Parsons Government Services, Inc. ( 2020 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                              )
    )
    Parsons Government Services, Inc.         )           ASBCA No. 62113
    )
    Under Contract No. W912DY-09-D-0062 et al.)
    APPEARANCES FOR THE APPELLANT:                        Kevin J. Slattum, Esq.
    Aaron S. Ralph, Esq.
    Pillsbury Winthrop Shaw Pittman LLP
    Los Angeles, CA
    APPEARANCES FOR THE GOVERNMENT:                       Arthur M. Taylor, Esq.
    DCMA Chief Trial Attorney
    Srikanti Schaffner, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Carson, CA
    OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS
    Pending before the Board is the motion to dismiss for lack of subject matter
    jurisdiction filed by respondent, the Defense Contract Management Agency
    (DCMA or government). Appellants, Parsons Government Services, Inc. (PGSI),
    formerly Parsons Infrastructure & Technology Group (PI & TG), and Parsons
    Constructors & Fabricators (PCFI) (collectively Parsons) appeal from a contracting
    officer’s final decision denying its claim regarding incurred costs from the sale and
    leaseback of a building in Pasadena, California. We find that the claim is barred by
    the statute of limitations and that it fails to assert a valid Contract Disputes Act (CDA)
    claim, and grant the government’s motion to dismiss.
    STATEMENT OF FACTS (SOF) FOR PURPOSE OF THE MOTION
    The relevant facts are not in dispute. PGSI and PCFI are both wholly-owned
    subsidiaries of the Parsons Corporation (PC) (compl. ¶¶ 5-9). 1 In the 1970s the parent
    entity (PC) constructed the Pasadena Tower Building (compl. ¶ 21). The government
    compensated Parsons for the use of the building through depreciation charges and later use
    1
    On August 28, 2019, Parsons submitted a request to file a first amended complaint to
    correct the omission of damage amounts in paragraphs 187 and 199, and to
    correct typographical errors. None of these changes are relevant to the pending
    motion to dismiss.
    charges recovered through Parsons’ incurred cost submissions (compl. ¶¶ 22-36). In 2011,
    PC sold the Pasadena Tower Building, and other nearby buildings, to a non-affiliated third
    party (compl. ¶¶ 38-39). The parent entity, PC, through another subsidiary then leased-back
    the Pasadena Tower Building with a 15 year lease (compl. ¶¶ 45-47; R4, tab 3).
    In September 2012, Parsons submitted to the government its FY2011 2 final
    indirect cost rate proposals which included PGSI and PCFI’s allocated portion of the
    lease costs for the Pasadena Tower Building and the gain on the sale of the building
    (R4, tabs 4-6). Parsons’ incurred cost proposals were still pending in March 2018,
    when, during discussions with the government regarding the incurred cost proposals,
    Parsons sent a letter to the Corporate Administrative Contracting Officer (CACO)
    arguing that it was entitled to building lease costs in excess of the amounts it proposed
    in its indirect rate proposal roughly five and half years earlier (R4, tab 13). Parsons
    concluded the letter by “respectfully request[ing] that the Government recalculate
    lease cost allowability, as well as the separate allowability of the other building costs
    the company incurred in 2011 and 2012 (id. at G-533-34). Notably, Parsons did not
    submit a revised indirect cost rate proposal incorporating the costs asserted in the
    letter, and did not include a claim certification.
    In September 2018, the CACO issued separate unilateral rate determinations for
    PGSI and PCFI for FY2011. The unilateral rate determinations rejected certain lease
    costs included in Parsons’ indirect cost rate proposals, and did not address Parsons’
    costs that were first raised in its May 2018 letter. (R4, tabs 15-16) Relevant to this
    appeal, the CACO stated in her unilateral rate determinations that “it is my final
    determination that [PGSI] included $1,237,603 of unallowable indirect costs in its
    Proposal” (R4, tab 16 at G-543; see also R4, tab 15 at G-538 for nearly identical
    language in the unilateral rate determination for PCFI). The CACO directed Parsons
    to submit adjustment vouchers for all affected contracts if the unilaterally determined
    rates differed from the rates used in Parsons’ interim billings (R4, tab 15 at G-542,
    tab 16 at G-548). However, the unilateral rate determinations did not include the
    customary notice of appeal rights (R4, tabs 15-16). The CACO sent the separate
    unilateral rate determinations to Parsons by Federal Express, and Parsons signed for
    the delivery on September 13, 2018 (gov’t mot, ex. G-1, declaration of CACO Grace
    Kim, dated September 3, 2019; ex. C).
