L3 Technologies, Inc. ( 2021 )


Menu:
  •                  ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeals of -                                )
    )
    L3 Technologies, Inc.                       ) ASBCA Nos. 61811, 61813, 61814
    )
    Under Contract Nos. FA8620-06-G-4002 et al. )
    APPEARANCES FOR THE APPELLANT:                         Karen L. Manos, Esq.
    Erin N. Rankin, Esq.
    Justin P. Accomando, Esq.
    Gibson, Dunn & Crutcher LLP
    Washington, DC
    APPEARANCES FOR THE GOVERNMENT:                        Arthur M. Taylor, Esq.
    DCMA Chief Trial Attorney
    Amelia R. Lister-Sobotkin, Esq.
    Trial Attorney
    Defense Contract Management Agency
    Chantilly, VA
    MAJORITY 1 OPINION BY ADMINISTRATIVE JUDGE PROUTY
    These three appeals, submitted by appellant, L3 Technologies, Inc. (L3), involve
    government claims challenging both indirect and direct costs paid to L3 on several
    government contracts for certain years. As the litigation progressed, the government
    apparently thought better of its claims and withdrew them in toto and represented it
    would make no further claims on the contract years in question. Consequently, the
    government has moved for dismissal of these appeals on mootness grounds. L3 opposes,
    seeking either summary judgment in its favor or that we deny the motion to dismiss and
    keep the appeals live so that it can obtain a victory that, it believes, would preclude its
    suffering similar government claims in other contract years. On the facts before us,
    we grant the government’s motion and dismiss these appeals as moot. L3’s motion for
    summary judgment is denied.
    1   These appeals were originally considered by a five-judge division of the Board,
    including Judge Kinner, who passed away while the matter was still under
    deliberation. Because three of the remaining four judges concurred in this
    opinion, there was no need to appoint a fifth judge to the division. Under the
    Board’s internal rules, this decision is precedential.
    STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
    For the purposes of deciding the motions before us, we need not delve too deeply
    into the merits of the underlying appeals, but need to understand their scope and the
    limits of what they may accomplish.
    I. What the Appeals are About
    The first of these appeals, No. 61811, challenges a Contracting Officer’s Final
    Decision (COFD) dated June 28, 2018, seeking repayment of $10,692,605 by L3 for
    certain “other direct costs” and overhead that had been included in L3’s final indirect
    cost rate proposals 2 for the fiscal years 2011, 2012, 2013, and 2014. See compl. ¶ 8. 3
    The COFD followed a group of audit reports (one for each contract year) 4 by the Defense
    Contract Audit Agency (DCAA), all issued on September 27, 2017, questioning
    $14,337,524 of these already-paid costs (id. ¶ 9). These audit reports all utilized some
    degree of statistical sampling of particular costs (e.g., individual instances of premium air
    travel that the auditor felt were not justified), with results extrapolated across the board
    for that cost (id. ¶¶ 12, 15, 20, 22; app. opp’n at 7-8, 10-11 5).
    Appeal No. 61813 is an appeal of a far more modest government claim. There, the
    June 29, 2018 COFD demanded the payment of $6,002 based upon a February 14, 2018
    DCAA audit report that questioned the use of premium airfare for two L3 employees for
    the years 2012-2015 (see R4, tab 4 at G000274, G000344-49).
    And Appeal No. 61814 is another, even smaller, government claim, resting upon a
    different COFD, though also issued on June 29, 2018, seeking $2,542 in premium airfare
    incurred by an L3 employee in 2011. It rested upon the same February 14, 2018 DCAA
    audit report that informed the COFD in Appeal No. 61813 (see R4, tab 4 at G000274,
    G000352-58).
    2 For an explanation of how indirect cost rate proposals work, we refer the reader to
    Tech. Sys., Inc., 
    ASBCA No. 59577
    , 
    17-1 BCA ¶ 36,631
    .
    3 The only appeal for which a complaint was submitted (and it was submitted by the
    government) is Appeal No. 61811.
    4 These were numbered 9511-2011G10100001, 9511-2012G10100001, 9511-
    2013G10100001, and 9511-2014G10100002 (compl. ¶ 9).
    5 With the exception of its objection to certain language it deemed inflammatory and some
    characterizations of the evidence, the government agrees with the facts presented in
    L3’s brief in opposition to its motion to dismiss. See gov’t reply at 2-3. Thus,
    much of the procedural history that we set forth here comes from L3’s brief since
    both parties agree that it is accurate.
    2
    II. The Present Litigation and the Government’s Unequivocal Withdrawal of its
    COFDs
    These three appeals (all submitted to the Board the same day) were immediately
    consolidated. L3 then requested that the Board order the government to file the
    complaint in Appeal No. 61811, which we directed and the government accomplished. 6
    The government’s complaint in Appeal No. 61811 seeks no declaratory or injunctive
    relief, but merely explains the basis of its claim and demands payment consistent with the
    COFD for the years covered by it. See compl. Discovery followed.
    Ultimately, as admitted in a February 28, 2020 email from government counsel to
    L3’s attorney, the government decided that it could not defend these appeals. See app.
    opp’n, ex. 2. Thus, in a letter to L3’s Chief Financial Officer dated February 28, 2020,
    the cognizant administrative contracting officer wrote:
    I hereby unequivocally withdraw the Contracting Officer’s
    Final Decisions (“COFDs”) and demands for payment dated
    28 June 2018 (
    ASBCA No. 61811
    ), signed by Gladys Broyles,
    29 June 2018 (
    ASBCA No. 60813
    ) signed by Cheryl L. Clark,
    and 29 June 2018 (
    ASBCA No. 60814
    ), signed by
    Jennings L. Summers that have been appealed to the ASBCA
    and assigned the respective docket numbers. A motion for
    dismissal of those appeals will be filed by the assigned trial
    attorney. The Government does not intend to re-assert the
    costs at issue in those disputes.
    (Gov’t mot., ex. 1) L3 makes no assertion that these COFDs may be re-imposed nor
    that the government will re-assert its challenge to the costs at issue in those disputes.
    We find, as a matter of fact, that the withdrawal of these claims is unequivocal.
