Haakenson Electric Company ( 2020 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Haakenson Electric Company                    )     ASBCA No. 62606
    )
    Under Contract No. W911KB-18-C-0010           )
    APPEARANCES FOR THE APPELLANT:                      Raymond H. Royce III, Esq.
    Taylor B. McMahon, Esq.
    Royce & Brain
    Anchorage, AK
    APPEARANCES FOR THE GOVERNMENT:                     Michael P. Goodman, Esq.
    Engineer Chief Trial Attorney
    Carl F. Olson, Esq.
    Engineer Trial Attorney
    U.S. Army Engineer District, Alaska
    OPINION BY ADMINISTRATIVE JUDGE SWEET
    On August 20, 2020, the government filed a motion to dismiss, arguing that we do
    not possess jurisdiction over this appeal because it involves a direct subcontractor claim,
    and is untimely. Appellant Haakenson Electric Company (Haakenson or subcontractor)
    responds that the appeal involves a pass-through claim, and is timely because appellant
    provided a timely, albeit misdirected, notice of appeal to the contracting officer (CO). As
    discussed in greater detail below, we do not decide whether this is a pass-through claim
    because, even assuming that it is, the appeal is untimely. 1
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On April 16, 2018, the Army Corps of Engineers (government) entered into
    Contract No. W911KB-18-C-0010 (0010 Contract) with ASRC Builders LLC (ASRC or
    prime contractor) to renovate an Aircraft Maintenance Unit and weather shelter (R4, tab 3
    at 25-26).
    2. The prime contractor entered into a subcontract with Haakenson (app. resp. ex. B).
    1   We do not address appellant’s request that we re-caption this appeal to include the
    prime contractor’s name because we do not decide whether this appeal involves a
    pass-through claim.
    3. On January 29, 2020, the prime contractor submitted a claim to the CO on behalf
    of itself and the subcontractor (R4, tab 8 at 60-61). The prime contractor’s project manager
    signed the claim (id. at 60).
    4. On April 14, 2020, the CO issued a final decision (COFD) denying the claim (R4,
    tab 2 at 3, 16-21). The prime contractor received the COFD on April 14, 2020 (R4, tab 9
    at 174).
    5. On May 29, 2020—less than 90 days after receiving the COFD—the prime
    contractor’s quality control manager emailed the government, requesting help finding a copy
    of the COFD on a file sharing system, stating that “[o]ur electrical subcontractor intends to
    appeal this decision” (app. resp., Chamberlain aff., ex. 1). There is no evidence that either
    the prime contractor or the subcontractor authorized the prime contractor’s quality control
    manager to pursue an appeal.
    6. On July 14, 2020—91 days after the prime contractor received the COFD—
    Raymond Royce of the Law Offices of Royce & Brain filed a notice of appeal with the
    Board. 2
    DECISION
    Although we entertain serious doubts that this appeal constitutes a legitimate
    pass-through claim because (notwithstanding appellant’s attempt to implicitly re-caption
    the case) it was not brought in the name of the prime contractor, we will decide this
    motion on the simpler matter of timeliness, finding that we do not possess jurisdiction
    because the appeal was brought too late. Under the Contract Disputes Act, 41 U.S.C.
    § 7104(a), we only possess jurisdiction over an appeal if a contractor files the appeal
    within 90 days of its receipt of the COFD. Cosmic Constr. Co. v. United States, 
    697 F.2d 1389
    , 1390-91 (Fed. Cir. 1982); Anaconda Constr. Co., ASBCA No. 60905, 17-1 BCA
    ¶ 36,789 at 179,315. Because the 90 day deadline is part of a statute waiving sovereign
    immunity, it must be strictly construed, and may not be waived. Cosmic 
    Constr., 697 F.2d at 1390-91
    . Thus, even if an appellant files an appeal 91 days after its receipt of the
    COFD, we do not possess jurisdiction over that appeal. Quimba Software, Inc., ASBCA
    No. 57636, 12-1 BCA ¶ 34,910 at 171,652.
    A misdirected appeal filed with the CO instead of the Board may satisfy the timely
    notice of appeal requirement. Afghan Active Grp., ASBCA No. 60387, 16-1 BCA
    ¶ 36,349 at 177,211. However, a person authorized to file an appeal must file any notice
    of appeal. Garrison Engineers Constr., Inc., ASBCA Nos. 29015, 29536, 85-1 BCA
    2   The notice of appeal was captioned as being brought by Haakenson Electric Company,
    the subcontractor. Appellant has subsequently captioned its submissions to the
    Board as being brought by ASRC, without requesting us to re-caption it.
    2
    ¶ 17,731; Universal Programming & Sys., Inc., ASBCA No. 15155, 71-1 BCA ¶ 8,900;
    Board Rule 1(b). The burden of establishing the Board’s jurisdiction over an appeal
    arising from the denial of a contractor claim is on the appellant. JWK Int’l Corp., 04-1
    BCA ¶ 32,561 at 161,057.
    Here, appellant has failed to meet its burden of establishing that it filed a timely
    appeal. Appellant did not file the July 14, 2020 notice of appeal with the Board until
    91 days after the prime contractor’s receipt of the COFD on April 14, 2020. (SOF ¶¶ 4,
    6) Therefore, the July 14, 2020 notice of appeal was untimely, and does not establish our
    jurisdiction. Quimba, 12-1 BCA ¶ 34,910, at 171,652.
    Instead of relying upon the July 14, 2020 notice of appeal, appellant argues that
    the May 29, 2020 email from the prime contractor’s quality control manager was a
    timely, albeit misdirected, notice of appeal. (App. resp. 2-3) However, by its own terms,
    that email appears to have been a request for help finding a document (the COFD) so that
    the subcontractor could pursue the appeal, not a notification of the appeal by that quality
    control manager on behalf of the prime contractor. Moreover, appellant has failed to
    show that either the prime contractor or the subcontractor authorized the prime
    contractor’s quality control manager to pursue an appeal (SOF ¶ 5). On the contrary, the
    fact that someone from the prime contractor besides the quality control manager signed
    the claim (SOF ¶¶ 3, 5), suggests that the quality control manager lacked such authority
    (which is consistent with the apparent goal of the email – document gathering). Because
    appellant has failed to show that a person authorized to file an appeal submitted the
    May 29, 2020 email, that email does not constitute an authorized notice of appeal
    sufficient to establish our jurisdiction, even if that email could constitute a misdirected
    notice of appeal—which we seriously doubt. Garrison, 85-1 BCA ¶ 17,731; Universal
    Programming, 71-1 BCA ¶ 8,900.
    CONCLUSION
    We do not possess jurisdiction because appellant failed to file a timely notice of
    appeal. Therefore, we grant the government’s motion to dismiss, and dismiss this appeal
    with prejudice.
    Dated: December 7, 2020
    JAMES R. SWEET
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    3
    I concur                                       I concur
    RICHARD SHACKLEFORD                            J. REID PROUTY
    Administrative Judge                           Administrative Judge
    Acting Chairman                                Vice Chairman
    Armed Services Board                           Armed Services Board
    of Contract Appeals                            of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 62606, Appeal of Haakenson
    Electric Company, rendered in conformance with the Board’s Charter.
    Dated: December 8, 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    4
    

Document Info

Docket Number: ASBCA No. 62606

Judges: Sweet

Filed Date: 12/7/2020

Precedential Status: Precedential

Modified Date: 12/28/2020