Raytheon Company ( 2016 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                  )
    )
    Raytheon Company                               )          ASBCA Nos. 57743, 57798, 58280
    )
    Under Contract No. N00024-04-C-6101            )
    APPEARANCES FOR THE APPELLANT:                            Karen L. Manos, Esq.
    John W.F. Chesley, Esq.
    Gibson, Dunn & Crutcher LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                           E. Michael Chiaparas, Esq.
    DCMA Chief Trial Attorney
    Stephen R. Dooley, Esq.
    Senior Trial Attorney
    Alexander M. Healy, Esq.
    Kathleen P. Malone, Esq.
    Trial Attorneys
    Defense Contract Management Agency
    Boston, MA
    OPINION BY ADMINISTRATIVE JUDGE SCOTT
    ON THE PARTIES' MOTIONS TO STRIKE
    In 
    ASBCA No. 57443
    , at issue, Raytheon Company (Raytheon) appealed under
    the Contract Disputes Act, 
    41 U.S.C. §§ 7101-7109
    , from the Defense Contract
    Management Agency's (DCMA's) corporate administrative contracting officer's
    (CACO's) final decision demanding the return of government payments of allegedly
    expressly unallowable costs and assessing penalties and interest against Raytheon for
    including the costs in its corporate incurred cost proposal for 2004 (2004 Corporate
    Proposal). In addition to cost allowability questions, the appeal focuses upon Federal
    Acquisition Regulation (FAR) 42.709-5(c)'s penalty waiver provisions. 1
    1
    In the other captioned appeals, Raytheon was assessed penalties and interest for
    including alleged expressly unallowable costs in the incurred cost proposals of its
    Integrated Defense Systems business segment for 2004 and 2005. It determined
    not to contest the non-waiver of penalties, but it continues to advocate that the
    costs in question are not expressly unallowable and thus not subject to penalties
    (app. pre-hearing br. at 9 n.4).
    The Board held a hearing on entitlement during which appellant moved to strike
    certain testimony by the CACO and related evidence on the ground that they contradicted
    a pre-hearing interrogatory response by the government. The parties briefed the motion
    after the hearing and, at appellant's request, the Board heard oral argument. 2 In its
    response to appellant's motion, the government moved to strike certain materials
    proffered by appellant in support of its motion, described below.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS TO STRIKE
    Appellant's first discovery requests in question, dated 17 February 2012, asked the
    government to produce all documents in connection with its decision to impose penalties
    regarding the costs included in Raytheon's 2004 Corporate Proposal (app. mot., ex. 1 at
    41, Request No. 7). Interrogatories included the following:
    Interrogatory No. 12 asked for the identification of all prior government audits or
    reviews related to Raytheon Corporate' s purported noncompliance with Cost Accounting
    Standard (CAS) 405 (Accounting for Unallowable Costs), from 1 January 2002 through
    1 September 2005 (app. mot. ex. 1 at 16). On 16 May 2012, the government responded:
    The Government is currently aware of the following Audit
    Reports which specifically concern Raytheon Corporate's
    compliance with CAS 405 between January 1, 2002 and
    September 1, 2005: Audit Report No. 2671-2006A19200008
    (dated October 30, 2006); and Audit Report
    No. 2671-2007A19200002 (dated September 24, 2007).
    (App. supp. R4, tab 682 at 33) The government describes the referenced 24 September
    2007 report, which it included in its supplemental Rule 4 file (tab 285), as the "Incentive
    Compensation CAS 405 Audit Report" (gov't opp'n at 23, 25).                             ·
    Interrogatory No. 20 asked:
    a. Do you agree that for the period of January 1, 2004
    through May 31, 2005, Raytheon's corporate finance function
    had appropriate policies and personnel training and an
    internal control and review system that provided assurance
    that unallowable costs subject to penalties were precluded
    2   At the oral argument the Board stated that it would include its decision on the motion to
    strike as part of its post-hearing decision. However, it is now apparent that it will
    be more efficient, and will not delay the Board's post-hearing decision, if the
    Board decides the motion to strike first.
    2
    from being included in its indirect incurred cost rate
    proposals?