    III. Other Litigation Involving L3’s Contracts and DCAA Audits
    As we will explain more below (and as noted in Judge Clarke’s dissent), L3
    opposes the government’s request to dismiss these appeals because it contends it has been
    here before. Many times. And without resolution. The dissenting opinion discusses this
    at length and, although we come to a different conclusion regarding the legal
    consequences, we agree that L3 has been to the Board quite often in recent years as a
    consequence of COFDs stemming from incurred cost audits and that none of these
    6   The government opposed L3’s motion to require it to file a complaint, stating in its
    November 9, 2018 opposition, inter alia, that, L3 “is fully aware of the issues in
    these appeals . . . . The disallowances are the results of an ongoing dispute that
    has existed for several years and which is the subject of several other disputes
    before the Board.” See app. opp’n at 12.
    3
    appeals has led to a decision on the merits. 7 This happened for appeals of audits of years
    2006, 2007, 2008, 2009, and 2010. (App. opp’n at 4-10) Moreover, some of these prior
    appeals involved audits which utilized statistical sampling as in the audit that is the basis
    of Appeal No. 61811. See, e.g., app. opp’n at 6-7 (referring to the use of decrement for
    audit of 2009 direct costs). Appeal Nos. 62123, 62267, and 62268, brought by L3
    challenging the disallowance of other incurred costs by the government resting in part on
    similar statistical extrapolation, remain pending before the Board, but stayed pending the
    outcome of the present appeals. (App. opp’n 13-14)
    DECISION
    As will be discussed below, the government’s withdrawal of the COFDs moots
    these appeals, which are premised upon them since there is simply no additional, legally
    cognizable relief that this Board can afford L3. Moreover, neither exception to the
    mootness doctrine asserted by L3 – voluntary cessation and capable of repetition yet
    evading review – is applicable here.
    I. The Mootness Doctrine: Generally, a Case is Moot When an Adjudicatory
    Body May No Longer Provide Relief.
    In the past, we have had no compunction against dismissing, as moot, appeals in
    cases analogous to this one, where the CO has withdrawn COFDs asserting government
    claims on incurred costs. In Combat Support Associates, ASBCA Nos. 58945, 58946,
    
    16-1 BCA ¶ 36,288
    , a case involving incurred cost audits and government claims
    disallowing costs already paid, we dismissed the appeal on government motion after the
    government claims were withdrawn, writing:
    Where a contracting officer unequivocally rescinds a
    government claim and the final decision asserting that claim,
    with no evidence that the action was taken in bad faith, there is
    no longer any claim before the Board to adjudicate, and the
    appeal is dismissed. KAMP Systems, Inc., 
    ASBCA No. 54253
    ,
    
    09-2 BCA ¶ 34,196
     at 168,995. In such circumstances, the
    government’s voluntary action moots the appeal, cf. Teddy’s
    Cool Treats, 
    ASBCA No. 58384
    , 
    14-1 BCA ¶ 35,601
    at 174,410 (dismissing appeal as moot where government
    changed default termination to a notice termination), leaving
    the Board without jurisdiction to entertain the appeal further.
    7   In a significant number of these appeals, however, the matters were settled with the
    consent of L3 and not over its objections. See app. opp’n at 4 (appeal of COFD
    for 2006 costs settled by parties shortly before hearing), app. opp’n at 5 (appeal of
    COFDs for 2007 costs settled by parties), app. opp’n at 7 (appeal of COFDs for
    some 2009 costs settled by parties), app. opp’n at 9-10 (appeal of COFDs for other
    2009 costs and 2010 costs settled by parties).
    4
    See Lasmer Indus., Inc., 
    ASBCA No. 56411
    , 
    10-2 BCA ¶ 34,491
     at 170,123.
    
    16-1 BCA ¶ 36,288
     at 176,974; see also Advanced Powder Solutions, 
    ASBCA No. 61818
    ,
    
    19-1 BCA ¶ 37,425
    , aff’d 
    831 Fed. Appx. 501
     (Fed. Cir. 2020) (dismissing appeal
    because, without claim, the Board had no jurisdiction).
    We ruled similarly in Quimba Software, Inc., 
    ASBCA No. 59197
    , 
    19-1 BCA ¶ 37,350
    , rejecting Quimba’s complaints that the government had wrongfully compelled
    it to expend resources defending against a claim that had no basis, (allegedly) being
    brought after the expiration of the statute of limitations. See Quimba Software, 19-1
    BCA at 181,613. Indeed, L3, itself, had a previous set of its appeals of government
    incurred cost claims dismissed over its objection upon the government’s withdrawal of
    the COFD’s in question. 8 See L-3 Communications Integrated Sys., L.P., ASBCA
    Nos. 60431, 60432, 
    16-1 BCA ¶ 36,362
    .
    The basis for such mootness dismissals is the constitutional requirement for a case
    or controversy. 9 “Simply stated, a case is moot when the issues presented are no longer
    ‘live’ or the parties lack a legally cognizable interest in the outcome.” Powell v.
    McCormack, 
    395 U.S. 486
    , 496 (1969). As the Federal Circuit summarized in Ferring
    B.V. v. Watson Labs., Inc.-Fla., 
    764 F.3d 1382
     (Fed. Cir. 2014), “[a] case becomes moot
    when interim relief or events have eradicated the effects of a defendant’s act or omission,
    and there is no reasonable expectation that the alleged violation will recur.” 764 F.3d
    at 1391 (citing County of Los Angeles v. Davis, 
    440 U.S. 625
    , 631 (1979)); see also
    Chapman Law Firm Co. v. Greenleaf Constr. Co., 
    490 F.3d 934
    , 939 (Fed. Cir. 2007)
    (“When, during the course of litigation, it develops that the relief sought has been granted
    or that the questions originally in controversy between the parties are no longer at issue,
    the case should generally be dismissed.”).
    It should be clear that this “legally cognizable interest” in the outcome is tied not
    merely to the conduct being challenged by the lawsuit, but the relief or remedy available
    through continued litigation. The Supreme Court recognized this in Powell v.
    McCormack when discussing one of its earlier opinions holding a matter moot: “[The
    earlier case] stands . . . for the proposition that, where one claim has become moot and
    the pleadings are insufficient to determine whether the plaintiff is entitled to another
    remedy, the action should be dismissed as moot.” 
