Avant Assessment, LLC ( 2015 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Avant Assessment, LLC                          )      
    ASBCA No. 58867
    )
    Under Contract No. W9124N-10-C-0109            )
    APPEARANCES FOR THE APPELLANT:                        Mark G. Jackson, Esq.
    Stowell B. Holcomb, Esq.
    Jackson Rosenfield LLP
    Seattle, WA
    APPEARANCES FOR THE GOVERNMENT:                       Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Harry M. Parent III, JA
    Kyle E. Chadwick, Esq.
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON APPELLANT'S
    MOTION FOR SUMMARY JUDGMENT
    INTRODUCTION
    This is a timely appeal, filed on 9 September 2013, from a 26 June 2013
    termination of a supply contract for cause. In its motion for summary judgment,
    appellant, Avant Assessment, LLC (Avant), requests the conversion of the termination
    to one for the convenience of the government. We grant the motion and sustain the
    appeal.
    BACKGROUND
    The following is undisputed. On 29 September 2010, the Department of the
    Army (government) and Avant entered into Contract No. W9124N-10-C-0109 for the
    provision of 3,300 foreign language test items (App. Statement of Undisputed Material
    Facts~~ 1, 3). 1 On 28 September 2012, the parties entered into Modification
    No. P00005, which extended a previous period of performance to 31December2012,
    and provided that ( 1) no later than 1 March 2013, the government would review all
    items that Avant had submitted by 31December2012; (2) "[a]ny items that are still
    1
    The government contests only paragraphs 2 and 15 of Avant's "statement of
    undisputed material facts" (gov't resp. at 1-2). We rely upon neither contested
    paragraph.
    required by the contract but not accepted by the Government shall automatically be
    descoped from the contract"; and (3) "[t]he Government will recover the initial
    submission payments made to the contractor for items that are descoped from the
    contract" (id.~~ 10, 12-13). 2 On 26 June 2013, the government terminated the
    contract for cause, pursuant to subparagraph (m) of Federal Acquisition Regulation
    clause 52.212-4, CONTRACT TERMS AND CONDITIONS-COMMERCIAL ITEMS
    (FEB 2012) (id.~~ 40-41).
    DECISION
    Summary judgment shall be granted if the movant shows that there is no
    genuine dispute as to any material fact and the movant is entitled to judgment as a
    matter of law. FED. R. CIV. P. 56(a); Mingus Constructors, Inc. v. United States,
    
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987). The government bears the burden of proof on
    the issue of the correctness of its actions in terminating a contractor for cause. See
    Lisbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 764 (Fed. Cir. 1987).
    Avant has shown that there is no genuine dispute as to any material fact and
    that it is entitled to judgment as a matter of law. The only justification that the
    government offers for terminating the contract for cause is that, it contends, Avant
    "fail[ ed] to deliver the required number" - 3,300 - "of acceptable test items" (gov't
    resp. at 4). The government elaborates that "[t]he items submitted by [Avant] were
    subsequently inspected and rejected, justifying the termination for cause" (id. at 5).
    However, Modification No. P00005 provides that any items not accepted by the
    government would be "descoped" from the contract. That is, with Modification
    No. P00005, the contract no longer required Avant to deliver 3,330 acceptable items;
    rather, any shortfall from that number would be removed "automatically" from the
    contract's scope, and the government would recover from Avant any initial submission
    payments that the government had made to Avant for items submitted by 31 December
    2012 that the government's review determined were unacceptable. In effect,
    Modification No. P00005 reduced the number of acceptable items that the contract
    required that Avant deliver from 3,300 to however many acceptable items the
    government determined Avant had delivered by 31December2012. Consequently,
    we agree with Avant that, as of 28 September 2012, the date that the parties entered
    into Modification No. P00005, delivering fewer than 3,300 acceptable items was not
    cause for terminating the contract.
    For these reasons, the motion is granted, and the appeal is sustained. Because
    of this decision, we find it unnecessary to address Avant's argument that the
    government waived the contract's 31 December 2012 delivery date.
    2
    Our paragraph citations incorporate the motion exhibits cited in footnotes to the cited
    paragraphs.
    2
    CONCLUSION
    The appeal is sustained, and the termination for cause is converted to one for
    the convenience of the government.
    Dated: 11 August 2015
    ~c~
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    ~/~
    //~£~-
    / 'MARKN. STEMPLER /
    ~                           --M
    RICHARD SHACKLEFORD
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeal in 
    ASBCA No. 58867
    , Appeal of Avant
    Assessment, LLC, rendered in conformance with the Board's Charter.
    Dated:    AUG 2 0 2015
    Recorder, Armed Services
    Board of Contract Appeals
    3
    

Document Info

Docket Number: ASBCA No. 58867

Judges: McIlmail

Filed Date: 8/11/2015

Precedential Status: Precedential

Modified Date: 8/24/2015