Environmental Chemical Corporation ( 2022 )


Menu:
  •                    ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of -                                  )
    )
    Environmental Chemical Corporation            )   ASBCA Nos. 59280, 60760
    )
    Under Contract No. FA8903-06-D-8511           )
    APPEARANCES FOR THE APPELLANT:                     R. Dale Holmes, Esq.
    Cohen Seglias Pallas Greenhall & Furman PC
    Philadelphia, PA
    Michael A. Richard, Esq.
    Obermayer Rebmann Maxwell & Hippel LLP
    Philadelphia, PA
    APPEARANCES FOR THE GOVERNMENT:                    Jeffrey P. Hildebrant, Esq.
    Deputy Chief Trial Attorney
    Lori R. Shapiro, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE THRASHER
    These appeals arise from the installation, removal, and replacement of internal
    wiring while performing a contract to construct two headquarters buildings in
    Afghanistan. Environmental Chemical Company (ECC) asserted two claims: a claim
    for the removal and replacement of the internal wiring in the two buildings (
    ASBCA No. 59280
    ) and a related compensable delay claim (
    ASBCA No. 60607
    ). Both claims
    were appealed, having been denied in their entirety by final decisions of Air Force
    Contract Officers (CO). The Board heard these appeals on the record per Board Rule
    11. Both entitlement and quantum are before us.
    Background: The Record
    The record consists of 566 exhibits or Rule 4 documents 1, filings in response to
    an Order on Proof of Costs, the government’s testimony from four witnesses by sworn
    1
    The government filed several different R4 files, with various titles, during these
    appeals. All references to the government R4 file will refer to the last R4 file
    submitted to the Board on January 5, 2018 and is cited as R4, tab __.
    Additionally, any reference to the R4 supplement filed on March 15, 2021 by
    ECC will be cited as app. supp. R4, tab __.
    affidavits filed with appellants brief 2, and an expert report on ECC’s delay claim. The
    record does not include a government brief, testimony from government witnesses or
    testimony from a government expert witness. The government did not file its initial
    brief and supporting affidavits within the time specified in the Board’s June 28, 2021
    Order, which were due no later than July 2, 2021. This due date was the result of two
    previously unopposed time extensions granted by the Board. The government did not
    file its brief. Instead, on July 3, 2021, the government filed seven supporting
    declarations/affidavits and a Defense Contract Audit Agency (DCAA) Audit Report,
    but not its brief, and requested a one-day extension to file its brief on July 4, 2021 (Bd.
    corr. ltr. dtd. July 3, 2021). The government did not file its brief on July 4th and on
    July 6, 2021 again requested another time extension till July 8, 2021 (Bd. corr. ltr. dtd.
    July 6, 2021).
    On July 6, 2021, appellant responded opposing the government’s requests
    arguing it had been prejudiced by the delay in that the government had gained an
    advantage by the additional time to work on its brief and requesting that we deny
    another extension of time to file its brief and that the government’s filed sworn
    statements/affidavits be rejected (Bd. corr. ltr. dtd. July 6, 2021).
    On July 7, 2021, we denied the government’s request for a time extension and
    ordered the government to show cause why we should not grant appellant’s request
    that we reject the government’s already filed sworn statements/affidavits (Bd. corr.
    Show Cause-Board Order dtd. July 7, 2021). Instead of responding to our order, on
    July 9, 2021 the government withdrew its already filed statements/affidavits and
    waived submittal of briefs stating in its response,
    the government respectfully withdraws its request that the
    statements/affidavits submitted on July 3 be accepted by
    the Board as part of the record. The government’s defense
    to the subject appeals will rely upon the Rule 11 record
    presently before the Board establishing that Appellant has
    failed to satisfy its burden to prove the certified claims
    (Gov’t R4, tabs 37 [ECC’s Removal and Replacement
    claim] and 116 [ECC’s Delay claim]) in the subject
    appeals, including the threshold question of law whether
    there was a constructive change to the contract
    requirements.
    (Bd. corr. ltr. dtd. July 9, 2021)
    2
    These attached witnesses’ sworn statements are entered into evidence and designated
    as: Exhibit 1, Mr. Scott A. Hayward; Exhibit 2, Mr. Dan Turek; Exhibit 3,
    Mr. Ivan Leung; and, Exhibit 4, Mr. Mark Serabian.
    2
    FINDINGS OF FACT
    
    ASBCA No. 59280
    Project Background
    1. The U.S. Air Force awarded Contract No. FA8903-06-D-8511 (the
    Contract), to ECC on April 12, 2006. The Contract was a Multiple Award Task Order
    Contract for Heavy Engineering Repair and Construction. (R4, tab 41) The contract
    delegated contract administration responsibility for providing management control
    over the contract to the Center for Engineering and the Environment (AFCEE) 3 (id.).
    On February 26, 2010, AFCEE awarded Task Order No. 0056 (TO 56) to ECC in the
    amount of $13,900,466, for the design and construction of two Headquarters
    Buildings: Camp Bastion and Brigade HQ Phase I COB Tombstone II (R4, tab 21
    at 2). The project was accepted for beneficial occupancy as of October 12, 2011, and
    $429,906 in liquidated damages were assessed (R4, tabs 486, 39 at 3-4, 487).
    3. Most AFCEE employees were not located in Afghanistan, including the COs
    responsible for administration of TO 56. However, AFCEE did have TO 56
    Contracting Officer Representative (COR) positions in Afghanistan that were
    frequently occupied by U.S. Air Force active duty engineering officers. AFCEE
    contracted out many of its contract administration activities performed on the ground
    in Afghanistan and AECOM Technology Company (AECOM) 4, a construction
    management firm, performed contract oversight responsibilities on TO 56. AECOM
    employees were referred to as Title II employees. (App. br. at ex. 4, aff. of M.
    Serabian ¶ 3-4, 8)
    Relevant Contract Provisions: Electrical Requirements
    4. These appeals involve the question of whether there was a constructive
    change related to installation of and subsequent removal and replacement of the
    internal electrical wiring (cable) 5 in the two buildings under construction. The dispute
    arises out of the parties’ disagreement over whether the wire met the contract
    requirements of the 2008 National Electric Code (NEC), specifically NEC § 110.3. 6
    3
    AFCEE has since been renamed the Air Force Center for Engineering and
    Environment (AFCEC).
    4
    AECOM as of 2015 is now AECOM Engineering Company.
    5
    The terms wiring and cable are often used interchangeably in this context.
    6
    The NEC is a set of standards published by the National Fire Protection Association
    (NFPA) for the safe installation of electrical wiring and equipment. The NEC is
    approved by the American National Standards Institute (ANSI) as ANSI NFPA
    3
    Contract Provisions Requiring Compliance with the NEC
    5. Various contract provisions addressed the applicability of NEC standards to
    the electrical cable to be installed. Relevant here, TO 56, Modification 01 contained
    provisions related to electrical requirements in Appendix A1 (04 January 2010), ¶
    3.1.7, Electrical, ¶ l. This provision requires design and construction of the power
    distribution system consistent with National Electric Code (NEC) and Unified
    Facilities Criteria (UFC) standards (R4, tab 10 at 48). Also, the Statement of
    Requirements, subpart 3.1.7, Distribution, stated that “[a]ll electrical installation shall
    be in accordance with the latest version of NEC and UFC standards.” (R4, tab 15 at
    40) We find that the 2008 version of the NEC was the latest version at time of award.
    6. The contract also included specialized clauses for the Joint Contracting
    Command Iraq/Afghanistan (JCC-I/A), some of which also addressed the standards for
    electrical cable. In particular, JCC-I/A clause 952.225-0013, Contractor Health and
    Safety (FEB 2010), directed contractors to “comply with all National Electrical Code
    (NEC 2008), Specifications as outlined, and MIL Standards and Regulations” (R4, tab
    10 at 207). Although not mandatory, the contract also included JCC-I/A clause
    952.236-0001, Electrical and Structural Building Standards for Construction Projects,
    which required compliance with the NEC and other standards “when it is reasonable to
    do so with available materials,” stating, “[A]s dictated by the Unified Facilities Criteria
    (UFC) the contract shall meet: . . . (2) 2008 National Electrical Code (NEC)” (R4, tab 10
    at 208-09).
    Application of NEC 110.3; ‘Listed’ and ‘Labeled’
    7. This dispute arises from the discrete requirements set out in NEC § 110.3,
    Examination, Identification, Installation, and Use of Equipment, (2008) that provides:
    (A) Examination. In judging equipment, considerations
    such as the following shall be evaluated:
    (1) Suitability for installation and use in conformity
    with the provisions of this Code
    FPN: Suitability of equipment use may be
    identified by a description marked on or provided
    with a product to identify the suitability of the
    product for a specific purpose, environment, or
    70. While the NEC is not itself a U.S. law, its use is commonly mandated by
    state and local law.
    4
    application. Suitability of equipment may be
    evidenced by listing or labeling.
    (R4, tab 60 at 36) (emphasis added in last paragraph) We find that the basic NEC
    110.3 requirements for labeling or marking are not restricted to a label or mark on the
    wire itself but may also be provided with the product.
    Laboratory Listing
    8. NEC 110.3 creates a system by which a contractor may rely upon electrical
    testing laboratories to determine if equipment is suitable for certain purposes. Such
    laboratories “list” equipment that they have tested and determined to be suitable. The
    NEC provides that “if the equipment has been listed by a qualified electrical testing
    laboratory,” then “factory-installed internal wiring . . . need not be inspected at the
    time of installation.” (R4, tab 47 at 1) In other words, one may rely upon that listing
    to conclude that the internal wiring and construction of the equipment is suitable for
    certain purposes and need not be additionally inspected at the time of installation
    (other than to verify that the equipment was not damaged or altered).
    9. The NEC defines “Listed” as a material included on a list published by an
    organization concerned with the evaluation of products that maintain periodic
    inspection of production of listed materials and that the listed product meets
    appropriate designated standards, or has been tested and found suitable for a specified
    purpose (R4, tab 60 at 32). An example is Underwriters Laboratories (UL) that is the
    United States organization that typically lists products it has evaluated (app. br. at ex.
    2, aff. of D. Turek 7 ¶ 20).
    Product Labeled
    10. Equipment manufacturers may choose to “Label” their products to indicate
    that a component has been listed by a testing laboratory. A label “indicates compliance
    with appropriate standards or performance in a specified manner.” (R4, tab 46 at 1)
    The NEC defines “Labeled” as material “to which has been attached a label, symbol, or
    other identifying mark of an organization that is acceptable to the authority having
    7
    Mr. Turek testified he has over thirty years of experience working for both
    government and the construction industry. From 2003-2008, Mr. Turek was an
    AFCEE senior division chief in San Antonio, Texas where he led the AFCEE
    Iraq and Afghanistan reconstruction programs from 2005-2007 and was
    intimately familiar with the technical content of the TOs and what AFCEE
    required of its contractors. He left AFCEE in 2008 to again work in the private
    sector. Since 2013 he has held various positions within ECC related to
    oversight of construction projects. (App. br. at ex. 2, aff. of D. Turek ¶ 2)
    5
    jurisdiction and concerned with product evaluation, that maintains periodic inspection
    of production of labeled equipment or materials.” (R4, tab 60 at 32) We find that
    Labeling is not restricted to a stamp on the wire itself. Labeling for United States
    products is done by Underwriters laboratory (UL) 8; a marking of “CE” denotes labeling
    by a European Union laboratory 9; and a “TSE” label denotes products tested by the
    Turkish Standards Institute 10. (App. br. at ex. 2, aff. of D. Turek ¶¶ 18, 20)
    Implementation of NEC Requirements in the Field
    11. The NEC did not designate the testing laboratories that were qualified to
    perform tests for every project. Rather, it stated that the “authority having
    jurisdiction” (AHJ) would determine the testing laboratories from which it would
    accept listings (R4, tab 46 at 1). An AHJ is “[a]n organization, office, or individual
    responsible for enforcing the requirements of a code or standard, or for approving
    equipment, materials, an installation, or a procedure.” The NEC cautions that the AHJ
    is defined “in a broad manner,” and that an AHJ may be a “federal, state, local or other
    regional department or individual,” or it may be “the property owner . . . commanding
    officer or departmental official” (R4, tab 60 at 28).
