Technology Systems, Inc. ( 2017 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Technology Systems, Inc.                      )       ASBCA No. 59577
    )
    Under Contract Nos. N00039-07-C-0006          )
    N00014-07-C-0236          )
    N00014-07-C-0340          )
    N41756-05-C-4775          )
    APPEARANCE FOR THE APPELLANT:                         Mr. Charles J. Benton
    President/Owner
    APPEARANCES FOR THE GOVERNMENT:                       E. Michael Chiaparas, Esq.
    DCMA Chief Trial Attorney
    Debra E. Berg, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Boston, MA
    OPINION BY ADMINISTRATIVE JUDGE PROUTY
    This appeal, brought by Technology Systems, Inc. (TSI), challenges the final
    decision of the Defense Contract Management Agency (DCMA) administrative
    contracting officer (ACO) to follow the recommendation of the Defense Contract Audit
    Agency (DCAA) and disallow certain expenses used to calculate its indirect cost rates for
    fiscal year (FY) 2007 as well as some direct costs. In addition to certain cost-specific
    arguments, TSI argues, in general, that the disallowed expenses had not been questioned
    by prior DCAA audits and that it relied upon this to its detriment because it did not
    preserve what DCAA would have considered to be necessary evidence for the FY 2007
    costs in question. The amount in dispute is the $159,303 that the government seeks to
    recoup from TSI after finding the already-paid costs to be unsupported.
    Judge Clarke heard this appeal and, for reasons detailed in his dissenting opinion
    and discussed further below, is of the view that TSI is entitled to significant relief through
    an application of the retroactive disallowance doctrine and as a result of the government's
    past course of conduct, and that it is due some other relief for different reasons. Though
    not unsympathetic to TSI, we respectfully disagree with our colleague and deny portions
    of the appeal that he would sustain (although also granting it in part): the DCMA-
    challenged costs were largely not allowable and, without more, an auditor's failure to
    challenge a cost in one audit does not require application of the principle of retroactive
    disallowance nor does it constitute a course of conduct precluding the government from
    disallowing the costs in subsequent audits.
    FINDINGS OF FACT
    TSI is a small technology business that, while operational, 1 conducted research
    and development of software systems relating to new ways. for ship navigation
    (tr. 2/227). TSI employed approximately 20 people (tr. 21193), including three
    executives: Mr. Charles Benton, chief technology officer, president and sole owner
    (tr. 2/229-30); Mr. Maxwell Fletcher, chief financial officer (CFO) (tr. 2/117); and
    Mr. Thomas Zysk, chief operating officer (COO) (tr. 2173, 76, 102). Mr. Benton started
    TSI in 1985 and it began contracting with the government in 1987 (tr. 2/230).
    During the time relevant to this appeal, TSI had four cost-plus-fixed-fee (CPFF)
    contracts for research and development with the Navy: Contract Nos. N00039-07-C-0006
    (0006), N00014-07-C-0236 (0236), N00014-07-C-0340 (0340), and N41756-05-C-4775
    (4775)2 (R4, tabs 1-3, 16 at 268, tab 17 at 269). These contracts contained standard clauses
    from the Federal Acquisition Regulation (FAR) that governed the payment of their costs by
    the government. 3 In a typical CPFF contract, subject to the standard FAR clauses included
    here, the government compensates a contractor for two types of costs: direct and indirect.
    FAR 52.216-7(b ). Direct costs, as suggested by the name, are those costs directly incurred
    for performing task orders on a contract. See FAR 2.101, Definitions, Direct Costs.
    Indirect costs are overhead costs that the company incurs during the time of contract
    performance that cannot be allocated to a single "cost objective." FAR 31.203(b). They
    are allocated to the contract on a pro rata basis, based upon the direct costs incurred during
    the base time period, typically the contractor's fiscal year. 4 FAR 31.203(b)-(g); see also
    1
    TSI ceased operations in August 2014, but continued to exist "on paper" to permit
    this litigation (tr. 2/230).
    2
    Contract 4775 was identified as a classified contract and a copy is not in the record
    (R4, tab 53 at 910).
    3
    Contracts 0006, 0236 and 0340 contained the following standard clauses: FAR 52.215-2,
    AUDIT AND RECORDS-NEGOTIATION (JUN 1999); FAR 52.216-7, ALLOWABLE
    COST AND PAYMENT (DEC 2002); FAR 52.233-1, DISPUTES (JUL 2002);
    FAR 52.242-1, NOTICE OF INTENT TO DISALLOW COSTS (APR 1984); FAR 52.242-3,
    PENALTIES FOR UNALLOWABLE COSTS (MA y 2001 ); and FAR 52.244-2,
    SUBCONTRACTS (AUG 1988), (contract 0006) or 1998 (contracts 0236, 0340)
    (R4, tabs 1-3). We infer that contract 4775 also had these required clauses.
    4
    Indirect costs are billed at a percentage rate which is based on the notion of dividing
    the pool of such costs for a year by the company's direct expenses for the year.
    To provide a rudimentary example, if a company incurred $50,000 in allowable
    overhead costs for a year and $100,000 in direct costs for the same year, its
    indirect cost rate would be 50%, which would lead to the invoicing of $500 of
    2
    KAREN L. MANOS, GOVERNMENT CONTRACT COSTS & PRICING, § 7:A:2 (2003). Whether
    a cost claimed by the contractor is compensated by the government is dependent upon both
    whether the costs claimed are allowable under the contract (which is controlled by the
    FAR) and whether they are satisfactorily proved to have been incurred as shown in the
    records maintained by the contractor. FAR 52.216-7(b )(1 )(ii)(F).
    In any event, a contractor with a CPFF contract generally regularly invoices the
    government for its direct and indirect costs throughout contract performance and is
    paid by the CO if he or she is provisionally satisfied that the costs are allowable and
    have been incurred (tr. 2/21-22). FAR 52.216-7(a)(l). Indirect costs are billed and
    initially paid at estimated rates. FAR 52.216-7(e). Often these estimated rates are
    submitted to DCAA prior to billing for review and provisional approval, but this does
    not always happen (tr. 1/28-31).
    Within six months of the end of the contractor's fiscal year, it is required to
    submit to the C0 5 and the CO's auditor (here, the DCAA) a "final indirect cost rate
    proposal" (ICP), which is based on the actual indirect costs incurred by the contractor
    during the time period of that fiscal year. FAR 52.216-7(d)(2)(i)-(iii). DCAA auditors
    typically select those portions of the ICP that appear most ripe for review and
    concentrate their review upon them because it would be impractical to closely audit
    the entirety of the IPC (tr. 1/21-22, 24). Upon completion of its review, the DCAA
    shares its audit results and recommendations with the CO, who is required to make an
    independent determination of whether to accept them (tr. 1/253). If costs are
    questioned, the CO ha~ authority to negotiate with the contractor regarding which
    costs would be approved. FAR 52.216-7(d)(3). After the indirect cost rates are agreed
    to between the contractor and the government (or, absent agreement, the government
    imposes its own rates upon the contract), the contractor is required to update the prior
    billing to reflect the final indirect cost rates. FAR 52.216-7(d)(2)(v).
    DCAAIDCMA Audit History Prior to FY 2007
    Ms. Winefield, a DCAA supervisory auditor, testified that DCAA conducted full
    audits of TS I's ICPs for FYs 1998 - 2003 and for FY 2006 (tr. 1/28). The FY 2001
    audit questioned several costs but it primarily questioned $70,072 in the Professional
    Fees Cost Element claimed in overhead and in G&A 6 for Messrs. Kemper, Ring and
    Wilson (ex. G-1 at 4-5, 9-11 ). These costs were questioned because, among other
    indirect costs for every $1,000 in direct costs charged to the government.
    Further complicating matters, contractors often (and appropriately) establish
    separate pools to associate particular overhead costs with different categories of
    direct costs such as labor and materials. FAR 31.203( c).
    5 The role of the CO here is interchangeable with the role of the ACO.
    6 "G&A" refers to "general and administrative" costs.
    3
    reasons, TSI failed to provide evidence supporting the work performed by the
    consultants, including "actual work product" (id.; see also tr. 1/84). The FY 2001 audit
    resulted in negotiations between the ACO and TSI, and a rate agreement was achieved
    (tr. 2/256). For FYs 2002 through 2006, DCAAIDCMA did not question costs and
    accepted TSI's indirect rates without change (tr. 2/60-63; R4, tab 6(a) at 72, tab 70 at
    1554). DCAA conducted a "desk review" for FYs 2004 and 2005. A desk review is not
    a full audit. (Tr. 1116-17, 26-28) The desk review for TSI's FY 2005 ICP included the
    statement, "We determined that no significant costs were questioned in prior years and
    that no indicators of audit risk had been identified" (app. supp. R4, tab 100 at 2904).
    The FY 2006 audit was a full audit (tr. 21174). This audit included the statement that,
    "In our opinion, the contractor's indirect rates are acceptable as proposed" (app. supp.
    R4, tab 101at6105).
    The FY 2007 Audit and Decrement Memorandum
    TSI's FY 2007 ICP was submitted on or about 25 June 2008 (R4, tab 15 at 227),
    and DCAA began its review of this ICP in the fall of 2008 (tr. 1/36). Ms. Waller and
    Ms. Pitts were the DCAA auditors conducting the audit (tr. 21161; R4, tab 53 at 626).
    Shortly after the audit began, TSI's relationship with Ms. Waller ran into
    difficulties. At the hearing, Mr. Fletcher testified that Ms. Waller "lost her temper'"
    during a meeting held on Friday, 17 October 2008 (tr. 21162; R4, tab 109). Mr. Benton,
    who was not present at the meeting, complained about it in a 20 October 2008 email to
    ACO Murray 7 (app. supp. R4, tab 103). Mr. Fletcher testified that he called ACO Murray
    complaining about Ms. Waller and that, in response, ACO Murray stated that TSI would
    not get an objective audit from Ms. Waller and that she (ACO Murray) would see that
    TSI got another auditor (tr. 2/163). A TSI-requested meeting with the government about
    Ms. Waller was subsequently held on 12 November 2008, with ACO Murray and
    Ms. Waller among the attendees. TSI asked that Ms. Waller be replaced (R4, tab 107 at
    1), but the government declined to do so (tr. 21164; R4, tab 107 at 2-3 ). ACO Murray
    also denied any memory of promising TSI that it would be getting a new auditor to
    replace Ms. Waller (R4, tab 107 at 3). 8
    Ms. Waller submitted her draft audit for peer review on 27 April 2009
    (R4, tab 53 at 552). At this point, outside concerns intervened, and DCAA ordered a
    halt to all incurred costs audits agency-wide so that it could focus on pricing audits
    that were holding up awards of contracts across the government (tr. 1/38, 42-43).
    When TSI's incurred cost audit was stopped, Ms. Waller had completed a substantial
    amount of the work. Her draft audit questioned over $360,000 in direct and indirect
    7
    ACO Murray was close to retirement and was later replaced by ACO Cuellar (app.
    supp. R4, tab 122 at 1; tr. 11227).
    8
    Neither party called Ms. Waller as a witness at the hearing.
    4
    costs (R4, tab 53 at 559-608). These questioned costs produced recalculated indirect
    cost rates, which we set forth, along with TSI's ICP, in Table I below:
    TABLE 1:
    Claimed by TSI              Draft audit recommended
    OHC9l Rate                  127.64%                     92.48%
    G&ARate                      18.40%                     12.02%
    Material OH Rate              1.05%                      0.00%
    (R4, tab 53 at 557)
    Some four years later, in 2013, DCAA grew concerned about the pending running
    of the statute of limitations acting to limit any potential recovery of mischarged
    expenses, and resumed its audit of TSI's FY 2007 ICP (tr. 1143). In April 2013
    Ms. Cote, a senior DCAA auditor, was assigned to review the status of the TSI audit
    (tr. 1144, 46; R4, tab 48). Ms. Cote submitted her findings in July 2013. She determined
    that more information was needed from TSI to complete the audit. (Tr. 1/44-47; R4,
    tabs 49, 50) Mr. Darcy, another DCAA senior auditor, was then assigned to finish the
    TSI audit (tr. 1148).
    By letter dated 18 March 2014 to ACO Cuellar, DCAA wrote that it was unable
    to meet the required audit date 10 and was withdrawing from "our engagement to audit
    the subject [TSI's] incurred cost proposal" (app. supp. R4, tab 136). The primary
    roadblock to a complete audit, apparently, was DCAA's inability to complete
    "additional [transaction] testing" of TS I's direct labor rates (tr. 1152). In any event,
    DCAA agreed to provide "non-audit" service to assist DCMA in determining final
    indirect cost rates for TSI in FY 2007 (tr. 11173-74, 230-32; app. supp. R4, tab 136).
    Also on 18 March 2014, DCAA provided ACO Cuellar a "decrement memo"
    itemizing the costs it questioned (tr. 1152-53; R4, tab 4). The memorandum stated,
    "Providing this information does not constitute an audit or attestation engagement
    under generally accepted government auditing standards" (R4, tab 4 at 2).
    The recommended rates in the decrement memo, compared to the rates
    originally requested by TSI, are reflected in Table 2 below:
    9
    OH represents labor overhead costs.
    10   DCAA calculated that the six-year limitation period would run out on 25 June 2014
    (tr. 11213).
    5
    TABLE 2:
    Claimed by TSI                Memo Recommended
    OH Rate                      127.64%                       106.26%
    G&ARate                       18.40%                        15.80%
    Material 0 H Rate              1.05%                         1.05%
    (R4, tab 4 at 48-49)
    The decrement memo did not question as many costs as Ms. Waller's draft
    audit had (compare Tables 1 and 2 above and R4, tab 4 to R4, tab 53; see also R4,
    tab 59 at 1466 (Mr. Darcy explaining, in a spreadsheet emailed to ACO Cuellar on
    14 April 2014, that he was not taking as much of a "hard line" on certain labor costs as
    Ms. Waller had) and tr. 1/ 218-19 (same)).
    The A CO 's Determination
    On 4 April 2014, after she received DCAA's decrement memo, ACO Cuellar
    emailed Mr. Benton, providing him with a copy of the decrement memo, requesting
    any additional data that he might want to submit, and offering to set up a time to meet
    (tr. 1/233-34; R4, tab 5). ACO Cuellar's email offered to close-out the action without
    assessing a penalty if TSI would accept DCAA's questioned costs (tr. 1/235-36).
    By email dated 23 April 2014 to ACO Cuellar, Mr. Benton stated that he did
    not accept the offer, argued that DCAA had not questioned similar costs in the
    past, and submitted documents aimed at supporting TSI's position (tr. 1/237-38; R4,
    tabs 6, 6(a)-(g)). ACO Cuellar acknowledged TSI's "non-acceptance of the
    Government's offer" in an email sent on 6 May 2014, stating in part:
    We understand your argument that DCAA has historically
    not questioned these costs; however, that does not mean
    DCAA deems those costs to be allowable. We here at
    DCMA cannot speak for the DCAA auditor(s) that
    performed the reviews, nor can we speak for the sampling
    methodology used by DCAA. Our job will be to address
    the audit as written. If you are able to substantiate the
    costs with the required documentation, we will reinstate
    the costs. If not, we have to sustain the costs.
    (R4, tab 7; tr. 1/238) Mr. Benton replied, submitting some additional information on
    12 May 2014, but ACO Cuellar considered most of this information to have been already
    provided to DCAA. She was, however, able to allow some previously-disallowed costs
    based on the new information (tr. 1/237-40; R4, tabs 9, 9(a)-(e)). ACO Cuellar testified
    6
    that she continued to attempt to negotiate with TSI, requesting additional documentation
    such as evidence of approval of subcontracts by the ACO, meeting notes, trip reports,
    bonus plan information, etc. (tr. 11242-45). By email dated 15 May 2014 to ACO Cuellar,
    Mr. Benton provided a statement to the effect that TSI was no longer interested in
    negotiations (tr. 1/245; R4, tabs 13, 13(a)). In the email, Mr. Benton complained that
    DCAA had significantly altered its view of the allowability of its costs in 2007 compared
    to previous years (R4, tab 13(a) at 212-13).
    ACO Cuellar issued a contracting officer's final decision (COFD) on 23 June 2014,
    setting the final determination of TSI' s rates and asserting a government claim for
    $159,303 (tr. 1/153; R4, tab 16). To arrive at this figure, she recalculated the overhead and
    G&A costs by decreasing their respective pools by the costs that she found disallowable
    (R4, tab 16 at 256-58, 263). She then used the revised allowable cost pools to generate
    revised overheard and G&A rates, which are reflected in Table 3, below:
    TABLE 3:
    Claimed by TSI                ACO Determined
    OH Rate                        127.64%                       109.88%
    G&ARate                         18.40%                       15.83%
    Material OH Rate                 1.05%                        1.05%
    (Id. at 263)
    ACO Cuellar then multiplied the allowable direct costs (which had also been
    decreased by questioned costs) by the difference in the revised indirect cost rates, and added
    the unallowable direct costs, which summed to the $159,303 claimed (R4, tab 16 at 263-64).
    We now tum to a closer examination of the cost components disallowed by the ACO.
    Disallowed Components of (Labor) 11 Overhead Costs
    The ACO disallowed four price components that were associated with the Overhead
    cost pool: professional fees to Strategic Marketing Innovations (SMI); the expensing of
    computer supplies; conferences; and "fringe benefits" (R4, tab 16 at 257). We examine
    each in tum.
    11   Often the parties and the documents in this appeal refer to an indirect cost pool of
    "overhead" costs, which is separate and apart from the G&A and Material
    Handling indirect cost pools. Although it is not an issue in this appeal, this
    nomenclature can be confusing. The "overhead" indirect price pool refers to a
    price pool that TSI tied to direct labor costs (see R4, tab 6(a) at 72; see also
    ex. G-1 at 2).
    7
    Professional Fees to SM!
    SMI was a consultant hired by TSI to provide it with both marketing and
    lobbying services (tr. 2/241-42). It had separate agreements with TSI for each (see R4,
    tab 53 at 1088, 1089), and invoiced TSI separately for each (see 
    id. at 1134-4
    7).
    ACO Cuellar disallowed the $51,340 claimed by TSI for the marketing services
    provided by SMI on the grounds that TSI did not provide enough documentation to
    permit an understanding of the work performed nor did it provide the "work products"
    and other items that the ACO believed were required in accordance with the provisions
    of FAR 31.205-33(t)(2) and (3) (R4, tab 16 at 258).
