Bushra Company ( 2016 )


Menu:
  •               ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                   )
    )
    Bushra Company                                )      
    ASBCA No. 59918
    )
    Under Contract No. M68450-06-M-7233           )
    APPEARANCE FOR THE APPELLANT:                        Mrs. Bushra Mohammed
    Owner
    APPEARANCES FOR THE GOVERNMENT:                      Raymond M. Saunders, Esq.
    Army Chief Trial Attorney
    ChristinaLynn E. McCoy, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE PROUTY ON THE GOVERNMENT'S
    MOTION TO DISMISS FOR LACK OF JURISDICTION
    Before the Board is the government's motion to dismiss for lack of jurisdiction,
    which has two bases: first, the government contends, appellant Bushra Company
    (Bushra) failed to file its appeal with the Board within 90 days of receipt of the
    contracting officer's final decision (COFD) terminating the subject contract for
    default; second, the government argues, Bushra's later claim to the contracting officer
    (CO) was (if timely) jurisdictionally defective because it did not include a sum certain.
    Bushra's response is confined to a defense on the merits of this action, arguing that it
    should not have had its contract terminated because of problems with the contracting
    officer's email. Bushra makes no effort, whatsoever, to address the government's
    challenges to our jurisdiction. The government's arguments prevail.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On 25 September 2006, the government's Joint Contracting Command for Iraq
    and Afghanistan (JCC-1/A) awarded Contract No. M68450-06-M-7233 (the contract) to
    appellant Bushra in the amount of $328,440.00 for the delivery of limestone at various
    sites within Iraq (R4, tab 1 at 2-3). The contract's statement of work anticipated that
    performance would begin within 7 days of the contract award and take no longer than
    30 days to complete (id. at 3). The contract also included a clause from the Department
    of Defense Federal Acquisition Regulation Supplement (DFARS) that provided that all
    correspondence with the government would be conducted in English (id. at DFARS
    252.225-7041, CORRESPONDENCE IN ENGLISH (JUN 1997)).
    2. Bushra never made the deliveries required by the contract (R4, tab 14 at 11
    (Bushra's 2015 "Claim for settlement for limestone contract")). Whether this was the
    fault ofBushra, the government, or neither party is not relevant for resolution of the
    pending motion.
    3. The government terminated Bushra's contract for cause 1 on 18 February
    2007 (R4, tab 4). The termination was received the same day (R4, tab 14 at 15). The
    letter informed Bushra of its "right to appeal [the] determination under the Disputes
    clause cited in [Federal Acquisition Regulation (FAR)] Part 33.211" (R4, tab 4 at 1).
    The letter did not include language required by the FAR explaining the right to appeal
    to the agency board of contract appeals within 90 days (see 
    id.,
     FAR 33.21 l(a)(3)(v)).
    In addition to a letter to Bushra stating so, the government also issued a contract
    modification effecting the termination on the same date (R4, tab 5 at 1).
    4. On 25 June 2012, Bushra sent an email to the Army stating that it had been out of
    Iraq "because of the security situation" and now wished to close out its contracts with the
    United States military (R4, tab 5 at 2). The email requested that the Army inform Bushra
    of the payments made on the contract (id.). The Army apparently responded to Bushra by
    forwarding it a copy of the contract modification terminating it for cause (id. at 1).
    5. Bushra made no attempt to challenge the termination for cause in any manner
    until 5 August 2013, when it sent an email to Army contract closeout personnel
    inquiring about the status of the contract (R4, tab 6). After some back and forth with
    Army personnel, Ms. Joan Wysoske, Chief ofReachback Closeouts for the Army
    Contracting Command, wrote to Bushra that the contract had been terminated for
    Bushra's "failure to perform" and that a copy of the modification was sent to Bushra on
    29 June 2012 2 (R4, tab 10 at 4). Ms. Wysoske also wrote that, "no compensation is
    coming to you" (id. at 3). Bushra responded that its failure to perform was the Army's
    fault (id.).
    6. More email traffic followed, including a statement from Bushra
    on 2 September 2013 that it "want[ ed] compensation equals to our lost money" (R4,
    tab 10 at 2). On 3 September 2013, the Army told Bushra that it needed to submit a
    claim telling the Army, "the exact amount of the money you wish the government to pay
    you and why the government should pay you any compensation" (id.). On 10 September
    2013, Bushra sent to the Army an email with an attachment that it characterized as its
    "claim for settlement" (see 
    id. at 1-2
    ; R4, tab 13 (the apparent attachment)).