    Task Force Power - AHJ in Afghanistan
    12. During the 2003-2009 time frame 18 military personnel died as a result of
    electrical mishaps in Iraq. These tragic deaths necessarily raised concerns by the
    8
    Underwriters Laboratories (UL) listing involves a process where an independent
    laboratory in the United States, UL tests and then “lists” products that pass the
    UL testing process. UL listed products typically have a marking or labelling on
    the product designating the UL listing. (R4, tab 60 at 32; app. br. at ex. 2, aff.
    of D.Turek ¶ 20)
    9
    Under a process established by the European Union, products are tested and then
    certified with a Conformitée Européenne (CE) marking indicating that the
    product has been assessed by the manufacturer and deemed to meet EU safety,
    health, and environmental protection requirements. The product’s manufacturer
    bears sole responsibility for declaring conformity with all requirements before
    affixing the CE mark to its product. (App. br. at ex. 1, aff. of S. Hayward ¶ 28)
    10
    In Turkey, third-party certification is done by a nationally established institute, e.g.,
    the Turkish Standards Institute (“TSE”), which provides certification of Turkish
    products. When products meet the requirements of the TSE, the TSE label is
    provided on that product, either through a label on the packaging, or in other
    instances, TSE is stamped on the actual product. (R4, tab 76 at 7, 9, 11; app. br.
    at ex. 2, aff. of D. Turek ¶¶ 18, 20, 21; app. br. at ex. 1, aff. of S. Hayward,
    ¶¶ 11-14) TSE is also member of the International Electro Technical
    Commission (IEC) (app. supp. R4, tab 30).
    6
    relatives of the deceased and eventually Congress called for an investigation and
    answers for why these tragic deaths occurred and what fixes were necessary. The DoD
    Inspector General conducted an investigation from August 2008 –March 2009 on the
    deaths in Iraq (R4, tab 162 at 8), as well as another Report which was issued July 24,
    2009 regarding an Assessment of Electrical Safety in Afghanistan. The Afghanistan
    report identified numerous problems with electrical safety in the Afghanistan theatre
    and made recommendations to address those problems (R4 tab 161 at 5, Report
    No. SPO-2009-005).
    13. In October of 2008 Task Force Protecting Our Warfighters and Electrical
    Resources (T F Power) was established by Combined Joint Task Force – 101 (CJTF-
    101) to “prevent the loss of life and government property through immediate and long-
    term measures that will significantly reduce the number of electrical and fire incidents
    throughout the combined/joint operations area.” (R4, tab 161 at 18) Thereafter, on
    August 3, 2010, T F Power was appointed the Authority Having Jurisdiction (AHJ)
    over electrical codes for all US Military Bases in the Islamic Republic of Afghanistan.
    Relevant to this appeal, T F Power became the authority to promulgate rules for
    implementing NEC 110.3 in Afghanistan. (App. supp. R4, tab 4 at 4, 14) By August
    3, 2010 its policy for electrical components in Afghanistan, required:
    Marking, Listing, Labeling
    All electrical components shall have either credentials:
    1. The CE marking certifies that a product has met EU
    consumer safety, health or environmental requirements.
    2. Listed / labeled and display the marking of a Nationally
    Recognized Testing Laboratory (NRTL) such as
    Underwriters Laboratory (UL).
    3. Items or electrical equipment without marking / listing /
    labeling shall not be used.
    4. Testing Laboratories within IRoA that are without
    National Recognition may submit credentials to the AHJ
    for review and consideration.
    5. Electrical equipment may be field tested to a recognized
    and commonly applicable performance and safety
    standard. Testing methods as well as the credentials of the
    7
    testing service must be submitted to the AHJ for review
    and consideration. 11
    (App. br. at ex. 1, aff. of S. Hayward 12 ¶ 27; app. supp. R4, tab 4 at 6) T F Power
    recognized two types of credentials: the CE marking (European Union marking) or
    Listed / labeled and displaying the marking of a Nationally Recognized Testing
    Laboratory (NRTL) such as Underwriters Laboratory (UL). Of note, this policy still
    did not restrict listing to a particular laboratory but instead retained the term
    “Nationally Recognized Testing Laboratory”. (Id.) However, on September 16, 2010,
    United States Armed Forces – Afghanistan (USFOR-A) issued an Electrical Policy:
    Laboratory Symbol Guide that restricted the definition of a qualifying NRTL to certain
    specified laboratories:
    USFOR-A ELECTRICAL POLICY: LABORATORY
    SYMBOL GUIDE . . . .
    The accepted laboratories as of 16 Sep 10 with the
    following limitations:
    1. All electrical products shall be In(sic)
    accordance with USFOR-A Electrical Policy.
    2. Items or electrical equipment without marking /
    listing / labeling or not meeting the product standard
    shall not be used.
    3. The symbol on the device is not enough. It is the
    purchaser’s responsibility to make certain:
    a. The laboratory is fully accredited for the
    location of test, product tested and test
    applied. Refer to the following for additional
    information:
    11
    TO 56 also references UFC 3-501-01, Electrical Engineering, providing that
    “Underwriters Laboratories (UL) or third-party certification is required for all
    basic equipment.” (R4, tab 164 at 65, ¶ 2-1)
    12
    Between September 2009 and December 2012, Mr. Hayward was ECC Senior
    Program manager for Northern Afghanistan, headquartered in Kabul. He
    managed the AFCEE and USACE projects, which were primarily located in
    Northern Afghanistan but also managed some projects in Southern Afghanistan
    and often conferred with ECC program managers for Southern projects
    regarding common issues. (App. br. at ex. 1, aff. of S. Hayward ¶ 5)
    8
    i. The Laboratory website as listed
    below.
    ii. For United Stated[sic] the
    Nationally Recognized Testing Labs
    (NTRL) as listed by the US
    Department of Labor OSHA
    www.osha.gov
    iii. For the European Union as listed
    by website below.
    (R4, tab 166 at 1) The record includes a copy of the specified CE mark qualified
    NRTLs but does not include the United States list on the OSHA website during this
    time period. 13
    14. TO 56 restricts mandatory regulatory updates to the date the TO was
    awarded, February 26, 2010. The contract statement of work at Attachment 1 (January
    2010) at § 2.0 provides:
    The Contractor shall identify, comply with and ensure that
    its personnel and its subcontractors and subcontractor
    personnel at all tiers obey all applicable federal, state, and
    local statutes; DoD/Air Force/host nation instructions,
    manuals, handbooks, regulations, guidance, and policy
    letters, International Building Code (IBC), Unified Facility
    Criteria (UFC), National Fire Protection Association
    (NFPA), National Electrical Code (NEC); Afghanistan
    federal, provincial, and local Statutes; ARCENT and Air
    Force/Army/Afghanistan Instructions, Manuals,
    Handbooks, Regulations, Guidance, and Policy Letters;
    Executive Orders (EOs), Afghanistan Construction
    Standards, Central Command orders and directives
    applicable to personnel in Afghanistan, including but not
    limited to USCENTCOM, North Atlantic Treaty
    Organization (NATO), International Security Assistance
    Force (ISAF) fragmentary orders, instructions and
    directives; and include all changes and amendments in
    effect on the date of issuance of this TO unless specific
    13
    We attempted to independently search for the specific 2010 U.S. laboratories but
    were unable to find the list.
    9
    relief is sought by the Contractor in writing and granted by
    the Contracting Officer (CO).
    (R4, tab 10 at 19-20 § 2.0) (emphasis added) T F Power’s promulgations of regulatory
    implementation of NEC 110.3 were never incorporated contractually into TO 56’s
    requirements. There were only three modifications to TO 56, none of which changed
    the implementation of NEC 110.3 at time of award. The first modification, effective
    June 7, 2010, incorporated some changes to the statement of work but there was no
    change to the above language at § 2.0. (R4, tab 15 at 11) Modification 2 did not
    involve the statement of work and was effective on November 30, 2010 (R4, tab 21
    at 1). Modification 3 was effective on November 28, 2011 but also did not make any
    changes to the above language at § 2.0. (R4, tab 27 at 1)
    Inspection and Approval Requirements
    15. TO Attachment 3 (Statement of Work Appendix A1, Statement of
    Requirements), Paragraph 4.0 Submittals, required submission of all materials and
    equipment to the Title II inspector (inspector) and COR for review and acceptance
    (R4, tab 10 at 51-52). Additionally, this section directs that, “[T]he Contractor shall
    submit the following to COR and Title II for review and approval: . . . Equipment,
    Fixture, Finishing, and Hardware Submittals: The Contractor shall submit equipment,
    fixture, finishing, and hardware submittals to the COR and Title II to review and
    approve or disapprove within seven business days.” (Id. at 52).
    16. Requests for approval of equipment and materials were usually
    accomplished by submittal of a Material Approval Submittal form that identified the
    relevant specification reference in the TO, a description of the material, and any
    supporting documents such as photos, etc. to the submittal register (see, e.g., R4, tab
    39 at 32-33). The submittal register list is 40 pages long, includes many items such as
    electrical equipment, and is very detailed. Although TO 56, Attachment 23 (Appendix
    C4, Submittal Register), indicates that all material construction submittals are to be
    submitted for government approval, it does not specifically list electrical wiring (app.
    br. at ex. 1, aff. of S. Hayward ¶ 20; R4, tab 10 at 149-50 § 26 20 00).
    17. TO 56 also included Paragraph 5, Section E, Inspection and Acceptance,
    which provided that inspections and acceptance (including the pre-final) would be
    performed by the COR in accordance with: FEDERAL ACQUISITION
    REGULATION (FAR) 52.246-01, CONTRACTOR INSPECTION REQUIREMENTS
    (APR 1984), FAR 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996) and
    PKV-E001, ISPECTION OF CONTSTRUCTION (AUG1996) (Deviation)
    (MAR2003) (R4, tab 10 at 3-4).
    10
    18. TO 56 SORS paragraph 8.0 states that “[t]he quality of all materials used
    on site will be verified by the Title II inspector and a recommendation to accept or
    reject the materials will be transmitted to the CO or COR. The CO or COR will be the
    final decision authority. Recommended criteria for the Contractor to follow include
    any recognized and current UFC standards.” (R4, Tab 10 ¶ 8 at 60) (emphasis added).
    ECC Use of Vatan Electrical Wire - COR Approval
    19. ECC decided to use a wire manufactured by a Turkish company, Vatan.
    Mr. Hayward testified that the use of Vatan wire was prevalent on projects in
    Afghanistan and that ECC previously submitted Vatan wire on both AFCEE and
    United States Army Corps of Engineers (USACE) task orders and contracts, including
    task orders under this contract. (App. br. at ex. 1, aff. of S Hayward ¶ 44) Mr. Turek
    also testified that “Vatan wire and cable was widely used and approved at Camp
    Bastion/Leatherneck on other AFCEE task order/contracts and was listed on an
    AFCEE ’pre-approval’ list of materials for this contract” (app. br. at ex. 2, aff. of D.
    Turek ¶ 20).
    20. AFCEE published a Recommended Materials List Afghanistan, in 2008
    and an updated list in February 2010. Both these lists recommended Vatan wires,
    among others, as pre-approved for AFCEE projects. Although there were Vatan
    electrical cables listed on theses pre-approved lists, the specific cable ECC proposed,
    TS 9758, was not one of the pre-approved cables. (R4, tab 76 at 35; app. supp. R4, tab
    13 at 1)
    ECC Seeks Guidance from the CO
    21. Before ECC submitted its interior wiring for approval in early September
    2010, some of their other electrical submittals were rejected by the Title II inspectors
    and CORs for not being listed/labeled. ECC argued that such rejections were contrary
    to the requirement of the contract; specifically that not all electrical materials were
    required to be listed/labeled. This issue continued back and forth until ECC forwarded
    a letter to the CO (Toscano) on September 22, 2010, requesting interpretation of the
    contract requirements regarding the listing and labeling of electrical equipment (R4, tab
    343 at 3-6). On September 29, 2010, CO (Toscano) responded that the contract
    required ECC to:
    provide electrical materials that are listed /labeled by either
    Underwriters Laboratory (where specified) or other third
    party testing certification laboratories for all basic
    electrical equipment. . . . . After reviewing ECC’s request
    for interpretation I believe this to be a material
    procurement issue and believe it is within the scope of the
    11
    contract for ECC to provide electrical materials that are
    listed/labeled.
