BES Construction, LLC ( 2021 )


Menu:
  •                   ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                 )
    )
    BES Construction, LLC                       )    
    ASBCA No. 62175
    )
    Under Contract No. FA4418-12-C-0023         )
    APPEARANCES FOR THE APPELLANT:                   Todd A. Jones, Esq.
    Raleigh, NC
    Edward P. Kendall, Esq.
    Montgomery, AL
    APPEARANCES FOR THE GOVERNMENT:                  Jeffrey P. Hildebrant, Esq.
    Deputy Chief Trial Attorney
    Lawrence M. Anderson, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    Appellant, BES Construction, LLC, seeks additional compensation related to its
    construction of a visitor center at a military base in South Carolina.
    FINDINGS OF FACT
    Much of the following is drawn from the parties’ apparent agreement that certain
    facts are not in dispute (app. br. at 2-8; gov’t br. at 1-12). On September 28, 2012, the
    parties contracted for BES to construct a visitor center at a military base in Goose Creek,
    South Carolina (R4, tab 8 at 1-2). The contract provides that “[t]he Notice to Proceed
    will be issued within 45 days of award,” and that BES “complete the entire work ready
    for use not later than 270 calendar days” (id. at 1). On or around October 2, 2012, the
    government received a bid protest from a disappointed bidder (app. br. ¶ 7; gov’t br. ¶ 7).
    On October 3, 2012, the government directed BES to “[c]ease all work associated with
    the Construct Visitors Center contract” pending the outcome of the protest (see R4,
    tab 10). The award protest was resolved on December 6, 2012 (app. br. ¶ 10; gov’t br.
    ¶ 10). On January 8, 2013 1, the government issued to BES a Notice to Proceed (R4,
    1
    The record reflects that the Notice to Proceed was dated January 8, 2012 (R4, tab 1).
    However, based upon the parties’ recitation of the facts and other documents in the
    record, we conclude that the Notice to Proceed was actually issued on
    January 8, 2013.
    tab 1). On July 12, 2013, BES requested of the government “a contract time extension
    due to excessive rainfall for the Months of February through June” 2013, stating that:
    There was measurable rainfall for 33 days out of 181 calendar
    days for January through June including 22 Days in June with
    a total accumulation that was 7.22 inches (June total) above
    normal as measured at the NOAA site in Goose Creek. We
    are asking for 46 days of calendar days of extension time to
    cover days lost due to weather.
    ...
    According to Weather underground.com (NOAA recording
    Data) there was rainfall from January 1st, 2013 through
    June 30, 2013 of 36.75". The normal rainfall for this same
    period is 21.96". Therefore there was a surplus of 14.79" of
    rain since the project started.
    (R4, tab 13 at 1-2) On August 8, 2013, the parties entered into Modification No. P0001,
    which extended the period of performance “by 70 days due to [the award] protest and a
    20 day PoP extension was given due to extreme inclement weather in the months of Mar,
    Jun, and July,” from August 8, 2013, to November 6, 2013; the modification states that
    “[t]his is a no cost modification,” and that “[a]ll other Terms and Conditions remain
    unchanged” (R4, tab 15).
    On August 22, 2013, BES submitted Submittal 48 related to the storefront
    windows (app. br. ¶ 27; gov’t br. ¶ 27). Submittal 48 was partially approved on
    September 3, 2013; the submittal was disapproved per a handwritten comment stating
    “08 41 13, Must provide PE calcs per 1.3.2 structural” (app. br. ¶ 28; gov’t br. ¶ 28). The
    government omitted or failed to provide the parameters for the calculation in the
    specifications (app. br. ¶ 29; gov’t br. ¶ 29). Fourteen days later, on September 17, 2013,
    BES received the design parameter of 1 psi for the storefront windows from the
    government (app. br. ¶ 30; gov’t br. ¶ 30). Upon receipt of the design parameter for the
    storefront windows, BES resubmitted Submittal 48 as Submittal 48A on September 17,
    2013, and final approval was received on September 18, 2013 (app. br. ¶ 31; gov’t br.
    ¶ 31). Following approval, the subcontractor reapplied to put the storefront windows into
    production which took another seven days (app. br. ¶ 31; gov’t br. ¶ 31).
    During October 2013, the government delayed payment to BES as a result of a
    government shutdown (app. br. ¶ 48; gov’t br. ¶ 48). On November 6, 2013, BES
    received Modification No. P0002 which extended BES’s contract completion date by
    twenty-one days to account for the government shutdown (app. br. ¶ 50; gov’t br. ¶ 50).
