AMEC Environment & Infrastructure, Inc. ( 2015 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                       )
    )
    AMEC Environment & Infrastructure, Inc.           )      
    ASBCA No. 58948
    )
    Under Contract No. FA8903-06-D-8507               )
    APPEARANCES FOR THE APPELLANT:                           David A. Rose, Esq.
    Gary L. Moser, Esq.
    Rose Consulting Law Firm
    Valdosta, GA
    APPEARANCES FOR THE GOVERNMENT:                          Lt Col James H. Kennedy III, USAF
    Air Force Chief Trial Attorney
    Christopher M. McNulty, Esq.
    Sarah L. Stanton, Esq.
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE O'CONNELL ON THE
    GOVERNMENT'S MOTION FOR PARTIAL SUMMARY JUDGMENT
    This matter is before the Board on the government's 8 August 2014 motion for
    partial summary judgment pursuant to Board Rule 7(c). Appellant, AMEC
    Environment & Infrastructure, Inc. (AMEC), has appealed a contracting officer's final
    decision denying AMEC's certified claim on a project for the design and construction
    of a building at Andrews Air Force base. The claim consists of two discrete issues:
    1) $192,062 for the repair of damaged fiber optic cable; and 2) $28,639 in costs related
    to an alleged change in permitting requirements by the Maryland Department of the
    Environment (MDE). It is the latter issue that is the subject of the government's
    motion. For the reasons stated below, the government's motion is granted.
    STATEMENT OFF ACTS (SOF) FOR PURPOSES OF THE MOTION
    Except as noted, the following material facts are undisputed 1:
    1
    In its brief, AMEC disputes only a small number of the 77 paragraphs in the
    government's statement of undisputed facts (nos. 12, 21, 28-30, 32, 38, 41, 44,
    and 46). However, it fails to identify with specificity why it disputes these facts
    and, in most cases, it simply repeats what the government stated in the proposed
    finding. Board Rule 7(c)(2) provides that:
    The parties should explicitly state and support by specific
    evidence all facts and legal arguments necessary to sustain
    1. On 12 April 2006, the Air Force awarded AMEC, then known as AMEC
    Earth & Environmental, Inc., a firm-fixed-price, indefinite quantity basic contract,
    No. FA8903-06-D-8507, for Heavy Engineering Repair and Construction (R4, tab 1).
    2. On 9 July 2008, the Air Force Center for Engineering and the Environment
    (AFCEE) issued Request for Proposal No. FA8903-06-R-9991-R025 (the RFP), which
    called for the issuance of a task order under the basic contract for the design and
    construction of a new strategic planning and development facility at Andrews Air
    Force Base, Maryland (R4, tab 9a).
    3. On 23 October 2008, AFCEE awarded task order No. 16 to AMEC in the
    amount of $28,953,273 (R4, tab 3). The task order incorporated the technical
    specifications of the RFP into the contract (R4, tab 3 at 10).
    4. Pursuant to the Clean Water Act, 
    33 U.S.C. § 1251
     et seq., and the National
    Pollutant Discharge Elimination System permit program, 
    33 U.S.C. § 1342
    , to control
    discharges into the navigable waters, Maryland construction projects of one acre or
    more of earth disturbance must obtain coverage under an Individual or General Permit
    for Stormwater Associated with Construction Activity. The Environmental Protection
    Agency has delegated to MDE the authority to issue these permits. (R4, tab 9f at 880,
    1113, tab 158, ~~ 4-5)
    5. As detailed extensively in the government's brief, the basic contract and the
    technical specifications incorporated into the task order contained numerous
    provisions that detailed the contractor's responsibility to obtain the stormwater
    discharge permit. Among other provisions, they incorporated FAR 52.236-7, PERMITS
    AND RESPONSIBILITIES (Nov 1991) (R4, tab 1 at 58, tab 9f at 81 ). This clause
    provides in relevant part:
    The Contractor shall, without additional expense to
    the Government, be responsible for obtaining any
    necessary licenses and permits, and for complying with
    any Federal, State, and municipal laws, codes, and
    regulations applicable to the performance of the work.
    6. At the time AMEC prepared its bid, and at the time that the parties executed
    the task order, there was a general permit in place. A general permit is a discharge
    a party's position. Each party should cite to the record and
    attach any additional evidence upon which it relies.... The
    Board may accept a fact properly proposed and supported
    by one party as undisputed, unless the opposing party
    properly responds and establishes that it is in dispute.
    2
    permit that is issued to a class of dischargers. See Code of Maryland Regulations
    (COMAR) 26.08.0l.Ol(B)(35). The amount of work involved in obtaining coverage
    under an existing general permit versus applying for and obtaining an individual
