Capy Machine Shop, Inc. ( 2014 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Capy Machine Shop, Inc.                       )      
    ASBCA No. 59085
    )
    Under Contract No. SPE4A6-13-M-S227           )
    APPEARANCE FOR THE APPELLANT:                         Mr. Salvatore Capacchione
    President
    APPEARANCES FOR THE GOVERNMENT:                      Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Edward R. Murray, Esq.
    Adrienne D. Bolton, Esq.
    Trial Attorneys
    DLA Aviation
    Richmond, VA
    OPINION BY ADMINISTRATIVE JUDGE TUNKS ON THE GOVERNMENT'S
    MOTION FOR SUMMARY JUDGMENT
    The government moves for summary judgment, alleging that there are no
    material facts in dispute and appellant's alleged default is unexcused. As a result, the
    government asserts that it is entitled to summary judgment as a matter of law.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. On 25 September 2013, Mr. John Vlachos, general manager of Capy,
    accepted Order No. SPE4A6-13-M-S227 in the amount of $37,431.60. 1 The order
    required Capy to supply 27 splice fairings and a first article to the Defense Logistics
    Agency Aviation (DLA Aviation), a field activity of the Defense Logistics Agency.
    (R4, tab 1 at l(A), 2of24) The delivery date for the production quantity was
    18 February 2015 (R4, tab 2 at 2of2). 2
    1
    The order resulted from a Request for Quotations issued by the government on
    16 August 2013 (R4, tabs 3, 4).
    2
    The order required the delivery of a First Article Unit, 30 days after the production
    quantity. This obvious mistake is not alleged to be relevant to this appeal.
    2. The order incorporated FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND
    SERVICE) (APR 1984) by reference (R4, tab 1 at 23of24). The clause provides, in
    part, as follows:
    (a)(l) The Government may, subject to paragraphs
    (c) and (d) of this clause, by written notice of default to the
    Contractor, terminate this contract in whole or in part if the
    Contractor fails to--
    (i) Deliver the supplies or to perform the services
    within the time specified in this contract or any extension;
    (c) Except for defaults of subcontractors at any tier,
    tqe Contractor shall not be liable for any excess costs if the
    failure to perform the contract arises from causes beyond
    the control and without the fault or negligence of the
    Contractor. Examples of such causes include (1) acts of
    God or of the public enemy, (2) acts of the Government in
    either its sovereign or contractual capacity, (3) fires,
    (4) floods, ( 5) epidemics, ( 6) quarantine restrictions,
    (7) strikes, (8) freight embargoes, and (9) unusually severe
    weather. In each instance the failure to perform must be
    beyond the control and without the fault or negligence of
    the Contractor.
    (d) If the failure to perform is caused by the default
    of a subcontractor at any tier, and if the cause of the default
    is beyond the control of both the Contractor and
    subcontractor, and without the fault or negligence of either,
    the Contractor shall not be liable for any excess costs for
    failure to perform, unless the subcontracted supplies or
    services were obtainable from other sources in sufficient
    time for the Contractor to meet the required delivery
    schedule.
    3. On 7 November 2013, Mr. Vlachos emailed Mr. Donnie W. Graves, the
    contracting officer (CO), as follows:
    Please cancel the above contract at no cost to Capy
    Machine.
    2
    Our forming vendor can't locate his tooling[.]
    (R4, tab 6)
    4. On 13 November 2013, CO Graves issued a show cause notice to Capy:
    Because you have indicated in an e-mail dated
    07 NOV 2013 citing an inability to locate tooling on
    contract SPE4A7-13-M-S227 within the time required by
    its terms and thereby requesting termination for
    convenience, the Government is considering terminating
    this contract under the provisions for default. Pending a
    final decision in this matter, it will be necessary to
    determine whether your failure to perform arose from
    causes beyond your control and without your fault or
    negligence. Accordingly, you are given the opportunity to
    present, in writing, any facts bearing on the question to
    me ... within 10 days after receipt of this notice ....
    If you have any questions, please contact
    Len DuPilka, Contract Administrator....
    (R4, tab 7)
    5. On 26 November 2013, Mr. Vlachos emailed Mr. Len J. DuPilka, the
    contract administrator, as follows:
    The cost of new tooling is $19,647.00 total which wasn't
    included on the quote.
    That is the reason for asking to cancel this contract.
    (R4, tab 8)
    6. The record contains a quotation from Banner Metalcraft, Inc., dated
    18 October 2013, 3 which includes a one-time tooling charge of $19,647.00
    (compl., attach.).
    7. On 12 December 2013, Ms. Janice Hicks, the terminating contracting officer
    (TCO), terminated the contract for default, stating as follows:
    3
    The contract having been awarded on 25 September 2013.
    3
    You are hereby notified that contract SPE4A6-13-M-S227
    is terminated for default effective immediately. Your right
    to proceed further with performance of this contract is
    terminated. The termination is based on your failure to
    perform in accordance with the terms and conditions of the
    contract. The terminated supplies may be procured against
    your account and you will be held liable for excess costs.
    (R4, tab 10)
    8. On 19 December 2013, Capy appealed the TCO's final decision to this
    Board where it was docketed as 
    ASBCA No. 59085
    .
    DECISION
    Summary judgment is properly granted only where the moving party has met its
    burden of proving the absence of any genuine issue of material fact and proven that it
    is entitled to judgment as a matter oflaw. Mingus Constructors, Inc. v. United States,
    
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987). In this appeal, the government bears the burden
    of proof to justify the default termination. If the government establishes a prima facie
    case that the termination was justified, the burden shifts to the contractor to
    demonstrate that the default was excusable. Hanley Industries, Inc., 
    ASBCA No. 56584
    , 14-1 BCA if 35,699.
    The government argues that there are no material facts in dispute and that it is
    entitled to summary judgment on the ground of anticipatory repudiation. By email
    dated 7 November 2013, Mr. Vlachos, Capy's general manager, requested CO Graves
    to cancel the contract at no cost because its forming vendor could not find its tooling.
    On 26 November 2013, Mr. Vlachos emailed Mr. DuPilka, the contract administrator,
    again requesting that the government cancel the contract. Capy stated that the reason
    for its request was that the cost of new tooling was $19,647 and that it could not afford
    to perform the contract.
    The government has not demonstrated that Capy repudiated the contract.
    Anticipatory repudiation requires a "positive, definite, unconditional, and
    unequivocal" manifestation on the part of the contractor that he will not perform the
    contract. Cascade Pacific International v. United States, 
    773 F.2d 287
    , 293 (Fed. Cir.
    1985). Capy communicated with the CO twice before the contract was terminated.
    On 7 November 2013, Capy requested a no cost cancellation, stating that its "forming
    vendor can't locate his tooling." On 26 November 2013, Capy advised that the "cost
    of new tooling is $19,647.00 total which wasn't included on the quote. That is the
    4
    reason for asking to cancel this contract." These communications do not reflect a
    positive, definite, unconditional and unequivocal refusal to perform.
    Accordingly, the government's motion for summary judgment is denied.
    Dated: 22 October 2014
    (}/,                              r/
    ~
    ......_ ,/""'11\_....,,/__.?1(.r(c{-;,   'I
    ·1~
    J_    -·,_~-
    ELIZ~ETH      A. TUNKS
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                                I concur
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in 
    ASBCA No. 59085
    , Appeal of Capy
    Machine Shop, Inc., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREYD. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 59085

Judges: Tunks

Filed Date: 10/22/2014

Precedential Status: Precedential

Modified Date: 11/3/2014