Aerospace Facilities Group, Inc. ( 2020 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                  )
    )
    Aerospace Facilities Group, Inc.              )      ASBCA No. 61026
    )
    Under Contract No. W912NW-12-C-0035           )
    APPEARANCES FOR THE APPELLANT:                       Theodore P. Watson, Esq.
    Watson and Associates LLC
    Washington, DC
    Wojciech Z. Kornacki, Esq.
    Watson & Associates LLC
    Denver, CO
    APPEARANCES FOR THE GOVERNMENT:                      Scott N. Flesch, Esq.
    Army Chief Trial Attorney
    Robert B. Neill, Esq.
    MAJ Mark T. Robinson, JA
    Trial Attorneys
    OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
    Appellant, Aerospace Facilities Group, Inc. (AFG), appeals from the
    termination of its contract to deliver “paint booth equipment” (for the painting of
    helicopters) to the Corpus Christi Army Depot; AFG also seeks breach damages
    (app. br. at 1, 32). Only entitlement is before us (tr. 1/7).
    STATEMENT OF FACTS
    In Aerospace Facilities Grp., Inc., ASBCA No. 61026, 18-1 BCA ¶ 37,105
    at 180,602-03, we recited facts that we incorporate here by reference. Familiarity with
    that opinion is presumed. In addition, the contract incorporates by reference Federal
    Acquisition Regulation (FAR) 52.249-1, TERMINATION FOR CONVENIENCE OF
    THE GOVERNMENT (FIXED PRICE) (SHORT FORM) (APR 1984), and
    FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY & SERVICE) (APR 1984)
    (R4, tab 1 at 68). AFG contracted with Global Finishing Solutions (GFS) to obtain the
    paint booth equipment required by the contract (see app. br. 1, 6 ¶ 14). On
    November 9, 2015, Contracting Officer June Gowen issued the following unilateral
    modification, withholding payment of $342,600 under the contract at issue here until
    AFG provided four pieces of equipment called “ergo test stands” due under a different
    contract between AFG and the government (Contract No. W912NW-12-C-0031),
    which were also meant for the Corpus Christi Army Depot:
    1. BACKGROUND: Aerospace Facilities Group has
    failed to deliver and install four ergo test stands called for
    in the specifications of Contract No. W912NW-12-C-0031.
    2. ACTIONS TAKEN: Because of this, funding will be
    withheld from another Aerospace Facilities Group contract,
    W912NW-12-C-0035 until such time as Aerospace
    Facilities Group delivers and installs the four ergo test
    stands at the Corpus Christi Army Depot. The amount of
    $342,600.00 has been moved out of CLIN 0001AA into
    new CLIN 0002. This amount will be withheld from
    payments in contract W912NW-12-C-0035 until such time
    as Aerospace Facilities Group delivers and installs the four
    ergo test stands at the Corpus Christi Amount Depot [under
    Contract No. W912NW-12-C-0031].
    R4, tab 35 at 1 (alteration added)
    On January 28, 2016, Ms. Gowen issued a unilateral modification that purports
    to incorporate into the contract FAR 52.212-4, CONTRACT TERMS AND
    CONDITIONS – COMMERCIAL ITEMS (MAY 2015) (R4, tab 49 at 1). On
    March 30, 2016, the parties modified the contract to extend the period of performance
    through June 28, 2016 (see R4, tab 92 at 1-3). That modification also provides:
    Installation payments were erroneously paid to contractor
    prior to installation efforts being performed. All funding
    prematurely and erroneously paid on CLINS 0001AF in
    the amount of $772,550.48 and 0001AS in the amount of
    $837,298.93, totaling $1,609,849.41, shall be returned to
    the Government by AFG via credits to all future invoices
    until paid in full.
    (Id. at 3)
    AFG did not deliver the paint booth equipment to the government by the
    contract’s June 28, 2016 deadline; indeed, AFG never delivered any of the paint booth
    equipment required by the contract (see app. br. at 1; tr. 1/31, 193). On July 8, 2016,
    Contracting Officer Peggy Echols issued to AFG an Order to Show Cause, informing
    AFG that the government was considering terminating the contract for default (R4,
    2
    tab 133). On July 27, 2016, AFG responded, admitting that it did not deliver the paint
    booth equipment on time--even though, according to AFG, the paint booth equipment
    had been manufactured and was in AFG’s storage--because, AFG said, the
    government had not made a $342,600 payment to AFG:
    All of the equipment for contract (W912NW-12-C-0035)
    has been manufactured and in our storage since June 2015
    awaiting the government to complete the ACCF building
    where the equipment is going to be installed. . . . The
    equipment delivery date (June 2016) given to AFG by the
    government could not be met by [sic] due to the fact that
    the government held up the contractual agreed payments of
    $304,406.32, so in turn AFG could not fulfill our
    contractual agreements with our suppliers.
