Capy Machine Shop, Inc. ( 2014 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                     )
    )
    Capy Machine Shop, Inc.                          )      
    ASBCA No. 59133
    )
    Under Contract No. SPE4A7-13-M-D099              )
    APPEARANCE FOR THE APPELLANT:                           Mr. Salvatore Capacchione
    President
    APPEARANCES FOR THE GOVERNMENT:                         Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Edward R. Murray, Esq.
    Adrienne D. Bolton, Esq.
    Trial Attorneys
    DLA Aviation
    Richmond, VA
    OPINION BY ADMINISTRATIVE JUDGE TUNKS ON THE GOVERNMENTS
    MOTION FOR SUMMARY JUDGMENT
    This appeal arises from the termination for default of an order to supply parts for
    the A-10 aircraft to the Defense Logistics Agency Aviation (DLA Aviation or
    government). DLA Aviation moves for summary judgment, alleging that there are no
    material facts in dispute and that it is entitled to judgment as a matter of law on the
    ground of anticipatory repudiation and appellant's alleged default is unexcused.
    Capy Machine Shop, Inc., (Capy or appellant) opposes the motion.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. On 9 July 2013, Mr. John Vlachos, general manager of Capy, accepted Order
    No. SPE4A7-13-M-D099 to provide 27 splice fairings to DLA Aviation. The order also
    required submission of one first article test for a total contract price of $52,232.85. 1 The
    first article delivery date was 6 January 2014. (R4, tab 9 at 1)
    2. The order incorporated FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND
    SERVICE) (APR 1984) by reference which provides, in part, as follows:
    (a)(l) The Government may, subject to paragraphs
    (c) and (d) of this clause, by written notice of default to the
    1
    The order resulted from a Request for Quotations issued by the government on
    3 June 2013 (R4, tabs 3, 4).
    Contractor, terminate this contract in whole or in part if the
    Contractor fails to-
    (i) Deliver the supplies or to perform the services
    within the time specified in this contract or any extension;
    (c) Except for defaults of subcontractors at any tier,
    the Contractor shall not be liable for any excess costs if the
    failure to perform the contract arises from causes beyond
    the control and without the fault or negligence of the
    Contractor. Examples of such causes include ( 1) acts of
    God or of the public enemy, (2) acts of the Government in
    either its sovereign or contractual capacity, (3) fires,
    (4) floods, ( 5) epidemics, (6) quarantine restrictions,
    (7) strikes, (8) freight embargoes, and (9) unusually severe
    weather. In each instance the failure to perform must be
    beyond the control and without the fault or negligence of
    the Contractor.
    ( d) If the failure to perform is caused by the default
    of a subcontractor at any tier, and ifthe cause of the default
    is beyond the control of both the Contractor and
    subcontractor, and without the fault or negligence of either,
    the Contractor shall not be liable for any excess costs for
    failure to perform, unless the subcontracted supplies or
    services were obtainable from other sources in sufficient
    time for the Contractor to meet the required delivery
    schedule.
    (R4, tab 1at18of18)
    3. On 7 November 2013, Mr. Vlachos emailed Mr. Donnie W. Graves, the
    contracting officer (CO), as follows:
    Please cancel the above contract at no cost to Capy
    Machine.
    Our forming vendor can't locate his tooling[.]
    (R4, tab 6)
    2
    4. On 13 November 2013, CO Graves issued a show cause notice to Capy:
    Because you have indicated in an e-mail dated
    07 NOV 2013 citing an inability to locate tooling on
    contract SPE4A7-13-M-D099 within the time required by
    its terms and thereby requesting termination for
    convenience, the Government is considering terminating
    this contract under the provisions for default. Pending a
    final decision in this matter, it will be necessary to
    determine whether your failure to perform arose from
    causes beyond your control and without your fault or
    negligence. Accordingly, you are given the opportunity to
    present, in writing, any facts bearing on the question to
    me ... within 10 days after receipt of this notice.
    If you have any questions, please contact
