LKJ Crabbe Inc. ( 2018 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    LKJ Crabbe Inc.                              )      ASBCA No. 60331
    )
    Under Contract No. W9124E-15-D-0002          )
    APPEARANCE FOR THE APPELLANT:                       Mr. Kevin Crabbe
    President
    APPEARANCES FOR THE GOVERNMENT:                     Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    CPT Harry M. Parent III, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE WOODROW
    This appeal arises from Contract No. W9124E-15-D-0002 (the contract) between
    appellant, LKJ Crabbe Inc. (LKJ Crabbe or appellant), and the Army Mission and
    Installation Contracting Command - Fort Bragg (Army or government) for custodial services
    at buildings located in two different locations at Ft. Polk, Louisiana. LKJ Crabbe appeals the
    Army's termination for cause, contending that the Army's termination was unjustified and
    that the Army breached the contract by failing to reform the contract after learning of an
    alleged mistake in LKJ Crabbe's bid. LKJ Crabbe also alleges that the Army breached the
    contract by violating its duty of good faith and fair dealing. The appeal is denied.
    FINDINGS OF FACT
    A.       Solicitation and Bids
    1. On January 7, 2015, the Army issued a solicitation to fulfill a requirement from
    the Fort Polk Department of Public Works for custodial services for various buildings
    and activities located on North and South Fort Polk and the Toledo Bend Army
    Recreation Site (TBRS) at Ft. Polk, Louisiana (R4, tab 17).
    2. The requirement was set aside for a HUBZone Small Business and the award
    process was conducted in accordance with Federal Acquisition Regulation (FAR) Part 14
    sealed bidding procedures (R4, tab 17 at 1).
    3. The Army issued three amendments to the solicitation. Amendment Nos. 0001
    and 0003 both pertained to the bid opening date. Amendment No. 0002, dated March 17,
    2015, released (among other things) all questions and answers received from contractors
    during the solicitation period (R4, tab 19 at 5-12).
    4. Fifteen ( 15) bids were received in response to the invitation to bid. LKJ
    Crabbe's bid was the lowest total bid amount received. (R4, tab 22 at 2)
    B.     Price Analysis and Contract Award
    5. Ronald Newlan was the contracting officer (CO) responsible for awarding the
    contract (tr. 1/84; R4, tab 1 at 1). Mr. Newlan determined whether appellant's price was
    fair and reasonable (R4, tab 22), and conducted an unbalanced price analysis (tr. 1/91;
    R4, tab 22 at 2).
    6. Mr. Newlan developed a pricing matrix that compared pricing from all offerors
    for the base year and option years by contract line item number (CLIN). A condensed
    version of this document is located at tab 21 ofthe Rule 4 file. (R4, tab 21)
    7. Mr. Newlan concluded that the bids were materially balanced in accordance
    with FAR 15.404-l(g) (R4, tab 22 at 2).
    8. Mr. Newlan testified that his unbalanced price analysis sought to determine
    whether there was consistency in the prices for each CLIN across the base and option
    years. He testified that the bids were balanced in this case, because each CLIN was priced
    the same across the base and option years. (Tr. 1/ 141) His analysis did not compare
    individual CLINs to other CLINs within the same year, nor did it compare the pricing for
    particular types of buildings. He acknowledged that his analysis did not include
    calculating a price per square foot for appellant or any of the offerors. (Tr. 1/93- 97)
    9. Mr. Newlan also determined that appellant's price was fair and reasonable pursuant
    to FAR 15.404-l(b)(2)(i), Commercial and Non-Commercial Items. Mr. Newlan conducted
    the fair and reasonable price determination by comparing the proposed bids received in
    response to the solicitation. (R4, tab 22 at 2)
    10. Appellant's bid for CLIN 0110 for "Routine Project Cleaning" was $0.0095 per
    square foot (R4, tab 1 at 111; tr. 1/117).
    11. The Army's solicitation procurement desktop computer system (PD2) only accepts
    entries up to two decimal places (tr. 1/110-11, 113). The system automatically rounded up
    appellant's proposed price of $0.0095 per square foot to $0.01 per square foot for CLIN 0110
    (tr. 1/114-16, 127-28).
    12. Mr. Newlan testified that he did not know whether the government had entered
    appellant's price into the procurement system as $0.0095 or $0.01. He further testified that, if
    the government had entered 0.0095 as the price, the system automatically would have rounded
    it to 0.01, because the government's payment system only goes to two decimal places.
    (Tr.1/115)
    2
    13. The contract, as awarded, listed the price of $0.0095 per square foot for
    CLIN 0110 (R4, tab 1 at 111).
    14. Mr. Newlan did not seek clarification from appellant regarding whether
    appellant intended its bid to be rounded up to $0.01 per square foot (tr. 1/112-30).
    15. The pricing matrix, used by Mr. Newlan to compare the pricing from all the
    offerors for the base and option years by CLIN, listed appellant's price at $0.01 per
    square foot for CLIN O110 (tr. 1/128-29; R4, tab 21 ).
    16. There is no evidence that Mr. Newlan had knowledge that appellant's
    proposal price for CLIN 0110 was rounded up to $0.01 per square foot when he
    conducted his pricing analysis prior to award (tr. 1/128-30).
    C.     The Contract
    17. On May 14, 2015, the Army awarded Contract No. W9124E-15-D-0002 (the
    contract) to LKJ Crabbe for "custodial services to various buildings and activities located
    on North and South Fort Polk and Toledo Bend (Lake) Recreation Site (TBRS)" {R4,
    tab 1 at 341 ). The indefinite-delivery, indefinite-quantity contract was for a one-year
    period of performance beginning July 1, 2015, and ending on June 30, 2016. The
    contract also included two 12-month option periods. (Id. at 342)
    18. The contract terms included CLINs which required appellant to separately
    price the cleaning services for each building, a few additional miscellaneous items, and
    a single price for all the required cleaning supplies (R4, tab I).