    Over six months later, on March 24, 2019, Parsons submitted a certified claim
    to the CACO, captioned “Certified Claim for Allowability of FY2011 Leaseback
    Costs, Withdrawal of Unilateral Rate Determination and Interpretation of FAR
    Contract Terms” (R4, tab 17). Parsons asserted a breach of contract due to the
    government’s failure to allow and pay leaseback costs, and other related costs, for
    FY2011. Parsons requested withdrawal of the unilateral rate determinations and return
    2
    The contractor’s fiscal year is the calendar year (compl. ¶ 95).
    2
    of the portion of the rates paid on invoices applying the unilaterally determined rates
    (R4, tab 17 at G-555). Parsons’ claim also asserted a purported claim for contract
    interpretation regarding the Federal Acquisition Regulation (FAR) provisions for
    leaseback costs (id.). On May 24, 2019, the CACO issued a final decision denying
    Parsons’ claim and finding that it was not a valid claim because it did not assert a sum
    certain, and because it was barred by the six-year statute of limitations (R4, tab 18).
    On July 1, 2019, Parsons submitted this appeal to the Board.
    DECISION
    A. Standard of Review
    Parsons bears the burden of proving the Board’s subject matter jurisdiction by a
    preponderance of the evidence. Reynolds v. Army & Air Force Exchange Service,
    
    846 F.2d 746
    , 748 (Fed. Cir. 1988); United Healthcare Partners, Inc., ASBCA
    No. 58123, 13 BCA ¶ 35,277 at 173,156. Pursuant to the CDA, 41 U.S.C. §§ 7101-09,
    a contractor may, “within 90 days from the date of receipt of a contracting officer’s
    decision” under 41 U.S.C. § 7103 appeal the decision to an agency board. 41 U.S.C.
    § 7104(a). Our reviewing court, the United States Court of Appeals for the Federal
    Circuit, has held that CDA jurisdiction requires “both a valid claim and a contracting
    officer’s final decision on that claim.” M. Maropakis Carpentry, Inc. v. United States,
    
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010) (citing James M. Ellett Constr. Co.
    v. United States, 
    93 F.3d 1537
    , 1541-42 (Fed. Cir. 1996)).
    B. The September 2018 Unilateral Rate Determination Is A Final And
    Unappealed Government Claim
    Resolution of the Government’s motion to dismiss requires that we first address
    the September 2018 unilateral rate determination. As set forth in the facts above, this
    appeal involves the treatment of Parsons’ leaseback costs for the Pasadena Tower
    Building. It is well settled that a unilateral rate determination is a government claim.
    See FAR 52.216-7(d) (4) (“Failure by the parties to agree on a final annual indirect
    cost rate shall be a dispute within the meaning of the Disputes clause.”); Edward
    Hayes, as Liquidator of Base Operation Services GMBH, ASBCA No. 59829,
    16-1 BCA ¶ 36,412 at 177,541; Fiber Materials, Inc., ASBCA No. 53616, 07-1 BCA
    ¶ 33,563 at 166,251. Upon receipt of the unilateral rate determination, Parsons could
    either accept the determined indirect cost rate as the final rate, or appeal the unilateral
    rate to this Board or the Court of Federal Claims within the time permitted by the
    CDA. Parsons did not appeal within the allowable time period (90 days for appeals to
    the Board) and the FY2011 unilateral rate determination became Parsons’ final
    indirect cost rate. See FAR 2.101 (“Final indirect cost rate means the indirect cost
    rate established and agreed upon by the Government and the contractor as not subject
    to change.”).
    3
    Parsons’ March 2018 letter regarding additional lease costs does not change the
    finality of Parsons’ FY2011 indirect cost rate. The parties disagree whether the lease
    costs at issue could be raised by Parsons’ letter, or whether Parsons was required to
    submit a revised indirect cost rate proposal to properly place the costs before the
    CACO (gov’t mot. at 9-10; app. resp. at 6-7, 9-10); however, the proper procedure is
    irrelevant to our analysis. If Parsons’ lease costs were properly raised by the letter,
    they were rejected by the unilateral rate determination which is now the final indirect
    cost rate for FY2011. If Parsons’ lease costs were not properly raised by the letter,
    they were not considered in the unilateral rate determination, and the unilateral rate
    determination is still the final indirect cost rate for FY2011.