    permit is disputed. (See, e.g., R4, tab 158, if 7) For purposes of this motion, we will
    assume that there is a significant amount of additional work to obtain an individual
    permit.
    7. The technical specifications for the RFP (as incorporated in the task order)
    referenced the contractor obtaining coverage under the general permit, including the
    following:
    1.6.10    STORM WATER DISCHARGE PERMIT AND
    STORMWATER POLLUTION PREVENTION
    PLAN
    In conjunction with the Construction Officer, the
    Contractor shall apply for and obtain coverage
    under State of Maryland MDE General Permit
    for Discharges of Storm Water from
    Construction Activities when 1 or more acres (or
    0.4 or more hectares) ofland area are disturbed
    by construction or related construction support
    operations, including clearing, grubbing,
    grading, excavation, soil or gravel lay down
    areas, and demolition that exposes soil.
    (R4, tab 9f at 81) There does not appear to be any reference in the technical
    specifications to an individual permit.
    8. The crux of the problem here is that the existing general permit,
    No. MDRl 0, expired on 31 December 2008, a little more than two months after task
    order execution. This permit clearly stated that it would expire on that date. 2 (General
    NPDES Permit Number MDRlO (MDRlO), cover page). It also stated that MDE had
    the authority to require an individual permit (MDRlO at 1).
    9. A new General Permit for Stormwater Associated with Construction
    Activity was set to take effect on 1 January 2009, but it did not due to a "legal
    challenge" on 31 December 2008. The legal challenge resolved on 13 July 2009, but
    2
    By Order dated 13 January 2015, the Board directed the parties to file a copy of the
    general permit. The Air Force filed the general permit with the Board on
    27 January 2015. By letter to the Board dated 13 February 2015, AMEC
    confirmed that the permit filed by the Air Force was the general permit that was
    in effect until 31 December 2008.
    3
    between 1 January 2009 and 13 July 2009, MDE required all applicants to apply for
    and obtain an individual permit. (R4, tab 158, ~ 4)
    10. These events not only caught AMEC by surprise but, according to AMEC,
    both the legal challenge and the non-renewal of the general permit caught MDE by
    surprise as well (compl. ~ 4 ). AMEC does not allege that the government knew about
    these events in advance and/or caused the non-renewal of the general permit.
    11. MDRlO provided that a contractor that wished to obtain coverage under the
    permit must submit an application, referred to as a notice of intent, that contained
    various information about the project (MDRlO at 2-3). It is undisputed that, if AMEC
    or any contractor had submitted a valid notice of intent and application for coverage
    under the existing general permit prior to 1 January 2009, it would not have been
    required to apply for an individual permit (R4, tab 15 8, ~ 11 ). It is not entirely clear
    when AMEC applied for an individual permit but it is undisputed that it was after
    1 January (see, e.g., R4, tab 15) (AMEC letter to Air Force dated 13 February 2009
    stating that individual permit would be required).
    12. In its proposal for the task order, AMEC represented that its "local
    professionals" in its northern Virginia office were "well versed in the environmental
    requirements for this project in Maryland." Further, it stated that its "knowledge of the
    local environmental regulations and permitting requirements will help us
    prepare ... permit applications that will streamline the permitting process." (R4, tab 11
    at 29-30)
    13. On 26 September 2011, AMEC submitted a request for equitable
    adjustment seeking costs related to the permitting issue that it estimated at $26,341
    (R4, tab 76 at 1-6). On 20 March 2013, AMEC submitted a certified claim seeking
    $28,639 related to the permitting issue (R4, tab 82). The contracting officer denied the
    claim in a decision dated 8 July 2013 (R4, tab 83 at 1-7).
    DECISION
    Summary judgment is appropriate when there is no genuine issue of material
    fact and the moving party is entitled to judgment as a matter of law. Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986). When considering a motion for
    summary judgment, the Board's function is not to weigh the evidence and determine
    the truth of the matter but to determine whether there is a genuine issue for trial. 
    Id. at 249
    . The moving party bears the burden of establishing the absence of any genuine
    issue of material fact and all significant doubt over factual issues must be resolved in
    favor of the party opposing summary judgment. However, the party opposing
    summary judgment must show an evidentiary conflict on the record; mere denials or
    conclusory statements are not sufficient. Mingus Constructors, Inc. v. United States,
    
