Munck Asfalt A/S ( 2021 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                 )
    )
    Munck Asfalt A/S                             )     ASBCA No. 61497
    )
    Under Contract No. W912DS-14-C-0019          )
    APPEARANCE FOR THE APPELLANT:                      Mr. Hans Christian Munck
    Chief Operations Officer
    APPEARANCES FOR THE GOVERNMENT:                    Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Lorraine C. Lee, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, New York
    OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN
    This appeal arises from a contract awarded to Munck Asfalt A/S (Munck or
    appellant) by the U.S. Army Corps of Engineers (USACE) to perform work on a
    runway at Thule Air Base in Greenland. Munck appeals the USACE’s final decision
    denying its claim for extra work to encase in concrete airfield runway edge light
    cables. Munck asserts that requiring concrete encasement for the installation of
    conduit on a portion of the runway renovation is a constructive change, since the
    drawings for this work do not state concrete encasement is required. The USACE
    maintains that encasing these electrical cables in concrete was always part of the basic
    contract. The issue before us then is whether the contract requires both duct and
    conduit to be concrete-encased where specified in the contract. The parties elected to
    submit the appeal on the record pursuant to Board Rule 11. We decide entitlement
    only. Appellant did not submit a brief. For the reasons discussed below, we find that
    the contract uses the terms duct and conduit interchangeably and therefore we deny
    this appeal.
    FINDINGS OF FACTS
    1. The USACE awarded Contract No. W912DS-14-C-0019 to Munck on
    August 21, 2014, in the amount of 130,042,220 Danish kroner ($22,782,050.07).
    Consistent with 10 U.S.C. 2304(c)(4) (International Agreement), the award was
    limited to Danish and Greenlandic firms only. This was a Design-Bid-Build contract.
    The contract provided for runway removal and replacement, including runway edge
    lights & thresholds, and other associated electrical upgrades. All work was to be
    performed in accordance with the plans and specifications as set forth in the special
    contract requirements entitled “Commencements, Prosecution and Completion of
    Work” at paragraph d. The project was to occur in two phases over a performance
    period of 905 calendar days. (R4, tabs 3a at 1-6, 32-33; 3b; 4) 1
    2. A Notice to Proceed was issued on September 10, 2014. Munck
    acknowledged receipt of the Notice to Proceed the following day. (R4, tab 4)
    The Dispute
    3. A preconstruction conference was held on January 13, 2015. Among the
    topics discussed during the meeting, was Munck’s request for the government to
    provide “details of the trench for the runway lighting power cables.” The government
    responded that the “Cross section of new runway edge lighting trench is detailed on
    sheet ED103 Concrete Encased Duct – 1 Conduit.” (R4, tab 6 at 1-2) Further written
    response was provided by the government on January 20, 2015, “[t]he 5kV cables
    shall be installed in concrete as per the details shown on Sheet ED103. Furthermore,
    Section 26 56 20, [paragraph] 3.6 and Section 33 70 02, paragraph 2.5 both state that
    the conduits shall be concrete encased.” (R4, tab 6 at 1-2)
    4. On January 20, 2015, Munck responded with a Request for Information
    “RFI” No. 013. In it, Munck states “[r]egarding the conduit trench we understand that
    you want the conduits concrete encased, similar to the ducts indicated on drawing
    ED103. We therefor[e] need a drawing for the conduit trench . . . giving indications
    on location related to the runway edge line etc.? Please note: The drawings ED101
    and ED 102 also need revision to provide the information on concrete encased ducts.”
    In responding to the government’s previous answer appellant states, “We do not
    acknowledge your references. The references are referring to ducts yes[,] however the
    drawings ES 101-107 + ED101 do not specify duct for the work in question.” (R4,
    tab 7).
    1
    The government provided a paper Rule 4 file with excerpts from the contract and a
    CD containing the full contractual documents at tab 3. This CD is not
    organized in tabs, so we refer here to the relevant file’s name. Drawings
    ES101-08 apply to Phase 1, while ES108-13 apply to Phase 2. Drawing ES114
    appears in different versions in each phase, but the differences are irrelevant for
    our purposes. Drawings ED101-103 are the same in both phases. For
    simplicity, we will cite to and the parties primarily refer to drawings in Phase 1,
    though the claim at issue spans work during both phases. Likewise, our
    decision applies to the disputed work in both phases.
    2
    5. USACE responded to RFI No. 013 on January 22, 2015, directing that the
    “cables shall be installed in concrete as per the details shown on Sheet ED103. . . .
    [T]he location of the conduit trench is indicated on Notes 1 and 2 of Sheets ES101
    thru ES107.” The USACE explained that “[s]heet ED101 is an Elevated Light
    Detail not a duct/conduit burial detail” with new duct bank details “shown on large
    scale details on sheet ED103 . . . .” Further reference is provided to specification
    sections 26 56 20, paragraph 3.6 and Section 33 70 02, paragraph 2.5 requiring that
    “conduits shall be concrete encased.” (R4, tab 8)
    6. Appellant performed the work as directed by the government and thereafter
    submitted a Request for Equitable Adjustment (REA) on September 21, 2015,
    seeking recovery of 3,028,559 Danish kroner asserting entitlement on the theory that
    encasing the cables in concrete represented a change to the contract. Appellant
    rejected the government’s reliance on Section 26 56 20, paragraph 3.6 and
    Section 33 70 02, paragraph 2.5 as requiring both duct lines and conduit be concrete
    encased in locations as indicated. Appellant declared that there is a difference
    between conduits and duct lines, relying on the distinction made in Section 31 00 00
    paragraph 3.7.1. Appellant argued further that the contract language is unclear, and
    it should be construed against the drafter. (R4, tab 9 at 1)
    7. By letter dated May 18, 2016, the government denied the REA (R4, tab 10).
    8. On June 3, 2016, Munck certified its claim and requested a final decision
    from the contracting officer (R4, tab 11). A COFD was issued on December 11, 2017,
    denying the claim in the amount of $530,572.17 (R4, tab 2 at 10). Appellant timely
    appealed. The Board has jurisdiction over this appeal.