    (R4, tab 374 at 2)
    22. AECOM’s daily Title II report of November 11, 2010 notes an ECC
    deficiency stating under significant events, “[m]aterials being used for installation of
    interior wiring which do not meet project specifications.” And references specification
    “Division 26 Section 26 20 00 Part 2 Product.” (App. supp. R4, tab 12) Although
    electrical wiring is not listed on the Contract Submittal Register, the specification cited
    refers to the Contract Submittal Register for electrical items (R4, tab 10 at 149-50).
    That same day, the new COR (Cpt. Jorge Lopez) sent an email to ECC (Greg Ross and
    Roger Stokes) and copied ECOM personnel (Mark Serabian and Ray Gillette) stating
    he understood that ECC was already pulling 14 electric cable that was not UL or third
    party listed. Additionally, he stated:
    I believe we have gone through this path before. My
    understanding is that electrical material requirements calls
    [sic] for materials to be listed by third party certification
    agency (or UL). This has been communicated several
    times including from the CO. Materials not meeting these
    requirement [sic] will be deemed deficient and should be
    requested to be removed from site.
    (R4, tab 350 at 2)
    23. An on-site meeting was held the next day, November 12, 2010, between
    ECC management, QC representatives, and the COR (Cpt. Lopez). (App. br. at ex. 4,
    aff. of M. Serabian ¶ 11) 15 Although Mr. Serabian now works for ECC, in November
    2010, he was employed in Southern Afghanistan by AECOM, an AFCEE support
    contractor responsible for performing Title II inspections (id. at ¶ 4). Mr. Serabian
    testified that Ray Gillette was the AECOM employee assigned full-time as the Title II
    QA manager for TO 56 but on or about November 12, 2010, Ray Gillette was out of
    the country of Afghanistan on R & R, and he was assigned to fill in for Mr. Gillette on
    the date of the meeting (id. at ¶¶ 9-10). Mr. Serabian also testified that one of the
    14
    The term “pulling wire” is an industry term for installing the wire.
    15
    Mr. Serabian is currently an ECC employee. In 2010, he was an AECOM employee
    responsible for oversight of AFCEE contracts in Southern Afghanistan. Part of
    his duties during November 2010, included performing Title II duties services
    for AFCEE’s various construction projects being performed in the region,
    including TO 56 located at Camp Bastion. (App. br. at ex. 4, aff. of M.
    Serabian ¶¶ 1, 3-5)
    12
    topics discussed was approval of ECC’s intended interior electrical wire cable for the
    TO 56 project (id. ¶ 12; app supp. R4, tab 12).
    24. ECC did not submit their proposed internal wire through the formal
    submittal process but instead presented a sample of the wire to the COR during the
    meeting. The cable proposed for approval was manufactured by a Turkish company,
    Vatan. (App. br. at ex. 4, aff. of M. Serabian ¶ 13; app. supp. R4, tab 27). During the
    meeting, ECC asserted that Vatan was listed on the AFCEE pre-approve list. COR
    Lopez examined the Vatan electrical cable and informed ECC that the Vatan electrical
    cable was acceptable for them to use on the project (app. supp. R4, tabs 12, 27; app.
    br. at ex. 4, aff. of M. Serabian ¶ 14). 16
    25. Later that evening, the COR sent an email to Mr. Albert Kellner (AFCEE)
    concerning their previous discussion about ECC’s wire deficiency informing him that
    the issue had been fixed and the “subject electrical wire is third party listed.”
    Additionally, in that same email, the COR also addressed the issue of ECC not
    submitting the wire through the contract submittal process. COR Lopez in discussing
    approval of the wire stated “the issue was not having the proper data sheet on site
    when our QA asked for it . . . . For some reason wiring was not required to be a
    submittal according to specifications for this project. I believe that this was an
    oversight in our documentation.” (R4, tab 350 at 1) We find that ECC was required to
    submit their proposed wire to the Title II inspector and COR for approval but was not
    required to submit a formal submittal request.
    26. COR Lopez’s acceptance of the Vatan electrical wire was also documented
    in the daily Title II report that same day prepared by AECOM’s representative
    Sanjay Kumar. The entry on that date noted, “Meeting between AFCEE, Title II and
    ECC QCM held to discuss materials being used for installation of interior wiring which
    do not meet project specifications. Materials were accepted by COR.” (App. supp. R4,
    tab 12; app. br. ex.4, aff. of M. Serabian ¶ 15)
    27. Likewise, later on December 16, 2010, the COR again confirmed his
    decision to approve the Vatan electric cable via email. COR Lopez stated to the
    ECC’s Project Manager at the time, Greg Ross, “So these are the same cables we
    discussed on site that other time… If so I already closed that chapter. On site it was
    shown it was third party listed.” (App. supp. R4, tab 27) Further, the government
    confirmed the Vatan electrical cable was CE marked. In response to a question from
    AECOM, Wayne McDermott, contacted Vatan directly asking if the wire ECC was
    installing met the requirements to receive the CE mark. A Vatan representative confirmed
    16
    Although Mr. Serabian was the acting Title II inspector during this meeting due to
    Mr. Gillette’s absence, there is no record or testimony from Mr. Serabian as to
    his advice to the COR, if any, during this meeting.
    13
    on December 22, 2010 that, in addition to the TSE marking on its wire, its wire also
    qualified for a CE marking. (App. br. at ex. 1, aff. of S. Hayward ¶ 40; R4, tab 22.)
    28. Thereafter, via email on December 23, 2010, ECC Project Manager Greg
    Ross confirmed to COR Lopez that the Vatan electrical cable was also CE compliant.
    The email provided catalogue data on Vatan wire and cables, including the interior
    wire being installed inside buildings. That wire was PVC insulated non-sheathed
    single core cables with copper conductor HO7V-U, 450/750 V, TS 9758, HD 21.3,
    S3/VDE 0281. The data sheet for that wire included ISO, , TSE, and CE
    marks. (App. br. at ex. 1, aff. of S. Hayward ¶¶ 28, 39; R4, tab 361) In response to the
    December 23rd Ross email, AECOM Wayne McDermott stated on December 23, 2010
    “Got your message. I sent an e-mail to Vatan yesterday evening. See attached.
    Concur that the wiring should meet spec, but notice in the reply that it says ‘with CE
    Marking.’” (App. br. at ex. 1, aff. of S. Hayward ¶ 41; R4, tabs 360; 361 at 4)
    29. We find that COR Lopez and AECOM representative Mr. McDermott
    conducted their due diligence and found that ECC’s proposed Vatan cable was listed
    by a Nationally Recognized Testing Laboratory (NRTL) TSE (i.e. “third party listed”)
    and CE compliant. We also find that COR Lopez had authority under the contract to
    approve ECC’s proposed Vatan wiring and did so.
    ECC Orders Wire and Proceeds to Install
    30. After the COR’s approval on November 12, 2010, ECC proceeded to order
    the electrical cable from Vatan, and obtained delivery to the project site at Camp
    Bastion, in southern Afghanistan. Upon receiving delivery of the Vatan electrical
    cable, ECC commenced installation of the electrical cable on the project. (App. br.
    at ex. 2, aff. of D. Turek ¶ 7) Mr. Turek testified that according to project records,
    installation started on December 3, 2010 and continued through April of 2011 (app.
    supp. R4, tab 26 at 970; app. br. at ex. 1, aff. D. Turek ¶ 7).
    AECOM Continues to Question the Use of Vatan Wire
    Task Force Power Report
    31. After the November 12, 2010 approval by the COR, ECC continued to
    install the wiring on the project but had to respond to various inquiries from AECOM
    representatives and AFCEE contracting officials about the Vatan electrical cable being
    installed (app. br.at ex. 2, aff. of D. Turek ¶ 8). Perhaps one of the most important
    events was when T F Power inspected the electrical aspect of the project and issued a
    report on January 29, 2011 (R4, tab 365 at 1). Among the nine other cited
    deficiencies, it found that the Vatan interior wire ECC had installed, (4 mm2, HO7V-U,
    TS 9758) was “not recognizable as labeled and listed per NEC 110.3.” (Id. at 1, item 6).
    14
    Each finding (deficiency) was accompanied by a photo. Although difficult to discern some
    details, the initial photo shows Vatan wire cable packaging captioned with “Wire type is not
    recognizable as labelled and listed per NEC 110.3” (id.). There is also an enlarged
    version of the same photo included in the report that clearly shows the packaging is
    Vatan manufactured, it is the cable (wire) installed by ECC, TS 9758, dated
    01/29/2011, and displays TSE markings on the packaging (R4, tab 365 at 3). Although the
    wire packaging clearly displays the TSE symbol, it does not display the CE mark.
    Additionally, there is an attached copy of a page from the Vatan’s catalogue that
    references 450/750 V TS 9758 wire and at the bottom of that same page displays the
    TSE and CE marks (R4, tab 365 at 4). However, T F Power report did not address
    these facts.
    32. ECC received a copy of the report on January 29, 2011. ECC’s project
    manager responded to the COR on February 16, 2011, addressing the Task Force’s
    findings related to the wire, “NEC 110.3 covers examination, identification,
    installation, and use of equipment. It is unclear how this section is applicable to wire
    installed in the building” (R4, tab 84 at 2-3).
    Questioning Continues
    33. The government ignored the COR’s approval of the wire and the
    questioning continued into March 2011. The Title II inspector Gillette emailed ECC’s
    project manager on March 30, 2011, that he had inspected some power cables staged
    onsite for intended use and did not observe any marking or listing as required by NEC
    110.3. Furthermore, he stated Title II would not recommend the materials for usage
    on the project. (R4, tab 65 at 1) It is uncertain whether the cables referenced are the
    interior wires at issue. ECC responded to Gillette by asking him to identify the
    specific cables referenced stating, “[we] have some that we are using and others that
    are scrap. We have a new shipment of cables on the way for the distribution system”
    (R4, tab 381 at 1).
    34. ECC continued to install the wiring but AFCEE representatives continued
    to pursue the Vatan electrical cable issue despite the COR’s approval. The minutes
    from the April 18, 2011 on-site meeting between ECC and AFCEE representatives,
    including then COR Cpt. Melvin, reflect that ECC was now seeking tests of the Vatan
    cable to demonstrate compliance with applicable standards. The state the electrical
    distribution cable may be replaced: “Electrical cables were minutes sent to a CE
    certified lab for testing. Because of the critical nature of this item, if ECC does not
    hear back from the lab in 1-2 days then the cable will be reordered and replaced.” The
    results of any lab results, if there were any, are not in the record. Additionally, no
    explicit order for removal is mentioned in the minutes. (R4, tab 94 at 2)
    15
    35. Additionally, the record is devoid of any evidence of government
    contracting officials, either COs or CORs, explicitly revoking the earlier November
    12, 2010 approval of the Vatan electrical cable, or any direction to ECC to stop
    installing the approved Vatan electrical cable. Mr. Turek testified that the government
    did not provided such direction, “until on or about May 9, 2011 or May 11, 2011”. He
    further testified that during the May 9th meeting the project COR “made clear that the
    Vatan electrical cable was a deficiency that would have to be corrected through
    removal and replacement”, which was then followed by a Contracting Officer
    Performance Deficiency Letter on May 11, 2011 (app. br. ex. 2, aff. of D. Turek, ¶¶ 9 -
    11). The May 9, 2011 meeting minutes are ambiguous at best on this point. The
    meeting minutes do not indicate Mr. Turek was an attendee nor do they indicate a
    direct order to replace the cable; they only state, “Electrical Distribution Cable – will
    be replaced. Order placed. Delivery date pending based on shipping company ETA –
    approximately 2 weeks, - May 18th.” (R4, tab 87 at 3)
    36. On May 11, 2011, the CO (Rendon) issued a Performance Deficiency
    Letter (PDL), requesting ECC submit a Corrective Action Plan (CAP) by May 18,
    2011 (R4, tab 394 at 2 ¶ 8). Included among the alleged performance deficiencies, was
    use of “unlisted wires.” The PDL asserts that electrical deficiencies were noted by
    Title II and Task Force Power since November 2010, and have yet to be addressed.