    Computer Supplies Expensed
    TSI "expensed" $26, 198 in computer supplies for the 2007 fiscal year (R4, tab 16
    at 258). The ACO disallowed this expense because depreciation over a multi-year
    period was deemed more consistent with TSI's past practice and thus more appropriate
    (id. at 258-59). Moreover, $18,840 of these computer expenses claimed by TSI had
    been claimed as depreciable assets in TSI's 2007 tax filings, indicating to the ACO that
    they should not have been "expensed" (id. at 259).
    Conferences
    The ACO disallowed $2,300 in claimed entertainment expenses for a meal that
    was not related to company business (R4, tab 16 at 259). TSI concurred with the ACO
    on this matter, which is no longer in dispute (id.).
    The ACO also disallowed $304 in per diem for conference attendance because
    it was more than permitted in the Joint Travel Regulations (JTR) (R4, tab 16 at 259).
    Fringe Benefits (Bonuses for TS! Executives)
    The ACO disallowed $29,967 in claimed compensation that TSI used as bonuses
    for its top three executives (TSI allocated $25,698 of this money to the Overhead pool
    with the remaining $4,269 being allocated to the G&A pool) (R4, tab 16 at 259). The
    basis for the ACO's decision was that TSI allegedly did not provide documentation to
    demonstrate an agreed-upon bonus plan, nor sufficient evidence to document the basis of
    its awards (id.). The ACO also disallowed some of the bonuses because they were paid in
    March 2008, in the fiscal year after FY 2007, which is the subject of this ICP (id. at 260).
    8
    Disallowed Components ofG&A Costs
    The ACO disallowed four components of G&A costs: professional fees;
    conferences; fringe benefits (a portion of the executive bonuses mentioned in the
    Labor Overhead pool above); and "B&P Overhead" (R4, tab 16 at 257). Again, we
    explain these in more detail below.
    Professional Fees (Primarily Attorney Fees)
    TSI expensed $39,060 in professional fees in FY 2007 that were disallowed by the
    ACO (R4, tab 16 at 260). Of this amount, $34,429 was to a law firm for expenses
    incurred in 2002-2005 when TSI was being criminally investigated by the government,
    not FY 2007; $1,000 was to the same law firm for preparation of Mr. Benton's income
    taxes; $706 was to the law firm for work involving the sale of a different company and
    for corporate database updates for a new company, which the ACO stated was disallowed
    by the FAR; and the remaining $2,925 was money paid to Mr. Charles Wilson for
    professional services that he provided to TSI (id.). The ACO also noted that the $34,429
    paid to the law firm for expenses during TSI's investigation would be reduced by 20%
    even if it were allowable because the FAR limits recovery of such costs to 80% of those
    incurred (id. at 260-61 ).
    TSI does not appear to dispute the ACO's finding that $1,706 in billing by the
    law firm was for matters not recoverable; nor that the law firm's representation of TSI
    during the criminal investigation needed to be discounted by the FAR-mandated 20%;
    it does, however, assert that it should be eligible for the (20%-discounted) money paid
    to the law firm because it was improper for it to seek payment until after the criminal
    investigation was closed (R4, tab 6(a) at 77). TSI also argued that Mr. Wilson had
    long provided useful advice to the company at a favorable rate and that DCAA had not
    questioned his billings in the past (R4, tab 6(a) at 78).
    Conferences
    The ACO disallowed $577 in claimed travel expenses that, she claimed, exceeded
    the maximum allowable per diem rates for lodging and meals (R4, tab 16 at 261 ).
    Fringe Benefits
    This is the same matter involving executive bonuses that is referenced with respect
    to questioned Overhead costs, above, and it sums to $4,269 (R4, tab 16 at 257, 261).
    9
    B&P Overhead
    The ACO did not elaborate (and this cost component was barely touched upom
    at the hearing), but the basis of this decrement was that labor used for bids and
    proposals (B&P) had been charged at a higher overhead rate than the amount the ACO
    found appropriate (R4, tab 16 at 261 ). The difference summed to $2,417 (id.).
    Disallowed Direct Costs
    There were some direct costs that were disallowed by the ACO as well. The ACO
    disallowed $1,07 4 of direct costs claimed under contract 0006 because the travel per diem
    rates sought by TSI exceeded those in the JTR (R4, tab 16 at 261). The ACO disallowed
    $466 of direct costs claimed under contract 0236 for similar reasons (id.), and disallowed
    an additional $2,661 on that contract because it was for the use of a subcontractor for
    which TSI had not sought prior approval from the ACO (id. at 261-62). Finally, the ACO
    disallowed $1,986 of direct costs claimed under contract 0340 for exceeding the per diem
    rates in the JTR and an additional $28,568 for the use of a subcontractor without prior
    approval (id. at 262).
    The Appeal
    TSI timely appealed the 23 June 2014 final decision by letter dated 17 September
    2014. The Board docketed the appeal as ASBCA No. 59577 on 18 September 2014.
    The Evidence Presented at the Hearing and Our Factual Conclusions
    As reflected by the approach taken in Judge Clarke's dissenting opinion, the
    evidentiary case advanced at the hearing focused less upon whether the particular
    decisions taken by the ACO were supported by the facts and more about whether the
    DCAA auditor had so changed the government's approach to TSI's proposal as to be
    unfair (see, e.g., app. br. at 1). There was, however, evidence presented about some of
    the particulars of the questioned costs, which we will also discuss below.
    Evidence Regarding the Differences in the Audits Previous to the 2007 JCP
    TSI advances two somewhat related factual allegations that are relevant to its
    course of conduct legal theory, which we will discuss shortly: first, that the DCAA
    auditor who performed the initial work on the FY 2007 ICP audit was, for some
    unstated reason, biased against TSI; and second, that the DCAA had been much easier
    on it in past audits (app. br. at 3-5; app. reply br. at 10-11). In testimony presented by
    TSI, Mr. Fletcher, its CFO, characterized the first DCAA auditor, Ms. Waller, as
    having been "on a witch hunt" (tr. 2/165). Moreover, as discussed above, there was
    ample evidence of friction between Ms. Waller and TSI and early indications from TSI
    10
    that it did not believe that it would get a "fair" audit from Ms. Waller. Nevertheless,
    the evidence also demonstrates that the preliminary work performed by Ms. Waller
    was not the end of the story, given the change in questioned costs demonstrated most
    clearly by Tables 1, 2, and 3 above. Moreover, the ACO credibly testified that her
    decisions regarding which costs to question were made independently (tr. 1/251 ),
    which is consistent with the back-and-forth which she attempted with TSI prior to
    issuing her COFD. We need not delve into these circumstances any further due to the
    fact that TSI, itself, has "concede[ d]" that its claim that the COFD should be set aside
    due to lack of auditor independence "cannot be sustained" (app. br. at 3).
    With respect to the allegation that DCAA had questioned fewer costs in prior
    audits, as discussed above, the evidence supports this contention (notably, the findings
    in the audits for FYs 2002-2006 and ACO Cuellar's 6 May 2014 email implicitly
    conceding the point), but the factual record is ambiguous, at best, with respect to the
    meaning of that fact. First, as we earlier noted, there is uncontested evidence that
    DCAA did question a substantial portion of professional costs in the FY 2001 ICP
    audit, and we specifically find that the government questioned some of TS I's
    professional services costs in its FY 2001 ICP audit on the basis that TSI failed to
    substantiate 12 them, including failing to provide any work product. Second, a number
    of the expenses questioned in the FY 2007 ICP audit were presented for the first time
    in that proposal, leaving no track record by DCAA with respect to such costs. These
    issues include the attorney fees, the executive bonuses, and the complete expensing of
    the computers. Notably, we have searched the evidentiary record for any indication
    that DCAA, the ACO, or any other person representing the government ever
    communicated to TSI that its incurred costs could be considered to be substantiated or
    proved at any different standard than that set out in the FAR; that anybody from the
    government had ever told TSI, specifically, that the proof that it submitted with prior
    ICPs constituted adequate substantiation for the expenses; or that any such persons had
    ever told TSI that no proof beyond what it had previously provided in its ICPs would
    ever be required by the government. There is, quite simply, no such evidence in the
    record. Finally, we note that Mr. Fletcher, TSI's CFO, testified that he understood that
    DCAA did not examine all the costs in any given ICP (tr. 2/175), which cuts against
    any inference that failure to challenge costs in a particular year constitutes an
    indication that the government finds the cost to be allowable.
    12
    The term, "substantiate," is not found in the relevant portion of the FAR and, is also
    absent from the COFD (see R4, tab 16). Nevertheless, the government's
    correspondence with TSI (see R4, tab 7) and its COFD indicate that the word is meant
    to be interchangeable with "provid[ing] adequate support" (e.g., R4, tab 16 at 258,
    260) or "sufficient evidence" (id. at 259), which we find to be appropriate.
    11
    Evidence Relating to Specific Costs
    We now turn from the general to the specific and make factual findings with
    respect to the components of the COFD.
    Marketing Consulting Costs Paid to SM!
    The Rule 4 file contains invoices from SMI for every month of 2007, breaking
    out, by the hour, what conferences that it attended on TSI's behalf; who it met with;
    and the topics of conversation (R4, tab 20). The Rule 4 file also contains the
    marketing consulting agreement between SMI and TSI (R4, tab 53). This agreement
    includes the statements that SMI will be expected to "[p]rovide position papers and
    relevant data on issues as required" and "[p]rovide a monthly report on SMI marketing
    and business development activities related to TSI projects" (R4. tab 53 at 1092).
    There is no evidence before us, however, of any "work product" from SMI, nor are
    there any minutes of meetings or "collateral memoranda and reports."
    At the hearing, Mr. Zysk, TSI's COO, testified that he was the primary point of
    contact for SMI regarding marketing matters and that he was not involved in lobbying
    (which is a disallowed cost) (tr. 2/85-88). Mr. Zysk further testified that his telephone
    conversations with SMI provided him the information that he needed from SMI to do
    his work and that waiting for more formal write-ups would have been unnecessary and
    taken too much time (tr. 2/86). Given Mr. Zysk's unchallenged and credible testimony
    and the details contained in the invoices, we find that there is no reason to believe that
    SMI charged TSI for lobbying or other unallowable costs in the guise of its fees for
    marketing consulting. We also find that the details contained in the SMI invoices are
    adequate to support a finding that SMI worked the hours charged.
    The Expensing of Computers
    TSI's CFO, Mr. Fletcher, testified regarding the depreciation of computers.
    According to Mr. Fletcher, some computers were for research and were "taken
    apart, components soldered on, sensors added in" and built into systems that would
    go out on vehicles/boats for testing (tr. 2/131, 205). They were "heavily modified"
    (tr. 2/221-22). After testing was complete the computer was "of no use" to TSI and it
    was "expensed" (tr. 2/131-32). Mr. Fletcher also testified that TSI also bought
    computers that were used on desks for routine office work and those computers were
    capitalized/depreciated (tr. 2/132) in contrast to the computers that were consumed in
    the research work that were expensed (tr. 2/133-34).
    Prior to 2007, there was no evidence that TSI had ever completely expensed its
    computers in one year (tr. 1/88). Indeed, TSI's books included accounts referencing
    continued depreciation of computers over multiple years that included FY 2007 (e.g.,
    12
    TSI purchased a laptop in 2004 and continued to write off its depreciation into 2007,
    even while it completely expensed similar laptops bought in 2007) (tr. 1/89-90). In
    2007, however, TSI did take advantage of "IRS Code Section 179," which permits
    small businesses to fully expense an asset (tr. 1/88).
    As far as we can tell, TSI completely expensed every computer that it purchased
    in 2007 in its FY 2007 ICP, and explained its practice to the ACO by asserting that it
    was a "leading edge software Research and Development firm" for which most
    computing equipment was obsolete within a year of purchase (see R4, tab 6(a) at 75).
    In this communication, TSI made no mention of the heavy modifications that allegedly
    made the computers useless after a year (id.). Based upon the evidence before us, we
    conclude that some of the computer equipment completely expensed by TSI was likely
    so modified that it could not be used beyond FY 2007, 13 and that other computer
    equipment obtained in FY 2007 and also expensed by TSI was not so modified.
    Indeed, Mr. Fletcher's testimony is completely lacking with respect to explaining what
    efforts TSI undertook to identify which computer expenses went to the heavily
    modified computers consumed in research and which computer expenses went to
    computers more routinely used by the company (see tr. 2/131-34).
    Conference Costs
    The $304 that remains at issue in this appeal under Overhead and the $577 asserted
    under G&A represent claimed travel expenses that exceeded the maximum daily per diem
    rates (tr. 11259). The COFD referred to the travel expenses being beyond the per diem
    rates in the "Joint Travel Regulations pursuant to FAR 31.205-46(a)(2)," (R4, tab 16 at
    259), and the DCAA decrement memo also referenced the prices as exceeding the amounts
    permitted by the JTR and thus unallowable under FAR 31.205-46(a)(2) (R4, tab 4 at 57).
    The travel referenced was, it turns out, within the Continental United States (see tr. 2/134 ),
    to which the parties agree the JTR is not applicable, but the Federal Travel Regulation
    (FTR) is (see app. br. at 10; gov't br. at 58). There is no evidentiary dispute that TSI's
    travel costs exceeded the per diem set forth in the FTR by the same amount challenged by
    the ACO's COFD (see tr. 1/101; app. br. at 10).
    Executive Bonuses
    Mr. Fletcher, TSI's CFO, testified that he created a bonus plan for himself,
    Mr. Benton, and Mr. Zysk sometime in late 2006 (tr. 2/189). He did so with the input
    of Mr. Benton, Mr. Zysk, and a former DCAA attorney (tr. 2/137), and it was
    13   It is worth noting here that TSI has given no explanation why such computers
    would constitute indirect costs, rather than costs that could be applied to
    identifiable contracts.
    13
    memorialized in a one-page document, signed by Mr. Benton and dated "l Dec 06" 14
    (R4, tab 9(c) at 129; tr. 2/138). The document provided that a "bonus pool," equating
    to 9% of the labor charges of these three executives would "be managed•by consensus
    decision of the [three named executives]" (R4, tab 9(c) at 129). It also specified that
    the three executives would meet quarterly "to adjust bonus pools based on company
    performance metrics" (id.). The metrics were listed "to include" orders, sales,
    backlog, revenue, overhead rates, special accomplishments, and successful program
    management (id.). It did not specify how these metrics were to be measured or by
    what criteria the three executives would determine the appropriate amount of bonus to
    award (id.). Mr. Fletcher testified that the pool "[came] out of company profits.
    I mean, where else would it come from?" (Tr. 21174) The one-page document
    outlining the bonus plan was apparently provided to the government for use in a
    provisional review of anticipated FY 2007 indirect costs, (tr. 2/146-51 ), but, as noted
    above, no government auditor ever performed such a provisional review of FY 2007
    costs (tr. 1131 ).
    The record includes three memoranda written to justify bonus awards, which
    are dated 30 May 2007 (R4, tab 9(c) at 130); 14 September 2007 (id. at 131); and
    27 February 2008 (id. at 132-33). The 30 May 2007 memorandum lists 5 bullet-point
    achievements for TSI and recommends $1,000 bonuses for each of the three
    executives. The 14 September 2007 memorandum listed 9 bullet-point achievements
    (repeating some of those in the 30 May 2007 memorandum) and recommended an
    award of "the bonus pool as it stands at the end of August 2007" to the 3 TSI
    executives (id. at 131). Finally, the 27 February 2008 memorandum, signed by
    Mr. Benton, included 11 bullet-point achievements (building upon those in the
    14 September 2007 memorandum) and authorized distribution of the award pool, as it
    stood on 1 January 2008, to Mr. Zysk for $9,000 and Mr. Fletcher for $6,000 (id. at
    133). TSI's internal timesheet reports reflect these payments as having been made the
    next day, on 28 February 2008 (id. at 134). Mr. Fletcher testified that, although the
    payment was made in 2008, the cost "accrued during the fiscal year 2007 because that
    was the year the expense was applicable to - that was the year that we did well and
    performed well" (tr. 21140). None of the three memoranda in any way quantify the
    metrics with respect to how they determined the amount of the recommended bonuses
    (see R4, tab 9( c) at 131-34).
    Mr. Fletcher testified that he met with DCAA auditor Marie Pepin for
    approximately two hours on 28 February 2008 to discuss the ICP for FY 2007 that
    would be submitted later in 2008, and raised the executive bonus plan with her during
    this discussion (tr. 2/121-22). According to Mr. Fletcher, Ms. Pepin said words to the
    14
    Although the document may appear to be aspirational or to be promising a plan in
    the future in the sense that it states that TSI "will establish a process," (see R4,
    tab 9(c) at 129), the document is apparently the plan, itself (tr. 21195).
    14
    effect of "this looks good to me," and then they moved on to other subjects (tr. 2/123).
    We find, as a matter of fact, that this discussion was relatively short and superficial in
    nature and did not constitute any representation that the government gave final
    approval to the bonus plan as proposed or executed.
    Legal Fees
    In 2002, the Naval Criminal Investigative Service (NCIS) began a criminal
    investigation of The Kemper Group, Inc. for overbilling, and later expanded the
    investigation to include TSI and Sonetech Corporation (Sonetech) (R4, tab 16 at 260; see
    also tr. 2/233). During this investigation, TSI was represented by the law firm of Preti
    Flaherty, LLC, which caused TSI to incur $34,429 in costs associated with the
    investigation from 2002 to 2005 (R4, tab 16 at 260, see also tab 53 at 1279-80). The
    investigation closed, with no decision to prosecute, in 2005, with NCIS sending a letter to
    Sonetech, advising it as much, but apparently not sending separate correspondence to TSI
    (see R4, tab 53 at 1278; tr. 2/234). On 20 June 2006, Sonetech faxed this NCIS
    correspondence to TSI (id.).
    TSI was prohibited by FAR 31.205-4 7 from seeking payment for the costs of
    defending itself in the investigation until after it was concluded without a finding of
    criminal conduct. According to the COFD, this prohibition prevented TSI from
    submitting its legal costs contemporaneously with their being incurred, 15 but the
    reason that TSI gave the DCAA for submitting the costs in the FY 2007 ICP, instead
    of in 2006 (when it supposedly became aware of the fact that it was cleared of
    wrongdoing), was that it "forgot" (R4, tab 16 at 260). Mr. Fletcher (with whom
    DCAA was dealing and would have been the person who DCAA claimed stated that
    he "forgot" to include the legal fees in FY 2006) denies ever making such a statement
    to DCAA (tr. 2/212).
    Through Mr. Benton's testimony, TSI alleged that it did not truly consider itself
    out of the woods, with respect to the investigation, until sometime in 2007 when NCIS
    returned documents to it (tr. 2/234-37). Based upon the testimony, we find it more
    probable than not that TSI was uncertain of the status of the investigation until 2007,
    which is the year for which it submitted its legal expenses.