    19. The contract incorporated Federal Acquisition Regulation (FAR) clause
    52.212-4, CONTRACT TERMS AND CONDITIONS - COMMERCIAL ITEMS (MAY 2014 ), by
    reference (R4, tab 1 at 428). This clause states in relevant part:
    ( c) Changes. Changes in the terms and conditions of
    this contract may be made only by written agreement of the
    parties.
    (m) Termination for cause. The Government may
    terminate this contract, or any part hereof, for cause in the
    event of any default by the Contractor, or if the Contractor
    fails to comply with any contract terms and conditions, or
    fails to provide the Government, upon request, with adequate
    assurances of future performance. In the event of termination
    3
    for cause, the Government shall not be liable to the
    Contractor for any amount for supplies or services not
    accepted, and the Contractor shall be liable to the
    Government for any and all rights and remedies provided by
    law. If it is determined that the Government improperly
    terminated this contract for default, such termination shall be
    deemed a termination for convenience.
    20. The contract also incorporated by reference FAR clause 52.249-8, DEFAULT
    (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984) (R4, tab I at 430).
    21. The contract included the full text of FAR clause 52.214-29, ORDER OF
    PRECEDENCE-SEALED BIDDING (JAN 1986), which states:
    Any inconsistency in this solicitation or contract shall be
    resolved by giving precedence in the following order: (a) the
    Schedule ( excluding the specifications); (b) representations
    and other instructions; (c) contract clauses; (d) other
    documents, exhibits, and attachments; and ( e) the
    specifications.
    (R4, tab I at 440-41, tab 17 at 223)
    22. On June 30, 2015, the Army issued Task Order (TO) 000 I against the
    indefinite-quantity, indefinite-delivery contract with a period of performance from July 1,
    2015 through June 30, 2016, for $859,900 to clean 108 buildings (R4, tab 4 at 1, 60).
    23. The Performance Work Statement (PWS) for the contract describes four
    categories of cleaning services: Installation, Fitness Centers, Child CareN outh, and
    Project Cleaning (R4, tab 17 at 129-30).
    24. For each category of cleaning service set forth in the PWS, individual
    cleaning tasks had to be performed according to the frequency set forth in technical
    exhibit 4 to the contract (R4, tab I at 392, tab 17 at 178).
    D.     Building 701
    25. The contract contains a discrepancy concerning the level of cleaning required
    for Building 70 I (CLIN 0019), one of the nine child care facilities included in the
    contract (R4, tab 17 at 8-9).
    4
    26. Building 701 was included in TO 0001 as requiring the "Child Care" level of
    cleaning as follows:
    Item No.   Supplies/Services              Quantity      Unit        Unit Price   Amount
    0019       0019- Bldg 701 Child Care FFP 12             Months       $800.00      $9,600.00
    0019 - Bldg 701 Child Care
    FOB: Destination
    PURCHASE REQUEST
    NUMBER: 0010711078
    0020       0020 - Bldg 702 Child Care FFP 12            Months      $2,390.00    $28,680.00
    0020 - Bldg 702 Child Care
    FOB: Destination
    PURCHASE REQUEST
    NUMBER: 0010711078
    (R4, tab 4 at 11-12)
    27. Technical exhibit 5 to the contract sets forth a "List of Facilities to Receive
    Services." However, Building 701 is inconsistently listed on technical exhibit 5 as
    receiving the "Installation" level of cleaning:
    Building Number        Activity                  Cleaning Level         Square Footage
    701                    MWR, CDC/SAC              Installation           14,895
    702                    MWR,CDC                   Child Care/Youth       10,490
    (R4, tab 1 at 395-97, tab 17 at 180-82)
    28. Technical exhibit 4 to the contract sets forth a "Tasks and Frequency Table"
    and shows the frequency of cleaning for the child care facilities, with tasks ranging from
    daily to every two years (R4, tab 1 at 392, tab 17 at 178).
    29. The PWS included the following provision relevant to the child care facilities:
    1.4.3 Child Care/Youth Cleaning Services: Services will be
    provided to child care and youth facilities issued on task
    orders. Services include restroom cleaning & supply,
    drinking fountain cleaning, trash & recycle removal, carpet
    vacuuming & cleaning, hard floor sweeping & mopping,
    buffing, tile stripping & finishing, dusting, furniture cleaning,
    interior & exterior window washing, window treatment
    cleaning, food service cleaning, door & door frame cleaning
    and wall & woodwork scrubbing.
    (R4, tab 1 at 342, tab 17 at 130)
    5
    30. Part 5 of the PWS, Specific Tasks, listed cleaning tasks for the child care
    facilities as well as other facilities (R4, tab 1 at 369-76, tab 17 at 155-62).
    31. Appellant's representatives, Mr. and Mrs. Blazer, attended the site visit in
    January 2015 prior to contract award (R4, tab 23 at 3). Building 701 was included in the
    site visit (id. at 1).
    32. On June 23, 2015, after performance had begun, appellant raised the issue of the
    discrepancy between the bid schedule and the technical exhibits with the CO (R4, tab 3 at 2).
    33. Matthew Wiggins, the contract specialist assigned to the contract, responded
    by email, referencing contract clause FAR 52.214-29 and explaining that the CLIN in the
    schedule takes precedence over the technical exhibit (R4, tab 3 at 2; tr. 2/9).
    34. At the hearing, the CO, Tamera Butler, admitted that the contract contains a
    discrepancy between the CLIN and technical exhibit 5 (tr. 2/11-13 ).
    35. She maintained, however, that the discrepancy is resolved by FAR 52.214-29,
    Order of Precedence clause. She explained that the CLIN (also called the bid schedule) takes
    precedence over the technical exhibits. (Tr. 2/11-13)
    36. According to appellant, the difference in pricing for Building 701 at the child care
    level versus the installation level of cleaning would be approximately $2,682 per year (tr. 1/38).