    395 U.S. at 499
    . Put another way,
    even if a litigant remains harmed by the actions of the other party after that party has
    8   This was one of the sets of appeals of which L3 complains above.
    9   L3 argues that, to the extent that these decisions rested upon the notion that withdrawal
    of the COFD’s divested the Board of jurisdiction by the fact that there was no
    longer a COFD to appeal, they were contrary to Board precedent holding that
    withdrawal of COFDs does not divest the Board of jurisdiction. See app. opp’n
    at 26-30. We rest our opinion here upon the mootness doctrine, which is centered
    upon the case-or-controversy requirement, not the lack of a COFD to appeal.
    5
    changed its behavior to remove the basis of the pending suit, if the court is no longer able
    to provide a remedy to that remaining harm, the case is moot. As the Supreme Court
    noted in Spencer v. Kemna, a case remains viable only if “throughout the litigation,
    the plaintiff ‘must have suffered, or be threatened with, an actual injury traceable to the
    defendant and likely to be redressed by a favorable judicial decision.’” 
    523 U.S. 1
    , 7
    (1998) (quoting Lewis v. Cont’l Bank Corp., 
    494 U.S. 472
    , 477 (1990)). The
    implications of this straightforward explanation of the law, it will be seen, are significant.
    II. On Their Faces, These Appeals Are Moot
    Simply speaking, the COFDs appealed here no longer exist – they have been
    withdrawn. Moreover, the government has unequivocally stated that it will never again
    challenge the incurred price proposals for the contract years at issue. Therefore,
    seemingly, there is no relief we may grant and the appeals should be dismissed. This is
    very much like the circumstances we saw in Combat Support Associates, Quimba, and
    the previous 2016 L3 decision. Thus, if there weren’t more to it, we could comfortably
    grant the government’s motion based upon our precedent.
    III. The Voluntary Cessation Doctrine Is Inapplicable Here Because The Harm
    Being Appealed Is Unlikely To Recur
    But there is somewhat more to it: L3 argues that the two exceptions to the
    mootness doctrine preclude dismissal. The first of these, “voluntary cessation,” is where
    L3 makes its primary argument. See app. opp’n at 21-32. L3 quotes the Supreme Court
    as holding that, “[i]t is well settled that ‘a defendant’s voluntary cessation of a challenged
    practice does not deprive a federal court of its power to determine the legality of the
    practice.’ ‘[I]f it did, the courts would be compelled to leave “[t]he defendant … free to
    return to his old ways.’” (App. opp’n at 18; citing to Friends of the Earth, Inc. v.
    Laidlaw Envtl. Servs., Inc., 
    528 U.S. 167
    , 189 (2000) (internal citations omitted)
    However, as L3 rightly concedes, it is not that voluntary cessation could never support a
    dismissal for mootness, just that the party seeking dismissal must also demonstrate that
    the objected to actions will not recur. Hence, in County of Los Angeles, the Supreme
    Court explained that the voluntary cessation doctrine would not apply if: “it can be said
    with assurance that ‘there is no reasonable expectation . . .’ that the alleged violation will
    recur, and (2) interim relief or events have completely and irrevocably eradicated the
    effects of the alleged violation.’” 
    440 U.S. at 631
     (citations omitted); see also United
    States v. W.T. Grant Co., 
    345 U.S. 629
    , 633 (1953) (though the burden is “heavy,” a case
    may be dismissed as moot if the defendant can demonstrate that there is “no reasonable
    expectation that the wrong will be repeated.”).
    The motion here turns on the question of what “wrong” is at issue. The
    government argues that the wrong at issue is delimited by the COFDs being appealed:
    the government’s rejection of cost submissions for particular contract years, which the
    government asserts it will never again reject. No argument is made by L3 that these will
    6
    ever return. If the government is correct (and it is), the voluntary cessation doctrine does
    not apply because there is no reasonable expectation that the wrong will be repeated.
    L3 appears to see the wrong(s) that may be repeated as the government’s
    challenges to L3’s corporate travel policy and its use of its statistical means of
    challenging its incurred cost submissions. See, e.g., app. opp’n at 20. If those were the
    wrongs that these appeals could legally eliminate, we would agree that the voluntary
    cessation doctrine might require our denial of the government’s motion. They aren’t.
    These appeals do NOT seek a declaratory judgment or injunctive relief finding
    L3’s corporate travel policy appropriate or preventing the statistical sampling
    methodology which L3 finds so objectionable. 10 Thus, if we refused to dismiss the
    appeals, and if L3 were to obtain a complete legal victory on the merits, the remedy that
    L3 would obtain would be no more than it is already getting by the withdrawal of the
    COFDs: it would no longer be obliged to repay the government the costs set forth in
    the three withdrawn COFDs. L3 and the dissent appear to be laboring under the
    mistaken notion that winning on the merits here would, per se, decide the propriety of
    L3’s travel policies once and for all and prevent the future use of DCAA’s statistical
    sampling and extrapolation methodologies in other audits, but there is no basis for such
    a belief. After all, entitlement to a decision on an appeal is not the same thing as
    entitlement to binding precedent, generalized beyond the years of a particular dispute,
    upon the issues of interest to a particular party. 11 To be sure, a victory on the merits
    would be satisfying to L3 and present a rhetorical cudgel to use against DCAA in the
    future – perhaps even to persuasive effect – but the only thing certain that it would do
    for L3 would be to provide relief for the years at issue and that is already being given. 12
    That is why we have placed so much emphasis on the “legally cognizable relief” part of
    the mootness definitions, for it defines the arena in which the mootness analysis and,
    necessarily, its exceptions apply. The 10th Circuit Court of Appeals came to a similar
    conclusion in Chihuahuan Grasslands Alliance v. Kempthorne, 
    545 F.3d 884
     (10th Cir.
    2008), a case in which the plaintiffs fought a motion to dismiss on mootness grounds by
    arguing that the court was presented with a case of both voluntary cessation, and
    10 Given the fact that, at L3’s demand, the government filed the complaint here, this is
    hardly surprising. But even if L3 had filed the complaint, itself, we are not so
    certain that its appeal of the government’s claims would have entitled it to seek such
    relief – a matter which we need not address as it remains hypothetical, just as the
    possibility of a claim seeking a contractual interpretation finding L3’s travel policies
    to be appropriate or barring the use of DCAA’s statistical modeling would be.