    Consulting Fees a/Charles Wilson
    Charles Wilson was a childhood friend of Mr. Benton's who signed a consulting
    agreement with TSI in 2005 (tr. 2/238-40; R4, tab 53 at 1026-27). The services specified
    in this two-page agreement were somewhat vague: Mr. Wilson was to provide
    15   Neither party argued that, subsequent to being cleared, TSI should have revised its
    2002-2005 ICPs to include the legal costs as being incurred in those years.
    15
    -----1
    compensated $100 per hour (R4, tab 53 at 1026-27). As Mr. Benton explained, he
    brought a business perspective to the company that Mr. Benton did not have the
    background to provide (tr. 2/238-40). Subsequent to the initiation of the DCAA audit of
    the FY 2007 ICP, TSI created a "Statement of Work" providing further detail of
    Mr. Wilson's duties, explaining his support to TSI (R4, tab 53 at 1039). The after-the-fact
    Statement of Work has little evidentiary value to us; nevertheless, despite their prior
    friendship, we are persuaded that Mr. Benton's retention of Mr. Wilson was legitimately
    intended to provide a business resource to the company.
    In 2007, Mr. Wilson charged $2,925 to TSI for consulting fees (see R4, tab 53
    at 1028, 1031, 1034, 1036). With these bills, Mr. Wilson specified the dates and hours
    that he spoke with TSI personnel or communicated with them via email, and included
    the general subjects about which they communicated (see R4, tabi 53 at 1030, 1033,
    1035, 1037-38). TSI has not provided any "work product" from Mr. Wilson, but did
    produce multiple emails on TSI business issues from 2007 to demonstrate that he was
    "in the loop" for company decisions (id. at 1040-86).
    Upon review of the invoices from Mr. Wilson submitted by TSI and
    considering their level of detail and the email traffic indicating his inclusion of
    discussions of company affairs, we find there to be adequate substantiation of his work
    to support a finding that he performed the hours billed. We further determine that the
    rate of $100 per hour was not, on its face, unreasonable.
    Direct Travel Costs
    There is no factual dispute that the direct travel costs for contracts 0006, 0236,
    and 0340 exceeded the maximum allowable per diem rates by $1,074, $466, and
    $1,986, respectively (R4, tab 16 at 261-62; tr. 1/268).
    Subcontractor Costs
    The "Subcontracts" clause, included in all four contracts, generally requires that
    prime contractors that do not have an approved purchasing system must obtain the CO's
    written consent to enter into cost-reimbursement, time-and-materials or labor-hour
    subcontracts. FAR 52.244-2(d)(l) (1988, 1998). TSI did not have an approved
    purchasing system (which is not atypical for a contractor of its size (tr. 2/55, 65)) and, as
    a result, was required by the contract to obtain approval to enter into subcontracts from
    the CO (tr. 2/55). This, it did not do for the time-and-materials subcontracts questioned
    by the ACO (R4, tab 16 at 261-62, tab 6(a) at 79-80; tr. 1/130-31, 2/58). Mr. Fletcher
    testified on TSI's behalf that it generally did not seek pre-approval for its actions because
    it had found it difficult to contact the ACO (tr. 2/135-36).
    16
    After DCAA identified the subcontracts that had not received prior approval
    and recommended their complete disapproval, ACO Cuellar requested that it attempt a
    post hoc justification of their prices (tr. 11250-51, 271 ). She allowed the cost for one
    of the questioned subcontracts because DCAA was able to perform an analysis that
    demonstrated the prices to be fair and reasonable (id., tr. 1/269). For the others,
    however, DCAA and the ACO felt themselves unable to perform such a post hoc
    justification of the costs with the information provided (tr. 11271-73 ). These costs
    were in the amount of $2,661 under contract 0236 (R4, tab 16 at 261) and $28,568
    under contract 0340 (id. at 262).
    In December 2008, after it became clear that approval of subcontracting costs
    would be an issue in the audit, Mr. Benton reached out to DCMA ACO, then,
    Ms. Sandee Murray, and requested retroactive approval of some the subcontract awards
    (R4, tab 6(f)). There was no apparent government response to this letter, and, in 2014,
    Mr. Benton reached out to a number of people seeking support for the subcontract costs.
    The record includes emails from Mr. Timothy Devin, Mr. Adam Cascioli (project officer
    for contract 0340), and Mr. Brian Almquist (the contracting officer's technical
    representative (COTR)) (app. supp. R4, tab 156, at 3-4, tab 157 at 1-2). All of these
    email correspondences indicate that the subcontracts "were in support of the [statement
    of work]" (e.g., app. supp. R4, tab 157 at 1), but none of them venture to provide an
    opinion regarding the reasonableness of the prices charged (see tr. 2/51-52). We have no
    reason to doubt that the subcontract prices were allocable to the contract, and so find
    here, but there is no evidence elsewhere in the record with respect to the reasonableness
    of the subcontract charges, except the earlier statement that the ACO was able to
    independently confirm the reasonableness of the cost of one subcontract (tr. 11269).
    DECISION
    TSI advances ten arguments, or "claims" in its appeal (see app. hr.) and, at
    Judge Clarke's invitation (see Bd. corr. ltr. dtd. 21March2016), modified its first
    argument (which had previously been more directly related to the statute of limitations
    (see app. br. at 2-3)) to transform it into an argument regarding "course of dealings" in
    its reply brief (see app. reply hr. at 1, 3-12). We will address and reject the "course of
    dealings" argument, along with Judge Clarke's related theory about the doctrine of
    "retroactive disallowance," first, then tum to the other general argument regarding the
    statute of limitations, which we also reject. We will then address the remaining
    arguments TSI raises against portions of the COFD and decide them upon their
    individual merits. We need not address the argument of auditor independence because
    TSI has conceded it (app. hr. at 3).
    17
    I.     The Doctrines of Retroactive Disallowance and Past Performance Do Not
    Preclude the Questioning of Costs in this Appeal
    TSI argues that DCAA' s prior "accept[ ance of its] legal and consulting services
    costs, along with [its] depreciation methods ... prior to 2007" constituted a prior course
    of dealing that would preclude their being questioned by the government in the
    FY 2007 audit (app. reply br. at 5-6). Judge Clarke's dissent revises the approach he
    took in his letter to the parties in which he requested them to brief the course of
    dealings theory because he is now of the opinion that the doctrine of retroactive
    disallowance more directly precludes the government from challenging costs allowed
    in prior years, although course of dealings remains his fallback position. Retroactive
    disallowance was not briefed by the parties, but we need not seek further briefing upon
    it because we find the law to have changed to make it an unsustainable theory here and
    that it is inapplicable to the facts of this appeal in any event.
    Retroactive disallowance is a theory for challenging audits whose heyday has
    come and gone. The theory was first set forth by the Court of Claims in Litton
    Systems, Inc. v. United States, 
    449 F.2d 392
    (Ct. Cl. 1971). We elaborated upon it, as
    Judge Clarke's dissent notes, in such cases as Gould Defense Systems, Inc., ASBCA
    No. 24881, 83-2 BCA ~ 16,676; and Data-Design Laboratories, ASBCA No. 21029,
    81-2 BCA ~ 15,190. In these cases, we characterized the principle as preventing the
    government from challenging costs already incurred when:
    [T]he cost or accounting method in question previously
    had been accepted following final audit of historical costs;
    the contractor reasonably believed that it would continue to
    be approved; and it detrimentally relied on the prior
    acceptance.
    Gould, 83-2 BCA ~ 16,676 at 82,981 (citing Data-Design, 81-2 BCA ~ 15, 190). The
    last appeal in which we granted relief based upon retroactive disallowance was our
    2002 decision of Lockheed Martin Western Development Laboratories, ASBCA
    No. 51452, 02-1 BCA ~ 31,803. Prior to Lockheed Martin, retroactive disallowance
    was last used to grant relief in the 1986 case of Data-Design Laboratories, ASBCA
    No. 27245, 86-2 BCA ~ 18,830.
    In 1984, however, the seeds of the doctrine's diminution were sown by the
    Supreme Court in the case of Heckler v. Community Health Services of Crawford
    County, Inc., 
    467 U.S. 51
    (1984), which explicitly recognized that, "the Government
    may not be estopped on the same terms as any other 
    litigant." 467 U.S. at 60
    . The
    United States Court of Appeals for the Federal Circuit (the Federal Circuit)
    subsequently held that "affirmative misconduct [has been recognized] as an element of
    18
    an estoppel claim against the government." Henry v. United States, 
    870 F.2d 634
    , 637
    (Fed. Cir. 1989) (citations omitted); see also Zacharin v. United States, 
    213 F.3d 1366
    ,
    1371 (Fed. Cir. 2000) ("While the Supreme Court has not squarely held that
    affirmative misconduct is a prerequisite for invoking equitable estoppel against the
    government, this court has done so.") (citations omitted). Being a "special application
    of estoppel principles," see Gould, 83-2 BCA ii 16,676 at 82,981, retroactive
    disallowance is thus now subject to the same affirmative misconduct requirement as
    other estoppel defenses. This sea-change was clearly recognized by the Federal
    Circuit in a case cited in Judge Clarke's dissent, Rumsfeld v. United Technologies
    Corp., 
    315 F.3d 1361
    (Fed. Cir. 2003).
    In United Technologies, which was an appeal of one of our decisions, the
    Federal Circuit characterized the retroactive disallowance argument (an argument that
    United Technologies had advanced at the trial level, but had been unnecessary for us
    to reach 16 ) as being that the "government [was] estopped from contesting" the
    accounting determination at issue. 315 F .3d at 13 77. Relying upon Zachar in, the
    Federal Circuit instructed us that "affirmative misconduct" on the part of the
    government would be required for the application of the principle. 
    Id. at 1377
    (citing
    
    Zacharin, 213 F.3d at 1371
    ). On remand, we quickly dispensed with appellant's
    argument that the Federal Circuit had been unfamiliar with the Litton line of cases, and
    made clear that our understanding of the Federal Circuit's opinion was that retroactive
    disallowance is a species of estoppel and, thus, the affirmative misconduct requirement
    applies to it. United Technologies Corp., Pratt & Whitney, ASBCA No. 47416 et al.,
    06-1 BCA ii 33,289 at 165,055-58.
    Little has happened with regard to retroactive disallowance since the decision on
    remand of United Technologies, in no small part, we believe, because affirmative
    misconduct is a difficult bar to clear. Nevertheless, as Judge Clarke notes, the defense
    was raised briefly last year when we denied a motion for summary judgment in the
    appeal of Raytheon Company, ASBCA No. 57576 et al., 15 BCA ii 36,043 at 176,055,
    finding retroactive disallowance to be unsupported by the undisputed facts. While it is
    16   To be sure, as Judge Clarke notes in his dissent, we did not explicitly call it
    "retroactive disallowance" in our initial opinion, see United Technologies
    Corp., Pratt & Whitney, ASBCA No. 47416 et al., 01-2 BCA ii 31,592 at
    156,133, but, inasmuch as appellant was clearly relying upon the Litton line of
    cases in its arguments to the Federal Circuit, see United Technologies, 06-1
    BCA ii 33,289 at 165,033-34, and, acting upon the remand, we read the Federal
    Circuit's opinion to plainly apply to United Technologies' retroactive
    disallowance argument, 
    id. at 165,056-58,
    we find the argument's label to be
    irrelevant. It was simply a rose by another name - another name that, not
    coincidentally, underscored that retroactive disallowance had always been
    premised upon estoppel.
    19
    true that we did not discuss the requirement of affirmative misconduct in Raytheon, that
    ·omission is far too slender a reed to support a view of the law that leaves out this critical
    element: in our offhand discussion of retroactive disallowance (in which we ruled in
    favor of the government), we did not purport to overrule our precedent in United
    Technologies nor the Federal Circuit's dictates in the same case. To sum up: there is no
    way to read our recent precedent or the Federal Circuit's except to include an affirmative
    misconduct requirement amongst the elements of retroactive disallowance. Period.
    Thus, turning to the facts of this case, we readily dispose of the application of
    retroactive disallowance to it. Judge Clarke does not assert that there is a factual
    predicate for finding affirmative misconduct on the part of the government in this matter.
    Without that element, there is no retroactive disallowance. United Technologies, 06-1
    1
    BCA ~ 33,289 at 165,055-58. Moreover, even without such a requirement, we would still
    find, on the facts before us, that retroactive disallowance is inapplicable to this appeal.
    The government's failure to challenge TSI's costs in prior audits (without more) was not
    enough to give TSI the reasonable belief that such costs would never be challenged in the
    future. 17 This would be the case even if we were not to read the law (as we do) to require
    an unequivocal statement by the government that the costs were considered to be
    supported. See Gould, 83-2 BCA ~ 16,676 at 82,981 (holding the doctrine applicable
    when the government "unequivocally accepts a contractor's proposed accounting
    treatment"). When we consider retroactive disallowance to include a requirement that the
    government make an unequivocal statement regarding the allowability, the case for
    applying this defense is even more plainly deficient here.
    TSI fares no better under the prior course of dealing theory. The notion, as
    explained by Judge Clarke, is that the interpretation of FAR part 31 by prior auditors,
    "set a standard TSI was entitled to rely upon." TSI makes a similar argument,
    although it combines retroactive disallowance with course of dealing in a somewhat
    confusing way (app. reply br. at 3-12). These arguments founder for the simple reason
    that DCAA' s inaction or failure to challenge a cost in prior audits as was the case here
    does not "set" any "standard," nor establish the "common basis for understanding" that
    is necessary for TSI to prevail under this contractual theory.
    Our law regarding course of dealing relies upon the standards set forth in the
    Second Restatement of Contracts. See, e.g., BAE Systems Technology Solutions &
    Services, Inc., ASBCA No. 57581, 13 BCA i-135,414 at 173,741-42; T&M Distributors,
    Inc., ASBCA No. 51405, 00-1BCA~30,677 at 151,509. The binding law in our Circuit
    hews to the Restatement as well. See Sperry Flight Systems v. United States, 548 F .2d
    915, 922-23 (Ct. Cl. 1977). The Restatement, itself, provides that:
    17   Even TSI's CFO, Mr. Fletcher, acknowledged that a different auditor could
    interpret risk differently and thus examine different matters than prior auditors
    (tr. 2/175).
    20
    § 223 Course of Dealing
    ( 1) A course of dealing is a sequence of previous conduct
    between the parties to an agreement which is fairly to
    be regarded as establishing a common basis of
    understanding for interpreting their expressions and
    other conduct.
    (2) Unless otherwise agreed, a course of dealing between
    the parties gives meaning to or supplements or qualifies
    their agreement.
    RESTATEMENT (SECOND) OF CONTRACTS§ 223 (1981). For our purposes, the key
    language from Section 223(1) of the Restatement is that a course of dealing is "a
    sequence of previous conduct between the parties to an agreement which is fairly to be
    regarded as establishing a common basis of understanding for interpreting their
    expressions and other conduct." The Court of Claims elaborated upon this language in
    Sperry Flight Systems, to state that "a course of dealing can supply an enforceable
    term to a contract...provided that the conduct which identifies that course of dealing
    can reasonably be construed as indicative of the parties' intentions - a reflection of
    their joint or common 
    understanding." 548 F.2d at 923
    .
    DCAA's failure to question certain costs in prior audits, without more, does not
    "establish[] a common basis of understanding," see RESTATEMENT § 223( 1), of what
    should constitute adequate substantiation of (or support for) TSI' s incurred costs. This
    is the case because, under the circumstances presented here, the failure to question
    certain costs could mean more than one thing: it could just as easily mean that the
    government is satisfied with the proof offered by TSI as it could mean that the auditor
    chose to more carefully investigate certain issues (for any of a variety of legitimate
    reasons) in some years than in other years. 18 Thus, without more information, a
    contractor could only speculate as to why the government chose not to question
    costs. 19 And, when there is only speculation as to the meaning of an auditor's silence,
    such silence cannot "reasonably be construed as indicative of the parties' intentions
    [or] their joint and common understanding." Sperry Flight 
    Systems, 548 F.2d at 923
    .
    18
    Indeed, the evidence is clear that in some years prior to the FY 2007 ICP audit, the
    government did question costs incurred by TSI that it did not in other years.
    19
    This is not to say that in no circumstances could an auditor's course of conduct
    establish evidentiary standards for substantiation. For example, in the case of a
    contractor that was specifically told that certain receipts were considered to be
    adequate substantiation of costs by the government and that it should not bother
    to preserve more evidence, the result might be different. We are not presented
    with that case here.
    21
    Judge Clarke's dissent cites two cases for the proposition that a prior course of
    dealing can be relevant to the allowability of costs: Blue Cross Association and Blue
    Shield Association, ASBCA No. 25778, 89-2 BCA ~ 21,840 at 109,907 n.41; and Ford
    Aerospace and Communications Corp., Aeronutronic Division, ASBCA No. 23833,
    83-2 BCA ~ 16,813 at 83,631 n.3. The general point is correct, but neither case
    presented circumstances remotely like those here, where the government's failure to
    raise a matter during an audit was contrived to constitute a course of dealing making
    all unquestioned costs allowable.
    We note finally that, as tempting as it might be to grant relief to TSI - for it
    does appear to be a sympathetic actor - such a course would lead to a number of
    unanticipated and undesirable consequences. Notably, a rule that would grant TSI
    relief here would encourage DCAA and COs to question as many costs as possible in
    early audits so as to "speak now or forever hold its peace." It is far better, we think, to
    encourage auditors to exercise judgment and discretion in determining the scope of
    their audits. In Sperry Flight Systems, the Court of Claims noted similar concerns
    about too readily applying a course of conduct to preclude government action, stating
    that, "what plaintiff argues for is a contract right that would undermine the authority
    and responsibility vested in a contracting officer .... [N]othing has been shown here
    that would justify placing the Government in so irretrievable a 
    position." 548 F.2d at 923
    . Such is the case here.
    II.    TSI's Statute of Limitations Arguments are Unavailing
    TSI concedes that its original contention that the entire COFD was time-
    barred "does not stand" (app. br. at 2), but alleges three questioned cost matters to
    which it argues the statute does apply (id. at 2, 5, 11 ). TSI is incorrect in all three
    particulars.
    Under the CDA, the government must present any claim against the contractor
    within six years of its accrual. 41 U.S.C. § 7103(a)(4)(A); Sikorsky Aircraft Corp. v.
    United States, 
    773 F.3d 1315
    , 1320 (Fed. Cir. 2014); Kellogg Brown & Root Services,
    Inc., ASBCA No. 58175, 15 BCA ~ 35,988 at 175,823 (KBR). The definition of
    "accrual" comes from the FAR, and is "the date when all events, that fix the alleged
    liability of... the contractor and permit assertion of the claim, were known or should
    have been known .... [M]onetary damages need not have been incurred." 
