North Arizona Construction Company ( 2017 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    North Arizona Construction Company            )      
    ASBCA No. 61028
    )
    Under Contract No. W5K9UR-12-P-7021           )
    APPEARANCE FOR THE APPELLANT:                        Mr. Mohammad Hussein Zamani
    President
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    MAJ Bruce L. Mayeaux, JA
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE YOUNGER ON THE
    GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION
    The government moves to dismiss this appeal, contending that appellant, North
    Arizona Construction Company (appellant or North Arizona) did not timely appeal to the
    Board from a contracting officer's final decision pursuant to the 90-day limitations period
    in the Contract Disputes Act, 
    41 U.S.C. § 7104
     (CDA). Appellant opposes the motion.
    We grant the motion and dismiss the appeal for lack of jurisdiction.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. On 21 May 2012, appellant and the Department of the Army (Army or
    government) bilaterally executed a purchase order, No. W5K9UR-12-P-7021 (contract),
    for the construction of upgrades to a police station in Afghanistan for a total value of
    1,295,306.06 Afghani or $26,640 (R4, tab 1 at 1-2). The contract incorporated the
    standard Federal Acquisition Regulation (FAR) clause 52.233-1, DISPUTES (JUN 2008)
    (R4, tab 1 at 20).
    2. During performance, appellant allegedly encountered problems in obtaining
    access to the construction site (see generally R4, tab 3). On 27 October 2012, appellant
    emailed a "Memo for Record," an invoice, and other documents to the contracting officer,
    Mr. Isaac Thorp (CO Thorp) (Bd. corr. file, app. 29 January 2017 notice of appeal, attach.
    file name "Gmail - Invoice PB Landay Upgrades - W5K9UR-12-P-7021.pdf'). The
    "Memo for Record" was characterized by appellant as its claim seeking payment for 70%
    of the costs related to materials allegedly stolen because an Army commander would not
    allow appellant to store the materials at the construction site, and as a result, the items
    were left unsecured outside the site. Appellant stated that the previous contracting officer
    advised it to submit a claim for the stolen materials after work was completed. (R4, tab 5)
    The Board is unable to locate copies of the invoice and other documents that were a part
    of the 27 October submission in the record.
    3. In an email dated 28 October 2012, CO Thorp notified appellant that quality
    issues with the construction work would need to be corrected prior to acceptance by the
    government. Additionally, CO Thorp informed appellant that the government was not
    responsible for appellant's loss and would not pay appellant's invoice for the allegedly
    stolen materials. CO Thorp advised appellant that once corrective actions were
    completed it could submit an invoice for the contract amount. (Bd. corr. file, app.
    29 January 2017 notice of appeal, attach. file name "Gmail - Invoice PB Landay
    Upgrades - W5K9UR-12-P-702 l.pdf') The email on its face is not styled as a final
    decision.
    4. Between October and November 2012, the parties continued to exchange email
    correspondence regarding responsibility for the costs of the allegedly stolen materials
    (see generally R4, tab 7; Bd. corr. file, app. 29 January 2017 notice of appeal, attach. file
    name "Gmail - Invoice PB Landay Upgrades - W5K9UR-12-P-7021.pdf'). After
    receiving confirmation from government personnel that corrective work was completed,
    CO Thorp, in an email dated 14 November 2012, directed appellant to submit its invoice
    for the contract amount (R4, tab 7).
    5. After continued insistence by appellant that it was entitled to payment for costs
    associated with the allegedly stolen materials, CO Thorp, in an email dated
    27 November 2012, advised appellant to submit two invoices, one pertaining to the
    contract amount and the other pertaining to appellant's request for the costs of the lost
    materials which would be treated as its claim under the contract. CO Thorp also advised
    appellant to provide supporting documentation with its claim. (R4, tab 7)
    6. On the same date, appellant submitted its claim package via email as directed by
    CO Thorp. The package included the earlier submitted 27 October 2012 "Memo for
    Record" (see statement 2) and an invoice in the amount of 1,071,444 Afghani.* (Bd. corr.
    file, app. email 28 U.S.C. § 1746
     (R4, tab 19). CO Bastiani states, in relevant part, that:
    It was on 01 March 2013 that I digitally signed the
    [final decision] and sent it to [appellant] via email (I generally
    make it a practice to send documents the same day they are
    signed for posterity sake), return receipt requested, as was my
    customary means of providing documentation for which
    evidence of receipt was necessary in the deployed
    environment. While the record does not contain a copy of the
    email by which I provided the [decision] to [appellant], in
    later email correspondence I did refer [appellant] to the
    4
    decision provided to them on 01 March 2013; a point that
    [appellant] does not refute.
    (Id. at 3)
    DECISION
    The government contends that appellant failed to timely appeal from the
    contracting officer's 26 February 2013 final decision (see statement 7) within the 90-day
    statutory period, depriving the Board of jurisdiction over this appeal. To support its
    contention, the government asserts that appellant received the final decision on
    1March2013, offering CO Bastiani's declaration, email correspondence between the
    parties after the decision was issued, and appellant's electronic transmission of a copy of
    the decision to government counsel and the Board on 3 February 2017 as evidence of
    receipt. (Gov't mot. at 5)
    In opposing the motion, appellant largely advances arguments related to the merits
    of the dispute. Appellant contends that it neither had knowledge, nor did CO Bastiani
    adequately inform it, regarding appealing to the Board. (Bd. corr. file, app. email dtd.
    13 March 2017). Appellant further elaborated that "[a]fter 4 years. I found the website of
    ASBCA and submitting my claims! When I found, I did submit my claim. The [Army] did
    not completely inform me. So I did not understand about law and process of ASBCA. I
    am so sorry about late of it. But please review all documents. Which show my claim is