    11 To state the obvious, the law provides a way for a litigant to get that binding precedent:
    declaratory or injunctive relief. If a party wants it, it must explicitly seek it, rather
    than hoping to obtain it as an incidental consequence of its monetary claims.
    12 Moreover, if “case or controversy” has any meaning at all, merely symbolic wins, with
    no formal legal consequence, no matter how helpful to a party, are not what courts
    are for. See, e.g., Massachusetts v. E.P.A., 
    549 U.S. 497
    , 547 (2007) (Roberts, CJ,
    dissenting).
    7
    “capable of repetition yet evading review” (which we address below). The Court of
    Appeals held that, for purposes of mootness determination, it was proper to “rely on the
    claims and requests for relief in the Complaint” and not the broader issues that the
    plaintiffs later wished to address. 
    545 F.3d at 892-93
    . Such are the circumstances here.
    IV. The Dismissed Appeals Are Not an Injury Capable of Repetition, Yet
    Evading Review
    If the voluntary cessation doctrine may be thought of as preventing one of the
    interested parties from pulling the rug out from under the other, “capable of repetition,
    yet evading review” is the circumstance where the very nature of the alleged wrong
    precludes judicial review because its duration is too short, but the controversy is expected
    to return. It was first enunciated in S. Pac. Terminal Co. v. ICC, 
    219 U.S. 498
     (1911),
    and has been part of jurisprudence ever since, recently discussed in a procurement
    context by the Supreme Court in Kingdomware Technologies, Inc. v. United States,
    
    136 S. Ct. 1969
     (2016). As summed up in Kingdomware:
    [T]his Court’s precedents recognize an exception to the
    mootness doctrine for a controversy that is “‘capable of
    repetition, yet evading review.’” Spencer v. Kemna, 
    523 U.S. 1
    , 17, 
    118 S.Ct. 978
    , 
    140 L.Ed.2d 43
     (1998). That exception
    applies “only in exceptional situations,” where (1) “the
    challenged action [is] in its duration too short to be fully
    litigated prior to cessation or expiration,” and (2) “there [is] a
    reasonable expectation that the same complaining party [will]
    be subject to the same action again.” 
    Ibid.
     (internal quotation
    marks omitted; brackets in original).
    
    136 S. Ct. 1976
    . But this is not the kind of case for which this exception applies.
    First, nominally, there would be ample time for the matter to be reviewed by the Board or
    the Court of Federal Clams. Cost allowability determinations, like the ones at issue here,
    are not the type of actions that end after a given period time; rather, they have no
    expiration date and are simply about who is entitled to a certain amount of money.
    Moreover, L3 obtained its full remedy: full review was, in fact, available and the
    only reason that a judicial decision wasn’t issued was because it was not necessary.
    To the extent that L3 attempts to argue that the government’s actions are what
    made the duration too short to afford review (see app. opp’n at 32-33), thus placing this
    matter into the capable of repetition yet evading review rubric, it has made the logical
    fallacy known as a category error. For under this approach, all instances of voluntary
    cessation would fall within the capable of repetition yet evading review classification and
    there would be no point in the separate analysis. It is more consistent with the legal
    paradigm of mootness exceptions to review the government’s actions here under the
    voluntary cessation umbrella. Moreover, as discussed above, the unavailability of a
    8
    legally cognizable remedy deprives us of a case or controversy, leaving no basis to apply
    the second exception, even if it were otherwise proper to do so.
    CONCLUSION
    Because these appeals are moot, they are dismissed. This action makes L3’s
    motion for summary judgment, itself, moot, since we no longer possess jurisdiction over
    these appeals, and we deny it as such.
    Dated: March 1, 2021
    J. REID PROUTY
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                        I concur
    RICHARD SHACKLEFORD                             ELIZABETH WITWER
    Administrative Judge                            Administrative Judge
    Acting Chairman                                 Armed Services Board
    Armed Services Board                            of Contract Appeals
    of Contract Appeals
    I dissent (see separate opinion)
    CRAIG S. CLARKE
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    9
    DISSENTING OPINION BY ADMINISTRATIVE JUDGE CLARKE
    I respectfully dissent because I believe the mootness exception applies. The
    majority decision subjects L3 (and other contractors) to the unfortunate chain of events
    discussed below until DCAA and DCMA resolve whatever their differences are. I wrote
    the original decision with which my colleagues disagree. I have attached my original
    decision as my dissent. 13
    In these appeals of government claims, the contracting officer unequivocally
    withdrew the supporting final decisions stating the claims would not be asserted again
    rendering the appeals moot. I find that the final decisions are moot. For the first time,
    the Board should allow a moot case to proceed based on the exception to mootness
    doctrine. After resolving the mootness matter, I interpret FAR 31.201-3, Determining
    reasonableness, to properly allocate the burden of proof. Finally, I would deny L3’s
    motion, which I deem to be a motion for summary judgment, because of material
    disputed facts concerning allowability of L3’s costs. The Board has jurisdiction pursuant
    to the Contract Disputes Act of 1978 (CDA), 
    41 U.S.C. §§ 7101-9
    .
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    Relevant FAR Clauses
    1. Two FAR clauses 14 play an important role in the Defense Contract Audit
    Agency (DCAA) Audits:
    FAR 31.201-2, Determining allowability.
    (a) A cost is allowable only when the cost complies with all
    of the following requirements:
    (1) Reasonableness.
    (2) Allocability.
    (3) Standards promulgated by the CAS Board, if
    applicable, otherwise, generally accepted accounting
    principles and practices appropriate to the
    circumstances.
    (4) Terms of the contract.
    13 I attempted to resolve the change from “we” to “I” in adapting my decision to a dissent
    but may not have been totally successful.
    14 I do not list FAR 31.201-4, Allocability, because there is no disagreement over the fact
    these costs are allocable to L3’s contracts.
    10
    (5) Any limitations set forth in this subpart.
    And:
    FAR 31.201-3, Determining reasonableness.
    (a) A cost is reasonable if, in its nature and amount, it does
    not exceed that which would be incurred by a prudent
    person in the conduct of competitive business.
