DCX-CHOL Enterprises, Inc. ( 2020 )


Menu:
  •                 ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of --                                 )
    )
    DCX-CHOL Enterprises, Inc.                    )      ASBCA Nos. 62453, 62454
    )
    Under Contract Nos. N00104-10-C-FA09          )
    N00104-06-C-FA67          )
    APPEARANCES FOR THE APPELLANT:                       Mark R. Thomas, Esq.
    Marcos Gonzalez, Esq.
    Reid Law, PC
    Denver, CO
    APPEARANCES FOR THE GOVERNMENT:                      Craig D. Jensen, Esq.
    Navy Chief Trial Attorney
    Matthew S. Hawkins, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE SWEET
    These appeals challenge the contracting officer (CO)’s decision to terminate two
    contracts for default. On June 8, 2020, the Department of the Navy (government) moved
    to dismiss these appeals on the grounds that we do not possess jurisdiction and these
    appeals are barred by res judicata (claim preclusion) and collateral estoppel (issue
    preclusion). Appellant DCX-CHOL Enterprises, Inc. (DCX) responded that we possess
    jurisdiction, and that neither res judicata nor collateral estoppel bar these appeals. For
    the reasons discussed below, we find that we do not possess jurisdiction because DCX
    did not file these appeals within 90 days of its receipt of the CO’s default termination
    decision. Therefore, we do not reach the government’s other arguments, and dismiss
    these appeals.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    I. Factual Background
    1. On August 2, 2006, the government and DCX executed Contract
    No. N00104-06-C-FA67 (FA67 Contract) for hull penetrator assemblies. On
    November 5, 2009, the government and DCX executed Contract No. N00104-10-C-FA09
    (FA09 Contract) for electric lead assemblies. The hull penetrator and electric lead
    assemblies are components of Trident class submarine sonar systems. DCX-CHOL
    Enterprises, Inc., ASBCA Nos. 61636, 61637, 20-1 BCA ¶ 37,483 at 182,065. 1
    2. The FA09 Contract and the FA67 Contract (collectively, Contracts)
    incorporated by reference Federal Acquisition Regulation (FAR) 52.249-8, DEFAULT
    FIXED-PRICE SUPPLY AND SERVICE (APR 1984), which allowed the government
    to terminate the Contracts if DCX failed to perform within the time specified in the
    Contracts. DCX, 20-1 BCA ¶ 37,483 at 182,065.
    3. The Contracts required first article testing (FAT) and approval. The
    Contracts, as modified, incorporated FAR 52.209-4, FIRST ARTICLE
    APPROVAL-GOVERNMENT TESTING (SEP 1989), which required DCX to deliver
    FAT samples within 180 days for the FA09 Contract and 90 days for the FA67
    Contract. DCX, 20-1 BCA ¶ 37,483 at 182,065. After several other modifications, the
    parties entered into bilateral modifications of the Contracts, which extended the FAT
    sample delivery deadline for both contracts to April 30, 2018 (Deadline). DCX, 20-1
    BCA ¶ 37,483 at 182,065-66.
    4. DCX did not meet the Deadline for either contract. Therefore, on May 11,
    2018, the government informed DCX that the government was terminating the
    Contracts for default. DCX, 20-1 BCA ¶ 37,483 at 182,066.
    II. Procedural History
    5. Without submitting a claim to the CO and obtaining a CO final decision
    (COFD), DCX filed notices of appeal challenging the validity of the government’s
    default terminations of the FA09 Contract and the FA67 Contract, which we docketed
    as ASBCA Nos. 61636 and 61637, respectively (collectively, DCX I). DCX-CHOL
    Enterprises, Inc., ASBCA Nos. 61636, 61637, 19-1 BCA ¶ 37,394 at 181,800. DCX
    asserted delay, constructive change, and waiver defenses to the default termination.
    DCX, 20-1 BCA ¶ 37,483 at 182,066.
    6. The government then moved to strike the delay and constructive change
    defenses (collectively, delay defenses), and for summary judgment on the waiver