    (App. mot., ex. I at 20)
    Interrogatory No. 23 asked:
    a. Explain under what circumstances a contractor may
    include expressly unallowable costs in its final indirect cost
    rate proposals, but obtain a waiver under FAR 42.709-5(c).
    b. State with specificity each and every fact, factor,
    criteria, or other piece of information on which Respondent
    relies in assessing a contractor's request for a waiver under
    FAR 42.709-5(c).
    (App. mot., ex. I at 22) In response to a government objection, by letter dated 15 June
    2012, appellant stated:
    Raytheon clarifies this interrogatory for the Government ....
    [E]xplain why a waiver was not granted to Raytheon under
    FAR 42. 709-5( c) for each cost in dispute in this litigation.
    Raytheon further requests that the Government respond to
    subpar[t] (b ) .. .in full.
    (App. mot., ex. 2 at 15)
    On 16 August 2012, the government responded to appellant's restatement of
    Interrogatory No. 23(a) as follows in relevant part:
    The Government construes Raytheon's revised Interrogatory
    No. 23 to seek information concerning the factors taken into
    account by the relevant contracting officers [COs] when
    considering whether it was appropriate to waive the penalties
    applicable to the Corporate ... CY 2004 Indirect Cost
    Proposa[l]. Our supplemental response identifies factors that
    the [COs] took into account when considering whether waiver
    of the penalties applicable to the CY 2004 Proposa[l] was
    appropriate; it does not necessarily constitute a description of
    the Government's contentions in these appeals or an
    exclusive list of all possible bases that could support the
    3
    determination that Raytheon is not entitled to a waiver of the
    penalties applicable to its CY 2004 Proposa[l].
    (App. supp. R4, tab 690 at 2-3) The government discussed factors that CACO Dowd had
    considered in concluding that Raytheon would not be entitled to a waiver under
    FAR 42.709-S(c), including: "Mr. Dowd considered Raytheon's recurring inclusion of
    these unallowable costs in its proposals as indicative of systematic and continuing
    deficiencies in its internal controls and a lack of proper care" (id. at 6).
    Regarding Interrogatory No. 23(b ), the government stated in relevant part:
    In deciding to assess penalties against Raytheon and in
    consideration of any request for waiver made by Raytheon,
    Mr. Dowd ... relied upon Raytheon Corporate's ... various Final
    Certified Incurred Cost Proposals that included unallowable
    costs, the various DCAA [Defense Contract Audit Agency]
    Audit Reports which determined that Raytheon had included
    unallowable costs in its Proposals, DCAA Audit Reports
    finding that Raytheon's internal controls were deficient in
    some respects, documentation and correspondence
    concerning the negotiation of Raytheon's Certified Incurred
    Cost Proposals ....
    (App. supp. R4, tab 690 at 8)
    On 3 October 2012 appellant deposed CACO Dowd, who testified:
    A. Yes, We have several CAS non-compliances, you
    know, that we are dealing with... So with those things in
    place, like I say, I would have to say we're working those
    non-compliances and inadequate system issues on a fairly
    regular basis.
    Q. And under what circumstances could it be
    inadvertent?
    A. Again, in my mind, I have to take a look at the
    entire situation. Again, we have the system issues, we have a
    number of CAS non-compliances, including a CAS 405
    4
    non-compliance for 2006, so in my mind I couldn't say it was
    inadvertent.
    Q. And do you look at CAS 405-CAS non-
    compliances, generally?
    A. Yes.
    Q. And with regard to expressly unallowable costs, which
    CAS provision would you look at to determine whether there are
    relevant non-compliances in your decision to waive penalties.
    A. I would consider other outstanding CAS 405
    non-compliances ....
    Q. And so for expressly unallowable costs, so you
    would look at CAS 405 non-compliances, correct?
    A. Correct.
    Q. So is it true that any outstanding CAS non-
    compliances would be considered relevant to your decision,
    whether to waive a penalty on an expressly unallowable costs?
    A. Yes.
    Q. And if a contractor had to satisfy you, if in 2004,
    Raytheon sought to satisfy you as to the fact that it deserved a
    penalty waiver, what kind of showing would Raytheon need
    to make?