    The Specification
    9. The contract incorporated by reference and FAR 52.233-1, DISPUTES
    (JUL 2002), and FAR 52.236-21, SPECIFICATIONS AND DRAWINGS FOR
    CONSTRUCTION (FEB 1997) – Alternate I (APR 1984) (R4, tab 3a at 12), which
    provides in part: “Anything mentioned in the specifications and not shown on the
    drawings, or shown on the drawings and not mentioned in the specifications, shall be
    of like effect as if shown or mentioned in both. In case of a difference between
    drawings and specifications, the specifications shall govern.” FAR 52.236-21(a)
    10. The contract also incorporated by full text DFARS 252.236-7001
    CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000) which provides:
    (a) The Government will provide to the Contractor, without charge, one set of
    contract drawings and specifications, except publications incorporated into the
    3
    technical provisions by reference, in electronic or paper media as chosen by the
    Contracting Officer.
    (b) The Contractor shall—
    (1) Check all drawings furnished immediately upon receipt;
    (2) Compare all drawings and verify the figures before laying out the
    work;
    (3) Promptly notify the Contracting Officer of any discrepancies;
    (4) Be responsible for any errors that might have been avoided by
    complying with this paragraph (b); and
    (5) Reproduce and print contract drawings and specifications as needed.
    (c) In general--
    (1) Large-scale drawings shall govern small-scale drawings; and
    (2) The Contractor shall follow figures marked on drawings in
    preference to scale measurements.
    (d) Omissions from the drawings or specifications or the misdescription of
    details of work that are manifestly necessary to carry out the intent of the
    drawings and specifications, or that are customarily performed, shall not relieve
    the Contractor from performing such omitted or misdescribed details of the
    work. The Contractor shall perform such details as if fully and correctly set
    forth and described in the drawings and specifications.
    (e) The work shall conform to the specifications and the contract drawings
    identified on the following index of drawings:
    “Upon completing the work under this contract, the
    Contractor shall furnish a complete set of all shop
    drawings as finally approved. These drawings shall show
    all changes and revisions made up to the time the
    equipment is completed and accepted.” See FAR 52.236-
    21 Alt. 1 (APR 1984)
    (R4, tab 3a at 27-28).
    4
    11. The project included work on the runway edge lights as described in
    Specification Section 26.56. 20.00 10, AIRFIELD AND HELIPORT LIGHTING
    AND VISUAL NAVAGATION AIDS, Part 2, specifically, 2.5 RUNWAY
    LIGHTING SYSTEM “Runway lights include runway edge lights, runway threshold
    lights, mounting structures, controls, and the associated equipment and interconnecting
    wiring to provide complete systems as indicated and specified herein. In-pavement
    light fixtures shall be able to withstand a minimum static single wheel load of 50,000
    pounds.” (R4, tab 3 at 174)
    12. Specification Section 26.56. 20.00 10, AIRFIELD AND HELIPORT
    LIGHTING AND VISUAL NAVAGATION AIDS, Part 2, Section 2.3
    ADDITIONAL REQUIREMENTS included requirements for duct and conduit:
    2.3.2 Conduit, Conduit Fittings, and Boxes
    2.3.2.1 Rigid Steel or Intermediate Metal Conduit (IMC)
    and Fittings.
    The metal conduit and fittings shall be UL 6 and UL 1242,
    respectively, coated with a polyvinylchloride (PVC) sheath
    bonded to the galvanized exterior surface, nominal 40 mils
    thick, conforming to NEMA RN 1.
    2.3.2.2 Flexible Metal Conduit
    Flexible metal conduit shall be UL 1, zinc-coated steel. UL
    360 liquid-tight flexible metal conduit shall be used in wet
    locations.
    2.3.2.3 Outlet Boxes for Use with Steel Conduit, Rigid or
    Flexible
    These outlet boxes shall be UL 514A, cast metal with
    gasket closures.
    2.3.2.4 Plastic Duct for Concrete Encased Burial
    These ducts shall be provided as specified in Section 33 70
    02.00 10, ELECTRICAL DISTRIBUTION SYSTEM,
    UNDERGROUND.
    5
    2.3.2.5 Plastic Conduit for Direct Burial
    This plastic conduit shall be provided as specified in
    Section 33 70 02.00 10, ELECTRICAL DISTRIBUTION
    SYSTEM, UNDERGROUND
    (R4, tab 3c at 1, 8-9)
    13. Execution of the work as provided for in Specification Section 26 56 20.00
    10 provides:
    3.2 GENERAL INSTALLATION REQUIREMENTS
    Circuits installed underground shall conform to the
    requirements of Section 33 70 02.00 10 ELECTRICAL
    DISTRIBUTION SYSTEM, UNDERGROUND, except as
    required herein. Steel conduits installed underground shall
    be installed and protected from corrosion. Except as
    covered herein, excavation, trenching, and backfilling shall
    conform to the requirements of Section 31 00 00
    EARTHWORK. Concrete work shall conform to the
    requirements of Section 03 30 04 CONCRETE FOR
    MINOR [STRUCTURES].