    Reasonableness of specific costs must be examined with
    particular care in connection with firms or their separate
    divisions that may not be subject to effective competitive
    restraints. No presumption of reasonableness shall be
    attached to the incurrence of costs by a contractor. If an
    initial review of the facts results in a challenge of a
    specific cost by the contracting officer or the contracting
    officer’s representative, the burden of proof shall be upon
    the contractor to establish that such cost is reasonable.
    (b) What is reasonable depends upon a variety of
    considerations and circumstances, including-
    (1) Whether it is the type of cost generally recognized as
    ordinary and necessary for the conduct of the
    contractor’s business or the contract performance;
    (2) Generally accepted sound business practices,
    arm’s-length bargaining, and Federal and State laws
    and regulations;
    (3) The contractor’s responsibilities to the Government,
    other customers, the owners of the business,
    employees, and the public at large; and
    (4) Any significant deviations from the contractor’s
    established practices.
    DCAA Audit Methodology 15
    2. The method DCAA uses to conduct its audits depends on the volume of cost
    data. In a few situations the volume of cost data may be small enough that DCAA can
    15   I readily admit that the audit reports, expert reports and briefs do not afford a complete
    understanding of DCAA’s procedures to include Dollar Unit Sampling (DUS),
    11
    conduct a 100% audit. In most situations the data is voluminous making 100% audit
    impossible. In these situations DCAA must use statistical analysis to perform its audits
    and reach its conclusions. DCAA has an in-house developed statistical tool called
    “EZ-Quant” that it uses to select a sample based on DCAA’s size criteria and then
    conducts a 100% audit of the sample to determine the questioned costs in the sample.
    DCAA then “extrapolates” the questioned costs in the sample to the remaining costs to
    arrive at its conclusions on total unallowable costs (app. opp’n at 10-11, 15-16, 24)16. At
    times DCAA will question the accuracy EZ-Quant results and resort to a sample based on
    auditor judgmental selection (app. opp’n at 11). DCAA discusses its methodology in its
    opposition, here is an example:
    DCAA auditor Cynitra Kennard, under the supervision of
    Mr. North, audited L3’s shelter differential costs for
    2011-2014, and selected a sample of transactions using
    EZ-Quant. Ms. Kennard testified that she used EZ-Quant
    again to audit shelter differential costs for 2015-2016.
    Kennard Dep. at 28:12-18. The 2015-2016 audit report
    confirms that DCAA used statistical sampling methodology
    to select a sample and extrapolate questioned costs. Ex. 25
    at 55. For 2017, Ms. Kennard likewise used EZ-Quant and
    statistical sampling to extrapolate questioned costs for L3’s
    off-site living allowances. 
    Id. at 26:20-22
    ; Ex. 26 at 43-44.
    Ms. Kennard also testified that she used EZ-Quant to select
    the sample transactions from the shelter differential account
    for the 2018 ICP audit, which is ongoing. Kennard Dep. at
    26:3-17.
    (App. opp’n at 16)
    The DCAA Audits
    3. These claims were audited by DCAA resulting in Audit Reports for L3’s
    Mission Integration Division (MID), dated September 27, 2017, and Platform Integration
    Division (PID), dated February 14, 2018. The audit report for MID are 9511-
    2011G10100001, 9511-2012G10100001, 9511-2013G10100001 and 9511-
    2014G10100002 for L3’s fiscal years 2011 to 2014 (R4, tab 2). The audit report for PID
    are 9511-2011W10100001, 9511-2012W10100001, 9511-2013W10100001 for L3’s
    fiscal years 2011 to 2013 (R4, tab 3).
    4. In the audit reports for MID, DCAA questioned the following costs:
    Physical Unit Sampling (PUS), and judgmental selection, but I have sufficient
    detail required for our decision.
    16 I rely on L3’s Statement of Facts because DCMA generally agrees with L3’s facts
    except for certain characterizations (gov’t resp. at 2-3).
    12
    • $56,285 of the contractor’s claimed CFY 2011-2014 Indirect Labor costs.
    • $5,539,395 of the contractor's claimed CFY 2011-2014 Outside Services
    costs.
    • $4,359,465 of the contractor’s claimed CFY 2011-2014 Employee
    Relocation costs.
    • $67,153 of the contractor’s claimed CFY 2011-2014 Settlement to Cost
    Center costs.
    • $178,270 of the contractor’s claimed CFY 2011-2014 Indirect Travel
    Airfare costs.
    • $137,975 of the contractor’s claimed CFY 2011 L3 Corporate Allocation
    costs.
    • $288,719 of CFY 2014 Corporate Home Office Allocation costs.
    • $791,170 of the contractor’s claimed CFY 2011 Home Office Allocation
    costs.
    • $14,337,524 of the contractor’s claimed Direct Costs. Exhibit C identifies
    the questioned amounts by account.
    (R4, tab 2 at 4) DCAA provided additional detail in Exhibit A (Indirect costs),
    Schedule A-07 (R4, tab 2 at 20-45), and Exhibit C (Direct costs), Schedule C-05 (R4,
    tab 2 at 80-100). At the end of the audit DCAA offered to provide more information,
    “Due to the voluminous nature of the calculations related to these questioned costs,
    additional information will be provided upon request” (R4, tab 2 at 100).
    5. In the audit reports for PID, DCAA questioned the following costs:
    • $297,177 ($267,113 + $30,064) of the contractor’s claimed CFYs 20112013
    Indirect Travel – Airfare costs.
    • $128,246 of the contractor’s claimed CFYs 2011-2013 Bonus Costs which
    are included in the claimed Fringe Expenses.
    • $37,511 of the contractor’s claimed CFY 2011 Workers Compensation
    Fringe Costs.
    • $82,429 of the contractor’s claimed Direct Costs.