    A. I don't think they could in 2004, because as we
    said before, we had issues with their systems, as well as we
    had issues with, you know, there was a CAS 405
    5
    non-compliance, and in regard to the 2006 cost and we had
    other CAS non-compliances outstanding as well.
    A. I think if we had all of our systems, you know,
    were adequate, we had squared away all of our CAS
    non-compliances, specifically the CAS 405 non-compliance,
    if all of those had been taken care of, you know, that would,
    you know, lead a long way towards me feeling more likely to
    waive penalties, but again, I would have to consider, you
    know, the specific circumstances, and stuff at the time ....
    (Gov't opp'n, ex. G-1 at 28, 35, 43-44, 229-31)
    CACO Dowd further testified in his deposition, in response to questioning whether
    CAS non-compliances listed in an audit report dated 27 April 2006 were considered in
    his decision not to waive penalties:
    I would have considered the outstanding CAS 405
    non-compliances and issues with CAS that were on the streets
    at the time. I mean that would have been part of my overall
    decision not to waive penalties.
    (Gov't opp'n, ex. G-1 at 239)
    On 4 October 2012 appellant deposed Rodger Christiansen, DCMA Raytheon's
    corporate contract specialist and DCMA's chief negotiator for Raytheon's 2004
    Corporate Proposal, who testified that he had drafted the CO's final decision (COFD) at
    issue (gov't opp'n at 17). He further testified:
    Q. But yet you considered this subsequent CAS 405
    non-compliance?
    A. That's correct.
    Q. And would you say that the subsequent CAS
    405 non-compliance was determinative of your decision to
    impose penalties?
    A. It was one of the factors considered to assess the
    penalty.
    6
    Q. What other factors were considered in assessing
    penalties in 2004?
    A. We also had on the street at the time and another
    CAS 405 on the incentive comp.
    Q. Incentive comp, there were no incentive comp
    issues - by incentive comp you mean what exactly?
    A. Raytheon's incentive compensation plan for
    bonuses and performance bonuses and so forth. I am not
    familiar. I know that there has been some sort of discussions
    on differences and equivalents on other areas, but the
    specifics of that audit report I am not familiar with.
    Q. Were there any other factors?
    A. Not to my knowledge. There could have been. My
    recollection is the principal one was the CAS 405 report.
    Q. So to recap, I asked you for the factors, the
    reasons why you issued penalties in the 2004 case and you
    said there was a CAS 405 non-compliance report for the
    calendar year 2006 year issue that related to some of the
    costs that were included in 2004, for example, the
    recruiting reminder items?
    A. That was one example, yes.
    Q. You mentioned there was another CAS 405
    non-compliance report that was issued related to incentive
    compensation costs?
    A. That's correct.
    (Gov't opp'n, ex. G-2 at 49-52)
    7
    Appellant's second set of discovery requests, dated 12 November 2012, asked for
    all documents, including audit reports, COFDs, CAS noncompliance findings, CAS 405
    noncompliances and DCAA indirect cost/ other direct cost audit reports relied upon by
    DCMA (including Messrs. Dowd or Christiansen) in DCMA's decision to impose
    penalties on Raytheon's 2004 Corporate Proposal (app. mot., ex. 3 at 16, Requests
    Nos. 53, 54). It also asked for all documents reflecting the reasons DCMA imposed
    penalties on the proposal (id. at 18, Request No. 69).
    On 20 February 2013, the government agreed to identify the audit reports
    CACO Dowd had considered in reaching his decision that Raytheon was not entitled to a
    penalty waiver (see app. mot., ex. 5 at 10; app. supp. R4, tab 701at13).
    In its 15 April 2013 third supplemental response to appellant's interrogatories, the
    government stated regarding Interrogatory No. 20(a):
    The Government answers sub-part (a) to this
    interrogatory in the negative. At the time Mr. Dowd issued
    his final decision, there were several DCAA audit reports in
    existence that identified problems in Raytheon's policies,
    personnel training, or internal control and review system
    related to excluding unallowable costs subject to penalty from
    its Corporate proposals. These included the following DCAA
    audit reports: [eight reports listed].
    In addition, Mr. Dowd had recently issued a final
    decision dated January 10, 2011, in which he found that
    Raytheon had included expressly unallowable incentive
    compensation in its Corporate proposals since CY 2002.