    1
    As in the referenced clause in the Federal Acquisition Regulation (FAR),
    FAR 52.212-4(m), the government could use the terms "termination for cause"
    and "termination for default" interchangeably.
    2
    The 29 June 2012 correspondence, itself, is not in any of the files produced in this
    case, though the statement that there was such correspondence is consistent
    with the documents in tab 5 of the Rule 4 file.
    2
    7. The 17-page attachment (Bushra's claim) consisted largely of "screen shots" of
    email between Bushra and various Army personnel discussing performance of the
    contract with a narrative interspersed between the screenshots (see R4, tab 13). We
    construe it to be solely a challenge to the Army's termination for cause, and to constitute
    an effort to recoup money that Bushra lost as a consequence of that termination (R4,
    tab 13 at 15). In general, Bushra argued that its designated point of contact with the
    Army, lLT Todd Lohstreter, was not receiving his emails as a result of a problem on
    lLT Lohstreter's end and that this prevented Bushra from performing (R4, tab 13 at 4).
    On page 15 ofBushra's claim, it stated that it needed to make a settlement for "all the
    cost we spent under this contract" and then referred the reader to its agreement with the
    Boad Almada company for limestone, which it purportedly paid (id. at 15). The
    remaining two pages ofBushra's claim appear to be in Arabic and include some tables
    with numbers in them, but it is not clear what the numbers represent or in what
    denomination they would be if the figures actually are costs (see 
    id. at 16-17
    ).
    8. Ms. Wysoske informed Bushra, on 26 September 2013, that the document
    referred to as Bushra' s claim did not, in fact, constitute a claim because it did not include
    the amount of money requested from the government and, ifthat amount were greater than
    $100,000, it needed to be certified (R4, tab 10 at 1). She also attached a sheet of
    instructions about how to file a claim (id.). On 17 October 2013, Ms. Wysoske, in
    response to a follow-up email from Bushra, informed it that she "reject[ed]" its claim as
    "untimely and unsupported" and added that Bushra never gave her a "dollar amount of the
    claim" (R4, tab 11 ).
    9. There, things laid for a little more than a year, until 28 October 2014, when
    Bushra sent another email to the Army, essentially resubmitting the identical claim,
    dated 10 September 2013, that Ms. Wysoske had earlier "reject[ed]" (R4, tab 13). The
    Army responded on the same date, explaining that it had reviewed the documentation
    provided by Bushra and that "[n]o payment will be made" (R4, tab 12 at 1). On
    5 January 2015, Bushra again sent an email to the Army attaching the same claim and
    requesting a response (R4, tab 14).
    10. On 8 January 2015, CO Thomas Petkunas issued what he characterized as a
    "final decision," rejecting the claim (R4, tab 15 at 1). This "final decision" noted that
    the claim was "untimely and unsupported" and that Bushra never gave a dollar amount
    for the claim (id.). It also noted that the contract had been terminated for cause on
    18 February 2007 and went on to explain Bushra's appeal rights under the Contract
    Disputes Act (id.).
    11. Bushra filed an appeal with the Board on 7 April 2015 - within 90 days of
    the 8 January 2015 letter.
    3
    DECISION
    We do not possess jurisdiction to consider this appeal because Bushra's appeal
    of the CO's decision to terminate the contract for default was presented to us more
    than 90 days after receipt of the final decision terminating the contract for cause.
    The timeliness of appealing a CO' s final decision is a matter of the
    Board's jurisdiction. See 41U.S.C.§7104 (2011) (formerly 41U.S.C.§606);
    Cosmic Construction Co. v. United States, 
    697 F.2d 1389
    , 1390 (Fed. Cir. 1982)
    (requirement that appeal be made within 90 days is jurisdictional).
    By statute, any challenge to a CO's decision must be brought before the Board
    within 90 days of that decision being received by the contractor. 
