Herai Alpha Construction Consultancy and Engineering Company ( 2015 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                               )
    )
    Herai Alpha Construction Consultancy        )     ASBCA Nos. 59386, 59774
    and Engineering Company                    )
    )
    Under Contract No. W5J9JE-13-C-0028         )
    APPEARANCE FOR THE APPELLANT:                     William J. Spriggs, Esq.
    Spriggs Consulting Services
    Lynchburg, VA
    APPEARANCES FOR THE GOVERNMENT:                   Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    James D. Stephens, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, Middle East
    Winchester, VA
    OPINION BY ADMINISTRATIVE JUDGE DELMAN
    ON APPELLANT'S MOTION FOR SUMMARY JUDGMENT
    Herai Alpha Construction Consultancy and Engineering Company (appellant) has
    filed a motion for a summary judgment, seeking reversal of a default termination under
    ASBCA No. 59386 and its conversion to a termination for convenience.* The government
    has filed in opposition to summary judgment. ASBCA No. 59774 relates to a deemed
    denial of appellant's affirmative claim for money and time. While appellant's motion
    captions both appeals, the motion does not substantively address appellant's affirmative
    claim. Accordingly, we address the motion solely as it pertains to the default termination
    under ASBCA No. 59386. We have jurisdiction under the Contract Disputes Act, 41 U.S.C.
    §§ 7101-7109.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. On 3 1 May 2013, appellant and the government entered into this contract for
    design and construction of a "Forward Area Arming and Refuel Point," in Kunduz
    Province, Afghanistan (R4, tab 9). The contract incorporated the following standard
    provisions by reference: FAR 52.233-1, DISPUTES (JUL 2002); FAR 52.243-4, CHANGES
    * Appellant's motion was dated 23 March 2015. On 24 March 2015, appellant filed a
    revised motion, adding a paragraph to its "Statement of Undisp"uted Material
    Facts" and attaching a declaration of its project manager.
    (JUN 2007); FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4,
    tab 9 at 18-19).
    2. The contract contained a 450-day period of performance (R4, tab 9 at 19). On
    24 June 2013, the government issued a notice to proceed to appellant, making the contract
    completion date (CCD) 18 September 2014 (supp. R4, tab 49). On 13 April 2014, the
    parties agreed to a 34-day time extension for weather and security-related delays, making
    the CCD 22 October 2014 (supp. R4, tab 46).
    3. During March-April 2014, the government sent appellant a number ofletters
    expressing concern with appellant's quality control, safety, and design implementation
    (R4, tabs 27, 28, 33). On 8 March 2014, appellant submitted to the government, by email,
    a request for equitable adjustment (REA). The REA sought a 167-day time extension for
    various delays for which appellant believed it was not responsible. (App. supp. R4,
    tab A-12)
    4. The contracting officer (CO) acknowledged receipt of the REA by email on
    10 March 2014. He replied as follows:
    Sir,
    I have received your SL H-0001 requesting 167 days - this
    is surprising to me since we have removed a large portion
    of the contract. You will be receiving a formal reply
    within the next 3 0 days - but based on this new
    information- I'm going to[] recommend to the customer
    that the entire project be terminated.
    (App. supp. R4, tab A-14) According to appellant's project manager, appellant did not
    receive any reply to its REA from the government (app. revised mot., attach., decl. if 6).
    5. The government issued to appellant proposals for work change on 18 February
    2014 (R4, tab 25) and on 22 March 2014 (R4, tab 31 ). Appellant submitted responses to
    these proposals but according to appellant's project manager, the government never
    responded (app. revised mot., attach., decl. if 7).
    6. The government issued a partial clearance for construction on 27 March 2014,
    as per 65% design approval (R4, tab 32). It also issued a partial clearance for
    construction on 24 April 2014, as per 95% design approval (R4, tab 34).
    7. On 30 April 2014, the CO issued a written notice to the appellant, suspending all
    work on the project. No reason was provided for this suspension. (R4, tab 35)
    2
    8. By letter to appellant dated 11May2014, the CO issued a final decision (COFD)
    terminating the contract for default. Insofar as pertinent, the COFD stated as follows:
    FACTUAL BACKGROUND:
    Currently, this contract is over 300 days into the period of
    performance and according to schedule the project should
    be 64% complete. However, HACC&E has only
    completed 9% of the work to date. HACC&E is still
    missing critical submittals to start construction work. In
    addition, mobilization was slow and the contractor has an
    insufficient workforce to complete the project by the