    C. Parsons’ March 2019 Claim Pertaining To FY2011 Indirect Rates, and
    Withdrawal of the Unilateral Rate Determination, Is Barred By The Statute
    Of Limitations
    Parsons submitted a claim to the CACO on March 24, 2019. The document
    sought (1) FY2011 leaseback costs; (2) withdrawal of the unilateral rate determination;
    and (3) interpretation of FAR contract terms (R4, tab 17 at G-555). Parsons’ claims
    for (1) FY2011 leaseback costs and (2) withdrawal of the unilateral rate determinations
    are barred by the statute of limitations. As noted in the facts, the CACO issued these
    unilateral rate determinations on September 12, 2018 (R4, tabs 15-16). The CACO
    sent the unilateral rate determination to Parsons by Federal Express, and Parsons
    signed for the delivery on September 13, 2018 (gov’t mot. at ex. G-1, ex. C). The
    CDA provides that a contractor must take an appeal to this Board within 90 days of
    receipt of a final decision 41 U.S.C. § 7104(a). 3 Thus, Parsons must have filed its
    appeal with the Board on or before December 12, 2018, for its claim to be timely.
    Parsons did not file its appeal until July 1, 2019, more than six months after the
    deadline and thus its appeal is untimely, unless the deadline was tolled, or unless there
    was a defect in the final decision that prejudiced Parsons. We find that neither of these
    exceptions apply.
    Board and Federal Circuit precedent holds that the 90 day statute of limitations is
    jurisdictional. Military Aircraft Parts, ASBCA No. 60308, 17-1 BCA ¶ 36,680
    at 178,609; Cosmic Construction v. United States, 
    697 F.2d 1389
    , 1390 (Fed. Cir. 1982).
    The Board’s precedent holds that the Federal Circuit’s holding in Sikorsky Aircraft
    Corp. v. United States, 
    773 F.3d 1315
    (Fed. Cir. 2014) that the six-year statute of
    limitations 4 is subject to equitable tolling did not overturn prior Federal Circuit
    3
    Parsons could have appealed to the United States Court of Federal Claims within one
    year of the final decision. 41 U.S.C. § 7104(b) (3). However, that deadline has
    also passed.
    4
    The six-year statute of limitations is for submitting a claim to the contracting officer.
    4
    precedent, such as Cosmic, that the 90-day statute of limitations was jurisdictional.
    Military Aircraft Parts, 17-1 BCA ¶ 36,680 at 178,609. As Parsons did not file its
    appeal within 90 days of its receipt of the unilateral rate determination, its claim
    pertaining to the FY2011 lease costs is barred by the statute of limitations.
    As noted in the facts above, the unilateral rate determinations did not include a
    notice of appeal rights. The government’s failure to include the notice of appeal rights
    does not render an otherwise valid final decision invalid. Alenia North America, Inc.,
    ASBCA No. 57935, 13 BCA ¶ 35,296 at 173,271 (citing Placeway Construction Corp.
    v. United States, 
    920 F.2d 903
    , 907 (Fed. Cir. 1990). The failure to include a notice of
    appeal rights does not prevent the start of the appeal period unless the contractor
    demonstrates that it was actually prejudiced by the lack of notice. Decker & Co.
    v. West, 
    76 F.3d 1573
    , 1580 (Fed. Cir. 1996) (“A contractor in Decker’s position must
    demonstrate that [incorrect appeal advice] actually prejudiced its ability to prosecute its
    timely appeal before the limitation period will be held not to have begun.”);
    Mansoor Int’l Dev. Services, ASBCA Nos. 59466 et al., 16-1 BCA ¶ 36,376 at 177,337.
    Here, Parsons does not allege that it was actually prejudiced by the government’s failure
    to include the notice of appeal rights. 5 Instead, Parsons attempts to distinguish the cited
    cases because they involved terminations for default pursuant to different FAR clauses,
    or defective rather than entirely missing appeal information (app. opp’n at 7-8). Our
    precedent is not limited to termination for default cases. Moreover, our decision in
    Mansoor notes that “[t]hree of the decisions at issue here lacked any mention of appeal
    rights” Mansoor, 16-1 BCA ¶ 36,376 at 177,337. Thus, we reject Parsons’ attempt to
    distinguish these cases.
    Parsons additionally alleges that the unilateral rate determination was not clearly
    final (app. opp’n at 8). We reject this argument also. The final decisions plainly
    announce that “it is my final determination that” (R4, tab 15 at G-538, tab 16 at G-543).