    13
    (R4, tab 3 at 6) DCAA provided supporting detail in Exhibit A, indirect costs 2011-2013
    (id. at 12); Schedule A-01, air travel and marketing, G&A and engineering for 2011 (id.
    at 16-18); Schedule A-02, engineering air travel for 2011 (id. at 21); Schedule A-03,
    fringe for 2011 (id. at 22-25); Schedule A-04, G&A air travel for 2012 (id. at 26);
    Schedule A-05, engineering air travel for 2012 (id. at 27); Schedule A-06, fringe for 2012
    (id. at 28); Schedule A-07, G&A air travel for 2013 (id. at 29); Schedule A-08,
    engineering airfare for 2013 (id. at 30); Schedule A-09, fringe air travel for 2013 (id.
    at 31); Exhibit B, penalties for 2011 to 2013 (id. at 32-44); and Exhibit C, direct costs air
    travel for 2011 to 2013 (id. at 45-47).
    DCMA Contracting Officer Final Decisions17
    6. According to the Board’s docketing notice (R4, tab 4 at 1) the following
    ASBCA Nos. are associated with the following government claims:
    ASBCA No.                                       Claim
    61810                             Government claim for $347,915
    61811                             Government claim for $10,692,605
    61812                              Government claim for $572,318
    61813                               Government claim for $6,002
    61814                               Government claim for $2,542
    
    ASBCA No. 61810
     was settled and dismissed with prejudice. 
    ASBCA No. 61812
    was dismissed without prejudice for lack of jurisdiction leaving ASBCA Nos. 61811,
    61813 and 61814 active in this appeal.
    7. On June 28, 2018, Ms. Gladys Broyles, Defense Contract Management Agency
    (DCMA) Administrative Contracting Officer (ACO), issued a Contracting Officer’s Final
    Decision (COFD) demanding payment of $10,692,605 based on DCAA Audit Report
    Nos. 9511-2011G10100001, 9511-2012G10100001, 9511-2013G10100001,
    9511-2014G10100002, dated September 27, 2017 (R4, tab 4 at 28). Based on the
    docketing notice this COFD relates to 
    ASBCA No. 61811
    . ACO Broyles broke down her
    decision into six unallowable direct cost amounts:
    ODC Travel Air                                  $1,335,924
    ODC Hotel                                       $443,368
    ODC Meals                                       $210,771
    ODC Shelter Differential                        $7,602,056
    ODC Other                                       $1,100,486
    G&A                                             $1,722,601
    17   At this point it is difficult, but also unnecessary, to trace the dollar amounts in the
    audits directly to the amounts in the final decisions.
    14
    (R4, tab 4 at 30-31) ACO Broyles provided the rational for her finding in six notes
    associated with each of the six amounts disallowed (id. at 31-40). ACO Broyles
    repeatedly relied on FAR 31.201-3(a) to place the burden to prove challenged costs are
    reasonable on L3 (id. at 31-38).
    8. On June 29, 2018, ACO Cheryl Clark issued a COFD demanding payment of
    $6,002 based on DCAA Audit Report No. 9511-2011W10100001 (R4, tab 4 at 71). Based
    on the docketing notice this COFD relates to 
    ASBCA No. 61813
    . ACO Clark explained
    the $6,002 as follows, “This pertains to contract number FA8620-10-G-3023-1118
    regarding the travel expenses of Frank Franklin and Mark Cross from January 1, 2012 to
    January 12, 2015 outlined in document numbers 19003022785 and 1900303999” (id.).
    ACO Clark further explained, “Under FAR 31.201-3(a) if the contracting officer
    challenges the specific costs . . . ‘the burden of proof shall be upon the contractor to
    establish that such cost is reasonable.’ As a result, in order to establish reasonableness, L3
    PIO has the burden of justifying the need for premium airfare under FAR 3 l-205-46(b) to
    include FAR 3 l.205(46)(a)(7)” (id. at 73).
    9. On June 29, 2018, ACO Jennings L. Summers issued a COFD demanding
    payment of $2,542 based on DCAA Audit Report No. 9511-2011W10100001 (R4, tab 4
    at 79). Based on the docketing notice this COFD relates to 
    ASBCA No. 61814
    . ACO
    Summers explained that the disallowed amount related to air travel by Mr. Bays. ACO
    Summers further explained, “Given the above, under FAR 31.201-3(a), I cannot find that
    a reasonably prudent person would incur the cost of business class airfare for air travel of
    three hours. The return coach airfare trip supports my position. As a result, under
    31.201-3(a) the burden of proof is on L3 to establish reasonableness fell to L3” (Id.
    at 81).
    L3 Appeals
    10. L3 appealed the COFDs to the Board (app. opp’n at 11 ¶ 22).
    DCMA Withdraws the COFDs and Moves for Dismissal
    11. On February 28, 2020 DCMA ACO Charles A. McGlothen withdrew the
    COFDs:
    I hereby unequivocally withdraw the Contracting Officer’s Final
    Decisions (“COFDs”) and demands for payment dated 28 June 2018
    (
    ASBCA No. 61811
    ), signed by Gladys Broyles, 29 June 2018
    (ASBCA No.60813) signed by Cheryl L. Clark, and 29 June 2018
    (ASBCA No.60814), signed by Jennings L. Summers that have been
    appealed to the ASBCA and assigned the respective docket numbers.
    A motion for dismissal of those appeals will be filed by the assigned
    trial attorney. The Government does not intend to re-assert the costs
    at issue in those disputes.
    15
    (Gov’t mot., ex. 1) DCMA filed a Motion to Dismiss on the same day, February 28,
    2020 (gov’t mot.).
    Other Audit Disputes
    12. In its opposition to DCMA’s motion to dismiss, L3 summarizes similar audit
    disputes between L3 and DCAA/DCMA from 2006 through 2018. These disputes all
    followed a similar path: DCAA conducts Audits challenging costs, DCMA issues
    COFDs implementing the DCAA Audits and demanding repayment of the challenged
    costs, L3 appeals the COFDs to the Board and DCMA either withdraws the COFDs or
    the parties settle for a nuisance amount resulting in dismissal of the appeals with
    prejudice (app. opp’n ¶¶ 3-5 (2006), 6-8 (2007), 9-12 (2008), 13-15 (2009) and 16-19
    (2010). The disputes involved in this decision followed a similar path but remain
    unresolved (app. opp’n ¶¶ 20-22 (CYs 2011 to 2014)). There are several similar appeals
    that have been stayed pending resolution of the appeals in ASBCA Nos. 61811, 61813
    and 61814 (app. opp’n ¶¶ 27-28, 33 (CYs 2011 to 2016)).