    (R4, tab 3c at 13)
    14. Specification Section 26 56 20.00 10 identifies the general requirements for
    the installation of cables as follows:
    3.3 CABLES, GENERAL REQUIREMENTS
    ....
    3.3.1 Duct Line Installation
    Install medium-voltage cables in duct lines where
    indicated. Cable splices in low-voltage cables shall be
    made in manholes and handholes only, except as otherwise
    noted. Cable joints in medium-voltage cables shall be
    made in manholes only. Neutral and ground conductors
    shall be installed in the same duct with their associated
    phase conductors. Electrical metallic tubing shall not be
    installed underground or enclosed in concrete.
    6
    ....
    3.3.2.3 Other Requirements
    Where direct-burial cables cross under roads or other
    paving exceeding 5 feet in width, such cables shall be
    installed in concrete-encased ducts. Where direct-burial
    cables cross under railroad tracks, such cables shall be
    installed in reinforced concrete encased ducts. Ducts shall
    extend at least 1 foot beyond each edge of any paving and
    at least 5 feet beyond each side of any railroad tracks.
    Cables may be pulled into conduit from a fixed reel where
    suitable rollers are provided in the trench. Direct-burial
    cables shall be centered in duct entrances. A suitable
    waterproof nonhardening mastic compound shall be used
    to facilitate such centering. If paving or railroad tracks are
    in place where cables are to be installed, coated rigid steel
    conduits driven under the paving or railroad tracks may be
    used in lieu of concrete-encased ducts.
    (Rule 4, tab 3c at 13-14)
    15. Specification Section 26 56 20.00 10 at 3.6 provides:
    3.6 DUCT LINES
    Duct lines shall be concrete-encased, thin-wall type for
    duct lines between manholes and for other medium-voltage
    lines. Low-voltage lines run elsewhere may be non-
    encased direct-burial, thick-wall type.
    ....
    3.6.3 Concrete Encasement
    Each single duct shall be completely encased in concrete
    with a minimum of 3 inches of concrete around each duct,
    except that only 2 inches of concrete are required between
    adjacent electric power or adjacent communication ducts,
    and 4 inches of concrete shall be provided between
    adjacent electric power and communication ducts. Duct
    line encasements shall be monolithic construction. Where
    a connection is made to a previously poured encasement,
    7
    the new encasement shall be well bonded or doweled to the
    existing encasement. At any point, except railroad
    crossings, tops of concrete encasements shall be not less
    than 18 inches below finished grade or paving. At railroad
    crossings, duct lines shall be encased with concrete,
    reinforced as indicated. Tops of concrete encasements
    shall be not less than 5 feet below tops of rails, unless
    otherwise indicated. Separators or spacing blocks shall be
    made of steel, concrete, plastic, or a combination of these
    materials placed not further apart than 4 feet on centers.
    Ducts shall be securely anchored to prevent movement
    during the placement of concrete and joints shall be
    staggered at least 6 inches vertically.
    (Rule 4, tab 3c at 16-17)
    16. Specification Section 31 00 00 EARTHWORK, Part 3, section 3.7.1, as
    part of SPECIAL REQUIRMENTS (section 3.7), provides that the Electrical
    Distribution System “[p]rovide a minimum cover of 24 inches from the finished grade
    to direct burial cable and conduit or duct line, unless otherwise indicated.” (Rule 4,
    tab 3d at 1, 6)
    17. Specification Section 33 70 02.00 10, ELECTRICAL DISTRIBUTION
    SYSTEM, UNDERGROUND includes a section identified as 2.5 CONDUIT AND
    DUCTS and required “[d]uct lines shall be concrete-encased, thin-wall type.” This
    section continues with section 2.5.1 and sets forth the requirements for Metallic
    Conduit identifying intermediate metal conduit, rigid galvanized steel conduit and
    metallic conduit fittings and outlets, and the standards they must meet. Then, section
    2.5.2 addresses Conduit Sealing Compound, and provides “Compounds for sealing
    ducts and conduit shall have a putty-like consistency workable with the hands at a
    temperature as low as 35 degrees F....Compounds shall adhere to clean surfaces of
    fiber or plastic ducts; metallic conduits or conduit coatings; concrete . . . .” (R4, tab 3e
    at 1, 9-10)
    18. Specification Section 33 70 02.00 10, ELECTRICAL DISTRIBUTION
    SYSTEM, UNDERGROUND, Part 3 provides the following with respect to the
    installation of ducts and cables:
    • Section 3.3.1.2 states that “[d]uct shall be cleaned with
    an assembly that consists of a flexible mandrel
    (manufacturers standard product in lengths
    recommended for the specific size and type of duct)
    that is ¼ inch less than inside diameter of duct . . . . The
    8
    cleaning assembly shall be pulled through conduit a
    minimum of 2 times or until less than a volume of 8
    cubic inches of debris is expelled from the duct.
    • Section 3.3.2, titled “Duct Line,” requires cables to be installed in
    duct lines where indicated.
    • Section 3.3.3, titled “Direct-Burial,” requires that medium voltage
    cables be buried directly into the earth.