    The PDL further states that “Contracting Officer, Mr. Santiago Toscano . . .
    determined that all electrical material is to be listed.” (Id. at 1 ¶ 2).
    ECC Removes Vatan Wiring and Orders UL Listed Materials
    37. As soon as possible after receiving the PDL on May 11, 2011, ECC moved
    to implement the corrective actions, including removal of all Vatan electrical cables
    that had been installed and ECC’s Quality Control Report shows removal was
    completed on May 20, 2011 (app. supp. R4, tab 26 at 1771). Additionally, ECC
    immediately ordered the UL listed materials necessary to replace the Vatan wire.
    These materials were not readily available in Afghanistan and had to be air shipped
    into Camp Bastion from the United States. This ordering and delivery of UL listed
    electrical cable took time to execute. ECC also immediately negotiated a lump sum
    subcontract modification with METAG, a Turkish subcontractor, who performed the
    removal of the Vatan electrical cable and the installation of the UL listed electrical
    cable. (App. br. at ex. 2, aff. of D. Turek, ¶¶ 23-27) By the time AFCEE sent its
    May 11, 2011 PDL, over 80% of the electrical cable work had been completed using
    the Vatan product (id. at ¶ 22; app. supp. R4 tab 26 at 970, 1540).
    Liquidated Damages
    38. On August 5, 2011, CO Renden issued a notice of forbearance to ECC,
    stating the government intended to assess liquidated damages (LDs) at a rate of $6,369
    16
    each day of unexcused delay after August 7, 2011 until the work was completed or
    accepted pursuant to the contract (R4, tab 101 at 2). By October 24, 2011, AFCEE
    calculated the LDs for 69 days at $429,906 (R4, tab 103). ECC’s REA and subsequent
    Claim challenged the ultimate assessment of $436,276.50 (R4, tab 30 at 3; R4, tab 37
    at 1).
    ECC’s Request for Equitable Adjustment (REA), Claim and the Government’s
    Contracting Officer’s Final Decision (COFD)
    39. On June 12, 2012, ECC filed an REA in the amount of $1,138,669 for the
    removal and replacement of Vatan electrical cables that were previously approved by
    the COR. The REA also challenged the government’s position on accessing
    $436,276.50 in liquidated damages given the delays alleged to have resulted from the
    government’s order. (R4, tab 30 at 3) The government denied ECC’s REA on July 17,
    2013 and thereafter, on September 6, 2013, ECC converted its REA to a certified claim
    (R4, tabs 35, 37).
    40. A COFD was issued on February 19, 2014 denying ECC’s claim in its
    entirety (R4, tab 39). Additionally, the CO found that the contract required liquidated
    damages be assessed for each day ECC failed to complete the work by the
    construction/field completion date. The CO also went on to conclude that because
    ECC did not meet the specifications of the contract it did not meet the construction
    completion date and therefore liquidated damages should be assessed until the date of
    acceptance (id. at 3-4). Thereafter, ECC timely filed a notice of appeal to the Board on
    April 28, 2014, that was docketed as 
    ASBCA No. 59280
    .
    ADDITIONAL FINDINGS OF FACT
    DELAY CLAIM, 
    ASBCA No. 60760
    41. ECC submitted a certified delay claim on April 19, 2016 seeking
    $916,840.82 for a compensable contract extension of 114 days of delay for the period
    between July 31, 2011 and November 21, 2011 (R4, tab 520). The government issued
    a COFD denying ECC’s claim in its entirety on August 1, 2016 (R4, tab 533 at 6).
    Thereafter, ECC timely appealed the COFD and their claim was docketed as 
    ASBCA No. 60760
    .
    17
    ECC’s Expert Delay Report
    42. ECC submitted an expert report on ECC’s delay claim dated January 8,
    2021 (app. supp. R4, tab 8). 17 The ECC Expert Delay Report (ECC Delay Report) was
    authored by Ms. Trudie Ward, an ECC employee (id). We reviewed Ms. Ward’s
    qualifications and find her qualified to be an expert in construction contract delay
    analysis. 18 Ms. Ward employed the Time Impact Analysis (TIA) method and
    concluded that ECC was delayed 168 calendar days between May 30, 2011 and
    November 14, 2011, as a result of direction from the government to remove the Vatan
    wire and that ECC is entitled to a compensable time extension of 114 calendar days for
    the delay period between July 31, 2011 and November 21, 2011 (app. supp. R4, tab 8
    at 5, 9, 22).
    43. Her review was based upon review of five time periods during the project:
    (1) The approved baseline: This is the original
    government schedule approved by the government on May
    13, 2010. This schedule projected a project completion
    date of November 29, 2010 with zero calendar days of
    float. (App. supp. R4, tab 8 at 13 at ¶¶ 6.1.1.)
    (2) April 2011 Progress – Original schedule: This
    schedule is the last approved contemporaneous schedule
    immediately prior to the impact period being analyzed.
    The schedule forecasted a project completion date of July
    11, 2011 with 81 calendar days of float. Validation of
    contract dates and actual start and finish dates was
    conducted between the schedule, Daily Quality Control
    Reports, Title II Reports and the contract period of
    performance. This validation identified needed revisions
    to this schedule in order to provide an accurate calculation
    of project impacts. 19 After review, the original 81 calendar
    days of float reported was found to be incorrect because it
    was projected from utilizing an incorrect contract
    completion constraint date of September 30, 2011. (App.
    supp. R4, tab 8 at 14, ¶¶ 6.2.2)
    17
    This report replaced a Time Impact Analysis, dated April 2016, submitted with
    ECC’s claim on April 19, 2016 (R4, tab 520 at 3).
    18
    Ms. Ward’s qualifications summary can be found at app. supp. R4, tab 8 at 23 and
    her curriculum vitae at app. supp. R4, tab 9 at 1-8.
    19
    These corrections are defined in section 6.3.2 of the report at 15.
    18
    (3) April 2011 Progress – Corrected: This schedule
    represents the corrected version of the last approved
    contemporaneous schedule prior to the impacts analyzed in
    the Report. The corrected 20 schedule projected a
    completion date of June 26, 2011 with 34 calendar days of
    float. (R4, tab 8 at 15 ¶¶ 6.3.1)
    (4) Vatan Wire-Fragnet Schedule: the purpose of this
    schedule was to model the impact of removing and
    replacing the Vatan wire in the two buildings. Ms. Ward
    took identified impact activities and added them into the
    Fragnet -1 schedule (see, table at app. supp. R4, tab 8 at 18
    ¶¶ 6.4.2). After the addition of the identified impact
    activities, “the original electric activities were progressed
    using the actual completion dates reported within the Title
    II Daily Reports.” (App. supp. R4, tab 8 at19) 21
    (5) The As-built Schedule November 21, 2011: The As-
    Built Schedule shows a final project completion date of
    November 21, 2011, this is 114 calendar days beyond the
    Construction/Field Date (FPoP) of July 30, 2011.
    Additionally, the As-Built schedule identified a 20-day
    performance gain to the project completion date. (App. supp.
    R4, tab 8 at 20)
    The Critical Path of FRAGNET-1
    44. Below are Ms. Ward’s conclusions regarding the critical path: 22
    The critical path of Schedule FRAG-1 started with
    AFCEC’s issuance of a Performance Deficiency Letter
    directing ECC to replace the existing Vatan wire with UL
    20
    The specific corrections are identified/discussed in section 6.3.2. at 15-16.
    21
    The actual four progressed activities are displayed in the table at app. supp. R4, tab
    8 at 19 ¶¶ 6.4.2.).
    22
    This specifically addresses the critical path (longest path) at the relevant time of the
    contract change till contract completion. The critical path for each to the
    previous time periods are found at: – Approved Baseline, (app. supp. R4, tab 8
    at 13, ¶¶ 6.1.2); April 2011 Progress- Original, (app. supp. R4, tab 8 at 14, ¶¶
    6.2.2); and, April 2011 Progress – Corrected (app. supp. R4, tab 8 at 17, ¶¶
    6.3.3).
    19
    listed material (Exhibit 7) [May 11, 2011] took over the
    critical path. [sic]
    On 05/12/2011 the critical path became ECC procuring the
    UL Approved wire and remained critical thru the
    forecasted delivery date of 05/27/2011.
    On 05/30/2011 the critical path becomes the installation of
    the UL Approved wire and remained critical until complete
    on 11/14/2011.
    Punch out and inspections for both buildings follows
    leading into commissioning of both buildings. On
    11/29/2011 the correction of punch list deficiencies was
    planned to complete initiating the pre-final inspection of
    both buildings on 11/30/2011. Government acceptance
    with final cleanup to be performed concurrently with
    demobilization completing the project on 12/11/2011.
    (App. sup. R4, tab 8 at 19, ¶¶ 6.4.3). In summary,
    Ms. Ward’s analysis found the government’s actions
    affected the activities on the critical path of the contractor’s
    performance of the contract.
    Overall Conclusions
    45. Ms. Ward’s overall conclusions are:
    The TIA [Time Impact Analysis] shows an impact of 168
    calendar days due to the Government directing the removal
    and replacement of the Vatan wire. The as-built schedule
    shows a net delay of 114 calendar days of delay. ECC’s
    efficiencies and mitigation efforts resulted in a 54 calendar
    day gain to the project completion date.
    Construction Project   Contract Delay/ Project
    Schedule Description   Data Date Completion Completion Completion Gain Impact
    Date       Date      Date     (CD’s) (CD’s)
    Approved Baseline      26-Feb-10 28-Nov-10 29-Nov-10 29-Nov-11      -
    April 2011 Progress –
    30-Apr-11 11-Jul-11        11-Jul-11     30-Sep-11         81   81
    Original
    April 2011 Progress –
    30-Apr-11 25-Jun-11        26-Jun-11     30-Jul-11      (47)    34
    Corrected
    20
    Vatan Wire – Fragnet
    30-Apr-11 10-Dec-11         11-Dec-11    30-Jul-11    (168)    (134)
    Schedule
    As-Built Schedule
    21-Nov-11 14-Nov-11         21-Nov-11    30-Jul-11      20     (114)
    11-21-2011
    (R4, tab 8 at 21 ¶ 7.0)
    46. Ms. Ward’s finding of 114 calendar days of project delay was based upon
    the difference between the contractual required completion date July 30, 2011, and the
    project completion identified on the As-built schedule, November 21, 2011. (App.
    supp. R4, tab 8 at 22 ¶¶ 7.1)
    The Government’s Non-Response
    47. The government chose not to submit any testimony in response to Ms.
    Ward’s expert report. Likewise, the government chose not submit a brief to advocate
    its position. The only response in the record consists of two internal government
    emails submitted in response to ECC’s response to the Board’s Order on Proof of
    Costs. The two emails addressed the government’s response for an analysis of ECC’s
    June of 2015 REA. (Bd. corr. ltr. dtd. November 19, 2020, Respondent’s Response to
    ECC’s July 15, 2020 Statement of Costs at exs. 3-4) (hereinafter “Respondent’s
    Response”) The first is an email review of Mr. Andrew Barboza dated June 18, 2015
    and the second, another email response authored by Mr. Mathew Fitch dated June 24,
    2015 (id.).
    48. We do not ascribe any weight to either of these documents. The government
    does not provide any foundation identifying who these individual are or their credentials.
    Furthermore, their analysis provides little, if any, relevant information. Their analysis is of
    ECC’s REA some six years before ECC’s evidence, including Ms. Ward’s Report.
