Carter Safety Consultants, Inc. ( 2017 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                  )
    )
    Carter Safety Consultants, Inc.              )      ASBCA No. 60779
    )
    Under Contract No. W912P8-10-P-0255          )
    APPEARANCE FOR THE APPELLANT:                       Ms. Cliftena Carter
    CEO
    APPEARANCES FOR THE GOVERNMENT:                     Thomas H. Gourlay, Jr., Esq.
    Engineer Chief Trial Attorney
    David R. Dyer, Esq.
    Engineer Trial Attorney
    U.S: Army Engineer District,
    New Orleans
    OPINION BY ADMINISTRATIVE JUDGE O'CONNELL
    ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION
    The United States Army Corps of Engineers moves to dismiss this appeal for lack
    of jurisdiction, contending that Carter Safety Consultants, Inc. (Carter) failed to file a
    timely appeal from the contracting officer's final decision (COFD). We grant the
    government's motion and dismiss the appeal.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. The government and Carter entered into Contract No. W912P8-10-P-0255
    (contract) on 30 September 2010 for information and project scheduling support (R4, tab 29).
    2. By letter dated 8 February 2016, Carter submitted a certified claim to the
    contracting officer (CO) for $109,542.60 for final payment under the contract (R4, tab 5).
    3. By letter dated 21 April 2016, the CO issued a final decision denying the claim
    (R4, tab 1). The COFD notified Carter of its right to appeal the decision to the Board
    within 90 days of receipt or to bring an action directly in the United States Court of
    Federal Claims within 12 months of receipt (id. at 22). The COFD also provided the
    mailing address for the Board (id.).
    4. The contracting officer emailed the final decision to Carter on 21 April 2016
    and also sent it by certified mail. Carter received the certified mail copy on 25 April
    2016. (R4, tab 1 at 1-2)
    5. By letter dated 5 August 2016, Carter appealed the COFD to the United States
    Government Accountability Office (GAO) (R4, tab 3). The letter stated that Carter had
    sent its appeal to the GAO several times before, the most recent attempt having been
    returned to Carter's offices on 12 July 2016 (id. at 1). Carter has not provided us with
    copies of its earlier appeals to the GAO.
    6. By letter dated 22 August 2016 (submitted in an envelope bearing a postal meter
    stamp of 3 September 2016 and received by the Board on 6 September 2016), Carter filed
    its appeal with the Board from the 21April2016 COFD. In the notice of appeal, Carter
    stated it received a letter on 19 August 2016 from the GAO Contract Appeals Board
    (CAB) in which the CAB stated that it did not possess jurisdiction to consider Carter's
    appeal and referred Carter to this Board.
    DISCUSSION
    The government moves to dismiss this appeal for lack of jurisdiction, asserting that
    Carter failed to file its appeal with the Board within 90 days of receiving the COFD. In its
    response, Carter did not address the timeliness of its appeal but merely argued the merits
    of its appeal.
    The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, requires a contractor
    to file an appeal of a COFD with the Board within 90 days from receipt of that COFD.
    41 U.S.C. § 7104. We lack jurisdiction over any appeal filed outside this 90-day appeal
    period. Cosmic Constr. Co. v. United States, 
    697 F.2d 1389
    , 1391 (Fed. Cir. 1982).
    For purposes of this motion, we will assume that Carter received the COFD on
    25 April 2016 (the date that it received the certified letter) rather than 21 April 2016 (the
    date that the contracting officer emailed it). With a starting date of 25 April 2016, Carter's
    appeal had to have been filed no later than Monday, 25 July 2016. Carter did not mail a
    notice of appeal to the Board until at least 22 August 2016 (ignoring for the moment the
    12-day gap between the date of its letter and the postal meter stamp of 3 September 2016 ),
    which is more than 90 days after Carter received the COFD (SOF ii 6).
    We have held that we possess jurisdiction under the CDA in narrow circumstances
    where the contractor sent a timely notice of appeal to other officials in the Department of
    Defense. E.g., Contraves-Goerz Corp., ASBCA No. 26317, 83-1 BCA ii 16,309 (timely
    notice of appeal addressed to the Secretary of the Air Force through the CO); Brunner
    Bau GmbH, ASBCA No. 35678, 89-1BCAii21,315 (timely notice of appeal to
    government counsel); Thompson Aerospace, Inc., ASBCA Nos. 51548, 51904, 99-1 BCA
    ii 30,232 (timely notice of appeal to CO).
    In Carter's letter to the GAO dated 5 August 2016, Carter stated that it had tried to
    file an appeal with the GAO on or before 12 July 2016 (SOF ii 5), which raises the
    possibility that Carter filed an appeal within the 90-day period, albeit at the wrong forum.
    2
    We have held that, in contrast to appeals filed with the wrong official within the
    Department of Defense, we do not possess jurisdiction over appeals filed at other tribunals.
    See Waterstone Environmental Hydrology and Engineering, Inc., ASBCA No. 57557,
    12-1 BCA ~ 35,028 (late appeal to ASBCA dismissed after wrongful appeal to the Civilian
    Board of Contract Appeals). Thus, Carter's alleged timely appeal to the GAO, which is not
    within the executive branch of the government, does not provide us with jurisdiction.
    Finally, we observe that this is not an appeal where we would have expected the
    appellant to be confused by litigation options which a novice in contracting with the U.S.
    Army Corps of Engineers might find daunting. Our records indicate that we docketed an
    appeal filed by appellant on 3 October 2011 from another contract it had with the Corps,
    which we docketed as ASBCA No. 57800. The docket identifies appellant's representative
    as Cliftena Carter, the same representative as in this appeal. The parties litigated that
    appeal for 14 months and then reported a settlement to the Board. Accordingly, we see no
    explanation for appellant's failure to file a timely appeal with the Board.*
    CONCLUSION
    The government's motion is granted and the appeal is dismissed for lack of jurisdiction.
    Dated: 22 February 2017
    \\           II   '   \
    MICHAEL N. O'CONNELL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                         I concur
    /~p?:~---
    STEMPLE~
    MARK N.
    M
    __ ___ _                              RICHARD SHACKLEFORD
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    * We express no opinion as to whether appellant may file an action in the Court of
    Federal Claims, which, as noted above, has a 12-month filing deadline from receipt
    of the contracting officer's final decision.
    3
    I certify that the foregoing is a true copy of the Opinion and Decision of the Armed
    Services Board of Contract Appeals in ASBCA No. 60779, Appeal of Carter Safety
    Consultants, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 60779

Judges: O'Connell

Filed Date: 2/22/2017

Precedential Status: Precedential

Modified Date: 3/7/2017