    defense. DCX, 19-1 BCA ¶ 37,394 at 181,799.
    1   As discussed in greater detail below, we issued two decisions in DCX I—(1) DCX-CHOL
    Enterprises, Inc., ASBCA Nos. 61636, 61637, 19-1 BCA ¶ 37,394, which granted
    the government’s motion to strike and denied its motion for summary judgment, and
    (2) DCX-CHOL Enterprises, Inc., ASBCA Nos. 61636, 61637, 20-1 BCA ¶ 37,483,
    which granted the government’s motion for reconsideration of our denial of the
    summary judgment motion.
    2
    7. On July 11, 2019, we granted the motion to strike the delay defenses on the
    grounds that we did not possess jurisdiction over those defenses under Securiforce Int’l Am.,
    LLC v. United States, 
    879 F.3d 1354
    (Fed. Cir. 2018) because DCX did not present a delay
    defenses claim to the CO. However, we denied the motion for summary judgment on the
    waiver defense. DCX, 19-1 BCA ¶ 37,394 at 181,799.
    8. On August 12, 2019, the government moved for reconsideration of the
    summary judgment motion denial. DCX, 20-1 BCA ¶ 37,483 at 182,065.
    9. While the motion for reconsideration was pending in DCX I, DCX presented
    a delay defenses claim to the CO on September 9, 2019 (DCX II Claim). The DCX II
    Claim did not seek a sum certain. (R4, tab 7 at 98, 100) Nor did DCX move the
    Board to stay DCX I while DCX pursued the DCX II Claim.
    10. On December 9, 2019, we granted both the government’s motion for
    reconsideration and its motion for summary judgment on DCX’s waiver defense in
    DCX I. Because waiver was the only remaining defense to the default termination in
    DCX I, we denied the DCX I appeals. 20-1 BCA ¶ 37,483 at 182,068.
    11. On April 2, 2020, DCX filed a notice of appeal with the Board based upon
    a deemed denial of the DCX II Claim, which we docketed as ASBCA Nos. 62453 and
    62454 (collectively, DCX II). 2 These are the appeals before us now.
    DECISION
    We do not possess jurisdiction to hear these DCX II appeals challenging the
    default termination because DCX failed to file them within 90 days of its receipt of the
    default termination decision. 3 Under the Contracts Disputes Act (CDA), a contractor
    must file an appeal of a default termination decision within 90 days of its receipt of a
    final decision. 41 U.S.C. § 7104(a). We do not possess jurisdiction to hear an appeal
    when a contractor fails to file a notice of appeal within 90 days of its receipt of that
    decision. Cosmic Const. Co. v. United States, 
    697 F.2d 1389
    , 1390-91 (Fed. Cir. 1982).
    The 90 day appeal period is not subject to equitable tolling. Id.; Waterstone Envtl.
    Hydrology & Eng’g., Inc., ASBCA No. 57557, 12-1 BCA ¶ 35,028 at 172,141-42.
    2 ASBCA No. 62453 relates to the FA09 Contract. ASBCA No. 62454 relates to the
    FA67 Contract.
    3 DCX admits that it merely is challenging the default termination decision, and not
    raising a monetary claim (SOF ¶ 9; app. resp. at 3). Indeed, we would not possess
    jurisdiction over any monetary claim because the DCX II Claim did not include a
    sum certain (SOF ¶ 9; 
    Securiforce, 879 F.3d at 1359-60
    ; Parsons Gov’t Servs., Inc.,
    ASBCA No. 62113, 20-1 BCA ¶ 37,586 at 182,510-11).
    3
    Here, DCX received the government’s default termination decision around May 11,
    2018 (SOF ¶ 4). However, it did not file these appeals until April 2, 2020—more than
    90 days later (SOF ¶ 11). Therefore, we do not possess jurisdiction over these appeals.
    Cosmic 
    Const., 697 F.2d at 1390-91
    .
    At oral argument, DCX argued that these appeals are timely under Afghan Active
    Group (AAG), ASBCA No. 60387, 16-1 BCA ¶ 36,349. In Afghan Active Group, we
    held that a notification of an intent to appeal provided by a contractor to the CO within
    90 days of receiving a COFD constitutes a timely notice of appeal.
    Id. at 177,211.