    2
    Modification No. P0002 is bilateral, and provides that “[t]his is a no cost modification”
    (R4, tab 21 at 1).
    The scope of work under the contract included “electrical systems” (app. br.
    ¶ 36; gov’t br. ¶ 36). On October 24, 2013, BES submitted Request for Information #43,
    requesting clarification of the specifications related to the primary power supply (app.
    br. ¶ 37; gov’t br. ¶ 37). On October 29, 2013, the contracting officer responded
    indicating that specifications omitted the neutral conductor and incorrectly provided for
    a #4 ground wire where it should have been a #2 ground wire (app. br. ¶ 38; gov’t br.
    ¶ 38). BES provided the neutral conductor and #2 ground wire which were required to
    complete the electrical service under the contract (app. br. ¶ 39; gov’t br. ¶ 39). On
    November 27, 2013, BES notified the contracting officer that it considered the neutral
    conductor and ground wire to constitute a change order (app. br. ¶ 41; gov’t br. ¶ 41).
    The November 27, 2013 notice stated the date, circumstances, and source of the change
    order (app. br. ¶ 42; gov’t br. ¶ 42). BES incurred actual costs in the amount of $1,867
    (including its markups) for the change order (app. br. 43; gov’t br. ¶ 43).
    During performance of the project, BES interpreted specification 2.3.6.1 entitled
    “Field Painting” to require BES to provide and install factory primed, field painted doors
    (app. br. ¶ 45; gov’t br. ¶ 45). The government questioned BES’s interpretation of this
    specification, and extensive discussions ensued pertaining to the required finish for the
    wooden doors on the project (app. br. ¶ 46; gov’t br. ¶ 46).
    On February 20, 2014, BES submitted to the government a “request[] [for]
    authorization to make the following changes in the project: . . . Color change for stucco”
    (R4, tab 12 at 2). On February 28, 2014 2, the contracting officer denied BES’s request
    for such a change order (see app. br. ¶ 57; gov’t br. ¶ 57; R4, tab 12 at 1).
    On May 23, 2019, BES presented to the contracting officer a certified claim
    seeking $623,205.34 in compensation for alleged changes and delays (see app. br. ¶ 58;
    gov’t br. ¶ 58; R4, tab 23 at 1). On June 11, 2019, the contracting officer issued a final
    decision granting BES $1,867 in direct costs (for the neutral conductor and changed
    ground wire), but denying the remainder of BES’s claim (app. br. ¶ 60; gov’t br. ¶ 60).
    The record includes the affidavit of William Walter Bolton, the sole owner,
    member, and operator of BES, who states:
    Available actual cost data (particularly the general conditions
    and certain direct labor costs) divided over the performance
    period for the Contract shows that daily rate of extended
    2
    The correspondence from the contracting officer was erroneously dated
    February 28, 2013 (R4, tab 12 at 1).
    3
    overhead was $967.61 / day. Attached hereto as Exhibit “A”
    is a true and accurate copy of the calculation of extended
    overhead based on the available cost data.
    This number does not account for all direct labor costs for the
    Project, all supervision costs for the Project, any field office
    overhead for the Project, or any allocation for home office
    overhead.
    Accordingly, BES estimates its daily rate of damages for
    Government caused delay exceeds $1,300.00 / day.
    (Bolton aff. ¶¶ 1, 18-20 (emphasis added)) The Exhibit A that Mr. Bolton cites consists
    of a “Breakdown of Daily Overhead Rate” that calculates a “daily rate” of $967.61
    (Bolton aff. at ¶ 18, ex. A at 1).
    The record also includes the affidavit of John Buziak, BES’s delay expert (app. br.
    at 1; Buziak aff.). Mr. Buziak states:
    Had the contract not been protested BES would have started
    demolition and site work in the final quarter of 2012. During
    this period the Charleston area experienced normal rain fall;
    1.06 inches for October, 2.2 inches for November and
    3.56 inches for December. The protest of the award pushes
    this work in to the Spring. This changes the manner in which
    weather is treated in going forward. The delay pushed the
    demolition, site work and shell into a period of exceptionally
    adverse weather. In the spring there were multiple dates
    where rainfall was recorded in a day that matched or
    exceeded a month’s worth of rain in the final quarter of 2012.