    (R4, tab 157 at 4) AFG admitted to its “failure to perform on this contact [sic],” and
    explained that, in its view, that failure was “due to the government issui[ng a h]old on
    our contractual payment schedule set up for this contract” (id. at 3-4 (referencing
    “AFG failure to perform on this contract”)). Through counsel, AFG reaffirms that
    admission, stating that “the cause of the non-delivery” was AFG’s “subcontractor not
    getting paid” (app. br. at 14), and that AFG “did not pay their subcontractors”
    (tr. 1/79). Indeed, in its post-hearing brief, AFG states:
    [AFG] also explained [to the government] that it could not
    meet the delivery date imposed by [the government]
    because [the government] did not make contractual
    payments to [AFG] which prevented [AFG] from making
    payments to the sub-contractor.
    (App. br. at 11 ¶ 53) (alterations added)
    However, AFG could have paid GSF for the paint booth equipment, from
    corporate funds. During the hearing of this appeal, AFG’s owner, Dennis Robinson,
    read the following from his deposition:
    Question: “But you could have paid Global Finishing
    Solutions with the money you had in the corporate
    account. Correct?” Answer: “Yes.”
    (Tr. 2/135, 171) AFG simply decided not to pay GFS because, in AFG’s view, the
    government owed AFG money:
    3
    Question: Is the reason why you didn’t pay Global
    Finishing Solutions because you believed that the
    Government owed you money on those additional invoices
    you submitted?
    [Mr. Robinson] Yes.
    ...
    Question: So [the Order to Show Cause is] dated July 8,
    2016. And so by that date, the final delivery date
    established in modification 6 had passed. Did you still not
    intend to deliver the paint booths until you received the
    payments that you believed were owed under the contract
    to you in order to pay Global Finishing Solutions?
    [Mr. Robinson] That is correct.
    (Id. at 171, 193) Additionally, Mr. Robinson testified that AFG could have paid its
    supplier from corporate funds, but chose not to do so because “[AFG] wasn’t going to
    be the bank for the government” (id. at 172, 216).
    Finally, the government was ready to receive the paint booth equipment when it
    was due: on this point, on May 31, 2016, Ms. Echols wrote to AFG that “the
    government has identified storage space for the remaining paint booth equipment”
    (R4, tab 114). In addition, the judge who presided over the hearing elicited the
    following answer to the following question:
    JUDGE YOUNG: So does this mean that, even though
    there was a concern about storage costs, the Government
    was ready to receive equipment?
    [Ms. Gowen]: Yes.
    (Tr. 1/212)
    On August 4, 2016, Ms. Echols issued a modification terminating the contract
    for default (using the term “Termination for Cause”), citing FAR 52.212-4(m) and
    stating that AFG had “failed to deliver in accordance with the terms of the contract”
    (R4, tab 158 at 1-2; see also tab 159 (cover letter to AFG)).
    4
    DECISION
    Termination for default
    The government says that FAR 52.212-4 is incorporated into the contract by the
    Christian doctrine (gov’t br. at 29). We need not address that issue, nor whether
    Ms. Gowen’s unilateral modification, purporting to incorporate that clause into the
    contract, is a nullity. The contract incorporates FAR 52.249-8, Default, which
    provides, at paragraph (a)(1):
    The Government may . . . by written notice of default to
    the Contractor, terminate this contract in whole or in part if
    the Contractor fails to—
    (i) Deliver the supplies or to perform the services
    within the time specified in this contract or any
    extension.
    FAR 52.249-8, itself, provides the contractual authority to terminate the contract under
    the circumstances of this case. See CKC Sys., Inc., ASBCA No. 61025, 19-1 BCA
    ¶ 37,385 at 181,749-50.
    The government says that the termination is justified because AFG failed to
    deliver the paint booth equipment by the contract delivery date (gov’t br. at 1). We
    agree. Because AFG did not deliver the paint booth equipment by the contract
    completion date, AFG defaulted; consequently, the termination for default is justified.
    See Truckla Services, Inc., ASBCA Nos. 57564, 57752, 17-1 BCA ¶ 36,638
    at 178,445.