    Subsequently, shortly after the May 2011 final decision at issue
    in this case, Mr. Dowd issued another final decision finding
    that Raytheon had included certain expressly unallowable costs
    associated with Raytheon's "Long Term Performance Plan" in
    its Corporate proposals since CY 2004. These expressly
    unallowable costs included "dividend equivalent" payments,
    which Raytheon did not contest. These additional instances of
    Raytheon including expressly unallowable costs in its
    Corporate proposals also indicated that its policies, personnel
    training, and/or internal control and review system related to
    excluding unallowable costs were lacking.
    8
    (App. supp. R4, tab 701at6-7) (Emphasis added) The eight audit reports the government
    listed did not include the two audit reports at issue in appellant's motion to strike.
    The government stated in relevant part regarding Interrogatory No. 23:
    The Government's supplemental response to
    Interrogatory No. 23 is given in accordance with Raytheon's
    restatement of subpart (a), which requests an explanation for
    why Raytheon was not granted a waiver of penalties under
    FAR 42.709-5(c) with respect to the specific costs in dispute
    in ASBCA No[]. 57743 .... The Government construed
    Raytheon's revised Interrogatory No. 23 to seek information
    concerning the factors taken into account by the relevant
    [COs] when considering whether it was appropriate to waive
    the penalties applicable to the Corporate and IDS CY 2004
    Indirect Cost Proposa[l]. Our supplemental responses identify
    factors that the [CO] took into account when considering
    whether waiver of the penalties applicable to the CY 2004
    Proposa[l] was appropriate; they do not necessarily constitute
    a description of the Government's contentions in these appeals
    or an exclusive list of all possible bases that could support the
    determination that Raytheon is not entitled to a waiver of the
    penalties applicable to its CY 2004 Proposa[l].
    (App. supp. R4, tab 701 at 12) The government identified the same eight audit reports it
    had listed in response to Interrogatory No. 20(a). The government does not now dispute
    appellant's contention that they "reported upon alleged events and conditions that
    occurred in 2006 and later," which post-dated the 2004 Corporate Proposal in question
    (app. mot. at 5-6).
    In the government's pre-hearing brief, dated 25 April 2013, over a year before the
    October 2014 hearing, it repeated its response to Interrogatory No. 20(a). It stated that,
    prior to the COFD at issue, Mr. Dowd had recently issued a COFD that Raytheon had
    included expressly unallowable incentive compensation in its Corporate proposals since
    2002 and that, shortly after the COFD at issue, he had issued another COFD finding that
    Raytheon had included expressly unallowable costs in its Corporate proposals since 2004,
    including dividend equivalents payments. (Gov't pre-hearing br. at 76-77)
    The government alleges, without contradiction, that, "since 2004, there have been
    only two CAS 405 noncompliances that resulted in CACO Dowd issuing COFDs against
    Raytheon Corporate," apparently referring to the decisions identified in its response to
    interrogatory No. 20(a) and in its pre-hearing brief (gov't opp'n at 20). It states that these
    9
    CAS 405 final decisions found that "incentive compensation" and "dividend equivalents"
    costs included in Raytheon's yearly incurred cost proposals were "expressly unallowable"
    (id.). The government also asserts, without contradiction, that Raytheon had copies of the
    two audit reports at issue in appellant's motion to strike, which were addressed in the two
    COFDs (gov't opp'n at 4).