    E.      The Fitness Centers
    37. Three fitness centers are included in the solicitation and contract. Technical
    exhibit 5 to the contract lists the facilities on the installation to receive services, including
    buildings 1262, 2276 and 3350. (R4, tab 1 at 395-97, tab 17 at 180-82) CLINs for all
    three fitness centers were included in TO 1 (R4, tab 4 at 19, 28, 38).
    38. Technical exhibit 4 to the contract shows the frequency of cleaning for the fitness
    centers, with tasks ranging from daily to every two years (R4, tab 1 at 392, tab 17 at 178).
    39. The PWS in the contract included the following provisions relevant to the
    fitness centers:
    1.4 Scope: The Contractor shall perform custodial services
    to the standards in this contract and in a manner that will
    maintain a satisfactory facility condition and present a clean,
    neat, and professional appearance. All work performed by
    the contractor shall be in accordance with all applicable laws,
    regulations (including AR 420-1 ), and commercial practices.
    6
    Services include: Installation, Fitness Centers, Child
    Care/Youth and Project Cleaning.
    1.4.2 Fitness Cleaning Services: Services will be provided to
    fitness centers issued on task orders. Services include
    restroom cleaning & supply, drinking fountain cleaning, trash
    & recycle removal, carpet vacuuming & cleaning, hard floor
    sweeping & mopping, buffing, tile stripping & finishing and
    dusting.
    (R4, tab 1 at 341-42, tab 17 at 129-30)
    40. Part 5 of the PWS, Specific Tasks, listed cleaning tasks for the fitness centers
    as well as other facilities (R4, tab 1 at 369-76, tab 17 at 155-62).
    41. The solicitation stated that: "All offers are subject to all terms and conditions
    contained in this solicitation" (R4, tab 17 at 1).
    42. Prior to contract award, a question was submitted to the CO regarding the
    fitness centers, and the following question and answer was added to the solicitation via
    Amendment No. 0002 on March 17, 2015:
    4. TE [Technical Exhibit] #4 does not indicate if the fitness
    center is serviced on weekends. Please clarify.
    Yes, fitness centers will be serviced on the weekends when
    open.
    (R4, tab 19 at 5)
    43. Appellant's proposal included pricing for each of the fitness centers as follows:
    Buildings 1262 (CLIN 0035) at $3,040 per month; 2276 (CLIN 0053) at $2,750 per month;
    and 3350 (CLIN 0073) at $1,425 per month (R4, tab 1 at 36, 54, 74, 395-97; tr. 1/28-29).
    The total aggregate price for the fitness centers was $7,215 per month (tr. 1/29).
    44. Appellant's proposal included providing services to the fitness centers on a
    daily basis only for Monday through Friday, not including weekends (tr. 1/26).
    45. If appellant had included weekends in its proposed price, the price would have
    increased disproportionately due to the costs associated with hiring additional employees
    to cover the weekend days (tr. 1/29-31).
    7
    46. Appellant's proposed price for cleaning the fitness centers was at least 30
    percent lower than it would have been if the price had included cleaning on weekends
    (tr. 1/29-30), reducing the price by at least $2,092 per month (tr. 1/30).
    F.     Financial Losses during Contract Performance
    4 7. The contract required appellant to clean 108 buildings for $732,300 annually or
    $61,025 per month (R4, tab 4 at 67-68). The total contract price was $859,900, $127,600
    of which was for non-cleaning services (CLINs 0109-13) (id. at 1, 54-56).
    48. Appellant estimated a profit of 15% (tr. 1/21), which equals $9,153.75 per
    month ($61,025 multiplied by 15 percent). Therefore, we conclude that appellant
    estimated its monthly cost of cleaning services to be $51,871.25 per month ($61,025.00
    less $9,153.75 (profit)).
    49. Appellant's estimate of total monthly losses resulting from the discrepancy in
    the cleaning level required for Building 701 was $2,682 (tr. 1/38).
    50. The total monthly losses resulting from the discrepancy in cleaning frequency
    for the three fitness center buildings was at least $2,092 (tr. 1/30).
    51. Taken together, appellant's total monthly loss resulting from the alleged
    breach was at least $4,774 ($2,682 plus $2,092) (tr. 1/38).
    52. According to appellant, it was losing more than $27,000-$32,000 per month
    during the performance of the contract (R4, tab 10 at 5; tr. 1/25), which is far more than
    the sum of the alleged losses for Building 701 and the fitness centers.
    53. The alleged breach, put in a light most favorable to appellant, would involve just
    4 of the 108 buildings, and with a total monthly price adjustment of $4,774 (tr. 1/36-40).
    G.     September 3, 2015 Meeting and Subsequent Show Cause Notice
    54. In September 2015, just over two months after commencing performance,
    appellant requested a meeting with the Army to discuss the negative economic impact of
    contract performance upon appellant and to investigate possible remedies (R4, tab 13 at 2).
    55. On September 3, 2015, the Army held a meeting with appellant at Ft. Polk (R4,
    tab 13 at 2). The attendees at the meeting were Mr. Crabbe on behalf of appellant, and
    Matthew Wiggins, Tamera Butler, Glenda Calcote, Simone Curtis and LTC Thomas Kelley
    on behalf of the government (tr. 1/154).
    8
    56. During the meeting, Mr. Wiggins, the Army's contract specialist, took notes to
    serve as a record of the meeting (R4, tab 7 at 5; tr. 1/53, 2/17). According to Mr. Wiggins'
    contemporaneous meeting notes, appellant stated the following:
    Mr. Crabbe then stated that in the month of July which was
    the first month of performance invoicing was $60,000.00 and
    their expenses was [sic] $110,000.00. Mr. Crabbe then stated
    that he was drowning in red ink (losses from the project).
    Mr. Crabbe then stated that in August alone there was a
    $26,000.00 loss. Mr. Crabbe stated that he did not see any
    recovery for LKJ Crabbe .... Mr. Crabbe stated that Building
    #701 and the Gyms were two big issues that was costing his
    company a lot due to the overtime as it was costing two
    people two extra days to complete the work ....
