor Lonza Hopkinton, Inc. (LHI), to manufacture
    BOT antigens, unilateral Modification No. P00431 (Mod. 431) directed DVC to
    perform its proposed change order work to add a subcontractor to complete the work
    terminated in LHI's subcontract at an additional cost of $4,629,326.19, but at no cost
    to the government "due to [DVC's] willful managerial misconduct and/or habitual
    employee carelessness." Mod. 431 cited FAR 52.246-8(h), but did not allege breach
    of an implied duty of good faith and fair dealing. We decided Mod. 431 was a
    government claim. See DynPort Vaccine, 15-1BCAif35,860 at 175,331, 175,333-34.
    The government's 31March2015 complaint alleged: "Count I-Habitual
    Carelessness (FAR 52.246-8(h)(2))"; "Count 2-Lack of Good Faith/Willful
    Misconduct (FAR 52.246-8(h)(l))"; "Count 3-Breach of Implied Covenant of Good
    Faith and Fair Dealing" and "51 .... Count 3 arises from the same operative facts as
    Counts 1and2" (compl. at 8, 10, 11). Appellant's answer to paragraph 51 of the
    complaint stated in pertinent part:
    51. . .. To the extent any response is deemed
    necessary, DVC lacks sufficient information to either
    admit or deny the allegations contained in Paragraph 51 of
    the Complaint and, accordingly, denies the same and
    demands strict proof thereof.
    (Answer at 10)
    DECISION
    Appellant argues that the FAR 52.246-8, INSPECTION OF RESEARCH AND
    DEVELOPMENT-COST-REIMBURSEMENT clause requires that a government demand
    for no-cost work must be proven exclusively in accordance with the criteria in
    paragraph (h)(l) or (2) of that clause, citing Century Exploration New Orleans, LLC v.
    United States, 
    745 F.3d 1168
    , 1179 (Fed. Cir. 2014) (the implied duty of good faith
    and fair dealing "cannot expand a party's contractual duties beyond those in the
    express contract or create duties inconsistent with the contract's provisions"), which in
    tum cited Metcalf Construction Co. v. United States, 
    742 F.3d 984
    , 991 (Fed. Cir.
    2014) (an act cannot violate the implied covenant of good faith and fair dealing "if
    such finding would be at odds with the terms of the original bargain, whether by
    2
    altering the contract's discernible allocation of risks and benefits or by conflicting with
    a contract provision.") in support of its motion (app. mot. at 2-3).
    The government argues that Count 3 alleges that appellant "failed to take
    reasonable steps to avoid or to minimize the dire consequences to the government of
    its subcontractor's default, despite repeated warnings that LHI would be unable to
    perform," the government did not assume the risk that DVC would not use its best
    efforts to work with its subcontractor to develop the vaccine, and the R&D Inspection
    clause gives it a non-monetary contract remedy in specified circumstances but does not
    bar the government from seeking monetary damages for breach of the duty of good
    faith and fair dealing equal to DVC's proposed change cost (gov't opp'n at 2-5).
    Appellant rejoins that "this appeal does not involve any government claim for
    money damages," but rather its demand for no-cost work under the R&D Inspection
    clause. Therefore, it "must be proven in accordance with the terms of that clause" and
    it "cannot, as a matter oflaw, prove its case by establishing a breach of the implied
    duty of good faith and fair dealing." (App. reply hr. at 2-3)
    Appellant does not cite any language in the FAR 52.246-8 clause or any legal
    precedent restricting the government's proof to sub-paragraphs (1) and (2) of that
    clause, nor is any known to the Board. Neither Century Exploration nor Metcalf
    Construction addressed our issue of dismissal from a party's pleading a count alleging
    breach of the implied duty of good faith and fair dealing. In Century, though the
    lessee's complaint did not allege a breach of the implied duty of good faith and fair
    dealing, the Federal Circuit did not reject the trial court's introduction of that duty into
    its decision and affirmed its holding that the government did not breach such duty
    because the lease expressly authorized the government action of issuing new, more
    onerous regulations under the Outer Continental Shelf Lands Act.
    In Metcalf, the contractor's sole claim alleged breach of the implied duty of
    good faith and fair dealing. The Federal Circuit Court vacated the trial court's
    decision which misinterpreted the implied duty of good faith and fair dealing to
    require a specific government design (targeting) to reappropriate the benefits that the
    contractor expected to obtain from the contract transaction. These decisions reflect the
    substantive rule urged by appellant and stated in the first paragraph of this decision.
    Appellant points to nothing in Count 3 of the complaint that expands appellant's duties
    beyond, or conflicting or inconsistent with, its duties specified in the FAR 52.247-8
    clause, and no altering of the risks allocated by that clause.
    Pursuant to the Contract Disputes Act of 1978 (CDA), the Federal Circuit held
    in Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed. Cir. 2003) that the
    same claim decided by the CO must be presented to the court; claims do "not require
    3
    l
    i
    rigid adherence to the exact language or structure of the original administrative CDA
    claim [when they] arise from the same operative facts, claim essentially the same
    relief, and merely assert differing legal theories for that recovery." See also American
    General Trading & Contracting, WLL, 
    ASBCA No. 56758
    , 12-1BCAii34,905 at
    171,639 ("[A] claimant is free to change the legal theory ... from what was described in
    the claim .. .if the action continues to arise from the same operative facts that were
    relied upon in the [claim], and essentially seeks the same relief.").
    As summarized above, movant denied that Count 3 arises from the same
    operative facts as Counts 1 and 2, but identifies no evidence of any new or different
    operative facts that must be considered to adjudicate Count 3. The Board will not need
    to review new or unrelated evidence to adjudicate Count 3, which claims essentially
    the same relief as do Counts 1 and 2: contractor liability for the costs of performing its
    remedial change order work at no cost to the government.
    The government argues that the FAR 52.246-8 clause bars it from seeking
    monetary damages for breach of the duty of good faith and fair dealing equal to
    DVC's sum certain proposed change cost (gov't opp'n at 4-5). Indisputably, Mod. 431
    did not claim any monetary damages. See DynPort Vaccine, 15-1 BCA ii 35,860 at
    175,332, ii 11. Therefore, the Board has no CDA jurisdiction to adjudicate a
    government monetary claim raised for the first time in its complaint.* See Optimum
    Services, Inc., 
    ASBCA No. 57575
    , 13 BCA ii 35,412 at 173,726.
    Accordingly, we deny appellant's motion to dismiss Count 3.
    Dated: 12 August 2015
    of Contract Appeals
    (Signatures continued)
    * We have already held that the government's claim herein is a claim for "other
    relief." DynPort Vaccine, 15-1BCAii35,860 at 175,333.
    4
    I concur                                       I concur
    ff;:t/Lff:;if---u _ _ __
    MARK N.    STEMPLE~                            RICHARD SHACKLEFORD
    Administrative Judge                           Administrative Judge
    Acting Chairman                                Vice Chairman
    Armed Services Board                           Armed Services Board
    of Contract Appeals                            of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59298
    , Appeal of DynPort
    Vaccine Company LLC, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 59298

Judges: James

Filed Date: 8/12/2015

Precedential Status: Precedential

Modified Date: 8/24/2015