    This makes weather impacts compensable, both additional
    effort and extended overhead.
    Going forward from Notice to Proceed weather ways were
    included in the schedule. Exhibit 3 indicates the state of the
    project at ground breaking. By this point BES had recovered
    27 days on the critical path, primarily by accelerating the
    submittal May 13, 2021 process and completing the
    demolition earlier than in the baseline. The adverse weather
    had started in February. But demolition activities are
    typically less impacted by rain. Exhibit 4 shows the state of
    the project where BES has reached a point where the Critical
    4
    Path activities are no longer susceptible to weather delays.
    The negative float at this point compared with state of the
    project at ground breaking indicates the impact of the weather
    on the project was 123 days. The driving factors in the delay
    included the saturated ground preventing the pouring of
    concrete. The contractor took exceptional measures to
    mitigate the effects of the saturated soil including “liming”
    the soil and covering the enclosed area with a heavy duty
    tarp once the trusses were in place. This permitted the
    interior rough in to go forward. In another instance heavy
    rains necessitated the rework of footings in the middle of
    July. A stop work order by a Government representative in
    late June was concurrent with the ongoing weather delay. All
    of the actions taken by BES is reimbursable. In order to
    account for the net affects [sic] of weather and mitigation of
    the delay accomplished by BES we subtract the previously
    identified delay from the total negative float in Exhibit 4.
    This yields a value of 96 days of additional delay attributable
    to the compensable weather impact.
    (Buziak aff., ex. B at 3-4) Nowhere in that report does Mr. Buziak identify store front
    windows, wooden doors, or neutral conductors and ground wires as delay issues (see
    Buziak aff., ex. B).
    DECISION
    1. Changes
    a. Electrical scope change
    The parties agree that BES is entitled to $1,897 for an alleged change to the scope
    of electrical work, plus interest pursuant to the Contract Disputes Act (CDA), 
    41 U.S.C. §§ 7101-7109
    , from May 23, 2019 (app. br. at 9; gov’t br. at 14, 29). We award that
    amount.
    b. Change of color of stucco
    BES requests $6,101.45 in alleged direct costs and $9,100 in alleged delay costs
    for an alleged government change to the color of stucco from buff to ivory (app. br. at 10,
    15-16). However, the government points (gov’t br. at 27) to a February 20, 2014 request
    that BES made of the government for “authorization to make the following changes,”
    specifically, “[c]olor change for stucco.” BES does not address that request. We find
    5
    that BES, not the government, requested the change to the color of stucco. Accordingly,
    BES’s request for additional compensation for a change to the color of stucco is denied.
    2. Delays
    a. Delay in issuing Notice to Proceed after protest of contract award
    BES seeks $110,500 for an alleged 85-day project delay caused by the issuance of
    the notice to proceed only after the resolution of a protest of the award of the contract to
    BES (app. br. at 13). That $1,300 figure appears to consist, at least in part, of extended
    overhead. BES states that “[t]he difference between BES’s claimed daily rate of
    extended overhead ($1,300.00) and the daily rate calculated using available actual cost
    data ($967.61) is $332.39” (app. br. at 11(emphasis in original)). In addition, BES cites
    in support of that $1,300 per day figure the affidavit of Mr. Bolton (app. br. ¶ 64), who
    states (emphasis added):
    Available actual cost data (particularly the general conditions
    and certain direct labor costs) divided over the performance
    period for the Contract shows that daily rate of extended
    overhead was $967.61 / day. Attached hereto as Exhibit “A”
    is a true and accurate copy of the calculation of extended
    overhead based on the available cost data.
    This number does not account for all direct labor costs for the
    Project, all supervision costs for the Project, any field office
    overhead for the Project, or any allocation for home office
    overhead.
    Accordingly, BES estimates its daily rate of damages for
    Government caused delay exceeds $1,300.00 / day.
    (Bolton aff. ¶¶ 18-20) The exhibit A that Mr. Bolton cites consists of a “Breakdown of
    Daily Overhead Rate” that calculates a “daily rate” of $967.61. Where the government
    delays the issuance of a notice to proceed, one of the things the contractor must prove in
    order to recover allegedly unabsorbed overhead is that additional contracts were
    unavailable during the delay when payment for the suspended contract activity would
    have supported such overhead. See Interstate Gen. Gov’t Contractors, Inc. v. West,
    
    12 F.3d 1053
    , 1057 (Fed. Cir. 1993). As the government points out (gov’t br. at 18),
    despite attempting to recover allegedly unabsorbed overhead caused by government
    delay, BES does not address, much less satisfy, that requirement.
