MOQA-AQYOL JV, LTD. ( 2018 )


Menu:
  •               ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of--                                  )
    )
    MOQA-AQYOL JV, LTD.                          )      
    ASBCA No. 60456
    )
    Under Contract No. W5J9JE-10-C-0031          )
    APPEARANCE FOR THE APPELLANT:                       Thomas J. Fraser, Jr., Esq.
    Eavenson, Fraser, Lunsford & Ivan
    Jacksonville, FL
    APPEARANCES FOR THE GOVERNMENT:                     Thomas J. Warren, Esq.
    Acting Engineer Chief Trial Attorney
    Daniel B. McConnell, Esq.
    Rebecca L. Bockmann, Esq.
    Engineer Trial Attorneys
    U.S. Army Engineer District, Middle East
    Winchester, VA
    OPINION BY ADMINISTRATIVE JUDGE O'CONNELL
    ON APPELLANT'S MOTION FOR RECONSIDERATION
    MOQA-AQYOL JV, LTD. (MOQA) has filed a motion for reconsideration of
    our decision in MOQA-AQYOL JV, LTD., ASBCA Nos. 57963, 60456, 17-1 BCA
    ,i 36,909, in which we denied MOQA's challenge to the default termination and its
    money claim. MOQA's motion concerns only the money claim, 
    ASBCA No. 60456
    .
    DECISION
    The standards for deciding a motion for reconsideration are well established.
    Reconsideration does not provide a party an opportunity to reargue issues that were
    previously raised and decided. Precision Standard, Inc., 
    ASBCA No. 58135
    , 16-1
    BCA ,i 36,504 at 177,860. The movant must establish a compelling reason to modify
    the earlier decision. 
    Id.
     We look to whether the movant presents newly discovered
    evidence, mistakes in findings of fact, or errors of law. 
    Id.
     A motion for
    reconsideration does not provide a litigant a "second bite at the apple" or the
    opportunity to advance arguments that properly should have been presented in an
    earlier proceeding. Dixon v. Shinseki, 
    741 F.3d 1367
    , 1378 (Fed. Cir. 2014).
    While MOQA sought damages in four discrete categories, it challenges our
    determination with respect to only one: $842,587.23 for work performed through the
    date of termination. It does not seek reconsideration of our decision with respect to
    materials and equipment left on site or consulting fees paid to Kevin Cato. (App. mot.
    at 23)
    We conclude that MOQA's motion falls squarely in the "second bite at the
    apple" category: its 30-page motion for reconsideration contains far more facts and
    arguments relating to damages than it presented in its post-hearing brief, which was
    devoted mainly to the termination for default. But there is nothing in MOQA's motion
    that leads us to change our opinion.
    The crux ofMOQA's motion is that it accomplished more work than reflected
    in the amount that it has been paid. As detailed in our opinion, the project was in a
    remote area of Afghanistan and none of the witnesses testifying at the hearing-had
    spent any significant time at the site. MOQA, 
    17-1 BCA 136,909
     at 179,811,
    findings 3, 5. As the party with the burden of proof on its money claim, this presented
    a challenge to MOQA that it could not overcome. None of MOQA's witnesses
    testified as to any specific facts that would allow us to award MOQA more money
    than the Corps paid.
    In calculating the final payment due MOQA, we found that there was internal
    disagreement at the Corps as to whether MOQA had completed 20 or 25% of the work,
    but it went with the higher number. Our opinion detailed the many problems the Corps
    discovered with MOQA's work. See MOQA, 17-1BCA136,909 at 179,828-29. In
    light of these problems, we held that the contracting officer did not abuse his discretion
    in having the replacement contractor remove most of MOQA's work, including the
    foundation for the headquarters building, the perimeter wall and foundation, and the
    guard tower support columns. 
    Id.
     Our conclusion was, and remains, that MOQA was
    paid 25% of the contract price even though it accomplished relatively little. 1 There is
    no basis for the Board to increase the amount paid.
    MOQA contends in its brief that we misunderstood testimony by the Corps
    quality assurance representative, Chester Lawrence. It contends that when he testified
    as to problems with the concrete and rebar it pertained only to MOQA's claim for
    materials left on site, which is a separate issue (app. mot. at 28). MOQA is incorrect
    to the extent it suggests that Mr. Lawrence's testimony supports a higher payment to
    MOQA. To the contrary, it was Mr. Lawrence who concluded that MOQA had
    completed only 20% of the project based on all of the defective work that had to be
    removed. MOQA, 
    17-1 BCA 136,909
     at 179,823, finding 100. Moreover, MOQA is
    also incorrect in contending that Mr. Lawrence was testifying only about materials left
    1
    Thus, although MOQA contends that it is entitled to about $320,000 more because it
    completed all of the work for the compound size modification, we found that
    the largest component of this was the wall around the new perimeter that had to
    be removed. 
    Id. at 179,825
    , findings 114-15.
    2
    on site. The testimony we relied upon for finding 110 concerned the document found
    at Rule 4, tab 419 at 18, which was a photo of the building foundation. He testified:
    Some of this stuff from the pictures that I got show cracks,
    and deformed work, and rebar laying on the ground which
    shows me that it wasn't properly inspected by them. It was
    just put in and thrown in there. And we were going to
    reject that.
    (Tr. 2/58)
    Finally, MOQA also challenges the Corps' reduction of earlier payments for
    mobilization and security payments. MOQA is correct when it observes that
    contracting officer's representative, Theodore Champine, testified inaccurately that the
    contract required MOQA to be paid 60% for mobilization and 40% for demobilization.
    But the evidence in the record does not go much beyond that. Other than a contract
    line item number (CLIN) for Defense Base Act insurance, the contract as awarded
    contained only one CLIN, which was to site adapt the design and build the project
    (CLIN 0001). (R4, tab 7 at 3) There was no mobilization CLIN. The parties
    apparently reached an agreement where they broke down CLIN 0001 into "cost
    loaded" items or "sub-CLINs" (tr. 1/138), but neither party presented evidence as to
    how this was done or what had to be accomplished for MOQA to paid in full for the
    sub-CLINs.
    The parties agree that there was a sub-CLIN for mobilization for $250,000.
    MOQA contends that the entire sum was due on mobilization while the Corps
    contends it was split between mobilization and demobilization. Neither party has
    directed us to a provision in the contract or other documents that supports its position.
    Because MOQA has the burden of proof on its money claim, we hold that MOQA has
    not met its burden on the mobilization issue. Wilner v. United States, 
    24 F.3d 1397
    ,
    1401 (Fed. Cir. 1994) (en bane). The same holds true for MOQA's project security
    issue. The evidence is inadequate for us to award MOQA any money. 2
    2
    MOQA's did not make its arguments concerning mobilization and security payments
    in its post-hearing briefs.
    3
    CONCLUSION
    MOQA's motion is denied.
    Dated: 27 March 2018
    ·m~r(\ J!J'L-OJJ
    M1CfIAELN. O'CONNELL
    Admini~trative Judge
    Armed Services Board
    of Contract Appeals
    I concur
    £)1_---..
    RICHARD SHACKLEFORD                              OWEN C. WILSON
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 60456
    , Appeal of
    MOQA-AQYOL JV, LTD., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 60456

Judges: O'Connell

Filed Date: 3/27/2018

Precedential Status: Precedential

Modified Date: 4/9/2018