    ... Mr. Crabbe then stated that the only solution that he sees is
    to let us revise our pricing, or to let the contractor work at no
    profit while the Government resolicits, and LKJ Crabbe sends
    certified cost and pricing data. Mr. Crabbe stated that his
    company was well above $100,000.00 in net losses with the
    award ....
    ... Mr. Crabbe stated that in reality that the requirements w_ere
    more than just a startup project and that the company had
    stepped way out of their comfort zone. Mr. Crabbe stated that
    they should not have done a project which encompassed an
    entire base .
    ... Mr. Crabbe did add that there was faulty pricing throughout
    the award, and the company had not understood the depth of
    the requirement.
    (R4, tab 7 at 1-5; tr. 1/156)
    57. Another meeting attendee, Ms. Simone Curtis, the Army's supervisory
    contract specialist, testified regarding the meeting:
    JUDGE WOODROW: I mean, was it your impression
    that if the situation remained unchanged, that LKJ Crabbe
    would be unable to continue performance?
    THE WITNESS: That is correct.
    9
    JUDGE WOODROW: Okay. And what, at that
    meeting, gave you that impression?
    THE WITNESS: Because when we went to him and
    asked for reasonable assurances to be able to continue to
    perform, the response back was, from a financial standpoint
    we could not.
    (Tr. 2/98)
    58. Mr. Crabbe admits that the content of the Army's contemporaneous meeting
    notes are "mostly accurate," but "different in tone" from the meeting (tr. 1/19-20).
    59. Mr. Crabbe suggested various alternatives that might have allowed appellant to
    continue performance, such as re-pricing certain CLINs or removing certain CLINs from the
    contract, but the Army did not take action on these alternatives (R4, tab 9 at 1-2; tr. 1/48-52).
    H.     Show Cause Notice
    60. Following the meeting, on September 8, 2015, the Army sent appellant a show
    cause notice via email. The letter stated, "the Government is considering terminating the
    contract for cause under the provision FAR 52.212-4(m) of this contract." (R4, tab 8)
    61. The letter specifically placed appellant on notice that the Army was
    considering appellant's statements at the September 3, 2015 meeting as an anticipatory
    repudiation of the contract:
    Based upon these discussions and correspondence, I take your
    comments to mean that you are advising the Government that
    absent an upward adjustment of the contract price, you will not
    continue to perform the contract beyond 30 September 2015.
    (R4, tab 8)
    62. The letter also directed appellant to respond as follows:
    Pending a final decision in this matter, it will be necessary to
    determine whether your anticipated failure to continue
    performance of services arose from causes beyond your
    control and without fault or negligence on your part.
    Furthermore, you are to provide me with adequate assurances
    of your ability (including, but not limited to, your financial
    ability) to continue performing this contract beyond
    10
    30 September 2015. Accordingly, you are given the
    opportunity to present, in writing, any facts bearing on the
    question to the Contracting Officer, Mrs. Tamera Butler, 6661
    Warrior Trail, Bldg 350, Fort Polk, LA, 71459 within 4
    business days after receipt of this notice, or no later than
    14 September 2015. Your failure to present adequate
    justification and assurances within this time may be
    considered as an admission that none exist. Your attention is
    invited to the respective rights of the Contractor and the
    Government and the liabilities that may be invoked if a
    decision is made to terminate for default.
    (R4 tab 8)
    63. On September 10, 2015, appellant responded to the show cause notice:
    [We] realize the major contributing factor to the losses that
    we have sustained thus far were due to not understanding the
    level of service that would be required to perform to
    specifications during the course of the contract [and] [t]he
    level of occupancy and traffic in the buildings was not
    understood.... [W]e now realize that we overstepped our
    comfort zone.
    [W]e feel we can _absorb the losses that will be incurred by
    our company through the end of November.
    (R4, tab 9 at 2)
    64. On September 11, 2015, the Army requested additional assurances that LKJ
    Crabbe would be able to continue performance and asked appellant to further supplement
    its response by September 14, 2015 (R4, tab 9 at 1).
    65. On September 16, 2015, LKJ Crabbe responded to the Army's show cause notice
    by email. Mr. Crabbe stated that the "company has and is sustaining catastrophic financial
    losses while performing the custodial services at Ft. Polk." He further stated that the
    "company is operating at a negative $137,036," and that this amount will grow "between
    $27,000 and $32,000 every month until we are forced to file bankruptcy." (R4, tab 10 at 5)
    66. Mr. Crabbe stated that the company has "credit lines available that would
    enable us to perform beyond September 30, 2015 but to do so puts all of the other
    contracts with the government at risk ofus having to default as well" (R4, tab 10 at 5).
    11
    67. On September 16, 2015, the CO asked appellant for additional clarification
    about the line of credit available to appellant and the other contracts that would be
    impacted (R4, tab 10 at 1-2).
    68. On September 16, 2015, appellant responded, explaining that the company
    had a line of credit that potentially could allow it to perform beyond September 30, 2015.
    Mr. Crabbe stated that the availability of the credit line "was not an implied reference to
    being able to sustain the monthly losses we have incurred and will continue to incur if we
    continue at Ft. Polk." (R4, tab 10 at 1)
    69. At the hearing, Mr. Crabbe explained that, without government cooperation to
    permit some type of change to the contract pricing, LKJ Crabbe would continue to lose
    tens of thousands of dollars per month (tr. 1/79).
    I.     Termination for Cause
    70. On September 25, 2015, after evaluating appellant's responses to the show
    cause letter, the CO terminated the contract for cause "because of an inability to perform
    and failure to provide adequate assurance of continued performance." The CO set forth
    the basis for her determination in a memorandum for record. (R4, tab 12; tr. 2/27-29)
    71. On September 25, 2015, appellant received notice of the termination for cause via
    email from the CO (R4, tab 14 at 2; tr. 2/28). The notice stated that the contract had been
    terminated for cause pursuant to FAR 52.212-4(m) which was incorporated into the contract.