    Sikorsky, 773 F.3d at 1320
    (quoting 48 C.F.R. § 33.201); see also KBR, 15 BCA ~ 35,988 at
    175,823-24. Inasmuch as Sikorsky established that that CDA statute of limitations is
    an affirmative defense, not a matter of jurisdiction, 
    see 773 F.3d at 1322
    , the burden of
    proof is on TSI to prove that it was not met. KBR, 15 BCA ~ 35,988 at 175,823.
    22
    As a general proposition, the costs questioned by ACO Cuellar's COFD were
    those set forth in TSI's FY 2007 ICP, which was submitted to the government on
    30 June 2008. Even if the mere submission of the ICP started the six-year statute of
    limitations clock (before the subsequent audit produced evidence that the costs were
    unsupportable) the statute would not have run until 30 June 2014. Since the COFD
    that constituted the government claim here was filed on 23 June 2014, it was within
    the statutory time period. We further note that it was legally impossible for the
    government to issue its COFD before the submission of the ICP, because the legal
    bases for the government's unilaterally establishing the indirect costs, FAR 42.705-1
    and FAR 42.302(a)(9) (see R4, tab 16 at 256), presupposed action upon a "'final" ICP
    submitted by the contractor. See FAR 42.705-l(b). Since no COFD approving or
    disapproving portions of the FY 2007 ICP could have been issued until after the
    submission of said proposal by TSI, and the ability to assert such a government claim
    is a prerequisite to claim accrual, 
    Sikorsky, 773 F.3d at 1320
    (quoting 48 C.F.R.
    § 33.201); see also KBR, 15 BCA ii 35,988 at 175,823-24, it is impossible for the
    statute to have begun to run here prior to the submission of TS I's FY 2007 ICP.
    TSI' s argument, on pages 2 and 3 of its brief, regarding use of prior years'
    audits to influence future audits is unclear and, to the extent it is an argument about the
    statute of limitations, is unpersuasive. The costs questioned for FY 2007 could not
    have been questioned until they were submitted, and, whatever decisions the ACO
    made with respect to other years did not give her the ability to question costs before
    they were formally submitted to her.
    TSI further argues that its marketing costs with SMI were much the same in 2007
    as in prior years, thus, the submittal of TS I's FY 2006 ICP should have tipped the
    government off that there was a problem with these costs (if, indeed, there were such a
    problem) more than six years prior to the COFD here (app. br. at 5-6). This argument is
    unpersuasive and is more in line with the retroactive disallowance and course of dealings
    positions expressed by Judge Clarke than a straightforward statute of limitations
    argument. Again, it would not have been possible for the ACO to question the actual
    costs submitted and to issue a decision constituting a claim until TSI submitted its
    FY 2007 ICP as noted above. At most, the prior years' information might be argued to
    have bearing upon when the government knew or should have known that the 2007 costs,
    as submitted in the FY 2007 ICP, were dubious, but this prior years' information would
    only be material subsequent to the FY 2007 ICP submittal.
    TSI's final particular statute of limitations argument is that the government
    knew the particulars of its executive bonus plan in early 2007, more than six years
    before the issuance of the COFD, so it should not have been able to question it more
    than six years later (app. br. at 11). Again, the pitfall in this argument, with respect to
    23
    the statute of limitations, 20 is that, whatever knowledge the government may have had
    with TSI's aspirational plans (and they were labelled as such), it could not have
    asserted a government claim until after TSI submitted its FY 2007 ICP.
    TSI has made no further allegations regarding the statute of limitations, thus,
    this affirmative defense poses no barrier to any of the government's other claims here.
    III.       TSI is Entitled to Some Relief upon the Merits
    As noted in the Findings of Fact section, above, the contractual provision governing
    the primary dispute in this matter requires payment of a contractor's indirect costs if the
    costs are allowable under the contract (which is controlled by the FAR) and if they are
    "shown in the records maintained by the contractor." FAR 52.216-7(b)(l)(F). As will be
    shown herein, some FAR provisions regarding allowable costs include sections setting
    forth the type of proof necessary to support the cost. See, e.g., FAR 31.205-33(1)(2) and
    (3 ). The government has the burden of proof for demonstrating that a cost is unallowable.
    Johnson Controls World Services, Inc., ASBCA Nos. 46674, 47296, 96-2 BCA ~ 28,464 at
    142, 166 (citations omitted). With these general principles in mind, we tum to the cost
    elements that remain disputed.
    A. TSI is Entitled to Payment for SMI' s Marketing Costs
    The government labors under the false impression that the FAR requires a consultant
    to create "work product" merely for the purposes of proving its costs (see R4, tab 16 at 258,
    260; gov't br. at 54-55, 64-66). Though the FAR language in question is not as clear as we
    might like, it can be read- as we read it here - to impose no such requirement, Moreover,
    we have factually found the invoices submitted by TSI to be adequate to support a finding
    that TSI incurred the charged costs for SMI's marketing activities.
    We begin by examining that language of the FAR that the government holds
    out as requiring the generation and provision of "work product" to entitle recovery of
    costs for professional and consultant services. FAR 31.205-33, Professional and
    consultant service costs, provides in relevant part that:
    (f) Fees for services rendered are allowable only
    when supported by evidence of the nature and scope of the
    service provided.... Evidence necessary to determine that
    20
    TSI did not argue that its submission of its executive bonus plan to the government
    in early 2007 should support invocation of the principles of retroactive
    disallowance or course of dealing. Even if it had, they would be inapplicable as
    we find factually that there was neither government misconduct nor
    unequivocal acceptance of this plan.
    24
    work performed is proper and does not violate law or
    regulation shall include -
    (1) Details of all agreements (e.g., work
    requirements, rate of compensation, and nature and amount
    of other expenses, if any) with the individuals or
    organizations providing the services and details of actual
    services performed;
    (2) Invoices or billings submitted by consultants,
    including sufficient detail as to the time expended and
    nature of the actual services provided; and
    (3) Consultants' work products and related
    documents, such as trip reports indicating persons visited
    and subjects discussed, minutes of meetings, and collateral
    memoranda and reports.
    The government makes a superficially persuasive argument, that the FAR's
    statement that the evidence necessary to determine that the work is proper "shall
    include ... work products" and related documents, makes the provision of such
    documents mandatory (gov't hr. at 54). The problem with this interpretation of the
    FAR is that it does not account for the case in which such documents were never
    created by the consultant. Moreover, it does not account for the case where, as here,
    the invoices include the data that the FAR defines as work product, such as persons
    visited and subjects discussed. We further note, that DCAA's own audit manual,
    reflecting the government's own interpretation of this FAR requirement, provides that,
    "[t]he auditor should not insist on a work product if other evidence provided is
    sufficient to determine the nature and scope of the actual work performed." DCAA
    Manual, at 58-2 - 58-3. Moreover, amongst the "Frequently Asked Questions" in the
    relevant portions of the audit manual are responses indicating that other additional
    evidence may be considered to determine whether the services were, indeed, provided
    and allowable. 
    Id. at 58-7.
    Thus, we conclude that FAR 31.205-33(f) may require the provision of a
    consultant's work product, if it exists, but is not so rigid as to require its creation when
    it would not otherwise be necessary for the consultant to perform its duties. To be
    sure, any lack of work product makes it more difficult for a contractor to prove that it
    incurred the costs for which it seeks compensation, and the lack of work product in an
    instance where the consulting work was of such a scale or scope that work product
    would be expected may properly subject the costs to question. As with most things,
    the proper amount of documentation and work product to be expected will largely
    depend on the scope of work performed, and we do not conclude that the FAR
    25
    intended to impose "make work" upon consultants that would only lead to higher costs
    to the contractor which would then be imposed upon the taxpayer.
    Turning to the facts before us, we have found that the consulting agreements
    and the invoices provided, combined with the testimony given at the hearing, persuade
    us that the costs included in TSI's FY 2007 ICP for SMI's marketing services were, in
    fact, for that purpose and are allowable. This portion of the appeal is sustained.
    B. TSI's Full Expensing of Computers was Properly Rejected by the ACO
    The use of depreciation as an indirect cost in the contracts here is governed by
    FAR 31.205-1 l(c), which provides:
    [A ]llowable depreciation shall not exceed the amount
    used for financial accounting purposes, and shall be
    determined in a manner consistent with the depreciation
    policies and procedures followed in the same segment
    on non-Government business.
    TSI had no written depreciation policy in 2007 or in years prior to 2007, but its prior
    practice was to depreciate computers and computer equipment over a period of years.
    In 2007, that changed when, in line with its IRS filings, it completely expensed the
    computers and computer equipment it purchased.
    We view TSI's depreciation practices in its FY 2007 ICP as inconsistent with
    its prior long-term practices. We also find its rationales for the new approach to be
    unpersuasive: being a "cutting edge" technology company does not appreciably
    change the useful lives of desktop computers used for office work; the fact that some
    computers were modified for non-office work does not affect the depreciation of those
    that were not- and TSI has not demonstrated what portion of the computers expensed
    actually were so modified; and the IRS Code's allowance for earlier write-offs, for tax
    purposes, of full depreciation in a year, does not have any effect on the proper
    depreciation for our purposes. Accordingly, the government prevails in this portion of
    the appeal. Computers and computer equipment not allocable as direct costs are to be
    depreciated at the same rate as in prior years.
    C. TSI's Travel Costs were Properly Challenged
    TSI has provided no good reason to depart from the decision of the government
    to challenge the travel costs that exceeded the proper per diem rates. There is no
    dispute that the costs challenged by the government exceeded those rates, nor that this
    forms a basis for disallowing the excess costs pursuant to FAR 31.205-45(a)(2).
    Nevertheless, TSI propounds two arguments for why this should not matter: first, TSI
    26
    argues that the CO wrongly identified the applicable travel regulation (app. br. at 9-10).
    The COFD references the JTR, which applies to travel outside of the Continental
    United States, instead of the FTR, which was truly applicable since all of the challenged
    travel was within the Continental United States (id.). Next, TSI argues that its general
    travel policy saved the government money (id. at 10). Neither argument is persuasive.
    Although the COFD did err, as both parties concur (see gov't hr. 58) in naming
    the JTR as the applicable regulation, rather than the FTR, this is a defect of form,
    rather than substance because FAR 31.205-45(a)(2) applies to when the per diem rates
    of either the JTR or the FTR were exceeded, and the applicable per diem rates were, in
    fact, exceeded here. Because we review the COFD de novo, see Wilner v. United
    States, 
    24 F.3d 1397
    , 1401 (Fed. Cir. 1994);Assurance Co. v. United States, 
    813 F.2d 1202
    , 1206 (Fed. Cir. 1987), we may sustain the ACO' s decision even if it is
    articulated with less precision than all would like. Here, we conclude that the ACO
    was correct to question the per diem payment for being contrary to regulation.
    TSI's allegation that its travel policies saved the government money is undeveloped
    and would not excuse it from compliance with travel regulation limits on per diem in any
    event. While there are exceptions to the strictures of FAR 3 l.205-45(a)(2), contained in
    subsection (a)(3) of the FAR provision, TSI has not attempted to apply these exceptions in
    its argument (see app. hr. at 10), and we can identify at least one - a requirement that a
    written justification for use of higher rates be made by an appropriate authority in the
    company, see FAR 3 l .205-45(a)(3)(ii)- that TSI did not meet.
    D. TSI is not Entitled to Payment for its Executive Bonuses
    We agree with the government that TSI' s executive bonus plan was too
    amorphous in its criteria for bonus award and subject to too unfettered discretion in its
    application to permit the inclusion of its costs in the ICP. As will be demonstrated
    below, when an executive bonus plan lacks measurable metrics and is essentially
    subject to the unfettered discretion of those who would benefit from it, as did TSI's, its
    costs are not compensable.
    We start with the governing FAR provision, FAR 3 l .205-6(f), Bonuses and
    incentive compensation, which provides in relevant part:
    ( 1) Bonuses and incentive compensation are
    allowable provided the -
    (i) Awards are paid or accrued under an agreement
    entered into in good faith between the contractor and the
    employees before the services are rendered or pursuant to
    an established plan or policy followed by the contractor so
    27
    consistently as to imply, in effect, an agreement to make
    such payment; and
    (ii) Basis for the award is supported.
    Thus, a bonus award must be made pursuant to an agreement or well-established plan
    or policy, and there must be support for the basis of the award. An underlying feature
    of the jurisprudence applying this FAR provision is an intent to avoid a company's
    "in-group" using the bonus pool as a means of distributing company profits amongst
    themselves. In Nolan Brothers, Inc. v. United States, 43 7 F .2d 13 71 (Ct. Cl. 1971 ), the
    Court of Claims noted that payment of bonuses from a family-owned corporation to
    officers who were members of the family "justified close scrutiny" to ensure that the
    bonuses were not a disguised "distribution of the corporation's 
    earnings." 437 F.2d at 1384
    . And in Northlich, Stolley, Inc. v. United States, 
    368 F.2d 272
    (Ct. Cl. 1966), a
    tax case cited by the court in Nolan Brothers, the Court of Claims expressed similar
    concerns when the officers to whom the compensation was paid were "in complete
    control of the corporation's 
    affairs." 368 F.2d at 278
    .
    Our prior cases have similarly expressed discomfort with, and rejected, bonus
    plans that give too much leeway in making bonus awards to those who would benefit
    from them. In SplashNote Systems, Inc., ASBCA No. 57403, 12-1BCA~34,899, we
    disallowed the use of a bonus plan because its "lack of specificity, constraints, or
    parameters contribute[d] to the conclusion that [the] bonus was a distribution of
    profit." 
    Id. at 171,610.
    We noted in Boeing Aerospace Operations, Inc., ASBCA
    Nos. 46274, 46275, 94-2 BCA ~ 26,802, that we "would not endorse 'a policy which
    would permit payments to be made or not made in the unlimited discretion of
    management or ... the kind of policy that was not consistently or clearly defined."' 
    Id. at 133,285
    (quoting General Electric Co., ASBCA No. 28753, 89-1BCA·~21,445 at
    108,056 21 ). This is consistent with the notion that, in order to be able to judge whether
    there is a supported basis for a bonus award, see FAR 3 l.205-6(t)(l )(ii), there must be
    some clearly defined criteria for making the award in the first instance.
    Thus, we turn to TSI's bonus plan. The government contends that there was no
    such plan because there was no written agreement between TSI and the three bonus
    recipients at any time during FY 2007 (gov't br. at 59). To be sure, the December 2006
    memorandum signed by Mr. Benton promising the establishment of such a plan is a
    shaky foundation for TSI to rely upon for proof of an agreement, though the testimony
    surrounding it might be sufficient for us to conclude, in this case, that it did constitute
    such an agreement. We need not decide that matter, however, because we conclude that
    21
    In this quotation contained in our Boeing decision, we inadvertently cited to a
    differently named case (though the citation was to the correct page of the
    reporter). The citation here has been corrected to reflect the proper case name.
    28
    TSI's "bonus plan" was fatally defective in that the one-page memorandum purporting
    to establish it was utterly lacking in clearly defined criteria for making bonus decisions
    and effectively left decision-making regarding the award of any bonuses to the
    unfettered discretion of the very same three individuals who were to be the recipients of
    the bonuses. 22 The arbitrary nature of the bonus awards is reflected in the memoranda
    supporting them, which referenced generalized achievements without tying them in any
    way to the amount of the bonuses awarded. Thus, because TSI's bonus policy lacked
    specificity and constraints, see SplashNote Systems, 12-1 BCA ,-i 34,899 at 171,610, and
    effectively provided "unlimited discretion" to management, see Boeing Aerospace
    Operations, 94-2 BCA ,-i 26,802 at 133,285, we hold that it is not a compensable cost.
    This determination is buttressed by evidence that Mr. Fletcher considered the bonus
    pool to effectively come from company profits and the fact its distribution came at the
    whim ofTSI's "in" group, justifying "close scrutiny," Nolan 
    Brothers, 437 F.2d at 1834
    , which it simply cannot withstand. 23
    E. TSI is Entitled to a Significant Portion of its Legal Fees
    TSI does not dispute some of the legal fees challenged by the government, but seeks
    inclusion of the allowable portion (80%) of the $39,060 it incurred defending itself in the
    NCIS investigation, $31,248 (app. br. at 13). For its part, the government does not dispute
    the fact that the legal fees for the investigation, as subjected to the 20% discount, would
    otherwise be allowable (see gov't br. at 62, 64 ), but argues that the fees were expensed to
    the wrong year (id. at 62-63). We disagree with the government.
    Although it would have been easiest if TSI had been able to have sought the
    legal costs contemporaneously with their incurrence, it was precluded from doing so
    by FAR 31.205-4 7(g), which generally precludes the CO's paying such fees while the
    investigation is pending. The government asserts that, once NCIS notified Sonetech
    that the investigation was complete and that company told TSI, TSI was obligated to
    immediately claim the costs (gov't br. at 62). But, as we found above, in the factual
    circumstances presented here, it was reasonable for TSI to wait until it received its
    documents back from the NCIS in 2007 to be certain that the investigation was
    complete and no longer pending. Accordingly, we find TSI to have acted
    appropriately in seeking its legal costs in the FY 2007 ICP, and rule that it was entitled
    to claim them (as discounted).
    22   In this holding, we respectfully part ways with Judge Clarke. Although he found
    adequate support for the awards and is of the general view that the small size of
    the company decreases the need for formality, we, nevertheless, cannot find
    support in the law for permitting a bonus plan with the kind of unfettered
    discretion that we encountered here.
    23   Because we find the bonus plan impermissible, we need not determine whether the
    March 2008 payment was properly allocable to the FY 2007 ICP.
    29
    F. TSI is Entitled to Payment for Mr. Wilson's Consulting Costs
    As we discussed at length in Section A above, the supposed requirement for
    "work product" is not fatal to a contractor's seeking compensation for consultant's
    work in the proper circumstances. In our Findings of Fact, above, we, determined that
    Mr. Wilson's hours were substantiated and not unreasonable. Accordingly, we hold
    that the government's determination that TSI was not entitled to compensation for
    Mr. Wilson's costs in its FY 2007 ICP was incorrect.
    G. The Government Correctly Determined that the Costs of Two TSI
    Subcontractors were Unallowable
    It is undisputed that the direct costs of the two subcontracts challenged by the ACO
    and remaining at issue were, contrary to the terms of the FAR (as incorporated into TSI's
    contracts), not pre-approved by the ACO. TSI attempts to evade that problem by alleging
    that, because the subcontracts were technical in nature, the ACO would have needed to
    consult with the COTR to decide if they were proper, and further alleging that the COTR
    has performed an after-the-fact review and found the subcontracts to have been performed
    in support of the statement of work (app. hr. at 16-17).