    On 6 March 2014 appellant filed a Motion In Limine to Exclude Evidence of
    Alleged Post-Certification Control Deficiencies. It asked the Board "to exclude all
    documents and testimony, from the Rule 4 File and at the hearing, concerning alleged
    control deficiencies at Raytheon post-dating the May 31, 2005 submission of Raytheon's
    [2004 Corporate Proposal]" (gov't opp'n, ex. G-3 at 1). The motion covered 11 audit
    reports, including the Incentive Compensation CAS 405 Audit Report referred to above,
    which is the subject of other appeals currently before the Board (supp. R4, tab 285; gov't
    opp'n at 25, ex. G-3 at 4-5, ex. G-5 at 7). Appellant acknowledged that this audit report
    and two others in the government's supplemental Rule 4 file, which it had inadvertently
    included as part of its motion in limine, concerned 2004 and prior year costs, but it
    advocated excluding them on other grounds. (Gov't opp'n, ex. G-5 at 4 n.2)
    The government's 28 March 2014 response to appellant's motion in limine stated:
    Mr. Dowd also considered other internal control
    deficiencies of which he was aware, including Raytheon's
    inclusion of several other expressly unallowable costs in its
    proposals on a recurring basis. [Citations omitted]
    Curiously, we note that several of the "post-
    certification" CAS noncompliances cited in Raytheon's
    motion and considered by the CACO actually concern
    noncompliances that occurred during and after FY2004,
    including during the period (January - June 2005), when
    Raytheon was preparing its FY2004 incurred cost proposal,
    and were also included in that proposal. For example,
    Mr. Dowd was aware when he determined that a waiver was
    not appropriate that, since at least 2002, Raytheon had been
    including expressly unallowable incentive compensation costs
    for unallowable activity in its proposals. He was also aware
    that, since 2004, Raytheon had been including expressly
    unallowable "dividend equivalent payments[") (see FAR
    31.205-6(i)(2)) in its proposals. Raytheon has accepted
    Mr. Dowd's CAS 405 noncompliance determination and has
    10
    paid the penalties on these dividend equivalent payments, so
    there need be no time-consuming debate about them. There
    are more examples. [Footnote omitted]
    (Gov't resp. at 5, 8) (Emphasis added)
    Appellant replied in support of its motion in limine that CACO Dowd's deposition
    testimony demonstrated with "crystal clarity" that his "refusal to waive penalties was
    premised upon alleged 'CAS non-compliances outstanding' at the time of his 2011
    COFD, in particular a report pertaining to '2006 costs"' (gov't opp'n, ex. G-5 at 3).
    In a teleconference on 29 April 2014, oral argument was held on Raytheon's
    motion in limine to exclude evidence of alleged control deficiencies that occurred after it
    submitted its Corporate 2004 Proposal on 31 May 2005, and on a government motion in
    limine to exclude the evidence of appellant's proffered expert, Darrell Oyer.
    Contemporaneously, appellant kept a record of the oral argument that is essentially
    undisputed in relevant respects (app. reply, ex. 15). During the argument appellant
    specified the documents that its motion was intended to cover, which did not include the
    Incentive Compensation CAS 405 Audit Report and other documents originally included
    by mistake (id. at 8 and see above). Appellant's record states that:
    Judge Melnick [asked] whether Dowd considered any of
    these documents in making his decision not to waive the
    penalties at issue, and [appellant's counsel] responded that he
    did, clarifying that he specifically referenced Tab 292, the
    CAS 405 noncompliance relating to 2006 costs.
    (Id. at 9) Judge Melnick denied both motions (Bd. corr., 1 May 2014 memo. of
    conference call) 3
    On 21 October 2014, at the hearing, CACO Dowd testified in response to a
    question by government counsel as follows in relevant part:
    Q.
    Can you tell me, Mr. Dowd, in considering whether
    Raytheon could satisfy you that the [waiver criteria in FAR
    42.709-5(c)(l)] are met, what factors did you consider?
    A.
    3
    The appeal was reassigned to Judge Cheryl Scott prior to the hearing.
    11
    Secondly, we had two [CAS} 405 noncompliances out
    there that we were addressing, the first one being it was for
    dividend [equivalents}. You know Raytheon conceded that
    and ultimately paid the government...for dividend
    equivalents. I believe it started roughly in the 2006 time
    frame forward and I want to say that it was for the 2004 to
    2006 long-term conformance plan I believe is how Raytheon
    identifies it.
    But anyway, I issued a demand letter to them for those
    dividend equivalents and Raytheon paid them. So, that
    concerned me.
    We have another CAS 405 that issued in the same time
    frame for what I called incentive compensation. It was
    Raytheon pulled out the labor and some fringe costs for this
    unallowable activity that they pulled out of their incurred cost
    submission but they didn't pull out the associated incentive
    compensation associated with that.
    (Tr. 6/252-53) (Emphasis added) At this point appellant moved to strike and oral
    argument ensued.