    13. In its opposition, L3 makes the point that this cycle of DCAA Audit using
    statistical analysis and extrapolation, DCMA COFDs, appeal and withdrawal of the
    COFDs is seen from 1006 through 2018:
    As described above, DCMA ACOs have issued COFDs
    disallowing L3’s airfare costs year after year since 2006 and
    then subsequently withdrew the claims or settled for nuisance
    amounts. This dispute has continued with DCAA’s 2015-2016
    and 2017 audit reports.
    (App. opp’n at 16) And:
    However, it is clear that DCAA continues to question the
    same types of costs for the same reasons, and DCAA also
    continues to use the same purported statistical sampling
    methods.
    (App. opp’n at 15) And:
    During those depositions, several of the auditors who were
    involved in subsequent audits of ICPs (i.e., the 2015, 2016,
    2017, and 2018 ICPs) admitted that DCAA employed
    statistical sampling to extrapolate and question costs in those
    subsequent audits.
    (App. opp’n at 15) And:
    16
    As of the date of this filing, DCMA has not issued a COFD
    sustaining the costs questioned in those reports. However, it
    is clear that DCAA continues to question the same types of
    costs for the same reasons, and DCAA also continues to use
    the same purported statistical sampling methods.
    (App. opp’n at 15)
    Expert Witnesses
    14. Each party employed an expert and submitted an expert report. Neither party
    objected to the expert status of the other party’s expert, therefore, I find both witnesses
    qualify as experts in statistical analysis.
    15. L3’s expert is Mr. Lynford Graham. In his expert report Mr. Graham explains
    that he was hired by L3 “to comment on the applications of statistical sampling in the
    Defense Contract Audit Agency (DCAA) claims of questioned costs as stated in the
    2 audit reports at issue in the appeals of L3 Technologies, Inc. (L3), ASBCA Nos. 61810,
    61811, 61813, 61814” (app. opp’n, ex. 22 at 4-5). Mr. Graham concludes that DCAA’s
    methods using Dollar Unit Sampling (DUS), Physical Unit Sampling (PUS), DCAA’s
    sample size selection, and DCAA’s “EZ-Quant” software used by the DCAA to apply
    statistical techniques all result in unreliable results (id. at 5-6). Specifically, DCAA’s
    methods and software used “for the purpose of estimating questioned costs are not
    supportable” (id. at 6). Attached to Mr. Graham’s report is Appendix A: Summary of
    Sampling Applications in L3 Technology Audits (id. at 46). The table indicates that
    sampling was used for six out of eight costs. By way of explanation I look at employee
    relocation costs. According to the table, DUS sampling was used on a “population” of
    $7,822,914 using a sample of 89 resulting in disallowing $4,359,456 18 (id.).
    16. DCMA’s expert is Mr. Ali Arab. 19 In his rebuttal report Mr. Arab starts out
    by distinguishing DCAA audits, “The audits performed by DCAA are significantly
    different than financial audits. The purpose of an incurred cost audit (the subject of the
    L3 ASBCA cases) is to provide an opinion on the contractor’s certified assertion that the
    incurred cost submission does not contain unallowable costs” (app. opp’n, ex. 23 at 6).
    He further explained:
    My report is focused on DCAA’s sampling program as used
    in the L3 audits. It is important to note that DCAA
    questioned a total of $26.2 million; of which $5.6 million
    (21.4 percent) was based on statistical sampling projections.
    18 The table is not completely self-explanatory and the numbers may be a little off
    because the table is a bit illegible but it serves its purpose for this decision.
    19 DCMA produced Mr. Arab’s expert rebuttal report but expressed its intention not enter
    it into evidence (gov’t resp. at 22).
    17
    The remaining $20.6 million is based on methods outside of
    the use of statistical sampling.
    (Id. at 7) Mr. Arab found that the sample sizes used by DCAA were based on 80% not
    90% confidence level and were therefore smaller than DCAA desired. DCAA’s use of
    DUS sample size planning procedure also contributed to a small sample size (id. at 8).
    He explained that when DCAA used statistical samples to calculate questioned costs, the
    DCAA audit reports present the point estimate as the most likely amount of the true
    questioned costs in the audit universe under review (id. at 11-12). Mr. Arab conducted an
    in-depth review of EZ-Quant and did not identify any issues or concerns (id. at 15).
    17. Mr. Arab explained that Audit Report No. 09511-2011G10100001, dated
    September 27, 2017, used statistical sampling for 21.8 percent of the total questioned
    costs while the remaining questioned costs were from reviewing individual transitions
    using judgmental selection (id. at 15-16). None of the questioned costs in Audit Report
    No. 09511-2011W10100001, dated February 14, 2018, resulted from projections of
    statistical samples. All costs questioned were from review of each transaction using
    judgmental selection. (Id. at 16) Mr. Arab also attached a table at the end of his expert
    report presenting DCAA’s methods of arriving at its questioned coasts (id. at 22).
    DCAA TOP Note
    18. On January 17, 2020, DCAA, apparently relying on Mr. Arab’s findings,
    issued a “TOP Note” that changed the sample size for Dollar Unit Sampling:
    Dollar Unit Sampling (DUS): DCAA's sampling program is
    intended to use a two-sided limit at the 90 percent confidence
    level. However, our evaluation determined that the AICP A
    Table we have used to determine minimum sample sizes is
    'based on a one-sided confidence limit. Consequently, the
    sample sizes correspond to a two-sided limit at the 80 percent
    confidence level; not the two-sided limit at the 90 percent
    confidence level we had instructed.
    Using a lower confidence level results in sample sizes that are
    smaller than desired which impacts the confidence we have in
    the point estimate. As a result, our sample sizes will increase.
    To address this issue, when performing a DUS sample, please
    use the chart below to determine minimum sample sizes.
    (Chart omitted).
    (App. opp’n, ex. 24 at 2) DCAA also changed the sample size for Physical Unit
    Sampling:
    18
    Physical Unit Sampling (PUS): Prior to this Top Note,
    DCAA used the DUS sample size planning procedure for a
    physical unit sample. We determined this methodology is not
    justifiable as the underlying theory for these two methods are
    quite different. Consequently, the sample sizes determined
    for PUS using this approach may potentially be smaller than
    required for a statistically valid sample. To address this issue,
    when performing a PUS sample, please use the EZ Quant
    sample sizer to determine the appropriate sample size. The
    Table is no longer valid for PUS. Enclosure 1 provides
    details on how to use the EZ Quant Sample Sizer.