    The termination was effective as of September 30, 2015. (R4, tab 12 at 1)
    72. The notice further stated:
    You failed to provide adequate reasonable assurances
    that LKJ Crabbe, Inc. could continue to perform custodial
    services issued under Task Order 0001 for the performance
    period of 01 July 2015 through 30 June 2016.
    (R4, tab 12 at 1)
    73. On September 27, 2015, appellant acknowledged receipt of the notice for
    termination for cause (R4, tab 14 at 1-2).
    74. On September 29, 2015, the CO modified both the base contract and TO 0001
    in order to effectuate the termination for cause (R4, tabs 15-16).
    12
    J.      Subsequent Appeal and Hearing
    75. On November 19, 2015, appellant filed a notice of appeal dated November 16,
    2015, with the Board, and, on November 20, 2015, the Board docketed the appeal as ASBCA
    No. 60331.
    76. On March 21, 2017, the Board conducted a two-day hearing at the Board's
    offices in Falls Church, Virginia.
    DISCUSSION
    A. Termination for Default
    A termination for default "is a drastic sanction which should be imposed (or
    sustained) only for good grounds and on solid evidence." Lisbon Contractors, Inc. v.
    United States, 
    828 F.2d 759
    , 765 (Fed. Cir. 1987) (quoting JD. Hedin Constr. Co. v. United
    States, 
    408 F.2d 424
    , 431 (Ct. Cl. 1969)). Though this is an appeal brought by LKJ Crabbe,
    because a termination for default is essentially a government claim, the government bears
    the initial burden of proving, "by a preponderance of the evidence, that a termination for
    default was justified." DayDanyon Corp., ASBCA No. 57681, 15-1 BCA ,i 36,073 at
    176,151; Keystone Capital Services, ASBCA No. 56565, 09-1 BCA ,i 34,130 at 168,753
    (citing Lisbon 
    Contractors, 828 F.2d at 765
    ). "If the government establishes a prima facie
    case justifying the termination, the burden shifts to the contractor to prove the default was
    excusable." Truck/a Services, Inc., ASBCA Nos. 57564, 57752, 17-1 BCA ,i 36,638 at
    178,444 (citingADTConstr. Grp., Inc., ASBCA No. 55358, 13 BCA ,J 35,307 at 173,312).
    1. Appellant's Response to the Cure Notice
    Appellant's failure to provide reasonable assurances of its ability to perform in response
    to the cure notice supports the Army's decision to terminate for cause. The contract
    incorporates by reference FAR 52.212-4, Contract Terms and Conditions - Commercial Items,
    which states, in relevant part:
    (m) Termination for cause. The Government may
    terminate this contract, or any part hereof, for cause in the
    event of any default by the Contractor, or if the Contractor
    fails to comply with any contract terms and conditions, or
    fails to provide the Government, upon request, with adequate
    assurances offuture performance.
    (Finding 15) (Emphasis added) Appellant's response to the show cause notice fails to provide
    reasonable assurances that it would be capable of performing for the full term of the contract.
    13
    Appellant's response to the Army's initial show cause notice indicated that appellant
    had failed to appreciate the level of service it would be required to perform and "overstepped
    [its] comfort zone" (finding 63). This statement is tantamount to an admission that poor
    pricing was the root cause of the losses on the contract. Appellant further stated that the
    company "can absorb the losses that will be incurred by our company through the end of
    November." (Id.) This is an unequivocal statement that appellant could not perform past the
    end of November, a full seven months prior to the end of the base performance period.
    When the Army sought clarification of appellant's initial response, appellant
    explained that it was "sustaining catastrophic financial losses while performing the custodial
    services at Ft. Polk" that would grow "until we are forced to file bankruptcy" (finding 65).
    Appellant mentioned, however, that LKJ Crabbe had credit lines available that would
    enable it to perform beyond September 30, 2015 (finding 66). The Army sought additional
    clarification regarding the credit lines, and appellant clarified that the availability of the
    credit line "was not an implied reference to being able to sustain the monthly losses we have
    incurred and will continue to incur if we continue at Ft. Polk" (finding 68). By this
    statement, Mr. Crabbe affirmed, for a third time, that his company would be unable to
    perform to the end of the contract without some form of accommodation from the Army.
    During his testimony, Mr. Crabbe emphasized that he repeatedly asked the Army
    to cooperate with him and suggested a variety of accommodations that would allow him
    to continue to perform (finding 69). However, Mr. Crabbe also was candid at the
    September 3, 2015 meeting that, without some form of accommodation, his company
    would not be able to complete the base period of performance without financial
    insolvency (findings 55-58). We find Mr. Crabbe's testimony to be credible, both with
    respect to his sincere interest in working constructively with the Army to pursue a
    reasonable accommodation, and with respect to the prospect of financial ruin if the
    contract were not modified.
    Appellant's response to the cure notice fails adequately to assure the government
    that appellant could continue to perform to end of the contract period and, therefore, is an
    adequate basis for the termination for cause. See SYMVIONJCS, Inc., ASBCA Nos. 60335,
    60612, 17-1 BCA ,i 36,790 (termination for cause justified in face of failure to provide
    adequate assurances that inability to perform could be overcome). Indeed, the Army
    reasonably believed Mr. Crabbe's statements about the financial losses from continued
    performance and reasonably concluded that LKJ Crabbe could not continue to perform the
    contract as written.
    2. Anticipatory Repudiation
    Although the government need only prove one sufficient basis for a termination
    for cause, Quality Trust Inc., ASBCA No. 59983, 16-1 BCA ,i 36,368, we also conclude
    that appellant's statements were tantamount to an anticipatory repudiation of the contract
    14
    and that the government has made a prima facie case justifying the termination for cause
    on that basis as well.