    At the time of oral argument, while not entirely clear, government counsel
    apparently thought that the Incentive Compensation CAS 405 audit report had been
    among the audit reports listed in the government's supplemental interrogatory responses
    and that only one audit report had been omitted. Counsel believed that it had been
    omitted because there had been no CAS 405 audit report on the dividend equivalents
    issue. Rather a CAS 415 (Accounting for the Cost of Deferred Compensation) audit had
    been "dispositioned" (tr. 6/256, 263), and the government's concerns later evolved into
    the CAS 405 matters addressed in the COFD on dividend equivalents, issued on 2 June
    2011. (See tr. 6/255-57, 263-64; gov't opp'n at 31-32)
    Post-hearing briefing on appellant's motion to strike and the additional oral
    argument ensued. Appellant moves to strike from the hearing record and post-hearing
    briefing: CACO Dowd's hearing testimony at transcript 6/252, line 6, through transcript
    61279, line 3; transcript 7/5, line 4 through transcript 7/48, line 4; ex. A-20 (5 July 2011
    letter from Raytheon to CACO Dowd concerning, inter alia, his COFD on dividend
    equivalents, and proffering payment); appellant's expert Oyer's hearing testimony at
    transcript 10/67, line 4, through transcript 10/78, line 4; and ex. G-3 (the latter COFD).
    12
    The government moves to strike appellant's inclusion of excerpts from otherwise
    sealed materials in a Court of Federal Claims proceeding, unrelated to the instant appeal,
    in which current government counsel were not involved, that include statements by the
    judge concerning the government's attempted submission of an errata sheet to CACO
    Dowd's deposition transcript in that proceeding.
    THE PARTIES' CONTENTIONS
    Appellant notes that, before the hearing, in its ultimate response to interrogatory
    No. 23, the government named the factors considered by CACO Dowd in his decision to
    assess, and not waive, penalties upon Raytheon arising from allegedly expressly
    unallowable costs included in its 2004 Corporate Proposal, submitted on 31 May 2005.
    The response stated that CACO Dowd had considered eight DCAA audit reports.
    Appellant asserts that each of those reports concerns purported "control deficiencies" that
    occurred after 31 May 2005 and were not a relevant consideration for a CO making a
    waiver determination under FAR 42.709-5(c) (app. mot. at 1-2).
    Appellant contends that, after the government learned of its position concerning
    relevance, CACO Dowd changed his factual position, but the government did not notify
    appellant or amend its interrogatory response. Appellant alleges that it was not until
    CACO Dowd was on the witness stand at the hearing that he stated he had relied upon
    two additional audit reports, which involved alleged CAS 405 noncompliances pertaining
    to the dividend equivalents issue, said to date back to 2004 and the incentive
    compensation issue, said to date back to 2002 (app. mot. at 6). Appellant states that the
    dividend equivalents audit report was not produced in discovery (id. at 7).
    Appellant asserts that the government's response to interrogatory No. 23 is a
    "judicial admission" that bars CACO Dowd's allegedly contradictory hearing testimony
    and warrants granting its motion to strike the testimony and exhibits identified above.
    Appellant further contends that, apart from the judicial admissions doctrine, the Board
    should grant its motion to strike as a sanction against the government for its alleged
    failures to supplement its interrogatory No. 23 response and to produce "critical
    documents" pertaining to CACO Dowd's testimony that were responsive to Raytheon's
    discovery requests, apparently referring to the two allegedly "previously undisclosed"
    incentive compensation and dividend equivalents audit reports and the associated COFDs
    (app.mot.at 11,ex. 7(tr. 7/31-32)).
    The government opposes appellant's motion to strike on the ground that appellant
    had prior notice of CACO Dowd' s disputed hearing testimony because: ( 1) the
    government's discovery responses and deposition testimony by Messrs. Dowd and
    Christiansen made it clear that CACO Dowd considered the two CAS 405
    noncompliances in reaching his COFD at issue; (2) the government's failure to list two
    13
    audit reports in its interrogatory response was inadvertent, plus one of them was included
    in the government's supplemental Rule 4 file and appellant already had a copy of both of
    them; (3) CACO Dowd's reliance upon those noncompliances was plainly disclosed in
    the government's pre-hearing brief; and (4) appellant conceded at the oral argument on
    its motion in limine that CACO Dowd had considered the Incentive Compensation CAS
    405 audit report in connection with the COFD at issue and Judge Melnick's denial of that
    motion disposes of appellant's current motion to strike. Appellant disputes this.