    In addition, after awarding the contract on September 28, 2012, the government
    received a bid protest on October 2, 2012, and, the next day, issued to BES a suspension
    6
    of work notice. The award protest was resolved on December 6, 2012, and on January 8,
    2013, the government issued to BES the Notice to Proceed. On August 8, 2013, the
    parties entered into Modification No. P0001, which, among other things, extended the
    period of performance “by 70 days due to [the award] protest,” and recited that the
    modification was “a no-cost modification.” Because Modification No. P0001 is a no cost
    modification, BES is not entitled to any additional compensation for the delay in issuance
    of the Notice to Proceed. See Jimenez, Inc., 
    ASBCA No. 52825
    , 
    01-1 BCA ¶ 31,294
    at 154,502 (citing cases); Loral Corp., Def. Sys. Div.-Akron, 
    ASBCA No. 37627
    , 
    92-1 BCA ¶ 24,661
     at 123,025.
    For these reasons, BES’s request for $110,500 for an alleged 85-day project delay
    caused by the timing of the issuance of the notice to proceed is denied.
    b. Weather
    BES requests $124,800 for an alleged 96-day, weather related, project delay in the
    Spring of 2013 also allegedly caused by the award protest (app. br. at 13-15). BES states:
    Through no fault of BES, as a result of the Award protest,
    BES was required to start demolition and site work in the
    Spring of 2013 instead of the fall of 2012. The rainfall in
    Charleston for the Fall of 2012 (October, November, and
    December) was a total of 6.82 inches. By contrast, in the
    Spring of 2013 there were multiple days where recorded daily
    rainfall exceeded the rainfall for the entire month in the Fall
    of 2012. In fact, the rainfall in the Spring was so heavy it
    saturated the ground such that it was impossible for work to
    proceed even on days when there was no rainfall. For
    instance, because of the sheer magnitude of rain, the ground
    was not dry enough for BES to obtain sufficient compaction
    to pour the concrete slab. This required BES to take
    extraordinary measures to mitigate the effect of the weather,
    particularly the saturated soil, leading to a ninety-six (96)-day
    delay in the Project schedule. The delays would not have
    occurred if the demolition, site work, and the building shell
    would have started in the Fall of 2012 during which the
    weather was more favorable and drier. Because the Award
    Protest, which was the fault of the Government, pushed the
    Project start unto a period of unfavorable weather, the
    weather delay is compensable.
    (App. br. at 13 (emphasis added, internal citations omitted))
    7
    Although BES points to the award protest as the reason it is due additional
    compensation because of rain, the parties signed a bilateral modification, Modification
    No. P0001, which extends the contract completion date by 70 days “for the Award
    Protest,” and recites that Modification No. P0001 is “a no-cost modification” (R4, tab 15
    at 1). Because Modification No. P0001 is a no cost modification, BES is not entitled to
    any additional compensation for having to begin work in Spring 2013, as opposed to Fall
    2012, even if the former turned out to be rainier than the latter. See Jimenez, 
    01-1 BCA ¶ 31,294
     at 154,502; Loral, 
    92-1 BCA ¶ 24,661
     at 123,025.
    Apparently anticipating that conclusion, BES argues in the alternative that “the
    weather encountered by BES is compensable because it was unusually severe”:
    [A]ccording to the [National Oceanic and Atmospheric
    Administration], normal rainfall for Charleston between
    January 1 and June 30, is 21.96 inches. However, between
    January 1 and June 30 of 2013, Charleston received 36.75
    inches of rain. This represents a surplus of 14.79 inches.
    Therefore, the weather in Charleston during BES’s
    performance was unusually severe when compared to prior
    years. Because the weather in Charleston during BES’s
    performance was unusually severe, the weather delay is
    compensable.