    In order to establish anticipatory repudiation, the government must show that a
    contractor communicated an intent not to perform in a positive, definite, unconditional and
    unequivocal manner. James B. Beard, ASBCA Nos. 42677, 42678, 93-3 BCA ,i 25,976 at
    129,171. Either an express refusal to perform, or a statement ofan inability to perform may
    constitute anticipatory repudiation. SYMVIONJCS, 17-1 BCA ,i 36,790 at 178,321. In
    particular, a statement that a contractor is unable to perform unless the government modifies
    a contract constitutes anticipatory repudiation. Cascade Pacific International v. United
    States, 
    773 F.2d 287
    , 293 (Fed. Cir. 1985); Tacoma Boatbuilding Co., ASBCA No. 50238,
    00-1 BCA ,i 30,590 at 151,068-69.
    Appellant contends that it gave three different dates for when it would be forced to
    stop work without conditions being granted by the government. Appellant also offered,
    in the September 3, 2015 meeting, to continue working at cost with no allowance for
    profit (finding 56). Appellant argues that this fell well short of the "positive, definite,
    unconditional and unequivocal" refusal to perform required by the Board's precedent
    (app. br. at 27).
    In response, the government contends that appellant made multiple statements that,
    taken together, "unequivocally communicated an intent not to perform the Contract through
    the end of the base period of performance without an increase in price." According to the
    government, these statements constituted an anticipatory repudiation of the contract and
    justified the CO's decision to terminate the contract for default. (Gov't br. at 27)
    Appellant's communications with the government left little doubt that appellant's
    business would be harmed by continuing to perform the contract as written. Appellant,
    itself, requested the September 3, 2015 meeting due to concerns about economic losses it
    was incurring during performance (finding 54). During the meeting, Mr. Crabbe made
    statements indicating that appellant could not sustain performance for another 30 days.
    These statements were recorded in contemporaneous notes recorded by Mr. Wiggins, the
    Army's contract specialist. (Finding 56) At the hearing, Mr. Crabbe admitted that the
    statements attributed to him in the notes are accurate (finding 58). At the time of the
    meeting, there were 301 days left in the contract's base period (from July 1, 2015 through
    June 30, 2016). The fact that appellant gave different dates for when it would be forced to
    stop work without conditions being granted by the government does not change the fact that
    it communicated to the government that it could not complete the base period of the contract.
    The Army also concluded that the major cause of the company's losses was faulty
    pricing throughout the contract. Although Mr. Crabbe raised Building 701 and the fitness
    centers as specific issues, the CO concluded that addressing these issues would not
    resolve the underlying problems with faulty pricing. (Finding 70)
    15
    Although the Army and Mr. Crabbe discussed alternatives that might have allowed
    appellant to continue performance, such as re-pricing certain CLINs or removing certain
    CLINs from the contract, the Army did not take action on these alternatives (finding 59).
    However, a party's refusal to perform its contractual obligations in the future without a
    change to the contract has been held to constitute anticipatory repudiation. Free & Ben,
    Inc., ASBCA No. 56129, 11-1 BCA ,i 34,719 at 170,954 (refusing to perform without a
    change to the contract is anticipatory repudiation); Howell Tool and Fabricating, Inc.,
    ASBCA No. 47939, 96-1 BCA ,i 28,225 at 140,941 (anticipatory repudiation where
    contractor manifested a positive and unequivocal intention not to render performance
    until it received a contract price increase). We do not doubt appellant's sincere desire to
    work with the Army to make changes to the contract to allow it to continue performance,
    but the Army is under no obligation to make changes to the contract to address
    appellant's financial inability to continue performance. A contractor ordinarily is
    responsible to provide sufficient financial resources for the performance of the contract;
    its financial incapacity is not a legitimate excuse for its failure to perform. Rashed Elham
    Trading Co., ASBCA No. 58383 et al., 17-1 BCA ,i 36,869; see also Danzig v. AEC
    Corp., 
    224 F.3d 1333
    , 1339 (Fed. Cir. 2000); TGC Contracting Corp. v. United States,
    
    736 F.2d 1512
    , 1515 (Fed. Cir. 1984).
    We conclude that appellant's statements were tantamount to an anticipatory
    repudiation of the contract and that the government has met its prima facie case justifying
    the termination for default.
    B. Whether Default was Excusable
    If the government carries its burden with respect to termination for default, the
    burden shifts to the contractor to demonstrate that its default was excusable, caused by
    the government's material breach, or that the CO's termination decision was arbitrary,
    capricious or an abuse of discretion. Pyrotechnic Specialties, Inc., ASBCA No. 57890 et
    al., 17-1 BCA ,i 36,696 at 178,691; see also US. Coating Specialties & Supplies, LLC,
    ASBCA No. 58245, 15-1 BCA iJ 35,957 at 175,707.
    Appellant advances several legal theories to excuse its default, but focuses on
    three main factual issues. First, appellant contends that the Army breached the contract
    with respect to the level of cleaning required for Building 701, one of the larger child
    development center buildings (app. br. at 24-25). Second, appellant contends that the
    Army breached the contract with respect to the frequency of cleaning required for the
    fitness center buildings (id. at 22-23, 26). Finally, appellant contends that the
    government unilaterally changed appellant's bid price when it input appellant's bid into
    its computer system and that appellant should have been notified of the mistake.
    We address each of these factual contentions and associated legal theories in tum.