    The decisions clearly state that they are unilaterally determining the final indirect cost
    rates, and direct Parsons to submit adjustment vouchers (R4, tab 15 at G-542;
    tab 16 at G-548) (“you must submit adjustment vouchers if the rates unilaterally
    determined herein differ from the rates used for [Contractor Fiscal Year 2011] in your
    previous interim billings”). These adjustment vouchers are the last step in the process
    for reimbursing contractors for indirect costs. Parsons’ argument that the unilateral rate
    5
    The government asserts that Parsons appealed from unilateral rate determinations
    that were missing a notice of appeal rights in ASBCA Nos. 60218 and 61309.
    As this is a challenge to the Board’s jurisdiction, we would be permitted to
    consider evidence beyond the pleadings; however, the government did not
    include copies of the relevant documents with its motion. The referenced
    information is not contained in our dispositions of those appeals, and we
    decline to take judicial notice of non-public information. Thus, we do not
    consider the government’s unsubstantiated allegations.
    5
    determination was “not clearly final” (app. opp’n at 8) is contrary to the undisputed
    evidence.
    Parsons further asserts that the additional lease costs first raised in its May 2018
    letter were not considered by the government in the September 2018 unilateral rate
    determinations. According to Parsons, these costs were raised in its March 2019
    certified claim, and thus, are properly before the Board. As explained above, we find
    that the unilateral rate determination is a final and unappealed government claim that
    precludes consideration of “new” costs in a later asserted contractor claim. However,
    even if Parsons were correct that it could raise a claim for new indirect costs after the
    establishment of the final indirect cost rates by the unilateral determination, Parsons’
    claim here would be barred by the six-year statute of limitations. Parsons’ claim
    asserts a sum certain for FY2011 costs, but not for any later years. Thus, to be timely,
    Parsons’ claim would have had to have been submitted by the end of 2017, but it was
    not submitted until March of 2019.
    The six-year statute of limitations, unlike the 90-day statute of limitations for
    filing an appeal, is subject to equitable tolling; however, Parsons has not alleged any
    basis for why it was unable to file its claim within six years. Thus, we find that
    Parsons’ claim for additional lease costs for FY2011, contained in its March 2019
    claim, is barred by the statute of limitations.
    D. Parsons’ March 2019 Claim Fails To State A Claim For Contract
    Interpretation
    Parsons’ certified claim also purportedly seeks contract interpretation of the
    FAR provision for allowability of contractor leaseback costs. The government moves
    to dismiss this portion of Parsons’ appeal as a monetary claim that fails to state a sum
    certain (gov’t mot. at 13-14). We hold that Parsons is asserting a monetary claim
    mischaracterized as a claim for contract interpretation. Parsons correctly cites Board
    precedent finding jurisdiction to entertain non-monetary claims for contract
    interpretation (app. opp’n at 9-13). However, the cases cited predate the Federal
    Circuit’s decision in Securiforce International America, LLC v. United States, 
    879 F.3d 1354
    , 1360 (Fed. Cir. 2018). Securiforce did not change the jurisdiction of the Board
    to consider non-monetary claims. Instead, Securiforce clarified when a purported
    non-monetary CDA claim actually seeks monetary relief. In Securiforce the circuit
    explained that “[i]f ‘the only significant consequence’ of the declaratory relief sought
    ‘would be that [the plaintiff] would obtain monetary damages from the federal
    government,’ the claim is in essence a monetary one.” 
    Securiforce, 879 F.3d at 1360
    (quoting Brazos Elec. Power Coop., Inc. v. United States, 
    144 F.3d 784
    , 787 (Fed. Cir.
    1998)).
    6
    In Garrett v. General Elec. Co., 
    987 F.2d 747
    (Fed. Cir. 1993), the Federal
    Circuit held that the CDA provides jurisdiction to entertain nonmonetary claims for
    contract interpretation. In that case, the court held that, pursuant to that contract’s
    inspection clause, the government had three options when it found that the contractor
    had not fulfilled the contract’s requirements; it could have: 1) reduced the contract
    price by an equitable portion of the contract price; 2) demanded that the contractor
    repay an equitable portion of the contract price; or 3) directed the contractor to correct
    or replace the defective product. General 
    Electric, 987 F.2d at 749
    . In General
    Electric, contract interpretation could relieve the contractor from its obligation to
    perform, and this would have been a “significant consequence” of the relief sought that
    was not monetary in nature. (Id.)