    • Section 3.3.3.2, titled “Cable Burial,” provides in part that “[c]ables
    shall be unreeled along the sides of or in trenches and carefully
    placed on sand or earth bottoms. Pulling cables into direct-burial
    trenches from a fixed reel position will not be permitted, except as
    required to pull cables through conduits under paving or railroad
    tracks. Where cables cross, a separation of at least 3 inches shall be
    provided, unless each cable circuit is protected by a nonmetallic
    conduit sleeve at the crossing.
    • Section 3.3.3.3, titled “Other Requirements,” provides for cable
    installation and requires that “[w]here direct-burial cables cross under
    roads or other paving exceeding 5 feet in width, such cables shall be
    installed in concrete-encased ducts. Where direct-burial cables cross
    under railroad tracks, such cables shall be installed in reinforced
    concrete-encased ducts. Ducts shall extend at least 1 foot beyond
    each edge of any paving and at least 5 feet beyond each side of any
    railroad tracks. Cables may be pulled into duct from a fixed reel
    where suitable rollers are provided in the trench. Where direct burial
    cable transitions to duct-enclosed cable, direct-burial cables shall be
    centered in duct entrances, and a waterproof nonhardening mastic
    compound shall be used to facilitate such centering. If paving or
    railroad tracks are in place where cables are to be installed, coated
    rigid steel conduits driven under the paving or railroad tracks may be
    used in lieu of concrete-encased ducts. Damage to conduit coatings
    shall be prevented by providing ferrous pipe jackets or by predrilling.
    Where cuts are made in any paving, the paving and subbase shall be
    restored to their original condition.”
    (Rule 4, tab 3e at 11-14)
    19. Specification Section 33 70 02.00 10, 3.6 DUCT LINES, provides
    at Section 3.6.3, Concrete Encasement:
    9
    Ducts requiring concrete encasements shall comply with
    NFPA 70, except that electrical duct bank configurations
    for ducts 6 inches in diameter shall be determined by
    calculation and as shown on the drawings. The separation
    between adjacent electric power and communication ducts
    shall conform to IEEE C2. Duct line encasements shall be
    monolithic construction. Where a connection is made to a
    previously poured encasement, the new encasement shall
    be well bonded or doweled to the existing encasement.
    Submit proposed bonding method for approval in
    accordance with the detail drawing portion of paragraph
    SUBMITTALS. At any point, except railroad and airfield
    crossings, tops of concrete encasements shall be not less
    than the cover requirements listed in NFPA 70. At railroad
    and airfield crossings, duct lines shall be encased with
    concrete and reinforced as indicated to withstand specified
    surface loadings. Tops of concrete encasements shall be
    not less than 5 feet below tops of rails or airfield paving
    unless otherwise indicated. Where ducts are jacked under
    existing pavement, rigid steel conduit will be installed
    because of its strength. To protect the corrosion-resistant
    conduit coating, predrilling or installing conduit inside a
    larger iron pipe sleeve (jack-and-sleeve) is required. For
    crossings of existing railroads and airfield pavements
    greater than 50 feet in length, the predrilling method or the
    jack-and-sleeve method will be used. Separators or spacing
    blocks shall be made of steel, concrete, plastic, or a
    combination of these materials placed not farther apart
    than 4 feet on centers. Ducts shall be securely anchored to
    prevent movement during the placement of concrete and
    joints shall be staggered at least 6 inches vertically.
    (Id. at 16)
    Drawings
    20. The drawings detailed new work including the installation of elevated and
    semi-flush lights along the edges of the runway, linked together by underground
    electrical wiring. Drawings numbered ES101-113 are small-scale drawings providing
    an overview of the runway work in Phases 1 and 2 of the construction, with ES114
    covering wiring between manholes north of the runway leading to the Airfield
    Lighting Vault. Drawings ED101-103, appearing in both phases, are large-scale
    drawings detailing the work to be done for individual elevated lights, semi-flush lights,
    10
    and the installation of concrete-encased ducts containing one, two, or four conduits.
    ED901-910, are the as-built drawings providing for the electrical detail existing at the
    site. (R4, tab 3 (Plans Phase 2 – Replace Runway Pavement) at 96-103, 111-120, 3f
    at 3-13)
    21. There are 18 drawings that comprise the electrical detail for the runway
    lighting installation, ED101-ED108 and ED901-ED910. In both phases, ED101-103
    contains notations “Sheet 1 of 3,” “Sheet 2 of 3,” and “Sheet 3 of 3.” Both phases also
    contain drawings ED104-107, which do not carry such a notation. However, other
    drawings contained in the electrical section also contain the designation of being part
    of a set. The electrical detail provided in ED101-103 shall be read as one continuous
    drawing. (R4, tabs 3 (both Plans Phase 1 and Plans Phase 2) at 96-103, 111-120; 3f
    at 2, 11-13)
    22. Drawings ED101 and 102 state that the electrical wiring connecting all the
    lights should be “cable #6 5 kV” housed in a “galvanized rigid steel conduit.” The
    detail provides that the cables shall be housed in “galvanized rigid steel conduit” with
    a “conduit coupling” on both sides of the “Liquid Tight Non-Metallic Flexible
    Conduit” that reaches to the fixture with the cables again housed in the galvanized
    rigid steel conduit wired directly to the fixture. This detail appears on both sides of the
    “Elevated Light Detail” (ED101, sheet 1 of 3) and “Semi-flush Runway Edge Light”
    (ED102, sheet 2 of 3). Outside the construction for each light, the cables have
    “conduit couplings” along their length in both directions, but otherwise extend to
    unlabeled white space. The detail required for installation is contained on ED103
    (sheet 3 of 3) and explicitly provides the electrical detail for Concrete Encased Duct –
    1 Conduit, Concrete Encased Duct – 2 Conduit, and Concrete Encased Duct – 4
    Conduit. The drawing does not differentiate between duct and conduit and notes 1 and
    2, and note 6 for the concrete encased duct with 2 or 4 conduit, identify them as
    interchangeable terms. (R4, tabs 3 (Plans Phase 2) at 104-110; R4, tab 3f at 11-13).