    (Respondent’s Response exs. 3-4)
    Summary
    49. We find that ECC is entitled to 114 days of compensable delay
    ADDITIONAL FINDINGS OF FACT
    QUANTUM ASBCA Nos. 59280, 60760
    21
    BACKGROUND
    Order on Proof of Costs
    50. We issued an Order on Proof of Costs on May 22, 2020. ECC filed their
    response to our Order on July 15, 2020 (Bd. corr. Appellant’s Response to Order on
    Proof of Costs dtd. July 15, 2020). The response was a short narrative explaining the
    materials submitted with reference to two Excel spreadsheets – one for the Remove
    and Replacement claim (
    ASBCA No. 59280
    ) and the Compensable Delay claim
    (
    ASBCA No. 60760
    ). The government’s response to ECC’s Response to the Order, on
    the removal and replacement claim, includes a DCAA audit conducted on the costs
    claimed (Respondent’s Response at ex. 2). No such audit was conducted on ECC’s
    Compensable Delay claim. Instead, the government responded with two internal
    government analyses dated June 18, 2015 of ECC’s REA and a May 2011 Impact
    Analysis Schedule. (Respondent’s Response at exs. 3-4: see also, finding 48)
    Testimony of Mr. Ivan Leung
    51. Mr. Ivan Leung testified he was ECC’s Director of Project Controls and
    supervised the project staff conducting the project controls for the project. He served
    in this role for the entire period of performance of TO 56. (App. br. at ex. 3, aff. of I.
    Leung ¶ 1) As Director of Project Controls, Mr. Leung was in charge of overseeing
    the establishment of the Project cost tracking systems, including development of the
    Work Breakdown Structure (WBS) for the Project. Mr. Leung was also the key ECC
    Manager involved with setting up, maintaining, and administering ECC’s Corporate
    Accounting, Project Controls, and Cost Tracking systems that were approved by
    DCMA in 2011. (App. br. at ex. 3, aff. of I. Leung ¶ 2) He explained in detail how
    ECC’s accumulated project costs were tracked on the TO 56 project and given a
    unique project number. Additionally, he testified that the Statements of Costs for the
    two TO 56 claims (app. supp. R4, tabs 18, 20.) were taken from ECC’s accounting
    system and the direct costs in the Statements of Costs in support of the two claims are
    the actual labor, materials, and subcontract costs are from ECC’s accounting system
    and are supported by documents included in ECC’s Supplemental R4 filings. (App.
    supp. R4, tabs 17, 32; app. br. at ex 3, aff. of I. Leung ¶ 5).
    52. Mr. Leung also testified in detail regarding the specific areas of the two
    costs claims. That testimony is addressed in those specific areas of the two quantum
    claims below.
    22
    ADDITIONAL FINDINGS OF FACT
    QUANTUM, 
    ASBCA No. 59280
    ECC’s Equitable Adjustment, Removal & Replacement Claim
    53. On September 6, 2013, ECC filed a claim for reimbursement for removing
    and replacing the Vatan cable with UL listed cable in the amount of $1,168,553 (R4,
    tab 37). The CO denied ECC’s Claim in its entirety (R4, tab 39). EEC appealed the
    denial which was docketed as 
    ASBCA No. 59280
     (R4, tab 40).
    Replacement Claim: Defense Contract Audit Agency (DCAA) Audit Report
    54. On September 18, 2015, DCAA issued Audit Report No.
    4141-2015E17200002 Independent Audit Report on Environmental Chemical
    Corporation’s (ECC) Contract Claim, dated September 6, 2013, Under Contract
    No. FA8903-06-D-8511, Task Order 0056. 23 (hereinafter “Audit”). The Report’s
    findings questioned $657,656 of the claimed $1,168,553. The auditors verified that all
    claimed costs were incurred, but questioned some costs due to finding of noncompliance
    with FAR 31.201-2, Allowability and FAR 31.201-4, Determining Allocability.
    (Audit at 2)
    55. The audit was divided into six elements: (1) Direct labor; (2) Applied
    Indirect Labor Rates; (3) Subcontract Costs; (4) General and Administrative (G&A);
    (5) Profit, and (6) REA Preparation Costs.
    1. Direct Labor
    56. Mr. Guy Simmons was responsible for the supervision of all the field work
    associated with replacing all the cable. ECC’s claim includes $32,939 in direct labor
    costs for Mr. Simmons. 24 Although the auditors took no exceptions to the labor rates,
    and validated all the claimed costs were incurred, they questioned the $32,939 in
    direct labor costs claimed. The auditors’ rationale was that they were unable to
    determine if the labor costs were associated with the removal and reinstallation of
    cable, therefore, they were not able to confirm whether or not the claimed labor
    amounts were allocable to the subject claim. (Audit at 10 ¶ 2 a.)
    23
    This government audit was conducted in response to ECC’s July 15, 2020 Statement
    of Costs and is found at Exhibit 2 of Respondent’s Response. In the interest of
    brevity, this audit will be referenced as “Audit”.
    24
    ECC initially claimed $34,989 in direct labor costs but the auditors discovered
    mathematical mistakes in the labor rates applied by ECC. ECC concurred in
    their corrections (Audit at 11).
    23
    57. The auditor’s conclusions were based upon their review of a sample of
    82 daily job site reports provided by ECC for the months of June, July and August of
    2011 (Audit at 12). They noted the review disclosed that Mr. Simmons attended at
    least five meetings 25 during July and August that appeared to be unrelated to the
    removal and reinstallation of the cable. The auditors interpreted this to indicate that he
    was managing other projects than the removal and reinstallation of cable. (Id).
    58. ECC disagreed with the auditor’s findings, stating:
    The second labor cost element in ECCI’s claim was for the
    supervision of all the field work associated with replacing
    all the wiring. A single supervisory individual’s time (Guy
    Simmons) was included in the claim for the duration of the
    field work. In spite of the fully supported actual cost
    evidence associated with Mr. Simmons time, and in spite
    of the fact that our contract requires all Subcontractor field
    work be supervised by an ECC representative, DCAA has
    questioned all of those costs as well.
    All questioned direct costs described above also had
    indirect markups applied and so the associated indirects for
    the questioned direct costs were also questioned by DCAA.
    (Audit at 26)
    59. We find the auditors’ conclusions, questioning all direct labor costs
    because of attending five meetings, to be speculative. Given the titles of these
    meetings, Mr. Simmons’ attendance could have been to discuss the progress on his
    portion of the project, i.e. when the replacement of wire would be completed so they
    would have power to test and complete their part of the project or probably various
    other possibilities. We just do not know: to guess at this would be mere speculation.
    What we do know is that the auditors confirmed that all these costs were incurred and
    that Mr. Simmons was responsible for overseeing the replacement of the wire (Audit
    at 26 ¶ 3). Additionally, Mr. Leung testified to collecting these costs and that they
    were directly incurred in furtherance of this claim (app. br. at ex 3, aff. of I. Leung ¶
    5). This evidence was not opposed by the government. In the nature of a jury verdict
    we find ECC is entitled to $32,939 in direct labor costs.
    2. Indirect Labor Costs
    25
    July 2, 2011, Telecommunications Cabling; July 15, 2011, Security Systems
    Installation; July 20, 2011, Fire stopping; August 06, 2011, DDC for HVAC
    Installation; August 17, 2011, Testing, Adjusting & Balancing (Audit at 12).
    24
    60. ECC claimed indirect costs totaling $32,939 were based on applying the
    2011 provisional billing rates (Fringe, Overhead, and G&A) to the claimed labor
    amounts for the Senior Project Manager, Guy Simmons. The claimed indirect rates
    were based upon ECC’s interim billing letter “Revised Provisional Billing Rates and
    Cost of Money Factors for Calendar Year 2011.” (Audit at 13 ¶¶3 b, c). Mr. Leung
    testified that from his review of ECC’s Rule 4 Supplement Tabs 24, 18, and 20, it is
    clear that ECC used the appropriate DCAA approved fringe rates. (App. br. at ex 3,
    aff. of I. Leung ¶ 6.) However, the auditors questioned the indirect costs in their
    entirety as a result of being directly associated with their findings that questioned all
    direct labor claimed (Audit at 3, 13 ¶ c.). Based upon our findings on ECC’s direct
    labor claim, we reject the auditor’s findings.
    61. Indirect costs include fringe benefits that are charged on direct labor costs
    and those fringe costs are included in the Statement of Costs (app. supp. R4, tabs 18,
    20). All fringe costs were prepared using the DCAA audit letter that established
    ECC’s indirect cost rates for 2011 (app. supp. R4, tab 24; app. br. at ex. 3, aff. of I.
    Leung ¶ 6). Our calculations, based upon our previous direct labor finding of
    entitlement, are:
    DIRECT LABOR (Mr. Simmons) & FRINGE, OVERHEAD, & G&A FINDINGS
    DIRECT LABOR                                                $32,939
    2011 ECC Fringe - Non DBA Field (35.69%)                   $11,756
    2011 Overhead-Engineering and Construction (E&C) (43.30%)  $14,262
    2011 G&A (8.70%)                                             $2,865
    TOTAL:  $61,822
    3. Subcontract Claims
    62. The claimed subcontract costs of $899,920 represents the largest segment
    of the overall claimed costs. Although the audit confirmed ECC’s claimed costs were
    incurred it was unable to determine whether $538,955 of the total costs claimed were
    allocable to the removal and reinstallation of cable claim (Audit at 14). The audit’s
    findings were based upon review of invoices covering the period between May and
    August 2011 from the four subcontractors that were contracted by ECC to complete
    the work. The subcontractors listed in the claim are: (1) Metag; (2) Vega Services,
    Inc.; (3) Kelly & Hayes Electrical Supply; and (4) DHL Express USA (id.).
    (1) Metag
    63. Mr. Leung testified that ECC negotiated modifications with its existing
    subcontractor Metag for the removal and replacement of the Vatan cable and that those
    25
    modifications are reflected in the Rule 4 Record (app. br. at ex. 3, aff. of I. Leung
    ¶¶ 9-10; app. supp. R4, tabs 22-23). There were two modifications to the existing
    subcontract, one for each building. The Camp Bastion modification was executed on
    June 26, 2011 and Camp Leatherneck on August 22, 2011. (Id.)
    64. ECC submitted five Metag invoices for the costs claimed (app. supp. R4, tab
    32 at 49-56). The auditors traced the amounts billed on the five Metag invoices to the
    amounts on ECC’s work authorizations and purchase orders for Metag, and did not find
    any discrepancies. They also reviewed ECC’s work authorizations and purchase orders
    to determine the scope of work to be performed by Metag. The auditor’s review
    revealed that Purchase Order 344675, dated June 14, 2011, awarded the installation of
    electrical, fire alarm, security access control, and non-secure communications for
    building 2 to Metag. Therefore, ECC contracted with Metag to perform work in
    addition to removal and reinstallation of wiring/cable. (Audit 16-17) The auditors
    questioned all the claimed Metag costs on the basis they could not verify their
    allocability, stating:
    During our review of the Metag invoices, we noted the
    description of the services billed was “TO 56 Electrical
    Works.” This description is very general and does not
    allow us to determine if the work billed is solely related to
    the removal and reinstallation of wiring/cable. Hence, we
    were unable to confirm ECC’s assertions, and we
    questioned the $356,931 claimed cost for Metag.
    (Audit at 17)
    65. Mr. Leung testified that all of ECC’s subcontract invoices in support of this
    claim were included in ECC’s Supplemental Rule 4 record at tab 32 (app. br. at ex. 3,
    aff. of I. Leung ¶ 5). Our review of the five invoices included as evidence at that
    location does include the invoice noted in the audit as the rationale for questioning all
    of Metag costs, i.e. we are unable to locate a “Purchase Order 344675, dated June 14,
    2011”. Additionally, it is obvious that the auditors did not have access to Mr. Leung’s
    testimony or the fact that the agreement for Metag to perform the work to remove and
    replace the electrical cable for both buildings was a modification to already existing
    subcontracts for other work on the project (app. supp. R4, tabs 22-23). Given our
    review of the evidence we find that ECC has proven its entitlement to the entire
    claimed amount of $356,931.
    (2) Vega Services Inc.
    66. The auditors traced the Vega Service Inc. invoices to ECC’s work
    authorizations and purchase orders for Vega, and did not find any discrepancies. They
    26
    also reviewed ECC’s work authorizations and purchase orders to determine the scope
    of work to be performed by Vega Services Inc. Below are details of their specific
    findings about the Vega Services scope of work:
    ECC’s work authorizations for Vega named
    VEGA.CSA.HERC.4502.056.WA01 awarded the
    installation of electrical, fire alarm, security access control,
    and non­secure communications for the Marine Brigade
    Headquarters buildings at Camp Bastion and Camp
    Leatherneck.