    The government also contends that there was no binding judicial admission; even
    if there were a judicial admission, the Board should permit the government to withdraw
    and correct its interrogatory response; sanctions are not warranted; and appellant's
    motion to strike is "'moot" because, in an abuse of discretion review, the Board must
    consider all reasonable bases for the CACO's decision (opp'n at 44).
    DISCUSSION
    We first consider the government's contention that Judge Melnick's denial of
    appellant's motion in limine is dispositive of its current motion to strike because, if it
    were, we need go no further. However, Judge Melnick's succinct order, and essentially
    undisputed portions of appellant's record of the oral argument before him (see app. reply,
    ex. 15 at 8-9), do not lead to the conclusion the government advocates.
    Regarding appellant's claim that the government is bound by judicial admissions,
    there is a distinction between evidentiary admissions and judicial admissions:
    When the term admission is used without any
    qualifying adjective, the customary meaning is an evidentiary
    admission, that is, words in oral or written form or conduct of
    a party or a representative offered in evidence against the
    party. Evidentiary admissions are to be distinguished from
    judicial admissions. Judicial admissions are not evidence at
    all. Rather, they are formal concessions in the pleadings in
    the case or stipulations by a party or its counsel that have the
    effect of withdrawing a fact from issue and dispensing wholly
    with the need for proof of the fact. Thus, the judicial
    admission, unless allowed by the court to be withdrawn, is
    conclusive in the case, whereas the evidentiary admission is
    not conclusive but is always subject to contradiction or
    explanation.
    McCORMICK ON EVIDENCE, vol. 2, § 254 at 142 (4th ed. 1992) (footnotes omitted).
    14
    The United States Court of Appeals for the Federal Circuit recently stated:
    Although this circuit has had limited opportunities to address
    the doctrine, it is clear from other circuits that judicial
    admissions, which "have the effect of withdrawing a fact
    from issue and dispensing wholly with the need for proof of
    the fact," are limited to formal admissions made in, for
    example, a complaint, answer, or pretrial order.
    Reliable Contracting Group, LLC v. Department of Veterans Affairs, 
    779 F.3d 1329
    ,
    1334 (Fed. Cir. 2015) (citations omitted). Other circuits have applied strict prerequisites
    for a finding that a judicial admission has occurred. For example, the First Circuit states:
    Unlike ordinary admissions, which are admissible but
    can be rebutted by other evidence, judicial admissions are
    conclusive on the party making them. Because of their
    binding consequences, judicial admissions generally arise
    only from deliberate voluntary waivers that expressly concede
    for the purposes of trial the truth of an alleged fact. Although
    there is a limited class of situations where, because of the
    highly formalized nature of the context in which the statement
    is made, a judicial admission can arise from the "involuntary"
    act of a party, considerations of fairness dictate that this class
    of "involuntary" admissions be narrow. Similarly,
    considerations of fairness and the policy of encouraging
    judicial admissions require that trial judges be given broad
    discretion to relieve parties from the consequences of judicial
    admission in appropriate cases.
    United States v. Belculfine, 
    527 F.2d 941
    , 944 (1st Cir. 1975) (citations omitted). The
    Third Circuit notes that, "to be binding, judicial admissions must be unequivocal." Glick
    v. White Motor Co., 
    458 F.2d 1287
    , 1291 (3rd Cir. 1972). The Sixth Circuit refers to
    "deliberate waivers of the right to present evidence" and quotes Belculjine in its
    description of judicial admissions. McDonald v. General Motors Corp., 
    110 F.3d 337
    ,
    340 (6th Cir. 1997). The Seventh Circuit refers to a judicial admission as "a clear,
    deliberate and unambiguous concession" and an "intentional waiver." United States v.
    Cunningham, 405 F .3d 497, 504 (7th Cir. 2005); see similarly McCaskill v. SCI
    Management Corp., 
    298 F.3d 677
    , 682 (7th Cir. 2002) (to be sufficient to constitute a
    judicial admission there must be a "deliberate, clear, and unambiguous statement
    evincing an intentional waiver").
