Relyant Global LLC ( 2022 )


Menu:
  •              ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                               )
    )
    Relyant Global LLC                          )    ASBCA Nos. 63024, 63257
    )
    Under Contract No. W912QR-18-C-0026         )
    APPEARANCES FOR THE APPELLANT:                   James H. Price, Esq.
    Michael R. Franz, Esq.
    Lacy, Price & Wagner, P.C.
    Knoxville, TN
    APPEARANCES FOR THE GOVERNMENT:                  Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Brett R. Howard, Esq.
    Thomas M. Barrett, Esq.
    James M. Inman, Esq.
    Engineer Trial Attorneys
    U.S Army Engineer District, Louisville
    OPINION BY ADMINISTRATIVE JUDGE O’CONNELL
    ON RESPONDENT’S MOTION TO STRIKE
    Respondent, the United States Army Corps of Engineers (USACE), has moved
    to strike Count III of appellant’s complaint, which is entitled Quantum
    Meruit/Quantum Valebant/Unjust Enrichment. The Board grants the motion and
    dismisses Count III for failure to state a claim.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    Appellant, Relyant Global LLC (Relyant), alleges the following in its
    complaint.
    The parties entered into the above-captioned firm-fixed price contract on
    August 9, 2018. The contract provided for Relyant to design and build a shipping
    and receiving building located at Fort McCoy, Wisconsin for $7,030,235.27.
    (Compl. ¶ 6)
    A dispute developed as to whether the contract required Relyant to include in
    the design a ceiling or other physical barrier in the freight area of the building to
    prevent storage greater than 10 feet in height (compl. ¶¶ 8-9, 15-16). After
    discussions, USACE required Relyant to either redesign the building’s fire suppression
    system or install a new ceiling to create a physical barrier to prevent storage above
    10 feet (id. ¶ 18). Relyant chose the latter option, designing and installing an added
    ceiling, but it contends that this was a constructive change to the contract (id. ¶ 19).
    Relyant submitted a claim to the contracting officer (CO) for $242,492.41 in
    added costs and a 110-day time extension for the ceiling work. The CO denied the
    claim on June 11, 2021. (Compl. ¶ 22) Relyant filed an appeal on September 7, 2021.
    Relyant’s complaint contains six counts alleging a variety of theories, including
    breach of contract (Count II), breach of the covenant of good faith and fair dealing
    (Count IV), and constructive change/cardinal change (Count V). The count relevant to
    the pending motion is Count III – Quantum Meruit/Quantum Valebant/Unjust
    Enrichment.
    The crux of Count III is conveyed by the following allegation:
    [T]he Army has been unjustly enriched and equity requires
    that the Army make payment to Relyant for the full value
    of the goods and services conferred upon the Army by
    Relyant – $242,492.41 plus interest, attorneys’ fees, and
    any other recoverable costs. Relyant is entitled to relief
    under the doctrines of quantum meruit, quantum valebant,
    unjust enrichment, and any other applicable theory of
    implied-in-fact contracts.
    (Compl. ¶ 40) Relyant does not contend that the contract is void or illegal. It states in
    the first paragraph of the complaint that “[t]his claim is based on an express written
    contract with the Army” (id. ¶ 1). It states in Count III that the goods and services
    at issue were “provided by Relyant under the Contract . . . .” (id. ¶ 39).
    DECISION
    In its motion to strike, USACE contends that the Board lacks jurisdiction to
    consider Relyant’s unjust enrichment cause of action because it is based on an
    implied-in-law contract theory. It further contends that the Board lacks jurisdiction to
    consider Relyant’s quantum meruit or quantum valebant theories 1 because USACE
    has not refused to pay due to the contract being illegal or void. (Gov’t mot. at 3-4)
    1
    Quantum meruit refers to services while quantum valebant refers to goods, but there
    is usually no significance to this difference. Barrett Refining Corp. v. United
    States, 
    242 F.3d 1055
    , 1059 n.1 (Fed. Cir. 2001) (citations omitted).
    2
    Relyant responds by emphasizing that it is not asserting an implied-in-law
    contract theory, only an implied-in fact contract that is within the Board’s jurisdiction
    (app. resp. at 1 (citing compl. ¶ 40)). Relyant further contends that at this early stage
    of the appeal it is allowed to proceed on alternative theories and that it should be
    allowed to take discovery that may reveal the existence of an implied-in-fact contract
    (app. resp. at 2-3).
    The Board agrees with USACE. Recovery in quantum meruit or quantum
    valebant is typically based on an implied-in-law contract, a type of claim that we lack
    jurisdiction to consider. Lee v. United States, 
    895 F.3d 1363
    , 1373 (Fed. Cir. 2018);
    Protec GmbH, 
    ASBCA No. 61161
     et al., 
    18-1 BCA ¶ 37,064
     at 180,420. Similarly,
    the Board lacks jurisdiction to consider an unjust enrichment theory because it is also
    based on a contract implied-in-law. Cross Country Indus., Inc. v. United States,
    