    required date.
    CONSIDERATION OF THE FACTORS: In
    accordance with FAR 49.402-3 (f), I am required to
    consider the following factors prior to reaching a decision
    as to whether to terminate this contract for default. Below
    is my consideration of each of the factors and my
    termination decision.
    2. The specific failure of the contractor and the excuses
    for the failure:
    i. As outlined above, HACC&E has failed to prosecute the
    work. HACC&C is currently over 300 days into the period
    of performance and has made little progress on this project.
    As noted, the construction as scheduled should be 64%
    complete at this point in the contrac[t]; however,
    HACC&E has only completed 9% of the work. HACC&E
    has been advised by the Government that it is not
    proceeding satisfactorily and has not adequately staffI ed]
    the project.
    Reference Serial letters: C-0006, Letter of Concern dated
    1 March 2014, C0007, Letter of Concern dated 3 March
    2014, al)d COOlO, Corrective Action dated 7 April 2014.
    ii. Given the contractor's lack of responsiveness and
    reliability, I cannot see how HACC(&E] can successfully
    complete this project.
    3
    7. Any other pertinent facts or circumstances:
    Contractor has been slow to mobilize to the project
    site, they were slow to provide a list of government
    furnished material to the point that we were forced into a
    position that would have required the government to
    modify the contract to have the contractor provide the
    material.
    A partial Termination for Convenience (T4C) was
    issued to remove 6 buildings from the contract to ensure
    completion of the project in the required time frame.
    Instead of speeding up construction the contractor came
    back and asked for additional time to complete less work.
    An RFP was issued to change many of the facilities
    to a more austere standard, HVAC units were replaced by
    simple wood burning stoves, and roads were left unpaved,
    yet the contractor again requested more time.
    In conclusion, the acts and omissions constituting
    the default is because of no significant progress on the
    project.
    Based on the above, the undersigned determines
    that a termination for default of this contract is proper and
    in the best interest of the Government. USACE does not
    intend to reprocure this project.
    (R4, tab 2)
    9. The COFD did not expressly address appellant's request for a 167-day time
    extension. According to the CO, he did consider the REA and concluded that it was
    without merit (gov't reply, attach., decl. ir 4). Appellant challenges whether the CO did
    in fact review the matter prior to the default termination decision, and even if he did,
    appellant challenges the CO's conclusion, asserting that appellant was in fact entitled to
    the 167-day time extension, and was thus entitled to a progress review based upon the
    CCD as so extended.
    10. Appellant timely appealed the COFD to this Board, and the appeal was docketed
    as ASBCA No. 59386.
    4
    11. On 30 October 2014, appellant submitted a certified claim to the CO, seeking an
    equitable adjustment in the amount of $1,722,800 and a time extension in the amount of
    239 days (supp. R4, tab 45). The CO did not issue a decision on this claim. Appellant
    appealed the deemed denial of its claim to the Board, and the appeal was docketed as
    ASBCA No. 59774. The appeals were consolidated.
    DECISION
    It is well settled that in order for a party to obtain summary judgment it must show
    that the material facts are undisputed and it is entitled to judgment as a matter of law.
    Mingus Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987).
    Appellant has not shown that the material facts are undisputed here. We find a
    number of such fact disputes of record, including ( 1) whether the CO' s decision to terminate
    for default was based upon an assessment of appellant's construction progress, taking into
    account any of the 167-day excusable delay asserted by the contractor; and (2) ifthe CO
    made such an assessment prior to his decision, whether such an assessment was correct.
    Given these material fact disputes, summary judgment is not appropriate.
    Appellant's motion for summary judgment is denied.
    Dated: 17 August 2015
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    _#_~-/~--'-/,/
    y_.;._;:J_~---1.'----=~------~ ~
    MARK N. STEMPL R                                  RICHARD SHACKLEFORD
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    5
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 59386, 59774, Appeals of
    Herai Alpha Construction Consultancy and Engineering Company, rendered in
    conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    6
    

Document Info

Docket Number: ASBCA No. 59386, 59774

Judges: Delman

Filed Date: 8/17/2015

Precedential Status: Precedential

Modified Date: 8/31/2015