    15
    While "[j]udicial admissions can be made at any stage of a litigation," Defoe
    Shipbuilding Co., 
    ASBCA No. 17095
    , 74-1BCAii10,537 at 49,907, the parties disagree
    as to whether interrogatory responses can constitute judicial admissions. The government
    contends, among other things, that they are not formal pleadings and they give rise, at
    most, to an evidentiary admission as to which the responding party is free to introduce
    additional or contrary evidence at trial, citing, e.g., Bradley v. Allstate Insurance Co., 
    620 F.3d 509
    , 527 n.21 (5th Cir. 2010) ("interrogatory responses are not binding judicial
    admissions") (gov't opp'n at 33-35).
    Appellant responds that there is a split in authority as to whether interrogatory
    responses constitute judicial admissions, citing, e.g., Spectrum Sciences and Software,
    Inc. v. United States, 
    98 Fed. Cl. 8
    , 27 (2011) ("a response to a contention interrogatory is
    a judicial admission"), but it alleges that the Board has so treated them (app. reply at 14).
    However, the two Board cases to which appellant cites for this proposition do not support
    it. In Polote Corp., 
    ASBCA No. 31115
    , 86-1 BCA ii 18,640, ajf'd on recon., 1986
    ASBCA LEXIS 802 (12 March 1986), there was no clear discussion of a "judicial"
    admission in an interrogatory response. Rather, the Board, on reconsideration, discussed
    an evidentiary admission by a party-opponent under FED. R. EVID. 801. In Allied
    Materials and Equipment Co., 
    ASBCA No. 17318
    , 75-1BCAii11,150 at 53,067,
    appellant "filed comprehensive pleadings and made extensive requests for admissions
    and interrogatories which have provided the Board with a nearly comprehensive record of
    admitted facts undisputed by the parties." The Board stated that one of the appellant's
    monetary claims was allowed as the result of "Government judicial admissions," 
    id. at 53,085
    , but it appeared to cite to government responses to requests for admissions and to
    the hearing transcript. Regardless, there was no specific finding that interrogatory
    responses were judicial admissions.
    We conclude that, although the government's supplemental response to
    interrogatory No. 23 was inadvertently incomplete, it did not make any binding judicial
    admissions. There were no clear, deliberate and unambiguous concessions and
    intentional waivers of its right to present evidence concerning audit reports or other
    information upon which CACO Dowd is alleged to have relied in his determination not to
    grant penalty waivers to Raytheon. In fact, considering the government's response to
    Interrogatory No. 23 as a whole; its responses to Interrogatories No. 12 and 20(a);
    Messrs. Dowd's and Christiansen's deposition testimony; and the government's
    pre-hearing brief, appellant was on notice prior to the hearing that, in arriving at his
    COFD at issue, CACO Dowd considered alleged CAS 405 noncompliances, including in
    the incentive compensation and dividend equivalents areas, pertinent to time periods prior
    to 2006.
    16
    Moreover, we do not find evidentiary sanctions against the government to be
    warranted. It is up to the Board in its sound discretion to determine what evidence is
    admissible and the weight to be given it. Laguna Construction Co., 
    ASBCA No. 58324
    .
    14-1BCAii35,748 at 174,947 (addressing appellant's motion to strike); Board Rules
    10(c), 11 (d), 13(d). We will consider the omission of the two audit reports from the
    government's response to Interrogatory No. 23, to the extent relevant, in weighing the
    government's evidence.
    In view of our decision, we do not reach the government's arguments that it
    should be allowed to withdraw and correct its response to Interrogatory No. 23 and that
    appellant's motion is '"moot."
    Turning to the government's motion to strike, the excerpts from the unrelated
    Court of Federal Claims proceeding that appellant would have us consider are not
    relevant to our decision on appellant's motion to strike. We grant the government's
    motion.
    DECISION
    We deny appellant's motion to strike and grant the government's motion to strike.
    Dated: 29 March 2016
    inistrative Judge
    :Armed Services Board
    of Contract Appeals
    I concur                                        I concur
    RICHARD SHACKLEFORD
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    17
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 57743, 57798, 58280,
    Appeals of Raytheon Company, rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    18