    23. ES105 (Electrical Site Plan for Area E) provides for the installation of the
    “new concrete encased 4” Four Way Ductbank between handhold HH E-2 and HH E-1
    with a notation to run temporary PAPI circuit into HH E-2, using the handhold and
    conduit system to route to existing lighting vault. The contractor is referred to Sheet
    ES114 for connection information. Notes 4, 5, and 6 also direct the contractor to the
    detail identified in the drawings at ED101, ED102 & ED103. Appellant argues that
    because drawing ES105 identified certain conduit to be concrete-encased, drawings
    ED101 and ED102 should have also identified conduit as concrete-encased if it was to
    be required by the contract (R4, tab 9 at 1). Appellant ignores the identification of
    concrete-encased conduit on ED103 (sheet 3 of 3). (R4, tabs 3 (Plans Phase 2) at 106;
    Rule 4, tab 3f at 7, 10-13)
    11
    24. Drawing ES105 identifies a conduit path that leads to the Airfield Lighting
    Vault. Because this conduit path does not travel under a road or asphalt, specification
    section 26 56 20 paragraph 3.3.2.3, “Other Requirements” (“where direct-burial cables
    cross under roads or other paving exceeding 5 feet in width, such cables shall be
    installed in concrete-encased ducts”) does not apply to the work identified on ES105.
    To ensure that the requirements of section 3.3.2.3 apply to the work identified on
    ES105, the requirement to provide concrete-encased conduit was added. (R4, tabs 3c
    at 14; 3f at 3-9)
    DECISION
    The Parties’ Contentions
    Appellant contends that its interpretation of the plans and specifications
    required only that duct, not conduit, were required to be concrete-encased. Appellant
    also contends that the contracting officer’s direction to encase both duct and conduit in
    concrete was a constructive change to the contract and requires compensation.
    Appellant submitted a three-page complaint presenting its argument, and did not file a
    brief. The complaint sets forth 15 numbered paragraphs in total, with six paragraphs
    establishing the facts and two paragraphs dedicated to rebutting the contracting
    officer’s final decision. Appellant advances two main arguments. First, in paragraph
    10, appellant states that since ED103 is specifically referenced on drawings ES105 and
    ES114, both of which contain the four inch four-way duct bank (which involves
    lighting leading north to the Airfield Lighting Vault), then ED103 must only refer to
    installation of the four-way duct bank. Further, drawings ES101-104 and 106-113,
    which contain new work for only the edge light trench, only refer to drawings ED101
    and 102, which do not discuss concrete encasement of ducts. (Compl. ¶ 10) Appellant
    concludes that the government’s direction to require concrete encasement of these
    ducts is a change in the contract. (Compl. ¶ 15) Second, appellant disputes that
    Section 33 70 02.00 paragraphs 2.5 and 2.5.1 require concrete-encasement for
    conduits, as 2.5 only references ducts, not conduit, and these “are considered as
    different entities” (id. ¶ 14). Included in its REA, Munck argues that if the contract
    language is susceptible to more than one meaning or is ambiguous, it should be
    construed against the drafter (finding 6).
    In its brief, the government points to several sections of the specifications that
    require encasing cable in concrete. They include Section 26 56 20.00 10,
    subparagraph 3.3.2.3, which requires concrete-encasing when “direct-burial cables
    cross under roads or other paving exceeding five feet in width” (gov’t br. at 2-5). The
    government also points to several places in the contract where it alleges the contract
    uses conduit and duct interchangeably, urging us to read references to concrete-
    encasing ducts as references to concrete-encasing conduits (id. at 13-19). The
    government challenges Munck’s assertions that the conduits do not require that they be
    12
    concrete encased because Drawings ED101 and ED102 do not indicate concrete
    encasement. The government also says Munck’s use of Drawing ES105 as proof that
    conduit must specify that it be encased in concrete is flawed and we should look to the
    specifics of that drawing. Furthermore, the government maintains that Munck’s
    premise that the drawings dictate over the requirements of the specification is
    erroneous. (id. at 14) As provided in contract clause 52.236-21, where there is a
    “difference between the drawings and specifications, the specifications shall govern”
    and “. . . . anything mentioned in the specifications and not shown on the drawings, or
    shown on the drawings and not mentioned in the specifications, shall be of like effect
    as if shown or mentioned in both” (finding 9).
    Contract Interpretation
    We review the contracting officer’s final decision de novo. 41 U.S.C.
    § 7104(b)(4). The parties present us with a question of contract interpretation.
    Contract interpretation is a matter of law. See, e.g., ThinkQ, Inc., ASBCA No. 57732,
    
    13 BCA ¶ 35,221
     at 172,825. The rules of contract interpretation require that we first
    look to the plain language of the contract. Langkamp v. United States, 
    943 F.3d 1346
    ,
    1349 (Fed. Cir. 2019); Banknote Corp. of America, Inc. v. United States, 
    365 F.3d 1345
    , 1353 (Fed. Cir. 2004); Hercules, Inc. v. United States, 
    292 F.3d 1378
    , 1380
    (Fed. Cir. 2002). We “appl[y] the principle of contract interpretation that possibly
    conflicting contract provisions should be read harmoniously.” Hometown Fin., Inc. v.