    1. Building 701
    The contract, as awarded, contains a clear discrepancy in the cleaning levels for
    Building 701 (finding 25). The government did not catch this discrepancy, either during the
    solicitation or after the award (finding 34 ). It was not detected until LKJ Crabbe raised the
    issue after award (finding 32). When appellant raised the issue with the government, the
    CO issued a Contractor Deficiency Report, arguing that any contractual ambiguity was
    resolved by the order of precedence of contract documents and that LKJ Crabbe should
    have known that the centers were to be cleaned seven days per week (finding 33 ).
    i.   Contract Interpretation
    Established court precedent and rules of construction require that contract
    provisions should not be interpreted as conflicting with one another unless there is no other
    possible reasonable construction of the language. Hal-Gar Mfg. Corp. v. United States,
    351 F.2d 972,979 (Fed. Cir. 1965). In the event ofa conflict between contract provisions,
    however, the Order of Precedence clause may be invoked to resolve the conflict. Hensel
    Phelps Constr. Co. v. United States, 
    886 F.2d 1296
    , 1298 (Fed. Cir. 1989).
    The contract in this appeal contains the full text of FAR 52.214-29, ORDER OF
    PRECEDENCE-SEALED BIDDING (JAN 1986), which states:
    Any inconsistency in this solicitation or contract shall be
    resolved by giving precedence in the following order: (a) the
    Schedule (excluding the specifications); (b) representations
    and other instructions; (c) contract clauses; ( d) other
    documents, exhibits, and attachments; and ( e) the
    specifications.
    (Finding 21)
    Here, the contract contains a clear inconsistency in the cleaning levels for
    Building 701. Building 70 I was included in CLIN 0019 in TO 000 I as requiring the
    "Child Care" level of cleaning (finding 26). However, Building 70 I is listed on technical
    exhibit 5 as receiving the "Installation" level of cleaning (finding 27).
    This clear inconsistency is plainly resolved by the Order of Precedence clause in the
    contract. Pursuant to FAR 52.214-29, the Schedule (setting forth each of the specific
    CLINs) is first in the order of precedence, superseding the "other documents, exhibits, and
    attachments," including technical exhibit 5 (finding 19). Thus, the government properly
    interpreted the contract to require "Child Care" level of cleaning in Building 701.
    17
    ii.   Mistake in Bid
    Appellant contends that the level of cleaning required for Building 701 was a
    mistake in bid and should have been addressed pursuant to FAR 14.407-4, Mistakes after
    award. According to appellant, a contract specialist lacks authority to make decisions on
    disputes with a contractor. (App. br. at 24-25)
    Under FAR 14.407-4, a CO may in limited circumstances rescind or reform a
    contract where the contractor has reported a bid mistake post-award. Such determinations:
    [M]ay be made only on the basis of clear and convincing
    evidence that a mistake in bid was made. In addition, it must
    be clear that the mistake was .. .if unilaterally made by the
    contractor, so apparent as to have charged the contracting
    officer with notice of the probability of the mistake.
    FAR 14.407-4(c), (2). This FAR provision then sets out procedures for the CO to follow
    in processing a mistake alleged after award. FAR 14.407-4(e).
    To prevail on its mistake in bid theory, appellant must prove that the error is of the
    type that may be compensable and that the CO knew or show have known of the mistake
    at the time the bid was accepted. DynCorp International LLC, ASBCA No. 59244, 17-1
    BCA, 36,653 at 178,497. An error of judgment is not a compensable error. Liebherr
    Crane Corp. v. United States, 
    810 F.2d 1153
    , 1157-58 (Fed. Cir. 1987) ("It is well
    established that an erroneous bid based, like this one, upon a mistake in judgment does
    not entitle the contractor to reformation of its contract."); FAR 14.407-4.
    In this appeal, appellant has not shown that the government knew, or should have
    known, of appellant's alleged mistake concerning its proposed price for CLIN 0019 for
    Building 701. The government's unbalanced price analysis focused only on whether there
    was consistency in the prices for each CLIN across the base and option years. The
    government did not compare individual CLINs to other CLINs within the same year, nor did
    it compare the pricing for particular types of buildings. (Finding 4) There was no way,
    therefore, for the government to know that appellant had underbid CLIN 0019. Moreover,
    because the government's unbalanced price analysis did not require it to compare prices on a
    per square foot basis across CLIN s, there is no way that the government should have known
    appellant's price was too low for CLIN 0019. (Findings 7-8)
    2. Fitness Centers
    Appellant's proposal included providing services to the three fitness centers on a
    daily basis only for Monday through Friday, not including weekends (findings 43-44).
    Amendment No. 0002 of the solicitation, which is incorporated into the contract,
    however, stated that "fitness centers will be serviced on the weekends when open"
    18
    (finding 42). If appellant had included weekends in its proposed price; its proposed price
    for the fitness centers would have been at least 30 percent greater had the price included
    cleaning on weekends ( finding 46).
    Appellant raises several legal issues with respect to the cleaning frequency of the
    fitness centers. First, appellant contends that the government possessed superior
    knowledge of the cleaning required for the fitness centers and failed to pass that
    information on to the bidders during the solicitation process (app. br. at 26). Second,
    appellant contends that the question-and-answer concerning the fitness centers during the
    solicitation created a latent ambiguity in the contract regarding whether the centers were
    to be cleaned on weekends (id.). Finally, appellant contends that the government acted in
    bad faith when appellant raised the ambiguity by issuing a deficiency report, instead of
    issuing an appealable CO decision (id. at 25).
    i.   Superior Knowledge and Latent Ambiguity
    Appellant claims that the government had superior knowledge of the cleaning
    schedule for the fitness centers and failed to disclose that information to bidders during
    the solicitation, or to appellant immediately after award prior to the start of work, or to
    appellant after award (app. br. at 26). Indeed, appellant claims that the government did
    not disclose the cleaning schedule until after appellant had been performing for several
    weeks and customers were complaining about overflowing trash cans (id.).