    As we expressed in our Findings of Fact, we entertain little doubt that the
    subcontracts were performed pursuant to the statements of work of the contracts and
    were thus allocable costs. The problem for TSI - a problem that it does not address -
    is that the support letter it received from the COTR stakes out no position on the
    reasonableness of the costs of the subcontractors. This omission is fatal to TSI' s
    attempts to provide an after-the-fact justification of these subcontracts. See
    FAR 52.244-2(e)(l)(vii) (requiring contractor's provision of information for
    determination of price reasonableness). Thus, the government properly disallowed the
    $2,661 in challenged subcontract costs under contract 0236 and the $28,568 in
    challenged subcontract costs under contract 0340.
    30
    CONCLUSION
    As discussed herein, neither the principles of retroactive disallowance and
    course of dealing, nor the statute of limitations prevent us from reaching the merits of
    the government's decision to challenge certain of the costs contained in TSI's FY 2007
    ICP. TSI's costs for SMI and Charles Wilson were allowable as were $31,248 in legal
    fees. The remainder of the disallowances in the COFD were proper.
    We return this matter to the parties to recalculate the rates in accordance with
    this decision.
    J.~
    Dated: 12 January 2017
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur in relief given and otherwise
    dissent (see separate opinion)
    (
    ALEXANDER YO
    Administrative Judge                                           ve Judge
    armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    31
    DISSENTING OPINION BY ADMINISTRATIVE JUDGE CLARKE
    I respectfully dissent. While I concur with the relief granted by the majority, I
    disagree with the reasoning. DCMA and DCAA engaged in retroactive disallowance
    and created an audit course of dealing that this small hi-tech business relied upon to its
    detriment. The majority's reasoning fails to hold DCMA and DCAA accountable. I
    was the trial judge and therefore drafted the initial version of the decision that my
    colleagues choose not to adopt. Therefore, to ensure my thinking is fully understood, I
    present my decision as my dissent.
    This is an appeal by Technology Systems, Inc. of a DCMA final decision reducing
    its final indirect rates for FY 2007 and demanding the return of $159,303. Appellant's
    owner presented its case pro se. The Board has jurisdiction pursuant to the Contract
    Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The appeal should be sustained in
    part as put forth in my dissent.
    FINDINGS OF FACT
    1. Technology Systems, Inc. (TSI) is a small technology business conducting
    research and development of software systems relating to new ways for ship navigation
    (tr. 2/227). TSI employs approximately 20 people 1 (tr. 2/193), including three
    executives: Mr. Benton, chief technology officer, president & sole owner (tr. 2/229-30),
    Mr. Fletcher, chief financial officer (CFO) (tr. 21117), and Mr. Zysk, chief operating
    officer (COO) (tr. 2173, 76, 102). Mr. Benton started TSI in 1985 and from 1987 on it
    was a defense contractor. TSI ceased operations in August 2014. 2 (Tr. 2/230)
    2. During the time relevant to the FY 2007 DCAA audit, TSI had four
    cost-plus-fixed-fee (CPFF) contracts for research and development with the
    Navy: Contract Nos. N00039-07-C-0006 (0006), N00014-07-C-0236 (0236),
    N00014-07-C-0340 (0340), and N41756-05-C-4775 (4775) 3 (R4, tabs 1-3, 16 at 268,
    tab 17 at 269).
    3. Contracts 0006, 0236 and 0340 contained the following clauses:
    FAR 52.215-2, AUDIT AND RECORDS-NEGOTIATION (JUN 1999); FAR 52.216-7,
    ALLOWABLE COST AND PAYMENT (DEC 2002); FAR 52.233-1, DISPUTES (JUL 2002);
    FAR 52.242-1, NOTICE OF INTENT TO DISALLOW COSTS (APR 1984); FAR 52.242-3,
    1
    In early 2008 TSI had only 15 employees (R4, tab 151 at 2).
    2
    Mr. Benton testified that TSI "still exists on paper so that it can interact in the way
    that we're doing today" (tr. 2/230).
    3
    Contract 4 77 5 was identified as a classified contract and a copy is not in the record
    (R4, tab 53 at 910).
    32
    PENAL TIES FOR UNALLOWABLE COSTS (MA y 2001 ); and FAR 52.244-2,
    SUBCONTRACTS (AUG 1988), (contract 0006) or 1998 (contracts 0236, 0340) (R4,
    tabs 1.:3 ). I infer that contract 477 5 also had these required clauses.
    4. The Subcontracts' clauses generally require that prime contractors that do
    not have an approved purchasing system must obtain the contracting officer's written
    consent to enter into cost-reimbursement, time-and-materials or labor-hour
    subcontracts. FAR 52.244-2( d)(l ). TSI did not have an approved purchasing system4
    and as a result had to obtain approval to enter into subcontracts (tr. 2/55).
    DCAAIDCMA Audit History before FY 2007
    ·5. There is no dispute over TSI's audit history prior to the FY 2007 audit.
    Ms. Winefield, DCAA supervisory auditor, testified that DCAA conducted full audits
    ofTSI's Incurred Cost Proposals (ICPs) for FYs 1998 to 2003 and 2006. DCAA
    conducted a "desk review" for FY s 2004 and 2005. The desk review for FY 2005
    included the statement, "We determined that no significant costs were questioned in
    prior years and that no indicators of audit risk had been identified" (app. supp. R4,
    tab 100 at 2904). A desk review could be conducted if, after review ofTSI's ICP,
    DCAA determined that there was a low risk that the ICP contained unallowable costs.
    A desk review is not a full audit. Desk reviews can only be conducted two years in a
    row. (Tr. 1/16-17, 26-28) As for the results of the audits, the record does not contain
    information on audit results before 2001. The FY 2001 audit questioned several costs
    but "it primarily questioned $70,072 in the Professional Fees Cost Element claimed in
    overhead and in G&A" for Messrs. Kemper, Ring and Wilson. These costs were
    questioned, because, among other reasons, TSI failed to provide evidence supporting
    the work performed by the consultants. (Ex. G-1 at 4-5, 9-11) The FY 2001 audit
    resulted in negotiations between the ACO and TSI and a rate agreement was achieved
    (tr. 2/256). For FYs 2002 to 2006, DCAA/DCMA did not question costs and accepted
    TSI's indirect rates without change (tr. 2/60-63; R4, tab 6(a) at 72, tab 70 at 1554). The
    FY 2006 audit was a full audit (tr. 21174). FY 2006 included, "In our opinion, the
    contractor's indirect rates are acceptable as proposed" (app. supp. R4, tab 101 at 6105).
    The FY 2007 Audit
    6. TSI's FY 2007 ICP was submitted on or about 25 June 2008 (R4, tab 15
    at 227). DCAA's incurred cost audit ofTSI's 2007 ICP started in the fall of 2008
    (tr. 1/36). Ms. Waller and Ms. Pitts were the DCAA auditors conducting the audit
    4   Administrative contracting officer (ACO) Cuellar testified that "a contractor such as
    TSI typically does not have an approved purchasing system because they don't
    meet the requirements, you know, where we would do a review in most cases,
    which is $25 million, I think" (tr. 2155, 65).
    33
    (tr. 2/161; R4, tab 53 at 626). Mr. Fletcher recalled that Ms. Waller "lost her temper"
    during a meeting held on Friday, 17 October 2008 (tr. 2/162; R4, tab 109). The
    incident was documented in a 20 October 2008 email from Mr. Benton5 to
    ACO Murray 6 (app. supp. R4, tab 103). Mr. Benton wrote in part, "TSI has been
    subject to annual audits for nearly 2 decades, and this auditor's approach and
    behaviors are outside that which we have ever experienced" (id. at 2). Mr. Benton
    questioned Ms. Waller's "objectivity" (id.). Seven employees ofTSI, two of whom
    were in the room, wrote memorandums documenting what they heard while the
    meeting was in process (tr. 2/231; app. supp. R4, tabs 108-14 ). Mr. Fletcher recalled
    that when he called ACO Murray 7 complaining about Ms. Waller, ACO Murray stated
    that TSI would not get an objective audit from Ms. Waller and that she (ACO Murray)
    would see that TSI got another auditor8 (tr. 21163). A meeting was held on
    12 November 2008 between the government and TSI. ACO Murray and Ms. Waller
    were among the attendees. TSI asked that Ms. Waller be replaced (R4, tab 107 at 1).
    Minutes of the meeting indicate that the government decided not to replace
    Ms. Waller9 (tr. 2/164; R4, tab 107 at 2-3).
    7. Ms. Waller submitted her draft audit for peer review on 27 April 2009
    (R4, tab 53 at 552). Before the FY 2007 audit could be completed, DCAA ordered all
    incurred cost audits stopped to focus on pricing audits that were holding up awards
    (tr. 1/38, 42-43). When TSI's incurred cost audit was stopped, Ms. Waller had
    completed a substantial amount of the work. Her draft audit questioned the following
    costs:
    5   Mr. Benton did not attend the meeting but it is well documented in the record
    (R4, tabs 108-14).
    6   ACO Murray was close to retirement and was replaced by ACO Cuellar (app. supp.
    R4, tab 122 at 1).
    7   Mr. Fletcher erroneously referred to ACO Cuellar in his account of the conversation,
    but the minutes of the 12 November 2008 meeting make it clear he talked to
    ACO Murray (R4, tab 107 at 3).
    8   At the 12 November 2008 meeting ACO Murray could not recall previously saying
    she would replace Ms. Waller but did not dispute that she probably did make
    that statement (R4, tab 107 at 3 ).
    9
    The government did not call Ms. Waller as a witness at the hearing. The only
    explanation was that she was no longer with DCAA (tr. 2/259-60).
    34
    Professional fees (overhead)                 $51,340 (R4, tab 53 at 559)
    Computer supplies (overhead)                 $26, 198 (id. at 562)
    Conferences                                  $19,241 (id. at 565)
    Severance pay                                $4,212 (id. at 572)
    Depreciation                                 $708 (id. at 573)
    Professional fees (G&A)                      $39,060 (id. at 576)
    Corporate affairs labor (G&A)                $36,498 (id. at 581)
    Travel (G&A)                                 $102 (id. at 583)
    Health Insurance (Yoga)                      $1,430 (id. at 589)
    Bonuses                                      $39,150 (id. at 590)
    Payroll taxes                                $2,866 (id. at 594)
    Holiday costs                                $4, 131 (id. at 595)
    All other fringe expenses                    $79,222 (id. at 596)
    Direct labor                                 $2, 184 (id. at 602)
    Direct travel                                $14,410 (id. at 603)
    Subcontracting/consulting                    $40,070 (id. at 608)
    The draft results were:
    Claimed by TSI                Audit determined
    OH Rate                       127.64%                       92.48%
    G&ARate                        18.40%                       12.02%
    Material OH Rate                1.05%                        0.00%
    (R4, tab 53 at 557)
    8. DCMA resumed TSI's incurred cost audit for FY 2007 in 2013 due to
    concerns over the statute of limitations (tr. 1/43). In April 2013 Ms. Winefield assigned
    Ms. Cote, senior auditor, to review the status of the TSI audit (tr. 1/44, 46; R4, tab 48).
    Ms. Cote submitted her findings in July 2013. She determined that more information
    was needed from TSI. (Tr. 1/44-47; R4, tabs 49, 50) Ms. Winefield then assigned
    Mr. Darcy, senior auditor, to complete the TSI audit (tr. 1/48).
    9. By letter dated 18 March 2014 to ACO Cuellar, JO Ms. Milshtein, DCAA,
    wrote that DCAA was unable to meet the required audit date and was withdrawing from
    "our engagement to audit the subject [TSI's] incurred cost proposal." DCAA agreed to
    provide "non-audit" service to assist DCMA in determining final rates for TSI in FY
    2007 "based on the information readily available from the audit files." (Tr. 1/173-74,
    230-32; app. supp. R4, tab 136) Also on 18 March 2014, DCAA provided ACO Cuellar
    JO   Ms. Cuellar replaced Ms. Murray as DCMA's ACO for TSI (tr. 1/227).
    35
    a "decrement memo" itemizing the costs it questioned (tr. 1152-53; R4, tab 4). The
    memo stated, "Providing this information does not constitute an audit or attestation
    engagement under generally accepted government auditing standards" (R4, tab 4 at 2).
    10. After ACO Cuellar received DCAA's decrement memo she emailed
    Mr. Benton, providing him with a copy of the decrement memo, and requesting any
    additional data he might want to submit and set up a time to meet (tr. 1/233-34; R4,
    tab 5). ACO Cuellar offered to close-out the action without assessing a penalty if TSI
    would accept DCAA's questioned costs (tr. 11235-36).
    11. By email dated 23 April 2014 to ACO Cuellar, TSI did not accept the
    offer and instead submitted documents explaining its position (tr. 11237-38; R4, tabs 6,
    6(a)-6(g)). By email dated 6 May 2014, ACO Cuellar acknowledged TSI's
    "non-acceptance of the Government's offer" stating in part:
    We understand your argument that DCAA has
    historically not questioned these costs; however, that
    does not mean DCAA deems those costs to be
    allowable. We here at DCMA cannot speak for the
    DCAA auditor( s) that performed the reviews, nor can
    we speak for the sampling methodology used by DCAA.
    Our job will be to address the audit as written. If you
    are able to substantiate the costs with the required
    documentation, we will reinstate the costs. If not, we
    have to sustain the costs.
    (Tr. 11238; R4, tab 7) TSI replied submitting some additional information, but
    ACO Cuellar testified that most of it was what had already been submitted to
    DCAA. She was able to allow some additional costs based on the new information.
    (Tr. 11237-40; R4, tab 9, 9(a)-(e)) ACO Cuellar testified that she continued to attempt
    to negotiate with TSI requesting additional documentation such as evidence of
    approval of subcontracts by the ACO, meeting notes, trip reports, bonus plan
    information, etc. (tr. 11242-45). By email dated 15 May 2014 to ACO Cuellar, TSI
    provided a statement to the effect that it was no longer interested in negotiations
    (tr. 11245; R4, tab 13, 13(a)). In the statement Mr. Benton wrote:
    TSI had a long established track record of never having
    any significant issues result from DCAA audits. All of the
    procedures and guidance in place had resulted in TSI's
    rates being accepted as admitted [sic] in the 5 years prior
    (2002-2006).
    36
    There is no manner in which TSI could have foreseen the
    DCAA audit findings for 2007. It is obvious that the
    management team was competent, diligent, and operating
    TSI in good faith insofar as accounting for all costs.
    Indeed, any similar management team would have
    operated TSI in the same manner in 2007.
    Why DCAA chose to totally alter their previous stances in
    2007 is a mystery. But DCAA has set into motion a
    process that will result in TSI's bankruptcy unless DCMA
    recognizes the fundamental lack of fairness in DCAA' s
    findings and positions. There is plenty of evidence already
    provided by TSI to substantiate this.
    The bottom line is that DCAA's claims were generally
    unfair and improper, and if they are allowed to stand to
    any substantial extent, there are no funds existing to
    recoup costs that are disallowed. No change in TSI's
    accounting practices would occur, because TSI has no
    revenues that are subject to DCAA audit anymore. The
    end result would be to force a company that has been
    recognized as an excellent contractor to the US military
    to cease operations, and the government to recoup
    virtually nothing.
    (R4, tab 13(a) at 212-13)
    12. By email dated 14 April 2014 to ACO Cuellar, Mr. Darcy forwarded
    a "TSI Negotiation Support Spreadsheet" he prepared for TSI's FY 2007 ICP
    (tr. 11214-16; R4, tabs 58-59). The spreadsheet included the following:
    Draft audit results questioned almost all of the labor costs
    in the corporate affairs labor account since the contractor
    could not provide detail of the labor hours by activity.
    Undoubtedly there is some directly associated
    unallowable labor in here related to other unallowable
    costs we questioned in the draft audit results and carried
    forward to the decrement memo. However, it looks like a
    hard line was taken in the draft audit results because the
    contractor was not providing the breakout of the labor
    costs comprising this account in the form the auditor
    37
    requested. For the purposes of the decrement memo we
    dropped this issue since more work still needed to be done
    to quantify the labor associated with the unallowable
    activities (i.e. TSI management interaction with SMI,
    patents, etc.).
    (R4, tab 59 at 1466) (Emphasis added) Ms. Winefield testified that Mr. Darcy did not
    include unallowable "activities" in the decrement memo because of his perception that
    the auditors took a "hard line" (tr. 1/218-19).
    13. Ms. Winefield prepared a Weekly Significant Activity Report for the week
    ending 13 June 2014 wherein she wrote, "Due to an impending Statute of Limitations
    date and per the request of DCMA, we prepared a decrement recommendation based
    on the findings from transaction testing that was performed to date on FY 2007 costs"
    (tr. 11212; R4, tab 66). She testified that DCAA calculated that the six-year limitation
    period would run out on 25 June 2014 (tr. 1/213).
    14. By email dated 12 May 2014 to ACO Cuellar, Mr. Benton provided
    information in response to ACO Cuellar's questions (tr. 2/40; app. supp. R4, tab 156).
    Concerning professional fees, ACO Cuellar requested information such as "trip
    reports, minutes of meetings, collateral memoranda and reports" to support the costs
    (app. supp. R4, tab 156 at 1). Mr. Benton attached a file summarizing Strategic
    Marketing Innovations, Inc.'s (SMI's) activities in FY 2007 and wrote:
    An issue with the 07 SMI documentation is that we were
    not made aware of an increased documentation
    requirement until 08. The files that are attached are from
    our accounting records, and refer to additional notes that
    Tom Zysk (company president at the time) would have.
    Unfortunately, Tom Zysk retired several years ago and
    his computer files are no longer on file and thus we have
    no way to forensically gather that information. Much of
    Tom's interactions were verbal. That said, the work
    performed by SMI was fundamentally the same for each
    year from 2002 through 2009, there were no changes to
    the contractual relationships or what they did. We were
    able to more comprehensively document in 2008-2009
    their business development activities, which included
    attending conferences to identify potential business
    opportunities, supporting our visits to DC area clients,
    and so forth.
    38
    (Id.) Mr. Benton also attached a file that gave examples of computer equipment that
    was expensed "due to short life" (id.). Mr. Fletcher discussed depreciation of
    computers. Some computers were for research and were "taken apart, components
    soldered on, sensors added in" and built into systems that would go out
    on vehicles/boats for testing (tr. 2/131, 205). They were "heavily modified"
    (tr. 2/221-22). After testing was complete the computer was "no good" to TSI and it
    was "expensed" (tr. 2/131-32). TSI also bought computers that were used on desks for
    routine office work and those computers were capitalized/depreciated (tr. 2/132).