    (App. br. at 14 (emphasis added, internal citations and footnote omitted)) Again,
    however, BES ignores that in their no-cost, August 2013, Modification No. P0001, the
    parties agreed to a 20-day extension of the contract completion date “due to extreme
    inclement weather in the months of Mar, Jun, and July,” and that Modification No. P0001
    is a no cost modification. Because Modification No. P0001 is a no cost modification,
    BES is not entitled to any additional compensation for inclement weather (including rain)
    in March or June 2103. See Jimenez, 
    01-1 BCA ¶ 31,294
     at 154,502; Loral, 
    92-1 BCA ¶ 24,661
     at 123,025. And in its briefing, BES makes no effort to identify any of the
    76 allegedly severe weather days “between January 1 and June 30 of 2013” that are not
    covered by the 20-day, weather-related time extension in Modification No. P0001
    (specifically, presumably, days in January, February, April, and May 2013), and for
    which BES currently seeks additional compensation. Consequently, we find that BES
    fails to prove its case with regard to any additional compensation due to unusually severe
    weather in Spring 2013. Cf. GSC Constr., Inc., ASBCA Nos. 59402, 59601, 
    21-1 BCA ¶ 37,751
     at 183,220 (finding that contractor had not proven that damage to panels for
    which the government was responsible delayed the completion date of the project where
    “it is not clear from the testimony if these are the same damaged panels to which
    [contractor] is referring and the record and briefing is inadequate for the Board to sort out
    which panels were damaged by which contractor or event.”); appealed Mar. 23, 2021.
    8
    For these reasons, BES’s request for $124,800 for an alleged 96-day project delay
    caused by rain in the Spring of 2013 is denied.
    c. Government shutdown
    BES requests $27,300 for an alleged 21-day project delay caused by the
    government’s delay in payment to BES arising from the October 2013 shutdown in
    government operations (app. br. at 15). The parties agree that “[d]uring October 2013,
    the Government delayed payment to BES as a result of a Government shutdown,” and
    that “[o]n November 6, 2013, BES received Modification No. P0002 which extended
    BES’s contract completion date by twenty-one (21) days to account for a Government
    shutdown.” However, Modification No. P0002, which is bilateral, provides that “[t]his is
    a no cost modification.” Because Modification No. P0002 is a no cost modification, BES
    is not entitled to any additional compensation for the delay in payment caused by the
    2013 shutdown in government operations. See Jimenez, 
    01-1 BCA ¶ 31,294
     at 154,502;
    Loral, 
    92-1 BCA ¶ 24,661
     at 123,025.
    d. Storefront window, wooden door, and neutral conductor and ground wire
    BES requests (1) $27,300 for an alleged 21-day project delay caused by
    specifications governing storefront windows; (2) $27,300 for an alleged 21-day project
    delay caused by specifications governing wooden doors; and (3) $9,100 for an alleged
    7-day project delay caused by specifications regarding a neutral conductor and a ground
    wire (app. br. at 16-18). BES has the burden here: to prevail on its claims for additional
    costs allegedly incurred because of the late completion of a fixed-price government
    construction contract, a contractor must show that the government’s actions affected
    activities on the critical path, and where the delays of the government and the contractor
    are concurrent, the contractor must establish its delay apart from that attributable to the
    government. BES Constr., LLC, 
    ASBCA No. 60608
    , 
    19-1 BCA ¶ 37,455
     at 181,989.
    BES cites the affidavits of Mr. Bolton and Carol Denise Bradley in support of its
    allegations of such delay to the contract work (app. br. at 5-7, 16-18). However, BES has
    not demonstrated that either of those individuals is a delay expert. In addition, as the
    government points out (gov’t br. at 28-29), nowhere in the report of BES’s delay expert
    are the issues of store front windows, wooden doors, or neutral conductors and ground
    wires identified as delay issues. For these reasons, BES does not demonstrate its
    entitlement to delay damages for these issues. Consequently, its request for
    compensation for those issues is denied.
    9
    CONCLUSION
    We find it unnecessary to address the parties’ other arguments. The appeal is
    sustained with regard to the electrical scope change in the amount of $1,897, plus interest
    pursuant to 
    41 U.S.C. § 7109
     for the period beginning May 23, 2019, until the date of
    payment. The appeal is otherwise denied.
    Dated: November 9, 2021
    TIMOTHY P. MCILMAIL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    RICHARD SHACKLEFORD                                OWEN C. WILSON
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Vice Chairman
    Armed Services Board                               Armed Services Board
    of Contract Appeals                                of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 62175
    , Appeal of BES
    Construction, LLC, rendered in conformance with the Board’s Charter.
    Dated: November 10, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    10
    

Document Info

Docket Number: ASBCA No. 62175

Judges: McIlmail

Filed Date: 11/9/2021

Precedential Status: Precedential

Modified Date: 11/30/2021