    Now it’s up to AFG to demonstrate that its default is excused. HK&S Constr.
    Holding Corp., ASBCA No. 60164, 19-1 BCA ¶ 37,268 at 181,352. AFG says that
    the government caused the default (including in bad faith) by withholding a $342,600
    payment to AFG that AFG says it needed to pay GFS for the paint booth equipment
    (app. br. at 1, 12-17, 23-27). We conclude otherwise: AFG is responsible for the
    default by not paying GFS for the paint booth equipment, even though it could have
    done so out of its corporate funds. ∗ Cf. Puma Energy Honduras, S.A. De C.V.,
    ASBCA No. 61966, 20-1 BCA ¶ 37,507 (granting summary judgment; finding no
    ∗
    In view of this conclusion, we need not decide whether, as AFG’s July 27, 2016
    letter ostensibly indicates, AFG actually had the paint booth equipment in its
    storage, available for AFG to deliver to the government notwithstanding any
    payment owed by the government to AFG (R4, tab 157 at 4 (“All of the
    equipment . . . has been manufactured and in our storage since June 2015”)).
    5
    dispute that contractor’s internal business practices, as well as its own invoicing errors,
    were the reason it failed to perform). In addition, the parties modified the contract to
    provide for the return to the government of up to $1,609,849.41 paid to AFG “via
    credits to all future invoices until paid in full,” expressly providing the government a
    contractual right to set off money owed to AFG against money that AFG owed to the
    government. Moreover, the government always had the same, common-law right
    “which belongs to every creditor, to apply the unappropriated moneys of his debtor, in
    his hands, in extinguishment of the debts due to him.” United States v. Munsey Tr. Co.
    of Washington, D.C., 
    332 U.S. 234
    , 239 (1947); accord Johnson v. All-State Constr.,
    Inc., 
    329 F.3d 848
    , 852 (Fed. Cir. 2003) (“The set-off right applies to government
    claims both under other contracts . . . and under the same contract.”); Raytheon Co.,
    Space & Airborne Sys., ASBCA No. 57801, 15-1 BCA ¶ 36,024 at 175,952 (“the
    government could use Contract II to offset debts that arose on other contracts”).
    AFG also says that it directed GFS to deliver the paint booth equipment, but
    that GFS refused (app. br. at 16-17, 31); but, if that is so, AFG is still responsible for
    the failure to deliver the paint booth equipment, because a contractor is responsible for
    the unexplained failures of its subcontractors. See Williamsburg Drapery Co. v.
    United States, 
    369 F.2d 729
    , 742 (Ct. Cl. 1966); United Schools of America, Inc.,
    ASBCA No. 38628, 90-3 BCA ¶ 23,199 at 116,426. AFG also appears to blame
    government communications with GFS for AFG’s failure to deliver the paint booth
    equipment (app. br. at 16-17); but we find AFG’s admissions that the default was the
    result of non-payment to GFS conclusive on this point. In addition, AFG appears to
    say that the government acted in bad faith to remove AFG so that it could contract
    with GFS (app. br. at 23-27), but we find none of the clear and convincing evidence
    that government officials acted from personal animus with the specific intent to injure
    AFG that would be necessary for AFG to overcome the presumption that the
    government officials who administered the paint booth equipment contract acted in
    good faith. See Watts Constructors, 19 BCA ¶ 37,382 at 181,728; Road and Highway
    Builders, LLC v. United States, 
    702 F.3d 1365
    , 1368 (Fed. Cir. 2012); Am-Pro
    Protective Agency, Inc. v. United States, 
    281 F.3d 1234
    , 1240 (Fed. Cir. 2002); Grow
    Life Gen. Trading, LLC, ASBCA No. 60938 et al., 19-1 BCA ¶ 37,361 at 181,676;
    Puget Sound Envtl. Corp., ASBCA No. 58828, 16-1 BCA ¶ 36,435 at 177,597-98.
    Finally, AFG says that had it delivered the paint booth equipment on time, the
    government would have had no place to store it (app. br. at 17). We reject this
    argument, for two reasons. First, AFG does not demonstrate that its obligation to
    deliver the paint booth equipment was contingent upon the government identifying a
    place to store it. Second, we have found that the government was ready to receive the
    paint booth equipment when it was due.