    Computers that were consumed in the research work were not depreciated, but were
    expensed (tr. 2/133-34). Mr. Benton explained that even though the bonuses were paid
    in 2008 they were based on performance in 2007 (id.). He attached 2007 cost
    proposals for software license fees (id.). Finally he attached an email from
    Mr. Almquist former program manager and contracting officer technfoal representative
    (COTR) for the Office of Naval Research (ONR) confirming that TSI's
    "subcontractor, consultant, and equipment costs incurred were in support of the SOW"
    (app. supp. R4, tab 156 at 3). ACO Cuellar testified that she did consider this email
    from the COTR but that she "didn't look at it for fair and reasonable pricing" and he
    wasn't a contracting officer (tr. 2/44). Mr. Benton also provided emails from
    Mr. Devin, ONR, and Mr. Cascioli, project officer, both verifying that ODC costs
    incurred by TSI under contract 0340 ''were in support of the SOW" (app. supp. R4,
    tab 157). ACO Cuellar testified that this information was insufficient because she
    could not make a determination that the costs were fair and reasonable (tr. 2/49-52).
    15. ACO Cuellar signed her 23 June 2014 contracting officer's final decision
    (COFD) setting the final determination of TS I's rates and asserting a claim for
    $159,303 (tr. 11153; R4, tab 16). Her decision is summarized as follows:
    39
    Note                             ~  DISALLOWED OVERHEAD
    Notel          Although SMI' s l?bbying fees were voluntarily removed, TSI failed
    Professional   to present adequate documentation such as white papers, trip reports,
    Fees           meeting minutes, reports, etc., showing that the costs were allowable
    $51,340        (tr. 1/253-56; R4, tab 16 at 258).
    Note2          TSI expensed the full value of computers purchased in FY 2007 in
    Computer       FY 2007 that should have been depreciated over five years
    Supplies       (Tr. 1/257-58; R4, tab 16 at 258-59).
    $26,198
    Note 3         Unallowable entertainment costs. TSI agreed. (Tr. 1/259; R4, tab 16
    Conferences    at 259)
    $2,604
    Note4          Bonuses 11 that were not supported by a plan and were partially
    Fringe         incurred in FY 2008 (tr. 1/260-62; R4, tab 16 at 259-60).
    $25,698
    DISALLOWED G&A
    Note 5         Legal fees, $34,429 to deal with criminal investigation. Should have
    Professional   claimed in FY 2006 and only entitled to 80%. $2,925 for lack of
    fees           documentation for Mr. Wilson. $706 expressly unallowable. $1,000
    $39,060        for preparation of personal tax returns. (Tr. 1/262-264; R4, tab 16
    at 260-67)
    Note 6         Exceeds maximum per diem for lodging and meals (tr. 1/267;
    Conferences    R4, tab 16 at 261).
    $577
    Note?          See Note 4 Fringe above (tr. 1/267-68; R4, tab 16 at 261).
    Fringe
    $4,269
    Note 8         Difference between claimed overhead B&P labor to the adjusted rate
    B&P            of 109.88% (tr. 1/268; R4, tab 16 at 261).
    Overhead
    $2,417
    DISALLOWED DIRECT COSTS
    Note9          Exceeds maximum per diem rates (tr. 1/268; R4, tab 16 at 261 ).
    $1,074
    Note 10        $466 exceeds maximum per diem rates. $2,661 failure to receive
    $3,127         consent to subcontract and failure to provide substantiation.
    (Tr. 11270-71; R4, tab 16 at 261-62)
    Note 11        $1,986 exceeds maximum per diem rates. $28,568 failure to receive
    $30,554        consent to subcontract and failure to provide substantiation.
    (Tr. 1/271-273; R4, tab 16 at 262)
    40
    ACO Cuellar did not know if the problems identified in 2007 existed in earlier years
    (2002 to 2006) or not (tr. 2/61, 63).
    FYs 2008 & 2009 Audits
    16. Ms. Henriquez-Aguilar was the DCAA auditor who conducted the FY 2008
    and FY 2009 audits at TSI (tr. 11278, 285). By email dated 7 May 2014 to
    ACO Cuellar, Mr. Benton informed her that during the FYs 2008 & 2009 audit
    out-brief, Ms. Henriquez-Aguilar told him that SMI's costs "were deemed allowable
    without exception" (tr. 11158, 280; app. supp. R4, tab 148 at 3658). ACO Cuellar
    wanted to verify Mr. Benton's statements in the email (tr. 11287; app. supp. R4,
    tab 148 at 3657). By email dated 8 May 2014 to Ms. Henriquez-Aguilar, ACO Cuellar
    asked her to "explain the differences between what DCAA found in FY07 and
    FY08/09" (tr. 2/287; app. supp. R4, tab 148 at 3657).
    17. By email dated 8 May 2014 to ACO Cuellar, Ms. Henriquez-Aguilar
    responded:
    Based on my review of invoices in 2008 and 2009 all
    lobbying costs were voluntarily removed as unallowable,
    and only costs related to marketing were claimed. Based
    on my evaluation I consider the 2008 & 2009 direct selling
    costs allowable per FAR 3 l .205-38(b )(5).
    I am not sure what support was provided in FY 2007 as I
    did not complete the audit, but for the years I examined I
    was able to differentiate between what was allowable and
    not allowable, and I have confirmed that all unallowable
    expenses were excluded from the claims
    (Tr. 11280, 287; app. supp. R4, tab 148 at 3656-57) Ms. Henriquez-Aguilar testified
    that her conclusion was based on only her review of the invoices (tr. 11281 ). She
    testified that at the time of the out-briefing she told Mr. Benton that the direct selling
    costs were allowable and Mr. Benton's 7 May 2014 email to ACO Cuellar was correct
    (tr. 11281; app. supp. R4, tab 148 at 3658).
    18. By email dated 13 May 2014 to Ms. Henriquez-Aguilar and ACO Cuellar,
    Ms. Winefield stated that in FY 2007 TSI "was unable to provide adequate work
    products for us to determine the extent of allowable marketing services that were being
    performed" (R4, tab 10 at 148). She stated that she thought "it is very likely that TSI
    11
    Prior to 2007 TSI did not have an executive compensation plan (tr. 2/183).
    41
    started keeping better documentation for FY 2008 and FY 2009" which "may explain
    why our audit of those years rendered a different opinion on the SMI costs" (id.).
    19. By email dated 9 June 2014 to Ms. Winefield, Mr. Cook, DCAA, stated:
    Mary and Peter - on with headquarters relating to the 2007
    audit now for TSI. Headquarters wants to insure offices
    closely coordinate so we are taking same position on same
    type of issues and no instances of same information
    provided but different DCAA positions.
    (Tr. 11159; app. supp. R4, tab 126 at 4038)
    20. In June 2014 Ms. Winefield compared the TSI's FY 2007 audit documents
    with FYs 2008/2009 and concluded that they were essentially the same except that in
    the later audits a Scope of Work was included for SMI. In a 12 June 2014 email to
    Ms. DeCourcy, DCAA, Ms. Winefield wrote:
    Unfortunately, I think the difference between the FY 2007
    and FY 2008/FY 2009 audit is auditor judgment. It doesn't
    look to me that TSI was providing much better support in
    FY 2008/FY 2009 than what we saw in FY 2007. I looked
    through the attachments and I would agree with Peter that
    the major difference in what VIC team got is that the
    SOWs attached to the agreements in FY 2009 were
    updated.
    (App. supp. R4, tab 123 at 4358; tr. 11160-63) (Emphasis added)
    21. Ms. Henriquez-Aguilar explained that when DCAA received a
    congressional inquiry from Senator Susan Collins (app. supp. R4, tab 130 at 1) about
    TSI' s FY 2007 audit, she met with her supervisor and manager and they decided "it was
    a good idea to expand testing, to make sure that we weren't missing anything in this
    area, and that's when I contacted technology systems again, and I asked for 100 percent
    .of what was claimed for 2008 and 2009, for invoices and any supporting documents"
    (tr. 11285, 296-98). As a result of this expanded testing, in Ms. Henriquez-Aguilar's
    draft and 29 July 2014 final audit report for FYs 2008 & 2009 12 she questioned SMI's
    professional costs, dues & subscriptions, conferences, and computer supplies (tr. 1/284,
    12   Ms. Henriquez-Aguilar testified that TSI's support for its costs improved in
    FY 2009 from what it had in FY 2008 (tr. 1/289-90).
    42
    289-90; app. supp. R4, tab 150; R4, tab 70 at 1535-36). 13 The results ofthis expanded
    testing were provided to Senator Susan Collins (R4, tab 130). At the hearing,
    Ms. Henriquez-Aguilar agreed that she would not have expanded her testing if it had
    not been for TSI's congressional inquiry and the resulting congressional inquiry to
    DCMAIDCAA (tr. 1/285-86, 288-89).
    TS! Cost Documentation Did Not Change for 2002 through 2008
    22. Mr. Zysk was COO for TSI from 2005 through 2012 (tr. 2/73, 76, 102).
    Mr. Zysk testified that since he arrived at TSI in 2005, he didn't recall the DCAA
    auditors having anything negative to say until 2007. The only difference between the
    earlier years and 2007 was the auditor. (Tr. 2/115) Mr. Zysk testified that the work
    SMI did for TSI was essentially the same from 2005 when he started with TSI until
    2007 (tr. 21102, I 05, I 07). They did not create minutes of phone conversations
    (tr. 21107-08).
    23. Mr. Fletcher was CFO for TSI from 2004 through 2014 (tr. 2/117).
    Mr. Fletcher testified that he paid "extreme attention" to what the DCAA auditors said
    when they visited TSI. 14 In 2004 to 2006 the auditors looked at SMI invoices and found
    them acceptable so he felt they must be "appropriate." (Tr. 2/119) The DCAA auditors
    were one of Mr. Fletcher's "primary sources of information and expectations" (tr. 2/120,
    185). Mr. Fletcher testified that prior to 2007 when the DCAA auditors came, they
    always looked at professional fees, SMI and Mr. Chuck Wilson, and they "never, ever
    had a problem prior to 2007 with the level of documentation" (tr. 2/160). This testimony
    is corroborated by documents in the record. The record includes monthly "activity"
    memorandums (invoices) from SMI 15 for April, June, July, August, September, October,
    November, and December 2006 (app. supp. R4, tab 141 at 1-7). The record also
    includes Ms. Waller's working papers for her 2007 audit that includes similar SMI
    memorandum that are heavily annotated that I infer is Ms. Waller's 16 handwriting. The
    annotations include questions about the adequacy of support for the memorandums such
    as "No work product! i.e. reports." (R4, tab 53 at 1139) Similar handwritten
    13
    ACO Cuellar issued a final decision demanding payment of $60,365 for
    overpayments in FYs 2008 and 2009 that was appealed, docketed as ASBCA
    No. 60126 and stayed by the Board at the request of the parties pending the
    outcome of this appeal.
    14
    The government elicited testimony from Ms. Winefield that DCAA auditors are not
    allowed to provide guidance to contractors (tr. 2/251-52).
    15   These memorandums are not on SMI letterhead, however, they are from
    Mr. Peterson, the same person on the 2007 memorandums that are on SMI
    letterhead (R4, tab 53 at 1139).
    16   We must infer this because the government did not produce Ms. Waller at the
    hearing (tr. 2/259-60).
    43
    annotations appear on all of the 2007 SMI memorandums (R4, tab 53 at 1139, 1146,
    1188, 1194, 1219, 1228, 1253, 1266, 1277). In any event, the SMI memorandum that
    were accepted without question in the FY 2006 audit were almost identical to those
    questioned in the FY 2007 audit. Mr. Fletcher testified, "It was my intent to do things
    exactly as DCAA wanted us to do." (Tr. 2/160) TSI was "following business practices
    that had been approved from 2002, '3, '4, '5, and '6 by DCAA as submitted. 17 To me
    that's a pretty good testimony that you're doing things properly and we didn't change - -
    other than the bonus plan we didn't change anything in 2007 or '8 or '9." (Tr. 2/214-15)
    Since the 2007 audit didn't actually take place until almost the end of 2008, TSI did
    make some changes in documentation in 2009 (tr. 2/216).
    24. Ms. Pepin (now Ms. Tremblay) was a DCAA auditor in 2007 (tr. 2/5).
    Mr. Fletcher recalled Ms. Pepin's visit to TSI on 20 February 2008 (tr. 21121). She was
    there to review TS I's proposed rates for 2008 (id.; app. supp. R4, tabs 151, 177). They
    discussed TSI's executive bonus plan and he provided documents that she photocopied
    and took with her (tr. 2/122-23, 142, 190). Mr. Fletcher testified that he and Mr. Zysk
    were hired at "salaries considerably below our last jobs" with the expectation that if the
    company did well they would share in the rewards (tr. 2/138-39). They discussed
    professional fees because it was one of the bigger numbers under overhead (id.). When
    Ms. Pepin left she stated that everything looked fine to her (id.). Ms. Pepin testified at the
    hearing but when asked, she could not recall her meeting with Mr. Fletcher (tr. 2/13).
    25. Mr. Benton testified that TSI "had been through many audits and those
    audits were while we were under contract with the government, subject to FAR
    interpretation. And those audits set the standard. And the fact that the government
    wants to change that standard yet doesn't notify us is sort of applying a different
    standard to the government's side of fence than they're trying to apply to us."
    (Tr. 2/225) Mr. Benton testified, "the fact that we had operated the company since
    1985 and never had any issues, ever, and then have this fiasco, just makes me shake
    my head. I get asked to speak at SBIR [Small Business Innovative Research program
    (tr. 177-78)] conferences, I won't anymore. I tell people, don't do business with the
    government, you can't trust them." (Tr. 2/240)
    Appeal
    26. TSI appealed the 23 June 2014 final decision by letter dated 17 September 2014.
    27. The Board docketed the appeal as ASBCA No. 59577 on 18 September 2014.
    17
    There are no DCAA working papers from 2002 to 2006 in the record so I rely on
    sworn testimony to reach my conclusions.
    44
    DECISION
    The parties in their post-hearing briefs 18 discuss each of the costs disallowed in
    ACO Cuellar's final decision. Because I analyze this appeal from two perspectives,
    "retroactive disallowance" and "course of dealing," I do not look at all individual
    costs. As explained below, I conclude that both "retroactive disallowance" and
    "course of dealing" support my decision to sustain TSI's appeal in part.
    Preliminary Matters-Time Bar
    TSI asserts that DCMA's final decision is barred by the CDA's six-year time
    bar (app. br. at 2, 5, 11). As DCMA correctly points out, TSI has the burden of proof
    in this argument (gov't reply br. at 15). This argument fails because TSI's FY 2007
    ICP was submitted 25 June 2008 19 (finding 6). Six years from 25 June 2008 is 25 June
    2014. The final decision was issued on 23 June 2014, within the six-year period. It is
    not as close as it seems because the date of the ICP typically does not start the running
    of the six-year period, but it is the earliest possible date. Combat Support Associates,
    ASBCA Nos. 58945, 58946, 14-1 BCA, 35,782 at 175,041-42 (Claim does not
    "accrue" upon submission of the Incurred Cost Submission until there is sufficient
    supporting data to establish government knowledge of the claim.). I need not discuss
    the other attempts by TSI to persuade us that certain aspects of the government's claim
    are time-barred other than to say I agree with DCMA's analysis concluding that TSI's
    arguments are unpersuasive (gov't reply br. at 17-24).
    Preliminary Matters -Auditor "Independence"
    While TSI "concedes" that its argument that the final decision should be "vacated"
    due to "impaired Auditor Independence" is unsustainable (app. br. at 3), it included
    supporting evidence and argument in the record and brief. I therefore address it. There is
    evidence in the record that TSI's concern over DCAA's FY 2007 auditor's behavior may
    have been justified (finding 6). There is even evidence that DCAA and DCMA had
    concerns over the auditor's work (findings 6, 12, 16, 19, 20). However, the record does
    not support a finding that the auditor was biased against TSI and that said bias influenced
    her recommendations to such an extent that it would justify sustaining this appeal. 20
    18
    By letter dated 21 March 2016 the Board invited the parties to address course of
    dealings in their reply briefs. After receipt of the reply briefs there was no
    request from either party for additional briefing.
    19
    DCMA contends the date was 30 June 2008 (gov't reply br. at 13, 16) but there is
    no need to sort this date out because the result is the same for both.
    20
    The government did not call Ms. Waller as a witness apparently since she was no
    longer with DCAA (finding 23 n.16).                                   ·
    45
    Retroactive Disallowance21
    ACO Cuellar's 23 June 2014 final decision disallowed costs incurred in 2007
    (finding 15). This final decision was the first official notice to TSI that DCAA's
    practice of accepting TSl's documentary support for its costs and final rates in years
    2002 to 2006 was going to change. Therefore, these facts raise the issue of
    "retroactive disallowance."
    The term retroactive disallowance" is a bit of a misnomer. If taken literally one
    could conclude that for it to apply, DCAA I DCMA would have to have disallowed costs
    that had previously been approved, i.e., costs for FY 2002 through 2006. To so hold
    would render the commendable goal of fundamental fairness and consistency of audit
    standards set forth in the law discussed below meaningless. I rely heavily on Gould
    Defense Systems, Inc., ASBCA No. 24881, 83-2 BCA iJ 16,676. Gould is a complicated
    accounting case, but it relies on Data-Design Laboratories, ASBCA No. 21029, 81-2
    BCA iJ 15, 190. In Data-Design the company allowed first class air travel from 1966
    through 1972 with DCAA's knowledge and the costs were not questioned. For the first
    time the costs for 1973 were disallowed in a DCAA Form 1 issued in 1975. This Board
    considered this to be retroactive disallowance even though no previously allowed costs
    were disallowed. This is directly analogous to what happened in TSI.
    Retroactive disallowance is a "special application of estoppel principles."
    Gould, 83-2 BCA ii 16,676 at 82,981. The Board in Gould explained:
    This rule is to be compared with the related precept that the
    Government may not disallow retroactively historical costs
    where: the cost or accounting method in question
    previously had been accepted following final audit of
    historical costs; the contractor reasonably believed that it
    would continue to be approved; and it detrimentally relied
    on the prior acceptance. See e.g., Data-Design
    Laboratories, ASBCA No. 21029, 81-2 BCA iJ 15,190
    (and cases cited). The retroactive disallowance rule
    applies regardless of the allowability of the historical cost
    under the Defense Acquisition Regulations and requires
    that the Government only may disallow the cost or method
    prospectively. (Id.) Final determination of costs or
    acceptance of an accounting methodology as a result of the
    audit called for in the "Allowable Cost, Fee and Payment"
    clause precludes the Government from disallowing even
    21
    This issue was raised sua sponte.