    absolutely correct!" (Bd. corr. file, app. email dtd. 3 April 2017 sent to government
    paralegal and copied to the Board in response to gov't reply)
    After careful consideration of the record, we conclude that the government's motion
    must be granted and the appeal dismissed for lack of jurisdiction. We reach the conclusion
    for two principal reasons.
    First, the appeal was filed long after the time specified by law. Under the CDA, a
    contracting officer's final decision "is not subject to review by any forum, tribunal, or
    Federal Government agency, unless an appeal or action is timely commenced." 
    41 U.S.C. § 7103
    (g). To initiate an appeal from a final decision to an agency board, a contractor must
    do so within 90 days from the contractor's receipt date of the decision. 
    41 U.S.C. § 7104
    .
    This 90-day appeal period is statutory and may not be waived or extended. See Cosmic
    Construction Co. v. United States, 
    697 F.3d 1389
    , 1390 (Fed. Cir. 1982). Therefore, a timely
    appeal is a jurisdictional prerequisite for the Board to entertain an appeal. Mansoor
    International Development Services, 
    ASBCA No. 58423
    , 14-1 BCA il 35,742 at 174,926-27.
    The CDA requires a contracting officer to "mail or otherwise furnish a copy of the
    decision to the contractor." 
    41 U.S.C. § 7103
    (d). FAR 33.211 further provides that the
    contracting officer is to furnish a copy "by certified mail, return receipt requested, or by
    any other method that provides evidence of receipt." While appellant bears the burden of
    5
    proof to establish that its appeal to the Board was timely filed, the government bears the
    burden of establishing the receipt date of the final decision by the contractor. Singleton
    Enterprises, 
    ASBCA No. 58235
    , 14-1 BCA ~ 35,554 at 174,227. To meet this burden,
    the government must provide "objective indicia" of actual physical receipt. Riley &
    Ephriam Construction Co. v. United States, 
    408 F.3d 1369
    , 1372 (Fed. Cir. 2005).
    CO Bastiani attested that he sent the final decision via email on 1 March 2013, and
    correspondence in the record shows that he later informed appellant that a decision was
    sent on that date (statement 8). While this alone may be insufficient to prove receipt,
    appellant's statements in response to the government's motion lead us to conclude that it
    did in fact receive the final decision on 1 March 2013. Appellant does not assert that it
    received the decision on a different date. Rather, its contentions center on the adequacy
    of the government's notice and its unfamiliarity with the Board and the contract dispute
    process. Appellant appears to concede that its appeal is untimely, stating that "[a]fter
    4 years. I found the website of ASBCA and submitting my claims! When I found, I did
    submit my claim. The [Army] did not completely inform me. So I did not understand
    about law and process of ASBCA. I am so sorry about late of it." (Bd. corr. file, app.
    email 809 F.3d 1244
     (Fed. Cir. 2016), that
    a contracting officer's indication that he was still willing to reconsider his final decision
    could lead a contractor to believe the statute of limitations, was being tolled, see
    Guardian Angels, 809 F .3d at 1249-51, we are not presented with such circumstances
    here. CO Bastiani never gave appellant any reason to hope that his decision was in any
    way not final - especially not after his 3 March 2013 email (see statement 8(b)) and the
    29 April 2013 email from the government (see statement 9) seeking a release of
    appellant's claims.
    Second, the advice of rights in the decision was adequate. It is clear that this appeal
    was filed substantially more than 90 days after appellant's receipt of the contracting
    officer's decision. However, a decision that does not adequately inform the contractor of
    its appeal rights may prevent the running of the statutory 90-day period provided that
    actual prejudice or detrimental reliance is shown by the contractor. See Decker & Co. v.
    West, 
    76 F.3d 1573
    , 1579 (Fed. Cir. 1996) (proof of harm caused by defect); Mansoor
    International, 14-1BCA~35,742 at 174,926 (proof of actual prejudice or detrimental
    reliance caused by omission of detailed appeal rights). The CDA requires the final
    6
    decision to include language that informs "the contractor of its rights as provided in this
    chapter." 
    41 U.S.C. § 7103
    (e). The implementing regulation, FAR 33.21 l(a)(4)(v),
    provides that the final decision shall include substantially the following language, in
    relevant part:
    This is the final decision of the Contracting Officer.
    You may appeal this decision to the agency board of contract
    appeals. If you decide to appeal, you must, within 90 days
    from the date you receive this decision, mail or otherwise
    furnish written notice to the agency board of contract appeals
    and provide a copy to the Contracting Officer from whose
    decision this appeal is taken. The notice shall indicate that an
    appeal is intended, reference this decision, and identify the
    contract by number.
    Here, the final decision quoted verbatim the language from FAR 33.21 l(a)(4)(v) above
    (statement 7). The notification was neither incomplete nor misleading. Acceptance of
    appellant's contentions that the government did not inform it regarding the Board would
    enlarge the government's obligation beyond what is required by the statute and
    regulation. As stated previously, we lack authority to waive or extend the 90-day
    statutory period. Because the final decision adequately apprised appellant of its appeal
    rights and this appeal was filed more than 90 days from receipt of the decision, we lack
    jurisdiction to hear this untimely appeal.
    CONCLUSION
    The government's motion is granted and the appeal is dismissed for lack of
    jurisdiction.
    ~~RYOUNGER
    Dated: 11 December 2017
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    7
    I concur                                        I concur
    ~/·
    RICHARD SHACKLEFORD                             J. REID PROUTY
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 61028
    , Appeal of North
    Arizona Construction Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    8
    

Document Info

Docket Number: ASBCA No. 61028

Judges: Younger

Filed Date: 12/11/2017

Precedential Status: Precedential

Modified Date: 12/18/2017