    United States, 
    409 F.3d 1360
    , 1369 (Fed. Cir. 2005) (citing Guar. Fin. Servs., Inc. v.
    Ryan, 
    928 F.2d 994
    , 999 (11th Cir. 1991).
    [P]rovisions of a contract must be so construed as to
    effectuate its spirit and purpose . . . an interpretation which
    gives a reasonable meaning to all of its parts will be
    preferred to one which leaves a portion of it useless,
    inexplicable, inoperative, void, insignificant, meaningless,
    superfluous, or achieves a weird and whimsical result.
    Gould, Inc. v. United States, 
    935 F.2d 1271
    , 1274 (Fed. Cir. 1991) (quoting Ariz. v.
    United States, 
    575 F.2d 855
    , 863 (Ct. Cl. 1978).
    The contract required appellant to provide “airfield and heliport lighting and
    visual navigation aids consisting of runway lights, visual glide slope indicator, and the
    lighting power supply and control” (finding 1). The work that forms the basis of this
    claim relates to the installation of new cable to the runway edge lights, and more
    specifically, whether the installation of those new cables, when buried under roadways
    or other paving in excess of five feet in width, are required to be encased in concrete
    when placed in conduit verses duct. While other provisions of the specification may
    come into play when determining certain aspects of the work, the controlling
    13
    provisions for that work are set out in Specification Section 26 56 20.00 20
    (AIRFIELD AND HELIPORT LIGHTING AND VISUAL NAVAGATION AIDS)
    and Section 33 70 02.00 10 (ELECTRICAL DISTRIBUTION SYSTEM,
    UNDERGROUND). Section 26 56 20.00 10 contains the requirements for the direct-
    burial of cables. Paragraph 3.3.2.3 requires that “where direct-burial cables cross
    under roads or other paving exceeding five feet in width, such cables shall be installed
    in concrete-encased ducts.” Paragraph 3.3.2.3 also dictates that “where direct-burial
    cables cross under railroad tracks, such cables shall be installed in reinforced concrete
    encased ducts.” (Finding 14) The specification plainly provides that concrete
    encasement is required when cable is to be buried under roads, paving or railroad
    tracks. The appellant maintains that because the contract says that “such cables shall
    be installed in concrete-encased ducts” and it doesn’t reference cables to be installed in
    concrete-encased conduit, that the work directed by the contracting officer was
    inconsistent with the requirements of the contract. The core of appellant’s argument is
    that ducts and conduit “are considered as different entities” and therefore the
    references in the specification to duct do not apply to conduit. (Compl. ¶ 14)
    The question that requires resolution is whether the plain language of the
    contract “supports only one reading or supports more than one reading and is
    ambiguous.” NVT Tech., Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004).
    Where a contract is susceptible of more than one reasonable interpretation, it is
    ambiguous. Hills Materials Co. v. Rice, 
    982 F.2d 514
    , 516 (Fed. Cir. 1992). “To show
    an ambiguity it is not enough that the parties differ in their respective interpretations of
    a contract term. Rather, both interpretations must fall within a ‘zone of
    reasonableness.’” NVT Tech., 
    370 F.3d at 1159
     (citing Metric Constructors, Inc. v.
    NASA, 
    169 F.3d 747
    , 751 (Fed. Cir. 1999)); See also TEG-Paradigm Envtl., Inc. v.
    United States., 
    465 F.3d 1329
    , 1338 (Fed. Cir. 2006) (“When interpreting a contract,
    the language of [the] contract must be given that meaning that would be derived from
    the contract by a reasonably intelligent person acquainted with the contemporaneous
    circumstances.” (citation omitted)). When analyzing the words in the contract, the
    context in which the words are used and the intentions of the parties are critical. We
    will not twist the words out of context. Andersen Consulting v. United States,
    
    959 F.2d 929
    , 934-35 (Fed. Cir. 1992).
    The specification is full of references for the installation of cable, placed in
    conduit or duct, and under what instances the cables shall be concrete encased.
    Section 26.56. 20.00 10 at 2.3.2 entitled “Conduit, Conduit Fittings & Boxes”,
    includes requirements relating to the installation of both conduit and duct. For each
    reference, whether duct or conduit, the installation must be in compliance with Section
    33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND.
    (Findings12-13) In Specification Section 33 70 02.00 10, the interplay between ducts
    and conduit becomes more clear. Section 3.3 provides for the general requirements for
    the installation of cables, including the requirements under Section 3.3.2.3 to provide
    14
    for direct burial cables that are installed under “roads or other paving exceeding 5 feet
    in width, shall be installed in concrete-encased ducts. Similarly, where the direct-
    burial cable is installed under railroad tracks, such cables shall be installed in
    reinforced concrete encased ducts. That section provides further that “cables may be
    pulled into conduit from a fixed reel where suitable rollers are provided in the trench.”
    (Finding 14) General requirements for duct lines provides in Section 3.6 that “duct
    lines shall be concrete-encased” and provides in more detail at 3.6.3 that “each single
    duct shall be completely encased in concrete with a minimum of 3 inches of concrete
    around each duct. (Finding 15) We find numerous references within Specification 26
    56 20.00 10 and 33 70 02. 00.10 that discuss the types of cable, installation of cable,
    and when concrete-encasement is required (under roads, paving or railroad tracks), all
    recognizing the interplay between the terms duct and conduit. (Findings 11, 13-14,
    16-18, 22) It is obvious that in performing this work, a contractor must first determine
    if the cable will be installed in a location that requires concrete-encasement; if it does
    then the requirements for concrete encasement (under roads, pavement or railroads)
    will apply (findings 13-15).