    46
    unallowable costs incurred prior to notice by the ·
    Government that its prior acceptance was rescinded.
    
    Id. After discussing
    the facts and granting relief the Board in Gould explained the
    principle behind its decision:
    The contrary position suggested by the Government
    essentially rests on the hypothesis that a Government agent
    can do no wrong if he misinterprets a cost accounting
    standard even though the contractor reasonably relies on
    the misinterpretation. We believe the contractors are
    entitled to a greater degree of certainty in their financial
    dealings with the Government. Once the Government
    unequivocally takes its stand and reads and applies the
    standard in the same manner as the contractor, it is
    essential that the contractor be entitled to rely on that joint
    interpretation until notified otherwise. This rule is
    essential to the orderly conduct of business with the
    Government and is applicable irrespective of whether a
    Defense Acquisition cost principle or a Cost Accounting
    Standard is involved.
    
    Id. at 82,984.
    I agree whole heartedly with this goal.
    The critical issue to decide is if the defense of retroactive disallowance, like
    traditional estoppel, requires the additional element of "affirmative misconduct":
    The Supreme Court also has held that estoppel may run
    against the government, but that "the Government may not
    be estopped on the same terms as any other litigant." A
    plaintiff "also must show that the government engaged in
    'affirmative misconduct."'
    Kingman ReefAtoll Development, L.L.C. v. United States, 
    116 Fed. Cl. 708
    , 767 (2014)
    (citations omitted). The Board has not unambiguously applied the requirement of proving
    affirmative misconduct to retroactive disallowance. In United Technologies Corp, Pratt
    & Whitney, ASBCA No. 47416 et al., 06-1 BCA ~ 33,289 the Board dealt with a remand
    from the Court of Appeals for the Federal Circuit (CAFC). The CAFC wrote:
    A final argument raised by Pratt before the Board
    was that the government is estopped from contesting Pratt's
    determination that the revenue payments for parts acquired
    under the collaboration requirements did not constitute
    47
    costs. This is said to be so because of the government's
    prior acceptance of Pratt's treatment of those items. United
    Techs., 01-2 BCA ~ 31,592, at 53 [sic]. Based on its
    interpretation of "cost," the Board did not reach this issue.
    
    Id. This question,
    therefore, remains open on remand.
    Adjudication of the estoppel issue must proceed under the
    "well settled [rule] that the Government may not be
    estopped on the same terms as any other litigant." Heckler
    v. Cmty. Health Servs. of Crawford County, Inc., 
    467 U.S. 51
    , 60, 
    104 S. Ct. 2218
    , 81L.Ed.2d42 (1984). Beyond a
    mere showing of acts giving rise to an estoppel, Pratt must
    show "affirmative misconduct [as] a prerequisite for
    invoking equitable estoppel against the government."
    Zacharin v. United States, 
    213 F.3d 1366
    , 1371, 55
    USPQ2d 1047, 1051 (Fed. Cir. 2000) (emphasis added).
    Rumsfeldv. United Technologies Corp., Pratt & Whitney, 
    315 F.3d 1361
    , 1377 (Fed.
    Cir. 2003). Retroactive disallowance was not mentioned in the Board's original
    decision. United Technologies Corp., Pratt & Whitney, 01-2 BCA ~ 31,592. The
    CAFC did not mention retroactive disallowance in its remand guidance. However,
    Pratt & Whitney did mention retroactive disallowance in its argument in the remand
    case. United Technologies, 06-1 BCA ~ 33,289 at 165,050. This Board did not
    mention retroactive disallowance in its remand decision. 
    Id. at 165,058
    ("We,
    therefore, will follow the guidance provided by the CAFC in deciding the estoppel
    issue in these appeals and require that appellant demonstrate some form of affirmative
    misconduct.. .. "). Given the CAFC's remand guidance and this Board's failure to
    specifically refer to retroactive disallowance, I do not interpret this Board's use of the
    term "estoppel issue" to definitively mean "retroactive disapproval." This position is
    supported by a more recent decision where this Board did not apply affirmative
    misconduct to retroactive disallowance. In Raytheon Co., ASBCA No. 57576 et al.,
    15-1 BCA ~ 36,043, we considered both retroactive disapproval and equitable
    estoppel. With respect to retroactive disallowance the Board held:
    We have applied the retroactive disallowance
    principle to bar recovery of government claims. Lockheed
    Martin Western Development Laboratories, ASBCA
    No. 51452, 02-1BCA~31,803. However, its application
    is largely fact-dependent. In these appeals, there are
    material factual disputes of record that need to be
    addressed to determine whether this principle is applicable
    here, including but not limited to, whether or not the
    government, with knowledge, consistently approved the
    subject BAIC and TSR metric costs; and if so, when the
    48
    government first put appellant on reasonable notice that
    said costs were unallowable. Given these material fact
    disputes, we decline to award summary judgment to either
    party on this defense. See Peat, Marwick, Mitchell & Co.,
    ASBCA No. 29847, 86-2 BCA ~ 18,915 at 95,400.
    
    Id. at 176,055.
    With respect to equitable estoppel the Board held:
    We further held that this added requirement of
    affirmative misconduct contemplates government
    misconduct "of a nature more compelling than the conduct
    that would otherwise apply against a private party. See,
    e.g., RGW Communications, 05-2 BCA [~ 32,972 at
    163,336 (referencing deliberate lies; a pattern of false
    promises, or intentional deception as examples of
    affirmative misconduct)." Northrop Grumman, 14-1 BCA
    ~ 35,501 at 174,024.
    Based upon the foregoing, we believe that Raytheon
    has failed to adduce any evidence to support a finding of
    affirmative misconduct by the government here. Hence,
    Raytheon has failed to adduce evidence necessary to
    support its estoppel defense as a matter of law. We grant
    summary judgment to the government on appellant's
    defense of equitable estoppel.
    
    Id. at l
    76',055-56. This decision does not apply affirmative misconduct to retroactive
    disallowance; if it did summary judgment would have also been granted to the
    government as to the defense of retroactive disallowance.
    Although not discussed in any case law found, I believe it is appropriate to treat
    retroactive disallowance and traditional estoppel differently. This is because traditional
    estoppel is a permanent prospective bar to the government's action; retroactive
    disallowance is not. In retroactive disallowance the government may change its standard
    and disallow costs it had previously allowed, i.e., the "estoppel" only applies between
    the previous approval(s) and the point when the government provides notice to the
    contractor that it will impose a different standard in the future. I therefore do not impose
    the requirement for affirmative misconduct to retroactive disapproval. I would sustain
    the appeal in part based on retroactive disapproval. However, I admit my concern over a
    possible alternative interpretation of United Technologies, 06-1 BCA ~ 33,289, so I
    consider an alternative theory to reach the goals of the "greater degree of certainty in
    their financial dealings with the Government" and "orderly conduct of business with the
    Government" set forth in Gould and quoted above.
    49
    Course of Dealing22
    At least one case suggests that "course of dealing" provides an alternative to
    retroactive disallowance. In a case involving the disallowance of post-retirement benefits
    (PRB ), this Board found that appellant failed to prove affirmative misconduct and "The
    government did not mislead appellant with respect to the allowability of the unfunded
    PRB costs in dispute here, nor did the parties have a course of dealing with respect to
    them." Northrop Grumman Crop., ASBCA No. 57625, 14-1 BCA, 35,501at174,024.
    In the Board's decision denying Northrop Grumman's motion for reconsideration we
    again held that appellant had not proven either affirmative misconduct or course of
    dealing. Northrop Grumman Corp., ASBCA No. 57625, 14-1BCA,35,743 at 174,930.
    I therefore, evaluate the applicability of course of dealing in this appeal.
    At the outset I accept the testimony of Messrs. Benton, Zysk and Fletcher that TSI
    did not change its contracting, record keeping and accounting practices for 2002 through
    2007, and that DCAA was satisfied with TSI's documentation and accepted TSI's proposed
    final indirect rates without question for the years 2002 through 2006 (findings 22-25).
    Messrs. Benton, Zysk and Fletcher testimony is corroborated by Ms. Winefield (finding 20).
    The 2002 to 2007 audits included invoices from SMI and Mr. Wilson (findings 11, 14, 20,
    22-25). It is also noteworthy that the initial audit of TS I's rate submission for FY 2008 and
    FY 2009 continued the practice from 2002 to 2006 of accepting TSI's proposed rates
    without question until the "expanded testing" occasioned by TSI's congressional inquiry
    disallowed costs (finding 21 ).
    DCMA explains that "each cost year stands on its own" and that since each audit "is
    dependent upon the particular auditor's assessment of the risk" there can be no course of
    dealings (gov't reply br. at 25). I reject DCMA's argument that there need be no consistency
    in DCAA' s audit practice with respect to a given contractor over the years. I also reject
    DCMA's apparent position that it has no discretion to question DCAA's recommendations
    unless additional substantiation is forthcoming from the contractor (finding 11 ).
    The record reflects a glimmer of understanding of the problem in Mr. Cook's
    9 June 2014 email stating that DCAA "headquarters wants to insure offices closely
    coordinate so we are taking same position on same type of issues and no instances of
    same information provided but different DCAA positions" (finding 19). Similarly in
    Ms. Winefield's 12 June 2014 email, "Unfortunately, I think the difference between
    the FY 2007 and FY 2008/FY 2009 audit is auditor judgment. It doesn't look to me
    that TSI was providing much better support in FY 2008/FY 2009£23 1 than what we saw
    22
    The Board raised the issue of course of dealing sua sponte and requested that the
    parties discuss it in their reply briefs.
    23   This was before the re look of TSI' s FYs 2008, 2009 rate submissions (finding 21 ).
    50
    in FY 2007." (Finding 20) Unfortunately this glimmer of understanding was not
    translated into action to protect TSI. TSI closed its doors in August 2014, one month
    after Ms. Henriquez-Aguilar's 29 July 2014 audit report of TS I's FYs 2008 and 2009
    incurred costs based on her "expanded testing" caused by TSI's congressional inquiry.
    (Findings 1, 17, 21 )
    I start with the Restatement:
    § 223 Course of Dealing
    (3) A course of dealing is a sequence of previous conduct
    between the parties to an agreement which is fairly to
    be regarded as establishing a common basis of
    understanding for interpreting their expressions and
    other conduct.
    (4) Unless otherwise agreed, a.course of dealing between
    the parties gives meaning to or supplements or qualifies
    their agreement.
    RESTATEMENT (SECOND) OF CONTRACTS§ 223.(1981). The Board has relied on
    Restatement, Section 223, Course of Dealing in past decisions. BAE Systems Technology
    Solutions & Services, Inc., ASBCA No. 57581, 13 BCA ii 35,414 at 173,742 (citing C.R.
    Pittman Constr. Co., ASBCA No. 54901, 08-1BCAii33,777 at 167,178; T&M
    Distributors, Inc., ASBCA No. 51405, 00-1BCAii30,677 at 151,509).
    DCMA also quotes the Restatement in its reply brief (gov't reply br. at 27).
    However, DCMA narrowly interprets the Restatement, stating"[ c]learly this rule [the
    Restatement] applies only in those instances where the parties have formed an
    agreement and the course of dealing gives meaning to that agreement" (id.). I disagree
    with this narrow interpretation. The Restatement is clear that a course of dealing may
    be based on conduct, "previous conduct between the parties to an agreement which is
    fairly to be regarded as establishing a common basis of understanding for interpreting
    their expressions and other conduct." RESTATEMENT (SECOND) OF CONTRACTS§ 223.
    It is the conduct of DCAA, DCMA and TSI for FY s 2002 to 2006 that forms the basis
    of a course of dealing.
    The first element of the Restatement is the "parties to an agreement"
    requirement. The Board has held that "[j]ustifiable reliance of a prior course of
    dealing requires proof of the same contracting agency, the same contractor, and
    essentially the same contract provisions." Tekkon Engineering Co., ASBCA
    No. 56831, 10-2 BCA ii 34,563 at 170,441. TSI's contracts were with the Navy, not
    DCAA or DCMA (finding 2). DCMA sees this issue but its analysis falls short
    arguing that DCAA "is not a contracting agency nor are there any contractual
    51
    agreements between DCAA and TSI that the Board could attempt to interpret" and
    "the course of dealing rule is simply inapplicable" (gov't reply br. at 28-29). I do not
    see this as an impediment to applying "course of dealing" for several reasons. First,
    the final decision was issued by DCMA based on DCAA 's "non-audit" service to
    assist DCMA (findings 9, 15). Second, contract clause FAR 52.215-2, Audit and
    Records - Negotiation (finding 3), subjects TSI to audit by the "authorized
    representative of the Contracting Officer" and those representatives are DCAA and
    DCMA. Finally, the actions ofDCAA and DCMA are imputed to the Navy based on
    the "close relationship" or "significant bond" between DCMA, DCAA and the Navy
    established by the contract and government regulations. See Raytheon Missile Systems
    Company, ASBCA No. 57594, 13 BCA ~ 35,264 at 173,112-15 (DESC's decision to
    raise the price of JP-10 fuel was imputed to NA VAIR because of the "significant
    bond" between the sole supplier of JP-10 DESC and NA VAIR). As far as the same
    contract provisions, DCAA applied FAR Part 31, Contract Cost Principles and
    Procedures, in its audits and there is no evidence that these provisions changed in any
    significant way from 2002 to 2007. The government is silent as to the validity of the
    audit standards between 2002 and 2006 arguing that the prior audits are irrelevant.
    However, if different auditors interpreted FAR Part 31 differently in 2002 to 2006 than
    in 2007, that course of dealing set a standard TSI was entitled to rely upon. Comptech
    Corp., ASBCA No. 55526, 08-2 BCA ~ 33,982 at 168,086 ("to nullify an
    unambiguous specification requirement based upon conduct, one must show: actual
    knowledge by both parties of consistent conduct by one party in its contract dealings
    with the other e>ver an extended period of time regarding a particular contract
    provision upon which the other is reasonably entitled to rely"). A corollary to this is
    the requirement for "mutuality." DCX-CHOL Enterprises, Inc., ASBCA No. 54707,
    08-2 BCA ~ 33,889 at 167,729 ("The missing element is mutuality, viz., the 'actual
    knowledge by both parties of the prior course of dealing and its significance to the
    contract."'). It is clear that both TSI and DCAAIDCMA understood the significance
    of the audits, the standards imposed and the acceptance without question of TSI' s
    indirect rates for five years prior to 2007 - there is mutuality.
    The Board has applied course of dealings in cases similar to this. Evidence of
    costs that have been routinely invoiced and paid can establish a course of dealing. Blue
    Cross Association and Blue Shield Association, ASBCA No. 25778, 89-2 BCA ~ 21,840
    at 109,907 n.41 ("disallowing costs is a Government claim, not a contractor claim, absent
    a formal demand by the contractor, at least where the costs have been routinely invoiced
    and paid in the past and it is the Government seeking to change a past course of
    dealing"). Course of dealing has been applied to G&A. Ford Aerospace and
    Communications Corp., Aeronutronic Division, ASBCA No. 23833, 83-2 BCA ~ 16,813
    at 83,631 n.3 ("This prior course of dealings by the parties with respect to a substantial
    portion of appellant's G&A pool reinforces our conclusion that greater benefits from
    G&A are furnished to labor intensive contracts in appellant's circumstances.").
    52
    Consistent with course of dealing, a presumption of reasonableness attaches
    where a contractor's cost allocation practices are consistently applied by the contractor
    and accepted by the government:
    Once it has been determined that an otherwise
    allowable and reasonable indirect cost item is allocable to
    Government contracts under the specific benefit standard
    of DAR l 5-201.4(ii), the salient question affecting the
    amount of cost that will be allowable is the reasonableness
    of the contractor's cost allocation method. A presumption
    of reasonableness ordinarily attaches to cost allocation
    practices that are consistently applied and followed by the
    contractor. Such consistently applied accounting practices
    will be disturbed only upon a persuasive showing by the
    Government that, due to particular circumstances, further
    use of that practice would be inequitable.
    Martin Marietta Corporation, ASBCA No. 25828, 84-1 BCA, 17, 119 at 85,255
    (citations omitted). 24
    Now I consider the evidence of the dealings between DCAA/DCMA and TSI
    during years 2002 to 2006. I do not ignore the fact that the 2001 DCAA audit
    disallowed professional fees for similar reasons professional fees were disallowed in
    the FY 2007 audit (finding 5). However, I do not know what, if any, changes were
    made in TSI's record keeping in 2002 and it is undisputed that DCAA accepted JSI's
    records, costs and indirect rates without question in years 2002 to 2006 (id.). I
    understand that in 2004 and 2005 DCAA conducted desk reviews rather than full
    audits, but that was DCAA's decision based on its conclusion that "after review of
    TSI's ICP, DCAA determined that there was a low risk that the ICP contained
    unallowable costs" (id.). I also note that DCAA's practice suggests that the 2007 audit
    could have been a desk review (id.). The desk reviews in no way diminish the
    importance of years 2004 and 2005 in evaluating a course of dealings. I also
    understand that there is no "magic number" of contracts that must be performed before
    course of dealing is established, "the parties' prior dealings must be regular and/or
    numerous enough to cause a reasonable expectation that the conduct relied upon was
    not mere accident or mistake, but was the performance actually expected by the other
    party." C.R. Pittman Construction Co., ASBCA No. 57387 et al., 15-1 BCA, 35,881
    at 175,425. The Restatement's standard, quoted above, is "sequence of previous
    conduct between the parties to an agreement which is fairly to be regarded as
    establishing a common basis of understanding for interpreting their expressions and
    24   The decision does not use the term "course of dealing," but it seems applicable to
    this appeal.
    53
    other conduct." The unchallenged testimony of TS I's management cited above
    supports my conclusion that based on DCAA's and DCMA's three full audits and two
    deskreviews approving TSI's documentation and final rates during 2002 to 2006 was
    a "sequence of previous conduct," that created a "common basis of understanding"
    between TSI and DCAA/DCMA that TSI had a reasonable expectation that its cost
    documentation and DCAA's audits were correct. Mr. Fletcher, CFO, provided
    credible testimony that he relied on DCAA's 2002 through 2006 audits to set the
    standard of review for TSI's records (finding 23). Messrs. Benton, TSI's president and
    owner, and Zysk, COO, likewise provided credible testimony, supported by the record,
    that TSI provided the same kind of support for its FY 2007 costs as it did for years
    2002 to 2006 (findings 11, 14, 22-23, 25). Ms. Winefield's 12 June 2014 email
    corroborates their testimony (finding 20).
    I conclude that all the elements required to prove a course of dealing are satisfied.