    AFG says that we should convert the default termination to one for the
    convenience of the government because, it says, Ms. Echols did not follow the
    6
    termination consideration factors listed at FAR 49.402-3(f) (app. br. at 17-21). We
    disagree. In McDonnell Douglas Corp. v. United States, 
    35 Fed. Cl. 358
    , 371-72
    (1996), the court found that the contracting officer had not considered the
    FAR 49.402-3(f) termination factors and had not exercised discretion in terminating
    the contract for default, holding that the termination was prompted not by the
    contractor’s default, but by the decision of the Secretary of Defense to withdraw
    funding for the A-12 program. The United States Court of Appeals for the Federal
    Circuit reversed, holding that the contracting officer terminated the contract for
    reasons related to contract performance: “the government denied additional funding
    for the A-12 program and terminated the contract for default because of concerns
    about contract specifications, contract schedule, and price—factors [all of which] are
    fundamental elements of contract performance.” McDonnell Douglas Corp. v. United
    States, 
    182 F.3d 1319
    , 1329 (Fed. Cir. 1999).
    Here, even if Ms. Echols did not address each of the factors in FAR 49.402-3(f),
    timely delivery of the paint booth equipment was a fundamental element of contract
    performance, and AFG’s failure to satisfy that fundamental element constitutes default.
    However Ms. Echols arrived at her termination decision, the government may rely upon
    AFG’s failure to do its job to justify the termination. HK&S, 19-1 BCA ¶ 37,268
    at 181,352; see Watts Constructors, LLC, ASBCA No. 61518, 19-1 BCA ¶ 37,382
    at 181,728 (citing and parenthetically quoting HK&S with approval). To paraphrase the
    Federal Circuit, if the government can establish that a contractor was in default, then
    the termination of the contract for default is valid.
    AFG says that the government waived the default termination by engaging in
    post-termination discussions with AFG in an attempt to obtain the paint booth
    equipment (app. br. at 27). In Aerospace Facilities, 18-1 BCA ¶ 37,105 at 180,605,
    for purposes of determining whether the notice of appeal was untimely, we held that
    “[t]he [government’s] willingness to engage AFG, discuss the facts surrounding the
    termination on three separate occasions and discuss whether AFG would deliver the
    paint-booth equipment served to keep the matter open and destroyed the finality of the
    termination notice.” However, we do not agree that the government “waived” its
    termination of the contract for default by engaging in post-termination discussions in
    an effort to obtain the paint booth equipment.
    AFG says that Ms. Echols did not exercise independent discretion in
    terminating the contract, but was directed to do so by her superiors (see tr. 1/184-85;
    app. br. at 36-37). We need not decide that issue. The contract incorporates
    FAR 52.249-8(a)(1), which provides (emphasis added) that “[t]he Government may
    . . . terminate this contract” for default; consequently, it does not matter whether
    Ms. Echols was directed by her superiors to terminate the contract. See Schlesinger v.
    United States, 
    390 F.2d 702
    , 709 & n.9 (Ct. Cl. 1968).
    7
    Breach of contract
    Finally, the government says that the Board does not possess jurisdiction to
    entertain claims for money damages for alleged government breaches of contract
    because AFG has not presented a claim for those damages to a contracting officer
    (gov’t br. at 41). The Board’s jurisdiction to entertain a contractor’s claim depends
    upon the contractor first submitting that claim to a contracting officer for a final
    decision. CDM Constructors, Inc., ASBCA No. 59524, 15-1 BCA ¶ 36,097
    at 176,238. Moreover, AFG must prove by a preponderance of the evidence that the
    Board possesses jurisdiction to entertain its monetary claims. See Parsons Gov’t
    Servs., Inc., ASBCA No. 62113, 20-1 BCA ¶ 37,586 at 182,508. AFG does not point
    to any money claim (or any claim at all) that it presented to the contracting officer;
    indeed, AFG seems to argue that it is not necessary for it to have done so (see app. br.
    at 32 (“To somehow suggest that [] there should be a concise [Contract Disputes Act]
    claim submitted to the contracting officer is unreasonable.”)). Because AFG has not
    proven that the Board possesses jurisdiction to entertain its money claims, those claims
    are dismissed.
    CONCLUSION
    AFG’s money claims are dismissed for lack of jurisdiction. Otherwise, the
    appeal is denied.
    Dated: August 11, 2020
    TIMOTHY P. MCILMAIL
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur
    LIS B. YOUNG
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    8
    I concur                                        I concur
    RICHARD SHACKLEFORD                             OWEN C. WILSON
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61026, Appeal of
    Aerospace Facilities Group, Inc., rendered in conformance with the Board’s Charter.
    Dated: August 11, 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    9