    41 U.S.C. § 7104
    ;
    Cosmic Constr., 
    697 F.2d at 1390
    ; Decker & Co. v. West, 
    76 F.3d 1573
    , 1578
    (Fed. Cir. 1996) (citing Cosmic Constr., 
    697 F.2d at 1390
    ). In the case of a
    termination for cause, such as the one presented here, receipt of notification of the
    CO's decision to terminate for cause begins the 90-day clock. Placeway Constr. Corp.
    v. United States, 
    920 F.2d 903
    , 906-07 (Fed. Cir. 1990).
    Here, it is undisputed that Bushra was informed of its termination for default more
    than 90 days before its appeal. The first such notification occurred on 18 February 2007,
    when the Army notified Bushra of its termination, and Bushra, in fact, received this
    termination letter the same day (SOF ii 3). Bushra did not file an appeal before 19 May
    2007, the 91 st day after notification of contract termination. At that date, this Board lost
    its jurisdiction to consider Bushra's appeal.
    Although the Army's termination letter failed to include language required by
    the FAR fully explaining its appeal rights, that deficiency, alone, does not prevent the
    letter from triggering the limitation period. The letter did refer Bushra to the proper
    FAR provisions explaining how to appeal the CO's decision (see SOF ii 3), and if
    Bushra does not prove that the letter's failure to more directly set forth the means
    of appeal caused it actual prejudice, it cannot use the deficiency to invalidate the
    decision and vitiate its finality. See Decker & Co., 
    76 F.3d at 1579
     (requiring proof of
    detrimental reliance); see also Mansoor International Development Services,
    
    ASBCA No. 58423
    , 14-1 BCA ii 35,742 at 174,926. Bushra, quite simply, has made
    no allegation that it was misled by the letter (indeed, it made no allegation in defense
    of the government's motion, whatsoever), and thus, the deficient notice of appellate
    rights does not invalidate the termination letter's starting of the appellate clock.
    See Medina Contracting Co., 
    ASBCA No. 53783
    , 02-2 BCA ii 31,979 at 158,020
    (declining to presume prejudice when not alleged by appellant).
    Similarly, Bushra's oblique reference, in its 25 June 2012 email to the
    government, to having been absent from Iraq for a time due to "the security situation"
    there (see SOF ii 4 ), does not change matters. Bushra has not alleged that its absence
    4
    from Iraq (during an unspecified period of time that apparently ended some time prior to
    25 June 2012) in any way prevented it from accessing its email and being aware of its
    termination for cause or that in any way it was hindered from pursuing its appeal rights in
    a timely manner. Moreover, even if "the security situation" provided a full and complete
    factual and legal excuse for Bushra to withhold its appeal until the situation were
    resolved (which it does not), by 25 June 2012, at the latest, Bushra was free enough of
    those concerns to be corresponding with the government about its contract. No
    correspondence beyond the 25 June 2012 inquiry was filed before 24 September 2012,
    the 91 st day. Thus, under no circumstances can the security situation in Iraq justify
    Bushra's failure to file a timely appeal.
    We further note that the government's communication with Bushra in 2013 and
    2014, acceptance of its claim3 and issuance of an apparently superfluous COFD has no
    effect upon our jurisdiction here. To be sure, there are cases in which the
    government's signaling to the parties that it was reconsidering a claim acted to stay the
    running of the appeal period, see, e.g., Guardian Angels Medical Service Dogs, Inc. v.
    United States, 
    809 F.3d 1244
     (Fed. Cir. 2016); Sach Sinha and Associates, Inc.,
    
    ASBCA No. 46916
    , 95-1ii27,499 at 137,040, but there is no evidence in this record
    that reconsideration occurred, nor does Bushra claim that it did. Moreover, it is
    well settled that communications after conclusion of the appeal period "perforce
    could not have had any effect" on the view of the finality of the termination decision
    during the appeal period. Shafi Nasimi Constr. & Logistics Co., 
    ASBCA No. 59916
    ,
    16-1BCAii36,215.
    Thus, we conclude that Bushra did not file a timely notice of appeal.
    CONCLUSION
    For the reasons stated herein, we dismiss 
    ASBCA No. 59918
     for lack of
    jurisdiction.
    Dated: 22 April 2016
    J.~
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    3
    To be clear, the only claim in this case is the government's termination for default.
    5
    I concur                                       I concur
    deM/,/M---
    N. STEMPLER
    Administrative Judge
    ~CKLEFORD
    Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of
    the Armed Services Board of Contract Appeals in 
    ASBCA No. 59918
    , Appeal of
    Bushra Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    6