    Appellant’s reliance on conduits and ducts being “different entities” leads to the
    misplaced conclusion that the mandate set forth in Section 33 70 02.00 10 paragraph
    2.5 to encase duct lines in concrete is exclusive of conduits. Appellant’s reading
    renders significant portions of the specification meaningless. The purpose of 3.3.2.3
    of Section 26 56 20.00 10 and 3.3.3.3 of Section 33.70 02.00 10 are to ensure that the
    buried cables are protected from damage caused by the weight placed upon roadways,
    railroads, and pavement. (Findings 11, 14-15, 19) If we were to accept appellant’s
    interpretation, we would need to conclude that where cable conduit is buried
    underground it would not need to be protected by concrete even where those cables are
    being installed under “roads or other paving exceeding 5 feet” or “under railroad
    tracks.” Such a reading would render superfluous those sections of the specification
    intending to provide additional protection where the cables are most at risk.
    (Findings 14, 18)
    It is not unusual for courts to consult dictionaries to assist in the common
    meaning of a term. Rocknel Fastener, Inc. v. United States, 
    267 F.3d 1354
     (Fed Cir.
    2001) The New Oxford American Dictionary defines Conduit as “. . . .2. a tube or
    trough for protecting electric wiring . . . .” It defines Duct as “[a] channel or tube for
    conveying something, in particular . . . a tube or passageway for air, liquid, cables, etc.
    . . .” See NEW OXFORD AMERICAN DICTIONARY (3d ed. 2010). The definitions in
    Webster’s New World Dictionary are nearly identical. Webster’s defines Conduit as “.
    . .2. A tube, pipe or protected trough for electric wires” and Duct as “. . . 4. A pipe or
    conduit through which wires or cables are run.” See WEBSTER’S NEW WORLD
    DICTIONARY (3d college ed. 1988). We note that the fourth definition of Duct, which
    is most applicable in these circumstances, includes the word “conduit.” Similarly, the
    American Heritage Dictionary of the English Language defines Duct as “3. A tube
    15
    or pipe for enclosing electrical cables or wires.” AMERICAN HERITAGE DICTIONARY
    OF THE ENGLISH LANGUAGE (5th Ed. 2020),
    https://www.ahdictionary.com/word/search.html?q=duct. It defines Conduit in a
    similar manner, only this definition of conduit includes duct as part of its definition of
    conduit “2. A tube or duct for enclosing electric wires or cable.” AMERICAN
    HERITAGE DICTIONARY OF THE ENGLISH LANGUAGE (5th Ed. 2020),
    https://www.ahdictionary.com/word/search.html?q=conduit.
    The plain and unambiguous meaning of the written agreement will control.
    Hercules Inc., 
    292 F.3d at 1380-81
    . We must give reasonable meaning to all of its
    parts. NVT Tech., Inc., 
    370 F.3d at 1159
    . We find that appellant puts too much weight
    on silence. Paragraph 2.5.1 does not specify what shall be done with conduits, only
    that “[r]igid galvanized steel conduit shall comply with” two published standards
    related to cable composition (finding 17). To the extent that appellant argues these
    paragraphs are entirely independent of each other, we are unpersuaded. Paragraph
    2.5.1 is a subset of paragraph 2.5 CONDUIT AND DUCTS, and are related. More
    importantly, paragraph 2.5 does not contradict 2.5.1 in any way, nor does it state that it
    is an exhaustive list of work that should be concrete-encased. Its failure to mention
    concrete encasement for conduits does not mean the cable conduits to the runway edge
    lights at issue should not be concrete-encased when traveling under roadways. Here,
    the contract provides in no uncertain terms that “Duct Lines” must be concrete-
    encased, except where specifically provided for in the contract documents.
    (Findings 14-15) Guided by the definitions of duct and conduit, a reasonable
    interpretation of the specifications requires that cables that are to be placed under a
    road or other paving, whether pulled through duct or conduit, are required to be
    concrete-encased. Several Board decisions have deduced that there is no functional
    difference between duct and conduit. See e.g., Amelco, Inc., ASBCA No. 50826, 
    99-2 BCA ¶ 30,549
     at 150,853 (the Board found that the encasement of the secondary cable
    conduit – not shown on the drawings – was nevertheless required when the cables
    were placed under pavement and roads.); Nagy Enterprises, ASBCA No. 48815 et. al.,
    
    98-1 BCA ¶ 29,695
     at 147,198 (“the contract did not provide [appellant] with the
    option to encase or not to encase the electrical conduit buried under the road . . . .
    [T]he contract drawings indicate a “Duct Section B” construction. . . [i]t merely
    indicates two kinds of duct lines for underground electrical distribution . . .”); Chamac,
    Inc. ASBCA No. 44905, 
    94-1 BCA ¶ 26,482
     at 131,816 (Board denied a constructive
    change claim for extra work installing concrete-encased electrical cables under road
    crossings, finding that the “reason for requiring concrete-encased cable crossings
    under the tank trails and other roads subject to tank traffic was to protect the electrical
    cables . . .”) While specifications are not always written with exact clarity, we have
    been unable to find a passage in the specifications that cannot be read harmoniously
    with the interpretation that conduits and ducts are the same entity. We conclude that
    the terms conduit and duct are used interchangeably for contract purposes.