    231 Ct. Cl. 899
    , 901 (1982).
    There is one relevant exception to these rules. Quantum meruit can be used as a
    measure of damages for breach of an implied-in-fact contract. Lee, 895 F.3d at 1374;
    United States v. Amdahl Corp., 
    786 F.2d 387
    , 393 (Fed. Cir. 1986). The Board
    possesses jurisdiction to consider appeals based on an implied-in-fact contract.
    Engage Learning, Inc. v. Salazar, 
    660 F.3d 1346
    , 1354 (Fed. Cir. 2011). But this
    would only help Relyant if it had a viable implied-in-fact contract theory.
    Relyant’s complaint generally contends that the work on the ceiling was not
    required by the express contract and is a change or extra work for which it is entitled
    to additional time and money. In Count III, it asserts an implied-in-fact contract
    theory. Relyant cannot pursue both theories. As the Court of Appeals for the Federal
    Circuit has explained, “[i]t is well settled that ‘the existence of an express contract
    precludes the existence of an implied-in-fact contract dealing with the same subject
    matter, unless the implied contract is entirely unrelated to the express contract.’”
    Lee, 895 F.3d at 1370 (quoting Bank of Guam v. United States, 
    578 F.3d 1318
     ,
    1329 (Fed. Cir. 2009) (quoting Schism v. United States, 
    316 F.3d 1259
    , 1278 (Fed.
    Cir. 2002) (en banc)). Because Relyant does not contend that the express contract was
    void and because it does not (and cannot) contend that the addition of a ceiling in the
    building it designed and constructed was entirely unrelated to the express contract,
    Count III must be dismissed.
    Relyant cites the Federal Circuit’s decision in Amdahl as an example of a
    contractor obtaining relief under an implied-in-fact contract theory. In Amdahl, the
    contractor provided goods to the government, but the contract was void due to
    statutory and regulatory violations in the procurement process. The Federal Circuit
    held that if the contractor conferred a benefit on the government, it could recover for
    the value of the conforming goods under an implied-in-fact contract on a quantum
    3
    meruit or quantum valebant basis. Amdahl, 
    786 F.2d at 393
    ; see Lee, 895 F.3d
    at 1374.
    Amdahl has no relevance to these appeals. As the Federal Circuit later
    explained, “Amdahl speaks to the situation in which the government receives the
    goods or services for which it contracted, but then seeks to avoid payment by arguing
    that the underlying contract was unlawful.” United Pac. Ins. Co. v. United States,
    
    464 F.3d 1325
    , 1334 (Fed. Cir. 2006). Neither Relyant nor USACE contends that the
    contract at issue was unlawful. USACE has not withheld payment because it believes
    that the contract, or any clause in that contract, is void or illegal. The parties simply
    disagree over the correct interpretation of the express contract and, as result, disagree
    whether the design and construction of the ceiling was required by that contract.
    Finally, the Board also rejects Relyant’s request that the Board deny the motion
    to dismiss so that it can take discovery that may uncover the existence of an implied-
    in-fact contract. Because it is undisputed that there is a valid written contract, the
    mere possibility that evidence might exist supporting a completely different set of facts
    is not enough to deny the motion. See Pure Gold, Inc. v. Syntex (U.S.A.), Inc.,
    
    739 F.2d 624
    , 627 (Fed. Cir. 1984).
    While the government moves to strike Count III based on a lack of jurisdiction,
    the Board possesses jurisdiction to consider implied-in-fact contract claims, as
    described above. In Lee, the Federal Circuit affirmed dismissal for failure to state a
    claim. Lee, 895 F. 3d at 1374. Accordingly, the Board dismisses Count III for failure
    to state a claim.
    CONCLUSION
    Count III of the complaint is dismissed for failure to state a claim.
    Dated: September 27, 2022
    MICHAEL N. O’CONNELL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    4
    I concur                                         I concur
    RICHARD SHACKLEFORD                              OWEN C. WILSON
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 63024, 63257, Appeal of
    Relyant Global LLC, rendered in conformance with the Board’s Charter.
    Dated: September 29, 2022
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    5