    In Securiforce, the government issued a partial termination for convenience and
    then terminated the contractor for default. The contractor filed its initial complaint in
    the Court of Federal Claims to challenge the termination for default and then filed a
    claim with the contracting officer challenging the termination for convenience.
    
    Securiforce, 879 F.3d at 1358-59
    . Thus, at the time Securiforce filed its claim, it had
    already been terminated for default and it could not obtain any relief other than money
    damages because it was no longer performing on the contract.
    Parsons cites to our holding, predating Securiforce, in Greenland Contractors
    I/S, ASBCA Nos. 61113, 61248, 18-1 BCA ¶ 36,942 at 179,973, for the proposition
    that that the Board can entertain a claim for contract interpretation. However, Parsons
    does not cite our subsequent holding in Greenland Contractors I/S, ASBCA
    Nos. 61113, 61248 19-1 BCA ¶ 37,259, applying facts not present in the initial
    decision, and determining that Greenland was, in fact, seeking to assert a monetary
    claim because it had already performed some of the work for which it sought an
    interpretation of contractual terms. We held that, because Greenland had already
    performed some of the work, there was no other significant consequence of a claim for
    contract interpretation, other than money damages. Greenland, 19-1 BCA ¶ 37,259
    at 181,332.
    In a similar (though not binding on us) case, the Civilian Board of Contract
    Appeals held in Duke University v. Dept. of Health and Human Services, CBCA
    No. 5992, 18-1 BCA ¶ 37,023, that the contractor had “already incurred costs
    associated with its contract interpretation dispute, and it could have quantified those
    costs and stated them in a sum certain in a claim to the contracting officer.” Duke,
    18-1 BCA ¶ 37,023 at 180,291. The Civilian Board explained that a “ruling in Duke’s
    favor would not result in Duke avoiding costs, but instead would be used only to
    entitle Duke to monetary relief in a separate proceeding. In such circumstances, it is
    clear that Duke has an uncertified and unquantified monetary claim.” (Id.) We find
    the Civilian Board’s reasoning here to be persuasive.
    7
    Here Parsons asserts that it is seeking an interpretation of contract terms related
    to the “calculation of allowable rent costs pursuant to FAR 31.205-36(b) and
    FAR 31.205-16(b), as applicable to FY2011 and all subsequent fiscal years in which
    these costs have been and will be charged to the Government” (app. opp’n at 11)
    (emphasis omitted). However, the only “significant consequence” of Parsons’ claim for
    contract interpretation would be the payment of money. The parent corporation, PC,
    signed a 15 year lease for the Pasadena Tower Building in 2011 and Parsons has
    continuously occupied space in the building (compl. ¶¶ 21-47). Thus, unlike the
    contractor in General Electric, Parsons will not be able to avoid performance of a
    contractual task by virtue of its claim for contractual interpretation. Parsons has already
    occupied the building pursuant to the lease for over eight years, and is obligated, by
    lease, to stay in the building until June 30, 2026. Thus, Parsons does not assert a valid
    non-monetary claim for contract interpretation.
    Moreover, to the extent Parsons’ claim for contractual interpretation for years
    after FY2011 could be interpreted as a claim for money damages, Parsons admits that
    its claim for years after FY2011 are only for contract interpretation (app. resp.
    at 10 (“Parsons’ Claim . . . articulates a sum certain for the FY 2011 year while at the
    same time seeking a non-monetary claim for contract interpretation for future years.”)).
    Thus, Parsons’ appeal purporting to assert a non-monetary claim for contract
    interpretation is dismissed for lack of jurisdiction.
    CONCLUSION
    For the reasons stated above, Parsons’ appeal is dismissed for lack of jurisdiction.
    Parsons’ August 29, 2019 motion for leave to file a first amended complaint is denied as
    moot.
    Dated: April 15, 2020
    DAVID D’ALESSANDRIS
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    (Signatures continued)
    8
    I concur                                         I concur
    RICHARD SHACKLEFORD                              J. REID PROUTY
    Administrative Judge                             Administrative Judge
    Acting Chairman                                  Vice Chairman
    Armed Services Board                             Armed Services Board
    of Contract Appeals                              of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 62113, Appeal of
    Parsons Government Services, Inc., rendered in conformance with the Board’s
    Charter.
    Dated: April 15, 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    9