    Here,
    DCX has not identified any notification of an intent to appeal that DCX provided to the
    CO within 90 days of receiving the default termination decision. To the extent that DCX
    is relying upon the DCX II Claim, that would not constitute a timely notice of appeal
    because DCX did not submit that claim to the CO until September 9, 2019—which was
    more than 90 days after DCX received the government’s default termination decision
    around May 11, 2018 (SOF ¶¶ 4, 9). Therefore, Afghan Active Group does not help
    DCX.
    Nor can DCX argue that DCX II is timely because it relates back to DCX I, which
    DCX filed within 90 days of receiving the default termination decision. A second appeal
    cannot relate back to an earlier appeal for purposes of establishing that the second appeal is
    timely if the earlier appeal no longer was pending when the contractor filed the later appeal.
    Bonneville Associates, Ltd. Partnership v. Barram, 
    165 F.3d 1360
    , 1363-64 (Fed. Cir.
    1999); Frazer v. United States, 
    49 Fed. Cl. 734
    , 736 (2001). Here, DCX I no longer was
    pending when DCX filed DCX II because we denied the DCX I appeals on December 9,
    2019, but DCX did not file DCX II until April 2, 2020 (SOF ¶¶ 10-11). Therefore, DCX II
    cannot relate back to DCX I. 
    Bonneville, 165 F.3d at 1363-64
    ; 
    Frazer, 49 Fed. Cl. at 736
    .
    Indeed, the contrast with Watts Constructors, LLC, ASBCA Nos. 61518, 61961,
    19-1 BCA ¶ 37,382 demonstrates why the DCX II appeals are untimely. As in Watts,
    DCX appealed the government’s default termination within 90 days, raising delay and
    waiver defenses in DCX I (SOF ¶ 5); 19-1 BCA ¶ 37,382 at 181,726. Moreover, as in
    Watts, the government then moved to strike the delay defenses on the grounds that DCX
    had failed to present those defenses to the CO, and for summary judgment on the waiver
    defense (SOF ¶ 6); 19-1 BCA ¶ 37,382 at 181,724. However, unlike in Watts, DCX did
    not move to stay DCX I while it submitted its delay defenses claim to the CO and
    obtained a COFD (SOF ¶ 9); 19-1 BCA ¶ 37,382 at 181,724. That distinction is crucial
    because it means that—unlike in Watts—DCX had not protected itself from a denial of
    DCX I while DCX was pursuing its DCX II claim. Watts held that the second appeal in
    that case was timely because it merely constituted a delay claim “proffered as a defense
    to a timely appealed default termination.” 19-1 BCA ¶ 37,382 at 181,726. Here, by
    contrast, DCX II could not have been proffered as a defense to a timely appealed default
    termination because the timely appeals of the default terminations in DCX I already had
    been denied by the time DCX filed the DCX II appeals (SOF ¶¶ 10-11). As a result,
    4
    unlike in Watts, we do not possess jurisdiction over these appeals because they are
    untimely. Cosmic 
    Const., 697 F.2d at 1390-91
    .
    CONCLUSION
    For the foregoing reasons, we grant the government’s motion to dismiss and
    dismiss these appeals.
    Dated: October 29, 2020
    JAMES R. SWEET
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                        I concur
    RICHARD SHACKLEFORD                             J. REID PROUTY
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Vice Chairman
    Armed Services Board                            Armed Services Board
    of Contract Appeals                             of Contract Appeals
    I certify that the foregoing is a true copy of the Order of Dismissal of the Armed
    Services Board of Contract Appeals in ASBCA Nos. 62453, 62454, Appeals of DCX-CHOL
    Enterprises, Inc., rendered in conformance with the Board’s Charter.
    Dated: October 29, 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 62453, 62454

Judges: Sweet

Filed Date: 10/29/2020

Precedential Status: Precedential

Modified Date: 11/10/2020