    Len DuPilka, Contract Administrator ....
    (R4, tab 7)
    5. On 26 November 2013, Mr. Vlachos emailed Mr. Len J. DuPilka, the contract
    administrator, as follows:
    The cost of new tooling is $26,512.00 total which wasn't
    included on the quote.
    That is the reason for asking to cancel this contract.
    (R4, tab 8)
    6. The record contains a quotation from Banner Metalcraft, Inc., dated
    23 September 2013, the contract having been awarded on 9 July 2013, which includes a
    one-time tooling charge of $26,512.00 (Bd. corr., attach. to notice of appeal).
    7. On 12 December 2013, Ms. Janice Hicks, the terminating contracting officer
    (TCO), terminated the contract for default, stating as follows:
    You are hereby notified that contract SPE4A7-13-M-D099
    is terminated for default effective immediately. Your right
    to proceed further with performance of this contract is
    terminated. The termination is based on your failure to
    perform in accordance with the terms and conditions of the
    3
    contract. The terminated supplies may be procured against
    your account and you will be held liable for excess costs.
    (R4, tab 10)
    8. On 9 January 2014, Capy appealed the TCO's final decision to this Board
    where it was docketed as 
    ASBCA No. 59133
    . The following was attached to Capy's
    notice of appeal:
    These parts required tooling. When we quoted the
    solicitation the tooling was available to us. After we were
    awarded this order we found out that the tooling could not
    be located. This meant that we would have to create new
    tooling at [a] cost of$26,512.00. This cost was not
    included in our original quote.... We could not afford to
    complete this order so we requested a cancellation with no
    cost to either party.
    DECISION
    Summary judgment is properly granted only where the moving party has met its
    burden of proving the absence of any genuine issue of material fact and that it is entitled
    to judgment as a matter of law. Mingus Constructors, Inc. v. United States, 812 .2d 1387,
    1390 (Fed. Cir. 1987). The government bears the burden of proof to justify the default
    termination. When the government establishes a prima facie case that the termination
    was justified, the burden shifts to the contractor to demonstrate that the default was
    excusable. Hanley Industries, Inc., 
    ASBCA No. 56584
    , 14-1 BCA ii 35,699.
    The government argues that there are no material facts in dispute and that it is
    entitled to summary judgment on the ground of anticipatory repudiation. The record
    establishes that the first article delivery date was 6 January 2014. By email dated
    7 November 2013, Mr. Vlachos, Capy's general manager, requested CO Graves to cancel
    the contract at no cost because its forming vendor could not find the necessary tooling.
    On 26 November 2013, Mr. Vlachos emailed Mr. DuPilka, the contract administrator,
    again requesting that the government cancel the contract on the same grounds.
    The government has not demonstrated that Capy repudiated the contract.
    Anticipatory repudiation requires a "positive, definite, unconditional, and unequivocal"
    manifestation on the part of the contractor that he will not perform the contract. Cascade
    Pacific International v. United States, 
    773 F.2d 287
    , 293 (Fed. Cir. 1985). Capy
    communicated with the CO twice before the contract was terminated. On 7 November
    2013, Capy requested a no cost cancellation, stating that its "forming vendor can't locate
    his tooling." On 26 November 2013, Capy advised that the "cost of new tooling is
    $26,512.00 total which wasn't included on the quote. That is the reason for asking to
    4
    cancel this contract." These communications do not reflect a positive, definite,
    unconditional and unequivocal refusal to perform.
    Accordingly, the government's motion for summary judgment is denied.
    Dated: 22 October 2014
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    &~-~-
    MARK N. STEMPLER
    Administrative Judge
    RICHARD SHACKLEFORD
    Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59133
    , Appeal of Capy
    Machine Shop, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 59133

Judges: Tunks

Filed Date: 10/22/2014

Precedential Status: Precedential

Modified Date: 11/3/2014