    16
    The reasonableness of the government’s interpretation that the specification
    required concrete encasement where cables were placed under roads, is further
    supported by the drawings (findings 20- 22). We are reminded that the Specifications
    and Drawings for Construction clause, states in relevant part, “[a]nything mentioned in
    the specifications and not shown on the drawings, or shown on the drawings and not
    mentioned in the specifications, shall be of like effect as if shown or mentioned in
    both. In case of a difference between the drawings and specifications, the
    specifications shall govern.” (Finding 9 (quoting 48 C.F.R. 52.236-21(a)). The
    Contract Drawings and Specifications clause, also provides that, “[l]arge-scale
    drawings shall govern small-scale drawings” (finding 10 (quoting 48 C.F.R. 252.236-
    7001(c)(1)). In this hierarchy, the drawings relied upon by appellant identified as
    ES101-114 are the least authoritative as to work to be done when a conflict with other
    provisions arise. ED101-103 are large-scale drawings and take precedence over small-
    scale, and of course the directions in the specifications take precedence over all the
    drawings (finding 20).
    Appellant claims that its interpretation of the specifications and drawings do not
    require concrete encasement around conduit unless specifically identified, as in
    drawing ES105. Munck’s use of ES105 as reflective of the need to identify concrete
    encasement around conduit is misplaced. Drawing ES105 specifically identifies
    conduit to be encased in concrete, but that is because drawing ES105 is a drawing of
    conduit that leads to the Airfield Lighting Vault which does not travel under roads or
    other pavement. (Findings 23-24) If it did travel under roads or other pavement then
    Section 26 56 20 paragraph 3.3.2.3 would control, as would paragraph 3.3.3.3 of
    Section 33 70 02.00 10 which provides for the cable distribution underground.
    Accordingly, the only way the government could require that the conduit be concrete
    encased at that location, was by including the additional requirement on drawing
    ES105. (Findings 14, 16-17, 19)
    Appellant also relies upon Drawings ED101 and ED102 and argues that these
    drawings do not call for concrete encasement in connection with conduit. ED101,
    ED102 and ED103 address the fixtures and electrical details for the runway edge lights
    and contain a reference to “sheet 1 of 3”, “sheet 2 of 3” and “sheet 3 of 3.” In the
    evaluation of the work to be performed under this contract, it appears appellant simply
    ignored drawing ED103. While ED101 and ED102 is limited to the fixtures
    themselves, it also contains conduit couplings attached to the cable between edge
    lights. ED103 provides the electrical detail for the installation of the fixtures and
    provide for “Concrete Encased Duct with 1 Conduit, 2 Conduits and 4 Conduits.” It
    provides a cross-section of construction for singular ducts with variations depending
    on the number of conduits contained within, whether one, two, or four. ED103
    provides unequivocal support for the conclusion that the conduits and ducts are to be
    considered as one, and ED103 instructs that either should be concrete encased where
    designated in the specification. (Findings 20-22) This set of drawings cannot be read
    17
    independent of each other, and contradicts appellant’s interpretation that duct and
    conduit should be considered as different entities.
    We fail to see how the language in this contract supports more than one
    reading. The words in the specification, required that where cables are to be installed
    under roads, railroad tracks, or pavement exceeding five feet in width, they are to be
    protected by concrete whether that cable is placed in duct or conduit. (Findings 14,
    18-19) Accordingly, we find appellant’s interpretation to be unreasonable. However,
    even if we found the contract to be susceptible to more than one reasonable
    interpretation, the context in the specification when considered along with the
    drawings, specifically ED101-103 raised a significant enough question that appellant
    should have discovered it and had a duty to inquire. See Interstate Gen. Gov’t
    Contractors, Inc. v. United States, 
    980 F.2d 1433
    , 1435(Fed. Cir. 1992); Newsom v.
    United States, 
    676 F.2d 647
    , 650 (Ct. Cl. 1982) (an ambiguity is patent if it is “so
    glaring as to raise a duty to inquire”). We conclude that in this instance, any
    inconsistency was so glaring as to impose a duty upon the contractor to inquire prior to
    submitting their bid. Had appellant made an inquiry, as it ultimately did on
    January 13, 2015, any misunderstanding would have been corrected, as it was in the
    communications leading up to the January 13, 2015 meeting, and in the
    communications that followed. (Finding 3)
    The provisions set forth in the specification and the drawings provide enough
    indications that the runway edge light cables buried under roadways or asphalt whether
    placed in duct or conduit should have been encased in concrete as shown on drawing
    ED103. The government’s interpretation gave the proper meaning to the contract
    requirements. Accordingly, the work directed by the Contracting Officer was in
    accordance with the contract requirements. Any ambiguity, if in fact one existed was
    patent, imposing a duty upon appellant to inquire. We conclude Munck was only
    required to perform work that the contract required it to do and cannot recover.
    18
    CONCLUSION
    For the reasons stated above, this appeal is denied.
    Dated: September 21, 2021
    STEPHANIE CATES-HARMAN
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                               I concur
    RICHARD SHACKLEFORD                                    OWEN C. WILSON
    Administrative Judge                                   Administrative Judge
    Acting Chairman                                        Vice Chairman
    Armed Services Board                                   Armed Services Board
    of Contract Appeals                                    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61497, Appeal of Munck
    Asfalt A/S, rendered in conformance with the Board’s Charter.
    Dated: September 22, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    19