    I must now determine the remedy available to TSI. As the Restatement quoted above
    indicates, the typical application of course of dealing is contract interpretation. This is
    not precisely the case here; here I deal with a course of dealing involving TSI's records,
    audits and final indirect rate determinations. I take at face value DCMA's discussion of
    the documentation required by FAR 3 l.205-33(f)(l-3) for professional fees (gov't reply
    hr. at 31-33, 41-43). It may well be that upon closer scrutiny TSI's documentary support
    for these costs was lacking, but that is not the point. I do not question DCMA's/DCAA's
    right to apply closer scrutiny to TSI's documentation, I find however that after accepting
    the exact same documentation for FYs 2002 to 2006, TSI was entitled to notice and time
    to change its record keeping to satisfy the auditors. This remedy is consistent with our
    decisions in retroactive disallowance cases. Blue Cross and Blue Shield Association,
    ASBCA No. 53632, 04-1 BCA ii 32,413 at 160,449 ("The Government must have
    'consistently accepted and allowed' the cost in question and failed to provide the
    contractor with proper notice that the cost will be disallowed in the future" (citation
    omitted)); Peat, Marwick, Mitchell & Co., ASBCA No. 29847, 86-2 BCA il 18,915 at
    95,400 ("If the guidelines set out above are met, the Government must authoritatively
    infonn the contractor of any subsequent disallowance of the earlier accepted costs ... .''):
    Gould, 83-2 BCA il 16,676 at 82,981 (the government may not disallow even
    unallowable costs incurred prior to notice by the government that prior acceptance was
    rescinded); Western Electric Co., ASBCA Nos. 21294, 21295, 79-1BCAil13,550 at
    66,384 ("Having given its approval to WECO, approval must remain in effect until notice
    of its recession is conveyed."). I conclude that the only reasonable remedy is to sustain
    the appeal and not enforce the COFD's disallowance of FY 2007 costs, contested by
    TSI, 25 based on the parties' course of dealing over the five years preceding 2007. I
    25   Disallowed costs that TSI agrees with are not included in the reliefl would grant. For
    example, TSI agrees with the disallowance of $2,300 for expressly unallowable
    entertainment costs unrelated to business and these disallowed costs are unaffected
    54
    disagree with ACO Cuellar's belief that, absent additional support for the costs from TSI,
    DCMA lacks discretion to disagree with DCAA (finding 11 ). The evidence of course of
    dealing between 2002 and 2006 is overwhelming and DCMA certainly had the discretion,
    and one might say obligation, to give TSI time to adapt to the new standard being
    applied. This is particularly true given TSI's warning that DCMA's decision would put
    TSI out of business, which it apparently contributed to. 26 (Findings 1, 11) The appeal
    shall be sustained as to the following costs:
    COFDNote                                DISALLOWED COSTS
    Note 1                $51,340 for marketing services provided by SMI (finding 23)
    Note2                 $26, 198 in computer supplies expenses in 2007 27 (finding 14)
    Note 5(b)              $2,925 for work performed by Charles Wilson (finding 23)
    Note 8                              $2,417 in claimed G&A expenses
    Note 10              $2,661 in subcontract costs that were not approved in advance 28
    Note 11             $28,568 in subcontract costs that were not approved in advance 29
    Costs Excluded from Course of Dealing
    Next I consider individual costs that I do not include in course of dealing.
    Expressly Unallowable Costs
    I do not include costs that were expressly unallowable in the course of dealing
    costs. Raytheon Company. ASBCA No. 57576 et al., 15-1 BCA, 36,043 at 176,051 ("An
    by our decision (R4, tab 6(a) at 74, tab 16 at 4, note 3). The same is true of the
    80% limitation of recovery of attorney's fees (R4, tab 16 at 5, note 5(a)).
    26   I do not find that DCAA/DCMA put TSI out of business because that matter was
    not litigated fully.
    27   I included computer supplies in the course of dealing costs, but if I had not, I would
    still sustain the appeal as to these costs. Mr. Fletcher explained that the .
    computers that were expensed in the year they were purchased were not used on
    employee desktops, but were heavily modified, sent to be used for field testing
    and were fully consumed in the year they were purchased, i.e., a useful life of
    one year (finding 14; app. reply br. at 20). It therefore made perfect sense to
    expense them and DCAA's insistence that these computers be treated as if they
    were used on office desktops makes absolutely no sense.
    28   The record as to similar unapproved subcontract costs in 2002 to 2006 is sparse and I
    rely on TSI witness testimony that TSI made no changes in its procedures in years
    2002 through 2007 to include these in the course of dealing costs (findings 22-25).
    DCMA's discussion of these costs may be correct (gov't reply br. at 43-45), but
    again misses the point that it varies from the parties' course of dealing.
    29
    See footnote 27.
    55
    'expressly unallowable' cost, by the plain terms of the definition, must be an item of cost
    or a type of cost that is specifically named and stated as unallowable by law, regulation or
    i contract.''). The appeal should be denied as to the following costs:
    COFDNote                                DISALLOWED COSTS
    (R4, tab 16)
    Note 3                   $2,300 entertainment; $304 travel over per diem rates
    Note 5(a)                       $6,886 - 80% limit on attorney's fees
    Note 5(c)                         $706 in legal fees unrelated to TSI
    Note 5(d)                 $1,000 in legal fees to prepare personal tax returns
    Note 6                              $577 travel over per diem rates
    Note 9                             $1,07 4 travel over per diem rates
    Note 10                             $466 travel over per diem rates
    Note 11                            $1,986 travel over per diem rates
    Executive Bonuses
    ACO Cuellar disallowed $29,967 30 ($25,698 Overhead and $4,269 G&A) 31 in
    executive bonus costs that cannot be included in the course of dealing costs because
    the bonuses didn't start until 2007 (findings 23-24). I did not include a discussion of
    the facts surrounding these costs in the Findings of Fact above so I include them here.
    Starting with a limitation imposed only on the owner, Mr. Benton, that the
    compensation cannot be a distribution of profit. FAR 31.205-6( 6)(ii)(B); SplashNote
    Systems, Inc., ASBCA No. 57403, 12-1BCAif34,899 at 171,610 ("We are not
    persuaded by SplashNote's argument that the bonuses for the other employees were
    not questioned whereas Mr. Tse's [majority owner] was; allowability of their bonuses
    is not restricted by the 'distribution of profits' prohibition, which is limited only to the
    designated individuals."). In her draft audit report, Ms. Waller found that $6,500 and
    $406 (year-end) bonuses paid to Mr. Benton were a distribution of profit, "in the
    absence of a proper employer/employee agreement, and the fact that TSI is an 'S ·
    Corporation," 32 it is our opinion that the bonuses paid to Mr. Benton were a
    distribution of profit (R4. tab 53 at 592-93). In her COFD. ACO Cuellar did not adopt
    Ms. Waller's finding and did not find that any bonuses were a distribution of profit
    (R4, tab 16 at 259. note 4). However, in its briefthe government argues that all
    $29,967 was a distribution of profit (gov't br. at 60). The government overlooks the
    fact that this limitation only applies to Mr. Benton· s bonuses, something less than the
    $29.967. The only evidence the government presents to prove that Mr. Benton's
    30
    Ms. Waller's draft audit report disallowed $39,150 in bonuses. ACO Cuellar
    apparently determined that some of the bonuses were allowable but the
    specifics are not readily apparent in the record.
    31
    COFD Notes 4 and 7 (finding 15).
    32
    The significance of an "S" Corporation is not explained in the record.
    56
    bonuses were a distribution of profits was testimony from Mr. Fletcher (gov't br. at 21.
    iii! 16, 60). When asked if the bonuses came out of company profits. Mr. Fletcher
    testified, "It has to come out of company profits. I mean, where else would it come
    from?" (Tr. 2/ 173-74) The question of distribution of profit is a more complicated
    matter than simply eliciting such testimony from Mr. Fletcher:
    In Lulejian and Associates, the Board looked at
    several factors to assess when a bonus was actually a
    distribution of profits: whether any dividends were
    declared (i.e .. whether the bonus was actually a disguised
    dividend), how large a share of the bonus pool was
    allocated to the top executive(s). and how '·substantial" the
    rest of the compensation was. Lulejian and Associates,
    Inc., ASBCA No. 20094, 76-1 BCA if 11,880 at 56,945
    (ASPR l 5-205.6(a)(2)(i) provided that --Determination
    should be made that such compensation is reasonable for
    the actual personal services rendered rather than a
    distribution of profits''). Because there were no dividends
    declared, the top four executives garnered 51 % of the
    bonus pool, and their compensation was otherwise
    substantial. the Board found certain bonus costs
    unallowable. Lulejian, 76-1 BCA if 11,880 at 56,945.
    Here, like Lulejian, SplashNote declared no dividends, and
    Mr. Tse's share of the bonus money was great-71%
    (findings 10, 12). Although DCMA determined Mr. Tse's
    total compensation to be reasonable. the bonus itself still
    must not be a distribution of profits. and the presence of
    the other two factors suggests that it was.
    SplashNote, 12-1 BCA if 34,899 at 171,609-10. Mr. Fletcher's testimony was
    equivocal, "I mean. where else would it come from?"· I do not consider this testimony
    alone sufficient to prove that the bonuses were a distribution of profit. The
    government has the burden of proof. The government failed to consider any of the
    factors discussed above, i.e. "S" Corporation, dividends, share of the pool, how
    substantial the other compensation was, and what portion of the $29,967 was paid to
    Mr. Benton. The government failed to meet its burden of proof that Mr. Benton's
    bonuses were a distribution of profit.
    The government correctly points out that FAR 31.205-6(f) governs the
    allowability of bonuses (gov't br. at 59-60):
    (i) Awards are paid or accrued under an
    agreement entered into in good faith between the
    57
    contractor and the employees before the services are
    rendered or pursuant to an established plan or policy
    followed by the contractor so consistently as to
    imply, in effect, an agreement to make such
    payment; and
    (ii) Basis for the award is supported.
    '
    FAR 3 l.205-6(f). TSI's bonus plan was agreed to by Mr. Benton, Mr. Zysk and
    Mr. Fletcher in late 2006 (tr. 21192). The written bonus plan, to take effect on
    1 January 2007, was signed by Mr. Benton on 1 December 2006 (R4, tab 9(c)). DCMA
    dismisses this document as, "nothing more than a one-page document which appears to
    evidence TSI's intent to establish an 'Executive Compensation Plan' effective January
    1, 2007" (gov't reply br. at 38). Considering that TSI is a company with less than
    twenty employees (finding 1) I consider the formality demanded by DCMA
    unreasonable. There was no written, signed agreement between Mr. Fletcher, Mr. Zysk
    and Mr. Benton concerning bonuses, however, Mr. Fletcher testified, "It wasn't signed
    but it was certainly agreed to" (tr. 2/192). The performance metrics included "Orders,
    Sales, Backlog, Revenue, Overhead Rates, Special Accomplishments, and Successful
    program management" (R4, tab 9(c)). The government contends that the bonuses are
    unallowable for five reasons: (1) there is no written (signed) agreement "between TSI
    and Messrs. Benton, Zysk and Fletcher before the compensation plan became
    operational or at any time in FY 2007"; (2) there is no "written company plan or policy
    relating to bonuses that was in effect in 2007"; (3) "TSI also failed to establish that the
    awards were paid pursuant to an established policy or plan which was consistently
    followed"; (4) "TSI failed to provide sufficient evidence to support the basis for the
    awards"; and (5) $15,000 in bonuses paid in March 2008 are not allocable to FY 2007
    (R4, tab 16 at 259-60, note 4; gov't br. at 59-60). I consider these reasons in turn. The
    government does not allege bad faith and there is nothing in the record that would
    support bad faith. It is true that there is no written agreement signed by Messrs.
    Benton, Zysk and Fletcher, but the government failed to prove that one was required.
    FAR 3 l.205-6(f)(l )(i) does not require a written agreement signed by these three
    individuals, and the second clause allowing for an implied agreement supports the
    conclusion that a signed agreement is not absolutely necessary. Mr. Fletcher's
    testimony that the three executives agreed to the plan in 2006 is undisputed. I find that
    the agreement existed before performance in 2007 and there is no requirement that their
    agreement be in writing and signed by the three executives. Second, the government
    argues the 1 December 2006 Executive Compensation Plan is not a plan because TSI
    was "going to" establish a plan starting 1 January 2007. This argument is only
    semantics and does not render the plan meaningless. I find that TSI produced a written
    bonus plan signed by Mr. Benton on I December 2006 commencing on I January 2007
    (R4, tab 9(c)). Third, I agree that there was no established plan that was consistently
    followed because the 2007 plan was new. However, this requirement in the second
    58
    clause of FAR 3 l.205-6(t)(l )(i) is an alternative to the agreement in the first clause and
    is therefore not a reason for disallowance. The fourth justification cited by the
    government is subjective. According to ACO Cuellar's COFD and the government's
    brief, "TSI did not provide sufficient evidence documenting the basis of the bonus
    awards" (R4, tab 16 at 259; gov't br. at 60). TSI provided the following four
    documents: ( 1) an unsigned one-page memorandum entitled "TSI Bonus Policy"
    (app. supp. R4, tab 146 at l); (2) a 30 May 2007 email with bullet comments supporting
    "a highly successful first quarter of 2007" recommending bonuses of $1,000 each for
    the three executives (id. at 6); (3) a 14 September 2007 memorandum with nine bullet
    comments supporting the award ofbonuses 33 (id. at 7); and (4) a 27 February 2008
    memorandum with eleven bullet comments authorizing bonuses of $9,000 to Mr. Zysk
    and $6,000 to Mr. Fletcher for performance for 2007 (id. at 8-9). There were also
    discussions with Messrs. Benton, Fletcher and Zysk. 34 I considered these documents
    and find that they provide adequate support for the FY 2007 bonuses for three reasons
    ( 1) the degree of formality was reasonable for a company with less than twenty
    employees (finding 1), (2) the fact that Mr. Zysk and Mr. Fletcher worked for salaries
    "considerably below" their previous salaries (finding 24), and (3) the total sum of the
    bonuses was modest. Finally, ACO Cuellar disallowed the $15,000 in bonuses paid to
    Mr. Zysk and Mr. Fletcher because the actual payment was in March 2008. She
    concluded that the $15,000 was allocable to FY 2008. She apparently gave no weight
    to the memorandum that authorized the payments based on performance in FY 2007
    (app. supp. R4, tab 146 at 8-9). Mr. Fletcher testified that $15,000 was accrued during
    FY 2007 and actually paid out in early March 2008 (tr. 2/140-41). This was partly
    because he and Mr. Zysk were traveling in January and February and they didn't get
    around to paying the bonuses until early March (tr. 2/142). DCMA gives no weight to
    these facts. I find that TSI's explanation of why the $15,000 was paid in early March
    was reasonable and that the $15,000 was allocable to FY 2007. I would sustain the
    appeal as to the disallowance of all of the bonuses.
    Legal Fees for Criminal Investigation
    ACO Cuellar disallowed $27 ,543 35 in legal fees incurred by TSI to represent its
    interests during a criminal investigation by the Navy (finding 15). I did not include a
    discussion of the facts surrounding these costs in the Findings of Fact above so I
    include them here.
    33
    The memo refers to the first quarter but the date persuades me that it referred to
    events up to September 2007.
    34
    Ms. Winefield testified that DCAA auditors cannot rely on statements from
    contractors to verify facts (tr. 1/210-12).
    35   This is 80% of the incurred cost of $34,429 (R4, tab 16 at 260, note 5(a)).
    59
    The $27,543 in legal fees that were incurred from 2002 through 2005 to defend
    TSI's interests during a criminal investigation by the U.S. Naval Criminal
    Investigative Service (NCIS). The costs were disallowed because ACO Cuellar
    concluded they were allocable36 to FY 2006 and should not have been claimed in
    FY 2007. (R4, tab 16 at 5, note 5(a)) The investigation also included The Kemper
    Group, Inc. and Sonetech Corporation. The document relied upon to disallow these
    costs was a 16 March 2005 message from NCIS addressed to Sonetech that stated the
    investigation was closed (R4, tab 53 at 1278). The message was not provided to TSI at
    that time and NCIS never sent such a message addressed to TSI. Sonetech sent the
    16 March 2005 NCIS message to TSI on 20 June 2006 (id.). DCMA's contention,
    "TSI was notified of the investigation's closure, at the latest, on June 20, 2006" fails to
    take into consideration that the message was addressed to Sonetech, not TSI (gov't
    reply br. at 39). ACO Cuellar decided that, based on the 2006 fax from Sonetech to
    TSI, the costs should have been claimed in FY 2006 (R4, tab 16 at 260, note 5).
    Mr. Benton explained that he never received a similar notice from NCIS addressed to
    TSI and wasn't confident the investigation of TSI was closed until an NCIS agent
    called and asked where to return TSI's documents (tr. 2/234-35). Mr. Benton did not
    recall the exact date the documents were returned 37 but testified he was not convinced
    the investigation was over as to TSI until the documents were returned (tr. 2/237). I
    find that Mr. Benton's uncertainty was caused by NCIS' failure to address a message
    directly to TSI informing it that the investigation as to TSI was closed. I will not
    penalize TSI due to the NCIS' failure. I find that Mr. Benton's explanation is
    credible38 and it was reasonable for him to consider the investigation of TSI, as
    opposed to Sonetech, might remain open, in the absence of an NCIS message
    addressed to TSI. There is no question that TSI incurred the costs. I also note that
    DCMA's argument seems to be influenced by the cost to the government rather than if
    TSI's actions were reasonable under the circumstances, "[h]ad TSI properly claimed
    the expenses in FY 2006, the amount that would have been allowable would have been
    significantly less than in FY 2007 because the Government participation in TSI' s
    G&A pool represented a smaller portion of TSI's base in 2006" (gov't reply
    br. at 40-41). I would sustain the appeal of the disallowance of$27,543 in legal fees to
    defend TSI during the NCIS investigation.
    36
    ACO Cuellar did not find that the costs were unallowable.
    37   Mr. Benton submitted an FOIA request in 2015 (R4, tab 149) to find the date
    the documents were returned but never received a response (tr. 2/235-36; ex. A-3).
    38   The COFD note 5a. states that TSI (Mr. Fletcher) said it "forgot" to claim the costs
    in 2006, but Mr. Fletcher disputes that statement (tr. 2/212; R4, tab 16 at 5).
    The evide.nce is insufficient for me to find that TSI "forgot" to claim the costs
    in 2006 or that it would matter if true.
    60
    CONCLUSION
    The appeal should be sustained as explained above. The demand for $159,303
    should be reduced accordingly.
    Dated: 12 January 2017
    Administr tive Judge
    Armed Services Board
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 59577, Appeal of
    Technology Systems, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    61