    Work authorization
    VEGA.CSA.HERC.4502.056.WA0l.MODl dated June 14,
    2011, modified ECC’s contract with Vega Services Inc. to
    de-scope its work. The modification de-scoped the work
    from two buildings to one building.
    (Audit at 17)
    67. The auditors also reviewed the description of the work billed on Vega
    Service’s invoices, and questioned $116,265 of the $133,567 claimed cost. The
    descriptions on the Vega invoice related to the questioned costs are as follows:
    Provide all labor and equipment required to complete the
    required remaining installation for all Electrical Works
    (interior and distribution) for the LCE and ACE Marine
    Headquarters facilities...
    Provide all labor and equipment required to complete all
    testing, commissioning, and integration as required per
    plans, specifications, and manufacturer’s instructions for
    the Electrical Works (interior and distribution) remaining
    for the LCE and ACE marine headquarters facilities.
    Provide all labor and equipment required to complete all
    required Power Generation Plant Cabling, controls,
    terminations, etc. for the LCE and ACE Marine
    Headquarters power generation facility (one facility) as
    detailed in the design drawings... This includes all other
    works that need to be completed to provide a fully
    functional, code compliant power generation plant.
    (Audit at 17-18)
    27
    68. Based upon these descriptions, the auditors were unable to confirm ECC’s
    assertions. The auditors accepted the difference of $17,302 because the description of
    the invoice was the following:
    Provide all labor and equipment required to re-pull all
    required Electrical Wiring for the LCE and ACE Marine
    Headquarters facilities that was removed as part of Option
    I and reinstall in accordance with the design drawing...
    (Audit at 18). We agree and find ECC is entitled to $17,302.
    (3) Kelly & Hayes Electrical Supply (K & H)
    69. ECC claims $365,957 on behalf of K & H (Audit at 18). The auditors
    traced the amounts billed on the ten Kelly & Hayes Electrical Supply invoices to the
    amounts of ECC’s purchase orders for K & H, and did not find any discrepancies. All
    invoices are found in the record (app. supp. R4, tab 32). Based on their review of
    ECC’s Claim and the K & H invoices, they determined ECC purchased compliant wire
    from Kelly & Hayes Electrical Supply for the TO 56 project in Afghanistan. As they
    noted, ECC’s claim states “Our claim includes all subcontractor and material costs
    for removing and replacing cable.” Thus, they reviewed the descriptions on the K &
    H invoices to verify ECC’s claimed cost for electrical materials related only to the
    purchase of compliant wire. (Audit at 18) Below are details of their review of the
    invoices and specific findings:
    • The description of items procured on invoice R00260 and
    R00267 is for plastic tape, a hammer drive anchor, conduit
    of different types, gloves, struts, adapters, connectors,
    temporary lighting, and various other electrical materials.
    • The description of items procured on invoice R00399 is for
    aluminum service poles.
    • The description of items procured on invoice R00352 is for
    switch boxes.
    • The description of items procured on invoice R00675 is for
    circuit breakers, marking tape, outlet box brackets,
    switches, couplings, adapters, and various other electrical
    materials.
    • The description of items procured on invoice R00772 is for
    struts and open lighting.
    28
    • The description of items procured on invoice R00782 is for
    NEMA 3 pole range, mounting panel for pole range, and
    power distribution block.
    (Audit at 19).
    70. The auditors were unable to confirm ECC’s assertions based upon the
    invoice descriptions. They accepted the difference of $316,008 because the
    descriptions on invoices R11573, R99788, R99876, and for some items on invoice
    R00675 (D-03c-4) were for electrical wire/cable (Audit at 19; app. supp. R4, tab 32
    at 37-47). They also noted ECC purchased 399,700 feet of wire (Audit at 19).
    71. We have reviewed the K & H invoices and concur with the auditors’
    findings. Although the invoices questioned appear to possibly relate to electrical
    installation of the cable, we have no direct proof that is the case. Therefore, we find
    that ECC has met its burden of proof on entitlement to $316,008 of the $365,957
    claimed in reimbursement for the purchase of cable from K & H.
    (4) DHL Express USA
    72. Mr. Leung and Mr. Turek testified it was necessary to air freight the
    replacement UL listed materials to Afghanistan, and this was done using the available
    air shipping company, DHL. Their air freight invoices for the UL listed electrical
    cable are included in ECC’s claim. (App. supp. R4, tab 32 at 1-22; app. br. at ex 3,
    aff. of I. Leung ¶ 10; app. br. at ex 2, aff. of D Turek ¶ 27) The auditors compared
    three of the five DHL invoices to ECC’s purchase orders for DHL, and did not find
    any discrepancies. ECC could not provide the auditors with purchase orders related to
    two of the DHL invoices. (Audit at 19).
    73. The auditors reviewed the descriptions on the DHL invoices and matched
    the DHL invoices to the K & H invoices to verify ECC claimed shipping cost related
    only to transporting compliant wire. They accepted the difference of $27,655 because
    invoice RNH0000085114 states “ECC Cable to Bastion” and the shipment date
    correlates to dates wire was purchased from Kelly & Hayes Electrical Supply.
    However, they did question $15,810 of $43,465 claimed for DHL Express because they
    could not find similar shipping references that correlate to the wire purchased in May
    2011. (Audit at 19-20)
    74. ECC disagreed with their audit findings (audit at 20 ¶ d; 26) Mr. Leung
    testified that the R4 record contains the invoices for materials purchased to replace the
    Vatan electrical cable and the invoices for ECC’s subcontractor, Metag, who removed
    29
    and replaced the Vatan electrical cable (app. br. at ex. 3, aff. of I. Leung ¶ 5). We
    accept the auditor’s findings. ECC is entitled to $27,655.
    (5) 2011 G&A (Applied to Subcontractors – 8.74 Percent)
    75. Mr. Leung testified that the (G&A) rates are uniform across work
    performed by ECC and that the G&A rates included in the Statement of Costs for ECC
    on the TO 56 claims are those determined by the DCAA in their 2011 audit letter (app.
    br. at ex 3, aff. of I. Leung ¶ 8; app. supp. R4, tab 1). ECC applied an 8.74% 2011
    G&A Rate to the total amount of subcontract costs, as presented on ECC’s claim
    submission. The auditors accepted the 8.74% number and applied it in their
    calculations to the questioned subcontract costs. (Audit Ex. A, at 9, 22)
    (6) Profit 11 Percent
    76. The Statement of Costs for the two TO 56 claims contains a profit rate that
    was calculated at 11% (app. supp. R4, tabs 18, 20). The 11% profit was calculated
    using the Weighted Guidelines Application and the various risk factors are shown in
    those calculations. The Weighted Guidelines Application is a common regulatory
    calculation for profit appropriate on modifications (app. br. at ex. 3, aff. of I. Leung ¶
    13).
    77. The auditors did not offer an opinion or recommendation on the applied
    11% since they considered it to be a matter of negotiation for the CO. We find the
    11% profit claimed to be reasonable.
    78. We find that total subcontract costs are as follows:
    METAG                                        $356,931
    Vega Services Inc.                                                        $17,302
    Kelly & Hayes Electrical                                                 $316,008
    DHL                                                                       $27,655
    Total Subcontract Costs                                                  $717,896
    2011 G & A, (8.74%)                                                       $62,744
    Profit (11%)                                                              $78,968
    Total Subcontract Costs                                                 $859, 608
    (7) Claim for Request for Equitable Adjustment (REA) Preparation Costs
    79. ECC claims $4,571 for ECC Contract Manager, Chris Cannon’s
    preparation of ECC’s REA submitted on June 12, 2012 and denied on July 17, 2013.
    This claim is based upon 33.5 claimed hours at $61.18 per hour plus applied indirect
    30
    costs and associated profit (Audit at 20 ¶ 5b). After reviewing ECC’s recorded costs
    and related documentation the auditors found 12.5 hours were not supported by
    employee time cards. This led the auditors to question $1,537 of the $4,118 (cost
    minus profit) claimed, leaving a verified amount of $2,581in total costs. 26 The
    auditors also verified that none of the claimed costs were incurred after July 17, 2013,
    the date the government denied the REA, i.e., none of these claimed costs were
    incurred in preparation of the resulting claim that followed on appeal. (Audit at 21 ¶¶
    (3)(i), (ii)).
    80. Although the audit verified a total cost of $2,581 that included fringe costs,
    overhead engineering and construction (E&C), and G&A, the auditors maintained their
    prior position of not addressing profit (Audit at 21, see cost calculation table). Based
    upon our prior profit rate finding of 11%, we find that ECC is entitled to $283.91 in
    profit on its REA preparation claim for a total amount of $2,865 (id.).
    Summary of Remove and Replace Claim Quantum findings 
    ASBCA No. 59280
    81. We find that ECC is entitled to an equitable adjustment of $924,295 based
    upon its claim in appeal 
    ASBCA No. 59280
    . Below is a summary of our findings:
    TOTAL DIRECT LABOR                                              $61,822
    TOTAL SUBCONTRACT COSTS                                        $859,608
    REA PREPERATION COSTS                                            $2,865
    TOTAL CLAIM AMOUNT                                            $924,295
    ADDITIONAL FINDINGS OF FACT
    COMPENSABLE DELAY CLAIM - QUANTUM
    
    ASBCA No. 60760
    82. ECC submitted a delay claim on April 19, 2016 seeking $916,840.82 for a
    compensable contract extension of 114 calendar days of delay for the period between
    July 31, 2011 and November 21, 2011 (R4, tab 520). Our findings have established
    entitlement to 114 calendar days of compensable delay (finding 49). Unlike the
    Removal and Replacement claim above, the government did not submit a DCAA
    Audit, expert report, or testimony.
    26
    The auditors originally questioned all of the proposed REA preparation costs. ECC
    disagreed with their findings. After discussing the findings with ECC during an
    exit conference, the auditors revised their questioned cost to reflect their current
    position - only labor costs associated with labor hours unsupported by the
    employee time cards. (Audit at 22 ¶¶ c, d)
    31
    Testimony on Preparation of Direct Labor Costs
    83. Mr. Ivan Leung testified that he prepared the detailed cost calculations for
    the delay claim (app. br. at ex. 3, aff. of I. Leung ¶ 6.). ECC maintained four Program
    Management Offices (PMOs) within Afghanistan to support its various projects.
    These PMO locations were Bastion, Kabul, Kandahar, and Bagram. The TO 56
    project was supported by the Bastion PMO which included Program Management,
    Accounting, Finance, Logistics, Procurement, and Administrative Staff. The labor
    costs of these personnel along with their support costs (Lodging, Meals, Incidentals,
    Office Equipment, Office Rent, etc.) were collected within the Bastion PMO costs on a
    monthly basis. These costs were then allocated to each project that the Bastion PMO
    supported (including TO 56) for any given month, using a percentage of Direct Labor
    cost charged to the project by those working in the Bastion PMO. (Id. at ¶ 7; app.
    supp. R4, tab 25).
    Testimony on preparation of Extended Field Overhead/General Requirements
    84. Mr. Leung testified that ECC’s costs for its General Requirements,
    sometimes referred to as extended field overhead, were included in the delay claim and
    the record is at app. supp. R4, tab 18. Mr. Leung also explained the methodology used
    to capture these costs. ECC’s WBS captured time-related Labor and Other Direct
    Costs (ODCs) for ECC’s General Requirements for the period of delay claimed in
    2011. From these monthly costs, Mr. Leung extrapolated the daily cost for any given
    month during that period. These daily costs were then applied to the specific number
    of days for any given month where delay occurred. (App. br. at ex 3, aff. of I Leung ¶
    11)
    85. Attached to ECC’s claim were 888 pages of supporting cost data (R4, tab
    520 at 20 – 908). The attached cost spreadsheets present the accounting data collected
    by ECC’s government approved accounting system for the period between July 31,
    2011 and November 21, 2011. ECC explains this costs data is divided into two
    sections. The first section presents all labor costs. An index (id. at 21-22) of all the
    labor costs is followed by the associated payroll evidence (id. at 24-90). The second
    section presents all non-labor costs, also referred to as Other Direct Costs (ODCs) (id.
    at 91-908). Pages 91 through 92 are a summary of ODC costs and pages 93-908 are
    the supporting data for the ODC costs. The cost and pricing data for the ODCs is
    organized by bookmarks. Each bookmark is labeled according to the line item
    number shown in the Non Labor Cost Index. (R4, tab 520 at 91-92. The spreadsheets
    also include a calculation for Fringe, Overhead, and G&A for labor costs (id. at 22-23)
    and G&A for ODC (id. at 91-92).