    Appellant's superior knowledge argument fails, because the contract expressly
    requires the fitness centers to be cleaned on weekends. Indeed, the contract included a
    question-and-answer specifically on this issue (finding 42). The inclusion of this
    question-and-answer also resolves any reasonable ambiguity about whether the contract
    requires the fitness centers to be cleaned on weekends. The statement that "the fitness
    centers will serviced on weekends when open" leaves no ambiguity about whether
    weekends are included. At most, this question-and-answer leaves open only the question
    of the specific weekend hours. Interpreting this phrase to mean that the fitness centers are
    never open on weekends - as appellant did when it omitted weekends from its bid - is
    outside the "zone of reasonableness" and is not sufficient to create ambiguity. "To show
    an ambiguity it is not enough that the parties differ in their respective interpretations of a
    contract term. Rather, both interpretations must fall within a 'zone of reasonableness."'
    NVT Tech., Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004) (citing Metric
    Constructors, Inc. v. NASA, 
    169 F.3d 747
    , 751 (Fed. Cir. 1999)).
    ii.   Good Faith and Fair Dealing
    Appellant contends that the government violated its duty of good faith and fair
    dealing by failing to seek a formal determination from the CO when appellant pointed out
    an error in its bid concerning the cleaning frequency for the fitness centers (tr. 1/16-17;
    app. br. at 25). According to appellant, the government should have followed
    FAR 14.407-4 and issued a CO determination regarding appellant's alleged mistake in
    19
    the frequency of cleaning for the fitness centers (app. br. at 24 ). Instead, by issuing a
    contractor deficiency report, appellant argues that the government unfairly shifted the
    burden to it and forced it to do additional work outside the scope of its bid (id. at 25).
    "Every contract imposes upon each party a duty of good faith and fair dealing in
    its performance and enforcement." SIA Construction, Inc., ASBCA No. 57693, 14-1
    BCA 135,762 at 174,986 (citing Metcalf Construction Co. v. United States, 
    742 F.3d 984
    , 990 (Fed. Cir. 2014)). In this appeal, the evidence demonstrates that the government
    dealt fairly with LKJ Crabbe. The implied duty of good faith and fair dealing is limited
    by the original bargain: it prohibits acts or omissions that, though not proscribed by the
    contract expressly, are inconsistent with the contract's purpose and deprive the other
    party of the contemplated value. Century Exploration New Orleans, LLC v. United
    States, 
    745 F.3d 1168
    , 1179 (Fed. Cir.2014) (the implied duty of good faith and fair
    dealing "cannot expand a party's contractual duties beyond those in the express contract
    or create duties inconsistent with the contract's provisions"). As we explained
    previously, the government is under no obligation to accommodate a contractor's
    financial inability to continue performance, because the contractor is responsible to
    provide sufficient financial resources for the performance of the contract. Rashed Elham
    Trading Co., ASBCA No. 58383 et al., 17-1 BCA ~ 36,869 at 179,653.
    Indeed, duty of good faith and fair dealing does not extend to an obligation to
    modify the terms of a contract to benefit a contractor in financial difficulty. Highland Al
    Hujaz Co., ASBCA No. 58243, 16-1 BCA 136,336 ( contractor's financial difficulties are
    not a legitimate excuse for its default).
    3. Unilateral Mistake Concerning Appellant's Bid Price
    Appellant contends that the government unilaterally changed appellant's bid price
    when it input appellant's bid into its computer system. Because the government pricing
    system accepted only prices up to two decimal places, appellant's proposed price of
    $0.0095 per sq. ft. was changed to $0.01 per sq. ft. (Finding 12) According to appellant,
    rounding up its proposed price increased appellant's total price by an additional
    $282,150, which would have prevented LKJ Crabbe from being the lowest bidder.
    Appellant contends that the Army should have notified appellant of the mistake and given
    appellant an opportunity to correct it pursuant to FAR 14.407. (App. br. at 23-24)
    Appellant's argument fails to take into account the fact that it was the lowest
    bidder (finding 4) and the fact that the Army compared appellant's price against the
    prices of the other bidders after rounding up appellant's price (findings 15-16). Because
    appellant had the lowest price after its price was rounded up to $0.01 per sq. ft., and
    because using the proposed bid price of $0.0095 only would have reduced appellant's
    bid, we conclude that the clerical error-if any-had no effect on whether appellant
    would have won the award.
    20
    4. Alleged Breach was Not Material
    Finally, even if we were to conclude that the government breached the contract
    under any of appellant's theories, it would not change our conclusion that the termination
    for cause was justified, because the breaches are not material.
    A breach is material if it relates to a matter of vital importance or goes to the essence of
    the contract. Tzell Airtrak Travel Grp. Corp., ASBCA No. 57313, 11-2 BCA ~ 34,845 at
    171,410 (citing Thomas v. HUD, 
    124 F.3d 1439
    , 1442 (Fed. Cir. 1997)). The government
    concluded that the major cause of the company's losses was faulty pricing throughout the
    contract. Although Mr. Crabbe raised Building 701 and the fitness centers as specific issues,
    the CO concluded that addressing these issues would not resolve the underlying problems with
    faulty pricing. (Finding 70) Mr. Crabbe himself admitted that there was faulty pricing
    throughout the award and that the company had not understood the depth of the requirement
    (finding 56).
    For example, even considering the acknowledged discrepancy in the Building 701
    cleaning levels and the extra cost associated with cleaning the fitness centers on weekends
    - including extra staffing necessary to do so - the difference in price is less than $5,000 per
    month (finding 51), only a fraction ofLKJ Crabbe's alleged $2,700-$32,000 monthly losses
    on the contract (finding 52).
    The testimony and evidence at the hearing demonstrated that appellant's losses on
    the contract fundamentally were the result of faulty pricing throughout the contract. Even
    if we assume that the government was to blame for appellant's pricing on the three fitness
    centers and on the child development center building, the financial losses resulting from
    having underbid these items is far less than the monthly losses appellant sustained
    (findings 47-53).
    CONCLUSION
    For these reasons, the appeal is denied.
    Dated: October 29, 2018
    KENNETH D. WOODROW
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    21
    I concur                                          I concur
    RICHARD SHACKLEFORD                               J. REID PROUTY
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 60331, Appeal of LKJ
    Crabbe Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    22