    812 F.2d 1387
    , 1390-91 (Fed. Cir. 1987).
    4
    The most cogent explanation of AMEC's legal theory is contained in the REA it
    submitted to the contracting officer and later incorporated in its claim. (AMEC's
    complaint responds to certain paragraphs in the contracting officer's final decision but
    does not contain a recitation of the facts or an explanation of its legal theory.
    Similarly, its brief contains no meaningful recitation of the facts or law from its
    perspective.) According to the REA, AMEC is entitled to recover under a constructive
    change theory. (R4, tab 76 at 1)
    The Court of Appeals for the Federal Circuit recently considered a claim for a
    constructive change in a case involving similar facts. In Bell/Heery v. United States,
    the contract for the design/build of a federal correctional institute required the
    contractor to perform cut-to-fill operations in compliance with the rules and
    regulations of the New Hampshire Department of Environmental Sciences.
    Bell/Heery, 
    739 F.3d 1324
    , 1326 (Fed. Cir. 2014). These requirements included
    obtaining and complying with an Alteration of Terrain (AOT) permit. 
    Id. at 1326-27
    .
    According to the complaint, the state agency would not allow the contractor to perform
    cut-to-fill operations in the manner upon which the contractor calculated its bid and it
    imposed numerous restrictions that went beyond the standard AOT permit
    requirements. 
    Id. at 1329
    . The contract in Bell/Heery contained the same Permits and
    Responsibilities clause as the contract in this case. 
    Id. at 1327
    .
    The Federal Circuit rejected the contractor's claim for a constructive change.
    As the Court of Appeals observed, to demonstrate a constructive change, the contractor
    must show: (1) that it performed work beyond the contract requirements; and (2) that
    the additional work was ordered, expressly or impliedly by the government.
    Bell/Heery, 739 F.3d at 1335. The Court of Appeals held that the complaint solely
    alleged that the actions of the state caused the contractor to incur the additional costs,
    and that the contractor failed to allege that the Federal Government demanded
    additional work beyond that required by the contract. Id.
    The Federal Circuit's opinion in Bell/Heery governs this case. The additional
    work that AMEC contends it performed arose as a result of a change in the state
    permitting requirements (SOF ~ 9). AMEC does not allege that the Federal
    government played any role in the non-renewal of the general permit. AMEC also
    does not allege that the Federal government required AMEC to perform any work
    beyond that required by the task order. In fact, AMEC's complaint affirmatively states
    that "[t]he physical requirements to implement erosion controls in accordance with
    MDE standards and Best Management Practices did not change" and AMEC did not
    request costs for any such work. To the contrary, the complaint states that its claim is
    solely for the additional time, expenses and professional services required to obtain the
    individual permit from MDE. (Compl. at 1-2) Under these facts, AMEC cannot
    recover for a constructive change. Bell/Heery, 739 F.3d at 1335.
    5
    To the extent that AMEC's complaint could be read as asserting a theory other
    than constructive change, we observe that the Federal Circuit in Bell/Heery also
    rejected the contractor's claim for relief based on a breach of contract. The Court of
    Federal Claims had rejected this contention, holding:
    [T]hat the Permits and Responsibilities clause clearly and
    unambiguously allocated the costs for complying with all
    permit requirements solely to BH because that clause
    expressly states that "[t]he Contractor shall, without
    additional expense to the Government, be responsible for
    obtaining any necessary licenses and permits, and/or
    complying with any Federal, State, and municipal laws,
    codes, and regulations applicable to the performance of the
    work .... "
    Bell/Heery, 739 F.3d at 1331. The Federal Circuit affirmed, holding that because "the
    Permits and Responsibilities clause ... unequivocally assigns all of the risk for
    complying with the permitting requirements" to the contractor without additional cost
    to the government and because the contractor had failed to identify any countervailing
    contractual duty, the trial court correctly dismissed the contractor's breach of contract
    claim. Id. at 1334.
    AMEC does not address the Permits and Responsibilities clause in its brief.
    However, it seems to contend that, because the contract referenced the procedures that
    were in place for obtaining coverage under the general permit, it should be
    compensated for any work beyond obtaining such coverage. But it is undisputed that
    AMEC was required to obtain an NPDES permit to perform the contract work and that
    the existing permit expired on 31 December 2008. Thus, if AMEC were unable to
    submit a notice of intent seeking coverage under the old permit by 31 December 2008,
    it would have had to obtain a permit under whatever procedures MDE implemented on
    1 January 2009. AMEC seems to have assumed that those procedures would be no
    more burdensome than the procedures that were in place until 31 December 2008. But
    the government made no such representation, and the contract provided no assurance
    that AMEC would be compensated for increased permitting costs after 1 January 2009.
    The Permits and Responsibilities clause addressed costs incurred in obtaining
    permits and it clearly required AMEC to obtain the necessary permits at no additional
    expense to the government. Because the Permits and Responsibilities clause placed
    this burden on the contractor, as a matter of law, it may not recover any additional
    expenses from the government.
    6
    CONCLUSION
    For the foregoing reasons, the government's motion for partial summary
    judgment is granted and the appeal is denied with respect to the claim for additional
    costs associated with permitting requirements.
    Dated: 16 March 2015
    lrJJkL~~
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur
    ---AA:/
    I concur
    d:~~
    Administrative Judge
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 58948
    , Appeal of AMEC
    Environment & Infrastructure, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    7
    

Document Info

Docket Number: ASBCA No. 58948

Judges: O'Connell

Filed Date: 3/16/2015

Precedential Status: Precedential

Modified Date: 3/31/2015