    86. Our findings establish ECC is entitled to $916,840 in compensable delay
    costs. The summary below details the elements of our findings:
    32
    COMPENSABLE DELAY CLAIM COST SUMMARY
    Direct Labor                               $251,682
    Fringe                                       $63,619
    Overhead                                   $139,205
    Subtotal Total Labor                       $454,506
    Subtotal Non Labor (ODCs)                  $388,643
    G&A                                          $73,691
    Entitlement Total                          $916,840
    87. Unlike the removal and replacement claim, the government did not submit
    a DCCA audit in support of this compensable delay claim. In fact, the government did
    not submit anything in opposition to this claim.
    DECISION
    ENTITLEMENT DECISION
    
    ASBCA No. 59280
    This appeal results from appellant’s installation of internal wiring during
    construction of two buildings in Afghanistan. Appellant alleges that after installing
    substantially all of the wiring, the government rejected the wiring and required
    appellant to remove and replace the wiring at appellant’s expense. Appellant argues
    that the government order to remove and replace the wire was a constructive change or
    in the alternative was a waiver of requirements because of the government’s previous
    approval of the initially installed wiring. (App. br. at 29) For appellant to demonstrate
    a constructive change, the burden of proof is on appellant to show: (1) that it
    performed work beyond the contract requirements, and (2) that the additional work
    was ordered, expressly or impliedly, by the government. Bell/Heery v. United States,
    
    739 F.3d 1324
    , 1335 (Fed. Cir. 2014). The parties agreed to have this appeal heard on
    the record per Board Rule 11. These appeals present an unusual challenge because the
    government has waived submittal of any briefs or any testimony in lieu of solely
    relying upon the record to establish that appellant is unable to meet its burden.
    Was Appellant’s Use of the Vatan Wire Rejected by the Government?
    To prevail in its appeal, appellant must show that the authorized government
    representative required or compelled the contractor to perform the work, and that
    government personnel did not merely offer advice, comments during discussions,
    suggestions, or opinion. See McElroy Mach. & Mfg. Co., 
    ASBCA No. 46477
    , 
    99-1 BCA ¶ 30,185
     at 149,358; Quality Plus Equip., Inc., 
    ASBCA No. 46932
    , 
    96-2 BCA 33
    ¶ 28,595 at 142,759; Labarge, Inc., ASBCA 19845, 
    78-2 BCA ¶ 13,376
    . Appellant
    argues in its brief that the government’s repeated rejections of the wire, within the
    context of the financial imperatives involved, amounted to a constructive rejection of
    the wire (app. br. at 34-35; 35 at n.2). We agree.
    The record is devoid of any evidence that the government explicitly ordered
    appellant to replace the wiring being installed and replace it with what the government
    considered compliant wire (finding 35). Mr. Turek testified that the government did
    provide such direction, “on or about May 9, 2011 or May 11, 2011”. He further
    testified that during the May 9th meeting the project COR “made clear that the Vatan
    electrical cable was a deficiency that would have to be corrected through removal and
    replacement”, which was then followed by a Contracting Officer Performance
    Deficiency Letter on May 11, 2011 (id.). Although Mr. Turek’s testimony is
    unopposed by the government, our findings indicate the May 9,, 2011 meeting minutes
    are ambiguous at best on this point. The meeting minutes do not indicate Mr. Turek
    was an attendee at these meetings nor do they indicate a direct order to replace the
    cable; they only state, “Electrical Distribution Cable – will be replaced. Order placed.
    Delivery date pending based on shipping company ETA – approximately 2 weeks, -
    May 18th.” (Id.)
    However, our findings do indicate that the government never accepted COR
    Lopez’s approval of the wire and continued to reject the wire by finding it non-
    compliant with contract requirements (finding 33). Even while the government knew
    appellant was installing the wire, inspectors continued to find the wire non-compliant
    with NEC 110.3 (findings 33-34). Additionally, T F Power conducted an investigation
    of the project and found that the wire did not comply with NEC 110.3 (finding 31).
    The CO met with appellant as the wire was being installed and discussed the issue of
    the wire and eventually on May 11, 2011 issued a Performance Deficiency Letter
    (PDL) requesting appellant submit a Corrective Action Plan to include an alleged
    performance deficiency of “unlisted wires.” The PDL asserted that electrical
    deficiencies had been noted by Title II inspectors and T F Power since November 2010
    and have yet to be addressed. (Finding 36) Appellant argues this letter was a clear
    rejection of the installed electrical wire and that removal and replacement with UL
    wiring was the only course available given the government’s repeated rejections of the
    wire within the context of the project given 80% of the wiring was already installed
    and the prospect of facing $6,369 in daily liquidated damages (app. br. at 35 n.2) 27.
    The government consistently found appellant’s wire non-compliant but did not
    specifically state why other than it failed to meet the requirements of NEC 110.3
    because the wire was not listed or labeled. We conclude the government’s consistent
    27
    $436,276.50 in Liquidated Damages were ultimately assessed at the completion of
    the contract.
    34
    position that the installed wire did not meet the contract requirements, culminating in
    the CO’s PDL, coupled with the business imperatives existing at that time, amounted
    to an implied government rejection of the wire and a constructive order to replace the
    installed wire with other compliant wire. Despite the fact the cable was approved by
    the COR, who had authority to do so, the government clearly rejected appellant’s wire
    as non-compliant with NEC 110.3.
    Given the Rejection of the Wire, the Burden Shifts to the Government to Prove
    the Installed Wire Did Not Comply with the Contract Requirements
    When the government rejects work as not in compliance with its specifications
    the burden of proof shifts to the government to demonstrate that fact. Ensign-Bickford
    Aerospace & Def. Co., 
    ASBCA No. 57929
    , 
    16-1 BCA ¶ 36,533
     at 177,969; (citing Sw
    Welding & Mfg Co. v. United States, 
    413 F.2d 1167
    , 1176 n.7 (Ct. Cl. 1969); and
    Yardney Tech. Prods., Inc., 
    ASBCA No. 53866
    , 
    09-2 BCA ¶ 34,277
     at 169,333-34).
    If the government does not meet that burden, the contractor “is entitled to an equitable
    adjustment under the Changes clause” of the contract. M. A. Mortenson Co., 
    ASBCA No. 53647
     et al., 
    06-2 BCA ¶ 33,400
     at 165,575. Therefore the burden shifts to the
    government to prove that the wire was not listed or labeled and thus non-compliant
    with NEC 110.3.
    The parties waived a hearing on these appeals and instead requested these
    disputes be heard on the record. The government also chose not to introduce any
    testimony or submit any briefs arguing its position. Instead the government relies
    upon our review of the record to ferret out and divine its legal arguments from a
    voluminous record. Ours is an adversarial system where it is incumbent upon, and a
    duty of, the advocates, not the Board, to advocate for their respective clients. It is not
    incumbent upon the ASBCA to make the government’s case for them, or to dig
    through a voluminous record in search of support for an unsubstantiated argument or
    uncorroborated assertion. Lebolo-Watts Constructors, LLC., 
    ASBCA No. 59740
     et al.,
    
    21-1 BCA ¶ 37,789
     at 183,426. Given the fact the government did not submit any
    testimony or briefs, we conclude the government has failed to meet its burden of
    showing the wire did not meet the contract requirements of NEC 110.3, i.e., that it was
    not labeled and listed. Therefore, appellant is entitled to an equitable adjustment.
    That being said, we have made a diligent effort to review the record and
    conclude the record yields the same conclusion i.e., based upon the record, the
    government has failed to prove that the cable did not meet the requirements of NEC
    110.3. The beginning point for arriving at this conclusion is a determination of what
    were the contract requirements? Surprisingly, the record discloses there was some
    confusion over this basic issue.
    35
    What were the contract requirements?
    NEC 110.3 creates a regime where specific testing laboratories are not
    designated for every project. Rather it creates the concept of an authority having
    jurisdiction (AHJ) that would determine which laboratories qualified to list wire. The
    NEC cautions that the AHJ is defined “in a broad manner,” and that an AHJ may be a
    “federal, state, local or other regional department or individual,” or it may be “the
    property owner . . . commanding officer or departmental official”. (Finding 12) We
    conclude this definition is broad enough to encompass a CO or COR. In fact, this
    appears to have been the practice in Afghanistan for some time. Additionally, TO 56
    specifically requires any electrical materials be submitted to the COR for approval or
    disapproval (findings 15-18). This necessarily required the COR (or CO in some
    cases) to interpret what laboratories met the requirements for listing wire and if the
    product was labeled in compliance with NEC 110.3. This all changed with the
    creation of T F Power.
    T F Power was created in October 2008 as a result of the tragic military deaths
    resulting from electrical accidents in Iraq and Afghanistan and the investigations that
    followed. It was tasked with several responsibilities but, relevant to this appeal, T F
    Power became the authority to promulgate rules for implementing NEC 110.3 in
    Afghanistan. (Findings 13-14). Although T F Power already existed at the time of
    award, February 26, 2010, the record does not disclose the existence or
    implementation of any T F Power NEC 110.3 rules at that time. In the face of this
    ambiguity, we conclude TO 56 envisioned the CO to be the primary AHJ by
    delegating authority to the COR for inspecting and approving or disapproving
    electrical items falling under NEC 110.3. Our reading of the record indicates this had
    been the practice in Afghanistan for some time. (Findings 19-20) In fact, appellant
    forwarded a letter to the CO on September 22, 2010 requesting interpretation of the
    contract requirements regarding the listing and labeling of electrical equipment. On
    September 29, 2010, the CO responded stating: “provide electrical materials that are
    listed / labeled by either Underwriters Laboratory (where specified) or other third party
    testing certification laboratory for all basic electrical equipment.” (Finding 21)
    The record indicates T F Power’s first promulgation of NEC 110.3 rules
    occurred on August 3, 2010, some six months after award. These new rules specified
    T F Power recognized only two types of credentials: the CE marking (European Union
    marking) or listed / labeled and displaying the marking of a Nationally Recognized
    Testing Laboratory (NRTL) such as Underwriters Laboratory (UL). (Finding 13) Of
    note, this policy did not restrict listing to a particular laboratory but instead retained the
    term “Nationally Recognized Testing Laboratory”. However, quickly thereafter on
    September 16, 2010, T F Power issued rules significantly narrowing the rules by
    restricting the definition of a “Nationally Recognized Testing Laboratory” to only
    specific laboratories, stating “For United Stated (sic) the Nationally Recognized
    36
    Testing Labs (NTRL) as listed by the US Department of Labor OSHA www.osha.gov”
    and “For the European Union as listed by website below.” (Id.) In other words, this
    latter proclamation imposed a new requirement to use only directed sources from the
    United States or the EU. (Id.)
    In summary, there were three possible NEC 110.3 standards by the time
    appellant sought to have the COR approve its proposed wire: one from the CO and
    two from the T F Power. Our review of the contract language leads us to conclude that
    the applicable standard to be applied is the one issued by the CO based upon the
    standard at time of award. It is self-evident in government contracts that a contractor
    is only bound to the requirements in the contract at the time of award unless modified
    by a change to the contract pursuant to the changes clause. Be that as it may, we read
    the following special clause in this contract to specifically address this principal as it
    relates to updates to regulations implementing NEC 110.3. The contract statement of
    work at Attachment 1 (January 2010) provides:
    The Contractor shall identify, comply with and ensure that
    its personnel and its subcontractors and subcontractor
    personnel at all tiers obey... [the] National Electrical Code
    (NEC)... [and] Regulations, Guidance, and Policy Letters;
    Executive Orders (EOs), Afghanistan Construction
    Standards, Central Command orders and directives
    applicable to personnel in Afghanistan, including but not
    limited to USCENTCOM, North Atlantic Treaty
    Organization (NATO), International Security Assistance
    Force (ISAF) fragmentary orders, instructions and
    directives; and include all changes and amendments in
    effect on the date of issuance of this TO unless specific
    relief is sought by the Contractor in writing and granted by
    the Contracting Officer (CO).
    (Finding 14) (emphasis added). We interpret this language to encompass any
    directives/regulations issued by T F Power and the contractor is only responsible for
    such rules as exist at time of award, February 26, 2010. It follows that any T F Power
    mandates issued after award are only binding on the contractor if formally
    incorporated into the contract by modification. Obviously, the government has the
    authority to change the contract requirements under the changes clause. However, if it
    chooses to do so it must do so bilaterally or unilaterally entitling the contractor to a
    possible equitable adjustment.
    There were only three modifications to TO 56 (finding 14). Although two
    modified contract requirements, none of them incorporated the requirement changes
    37
    specified by T F Power. 28 Additionally, Modification 1 was effective June 7, 2010 and
    T F Power’s first promulgation of NEC 110.3 rules did not occur until August 3, 2010.
    So we conclude that the appropriate standard to apply is the one stated by CO Toscano
    on September 29, 2010. The CO stated that appellant must, “provide electrical
    materials that are listed/labeled by either Underwriters Laboratory (where specified) or
    other third party testing certification laboratory for all basic electrical equipment . . .
    that are listed/labeled.” (Finding 21)
    Was Vatan a Listed Third Party Qualified / Nationally Recognized Testing
    Laboratory 29
    The burden of proof is on the government to show the wire installed was non-
    compliant with the requirement of NEC 110.3 as stated by CO Toscano, i.e. that the
    wire was not listed. Mr. Turek’s unopposed testimony is that TSE is the nationally
    recognized testing laboratory in Turkey (finding 10 at n.10). Despite this, the
    government’s repeated rejection of the Vatan cable implicitly meant that the
    government found TSE not to be a qualified third party or nationally recognized
    testing laboratory per NEC 110.3. Although implied, we are unable to find anything in
    the contemporaneous record where the government specifically alleged TSE was not a
    NEC 110.3 qualified third party or nationally recognized testing laboratory. In fact,
    after COR’s approval of the wire, any government mention of TSE is conspicuously
    absent in the contemporaneous record. On the other hand, Mr. Turek’s unopposed
    testimony was that Vatan cable had been used on other projects in Afghanistan and
    that TSE is the nationally recognized testing organization in Turkey. Likewise, Vatan
    wire, although not this specific wire, was among AFCEE pre-approved wire lists.
    (Findings 19-20) In summary, the government has failed to present any proof that
    TSE was not a qualified third party or nationally recognized testing laboratory per
    NEC 110.3. and, as a result, that the Vatan wire was not “listed”.
    28
    The first modification, effective June 7, 2010, incorporated some changes to the
    statement of work but there was no change to the above language at § 2.0.;
    Modification 2 did not involve the statement of work and was effective on
    November 30, 2010 after the COR had already approved the wire; and
    modification 3 was effective on November 28, 2011, after the wire had been
    removed and UL compliant wire ordered May 20, 2011. (Findings 14).
    29
    We agree it is unclear whether appellant’s cable was CE certified. The Title II
    inspector who assisted and advised the COR when he approved the cable
    contacted the manufacturer who confirmed they were authorized to display the
    CE mark. Likewise, the COR had access to Vatan’s catalogue which also
    displayed the CE mark. However, there is no direct proof such as testimony or
    photos displaying the CE mark. As a result, based upon the record, we cannot
    conclude whether or not the cable was CE certified.
    38
    Labeled by a Qualified Testing Laboratory
    We also conclude the Vatan wire was labeled in accordance with NEC 110.3.
    Our findings establish that NEC 110.3 states the “suitability of equipment use may be
    identified by a description marked on or provided with a product” (finding 7)
    (emphasis added). Likewise, NEC 110.3 defines “Labeled” as material “to which has
    been attached a label, symbol, or other identifying mark of an organization that is
    acceptable to the authority having jurisdiction and concerned with product evaluation,
    that maintains periodic inspection of production of labeled equipment or materials”
    (finding 11). Our findings establish, per the definition above, that NEC 110.3 does not
    require the label, symbol, or other identifying mark to be stamped on the wire (finding
    7). There is evidence in the record, a photo taken during T F Power’s inspection,
    showing that the wire’s packaging as delivered displays the TSE label (finding 31).
    Our conclusion is that this is sufficient to meet the definition of labeled under the
    appropriate standard at that time. Again, the government has failed to prove
    otherwise.
    COR Approval
    Additionally, probably the strongest evidence that the wire was compliant with
    NEC 110.3 requirements is the fact that the COR, who possessed authority to approve
    the wire, inspected the wire and approved it on November 12, 2010 (findings 23-29).
    T F Power had already issued two regulations changing the rules for complying with
    NEC 110.3 by the time the COR approved the wire but the government had not
    contractually implemented those rules (findings 13-14). Surprisingly, there is no direct
    contemporaneous evidence in the record that anyone at the construction site was even
    aware of the T F Power changes. There is no mention of the T F Power rules by the CO,
    COR, or even the Title II inspectors who later found the wire non-compliant.
    Additionally, the record is devoid of mention of T F Power until it was brought in to
    conduct an inspection after the approval and the wire was almost installed. Although T
    F Power’s inspection report found the wire non-compliant, it only referenced NEC 110.3
    but none of its implementing regulations.
    CONCLUSION ON ENTITLEMENT
    In summary, we conclude, based upon the record, that appellant did meet the
    requirements of NEC 110.3 as awarded, i.e. that the wire was listed and labeled per
    NEC 110.3, and the government has not entered any evidence to the contrary.
    Conversely, the government has failed to meet its burden of proof, i.e. that the wire
    was not listed or labeled per NEC 110.3. As a result, appellant is entitled to an
    equitable adjustment under the contract’s Changes clause.
    39
    QUANTUM DECISION
    
    ASBCA No. 59280
    As claimant, appellant has the burden of proving its damages with “reasonable
    certainty.” Precision Pine & Timber v. United States, 
    596 F.3d 817
    , 833 (Fed. Cir.
    2010). “[R]easonable certainty” has been defined as, “more than a guess, but less than
    absolute exactness or mathematical precision” (id.). This standard has sometimes also
    been stated as the moving party “bear[ing] the burden . . . of proving the amount of
    loss with sufficient certainty so that the determination of the amount of damages will
    be more than mere speculation”. Lisbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 767 (Fed. Cir. 1987). To prevail, appellant must prove three elements:
    (1) liability- that the government did something that changed the contractor’s costs for
    which the government is legally liable, i.e. entitlement; (2) causation-that there exists a
    causal nexus between the basis for liability and the claimed increase in costs; and
    (3) resultant injury. Servidone Constr. Corp. v. United States, 
    931 F.2d 860
    , 861 (Fed.
    Cir. 1991). We conclude, based upon our findings, that appellant has proven its
    damages with reasonable certainty. Additionally, we conclude that appellant has
    proven entitlement, causation, and resultant injury entitling appellant to an equitable
    adjustment under the changes clause in the amount of $924,295, plus interest under
    
    41 U.S.C. § 7109
     from September 6, 2013 until payment. (Findings 53-81)
    DECISION
    COMPENSABLE DELAY CLAIM - 
    ASBCA No. 60760
    Entitlement
    ECC seeks a compensable contract extension in the amount of $916,840.82 for
    114 calendar days of delay for the period between July 31, 2011 and November 21,
    2011. “To prove entitlement to a compensable delay, [ECC] must show that the
    government was responsible for specific delays; overall project completion was
    delayed as a result; and any government-caused delays were not concurrent with
    delays within appellant’s control”. WECC, Inc., 
    ASBCA No. 60949
    , 
    21-1 BCA ¶ 37,948
     at 184,306, citing,Columbia State Bank, 
    ASBCA No. 59531
    , 
    16-1 BCA ¶ 36,399
     at 177,456, (quoting, Versar, Inc., 
    ASBCA No. 56857
     et al., 
    12-1 BCA ¶ 35,025
     at 172,128). Additionally, ECC “must show that the government’s actions
    affected activities on the critical path of the contractor’s performance of the contract.”
    Kinetic Builder’s Inc. v. Peters, 
    226 F.3d 1307
    , 1317 (Fed. Cir. 2000).
    ECC submitted an expert report that found ECC is entitled to 114 calendar days
    of compensable delay for the period between July 31, 2011 and November 21, 2011
    (findings 42-48). Based upon our review of the report, we concur with its conclusions.
    40
    Accordingly, our findings establish that the government was responsible for specific
    delays; the overall project completion was delayed as a result; the government-caused
    delays were not concurrent with delays within appellant’s control; and, the
    government’s actions affected activities on the critical path of the contractor’s
    performance of the contract (findings 41-46). The government did not submit any
    testimony or brief in opposition to appellant’s expert report. The government did
    submit two emails in opposition that responded to appellant’s REA submittal but not to
    the appellant’s expert report. Consequently, we did not ascribe any weight to these
    submittals. (Findings 47-48)
    We conclude that ECC has proven entitlement to a compensable delay of 114
    calendar days.
    Quantum Compensable Delay Claim, 
    ASBCA No. 60760
    Appellant presented testimony from Mr. Leung explaining that he prepared the
    cost calculations for the delay claim and how the claimed costs were collected and
    captured in ECC’s accounting system. He also testified that the associated general
    requirements costs (or extended field overhead costs) were included within the delay
    claim and how he calculated those costs. (Findings 83-85) Appellant’s claim included
    a large amount of detailed support documentation (888 pages of supporting costs data)
    collected from ECC’s accounting system that included names of employees, payment
    amounts, etc. (Finding 85) Below is a summary of our findings:
    COMPENSABLE DELAY CLAIM COST SUMMARY
    Direct Labor                              $251,682
    Fringe                                     $63,619
    Overhead                                  $139,205
    Subtotal Total Labor                      $454,506
    Subtotal Non Labor (ODCs)                 $388,643
    G&A                                        $73,691
    Entitlement Total                         $916,840
    Unlike the removal and replacement claim, the government did not submit a
    DCCA audit addressing this compensable delay claim. In fact, the government did not
    submit anything in opposition to this claim (finding 87).
    Based upon our review of Mr. Leung’s testimony and the associated supporting
    data, we conclude that appellant has met its burden of proof by a preponderance of the
    evidence. Additionally, the government has not entered any evidence in opposition.
    Accordingly, we conclude appellant is entitled to compensable delay in the amount of
    $916,840 with interest under 
    41 U.S.C. § 7109
     running from April 19, 2016 till paid.
    41
    Liquidated Damages
    The government assessed liquidated damages based upon 69 days of delay in
    the amount of $429,906 (finding 38). The government is not entitled to these damages
    because we have determined ECC is entitled to 114 days of excusable delay.
    CONCLUSION
    ECC’s appeal in 
    ASBCA No. 59280
     is sustained and ECC is entitled to
    $924,295 with interest under 
    41 U.S.C. § 7109
     running from September 6, 2013 until
    paid. Additionally, ECC’s appeal in 
    ASBCA No. 60760
     is sustained and ECC is
    entitled to $916,840 in compensable delay damages with interest under 
    41 U.S.C. § 7109
     running from April 19, 2016 until paid. The government assessed liquidated
    damages based upon 69 days of delay in the amount of $429,906. The government is
    not entitled to these damages.
    Dated: July 15, 2022
    JOHN J. THRASHER
    Administrative Judge
    Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                       I concur
    RICHARD SHACKLEFORD                            OWEN C. WILSON
    Administrative Judge                           Administrative Judge
    Vice Chairman                                  Vice Chairman
    Armed Services Board                           Armed Services Board
    of Contract Appeals                            of Contract Appeals
    42
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 59280, 60760, Appeals of
    Environmental Chemical Corporation, rendered in conformance with the Board’s
    Charter.
    Dated: July 15, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    43