    (Id. at 3)
    DECISION
    Procedural Background
    After L3 appealed DCMA’s COFDs (SOF ¶ 10), ACO Charles A. McGlothen
    issued a February 28, 2020 letter “unequivocally” withdrawing COFDs for Appeal
    Nos. 61811, 61813 and 61814. The ACO stated, “The Government does not intend to re-
    assert the costs at issue in those disputes” (SOF ¶ 11). Also on February 28, 2020,
    DCMA filed with the Board a Motion to Dismiss ASBCA Nos. 61811, 61813 and 61814
    as moot (id.).
    Rather than accepting dismissal, L3 chose to fight. On March 4, 2020 L3 filed its
    Opposition to Government’s Motion to Dismiss and Cross-Motion for a Decision
    Sustaining the Appeals (app. opp’n). On April 16, 2020 DCMA filed its Response to
    Appellant’s Opposition and Cross-Motion arguing that the appeals were moot (gov’t
    resp.). On May 18, 2020, L3 filed its Reply in Support of its Opposition to the
    Government’s Motion to Dismiss and Cross-Motion for a Decision Sustaining the
    Appeals (app. reply). I view L3’s Cross-Motion for a Decision Sustaining the Appeals as
    a Motion for Summary Judgment.
    The details of above procedural posture is a little confusing. However, the “big
    picture” is that first I must decide if the appeals are moot and if so, does the mootness
    exception apply? If the exception applies, I address L3’cross motion that I deem a
    Motion for Summary Judgment. As explained below, I find the appeals are moot but the
    mootness exception applies and I deny L3’s motion. Therefore, L3 may continue to
    pursue its appeals and (1) challenge DCAA’s statistical audit procedures and
    extrapolation of costs found to be unallowable and (2) prove the reasonableness of the
    alleged unallowable costs.
    19
    Positions of the Parties
    DCMA believes that the appeals should be dismissed as moot based on the
    unequivocal withdrawal of the final decisions and promise not to reassert the claims
    (gov’t mot. at 1). DCMA opposes L3’s argument that the appeal remains “live” because
    there is no possibility that DCMA will reassert the claim (gov’t resp. at 2, 4, 15, 20, 23).
    L3 sums up what it wants as follows:
    More importantly, the appeals are not moot because the issues
    presented in the appeals remain live: L3 seeks a decision on
    the merits to resolve the issues presented in these appeals—
    the continuing dispute over the correct interpretation of
    various FAR sections related to L3’s incurred costs and
    DCAA’s use of purported “statistical” sampling to extrapolate
    questioned costs—which remain live despite the withdrawal
    of the COFDs.
    (App. opp’n at 24) L3 argues that DCAA’s statistical sampling and “extrapolation” of
    questioned costs is flawed. L3 argues, “EZ-Quant is DCAA’s fundamentally flawed
    statistical sampling software application” (app. opp’n. at 16).
    Next L3 raises the issue of the correct interpretation of various FAR sections
    related to L3’s incurred costs. Central to L3’s position is the allocation of burden of
    proof. L3 contends that since these are government claims, DCMA has the burden of
    proof. L3 reasons that since DCMA abandoned its claims, L3 is entitled to judgment on
    the merits due to DCMA’s failure to prove its case.
    ASBCA Nos. 61811, 61813 and 61814 are Moot
    The Board has many decisions dismissing appeals as moot. One of the latest is
    Quimba Software, Inc., 
    ASBCA No. 59197
    , 
    19-1 BCA ¶ 37350
    :
    In seeking dismissal of the appeal on the ground of mootness,
    the government argues that the ACO granted all the relief that
    Quimba sought by voluntarily rescinding the demand for
    repayment of indirect costs paid through provisional billing
    rates and stating that it does not intend to issue another
    decision disallowing the same costs (gov’t mot. at 3-5; see
    statement 7).
    Quimba opposes the dismissal. Quimba's main argument is
    that, while the final audit report was issued in 2008, the
    government waited until December 2013, after expiration of
    20
    the Contract Disputes Act statute of limitations, 
    41 U.S.C. §7103
    (a)(4)(A), to issue the final decision.
    ....
    We reject Quimba's argument and dismiss the appeal as moot.
    (Id. at 181,613) In Beechcraft Defense Co., 
    ASBCA No. 61550
    , 
    18-1 BCA ¶ 37,069
     we wrote:
    Where a contracting officer unequivocally rescinds a final
    decision asserting a government claim, there is no longer any
    claim before the Board to adjudicate, and the Board has
    dismissed the appeal as moot. URS Federal Support Services,
    Inc., 
    ASBCA No. 60364
    , 
    17-1 BCA ¶36,587
     at 178,204;
    Combat Support Associates, ASBCA Nos. 58945, 58946, 
    16-1 BCA ¶36,288
     at 176,973. Accordingly, the appeal is
    dismissed as moot.
    (Id. at 180,431) I find that DCMA’s February 28, 2020 “unequivocal” withdrawal of
    COFDs in ASBCA Nos. 61811, 61813 and 61814 and promise not to “re-assert the costs
    at issue in those disputes” (SOF ¶ 11) renders these appeals moot.
    The Exception to Mootness20
    At the risk of stating the obvious, this repetitive cycle of DCAA Audits
    challenging costs, DCMA COFDs demanding repayment of the challenged costs, L3’s
    ASBCA appeals and DCMA’s dismissals without reaching the merits is untenable
    (SOF ¶¶ 12-13).21 The root cause of why DCMA first adopts DCAA’s audit results and
    then abandons the audits after an appeal is filed is unclear.
    20   The majority seems to focus on “voluntary cessation” not the mootness exception.
    21   This situation is apparently not limited to L3. Quimba Software, Inc., 
    ASBCA No. 59197
    , 
    19-1 BCA ¶ 37350
    ; Advanced Powder Solutions, Inc., 
    ASBCA No. 61818
    , 
    19-1 BCA ¶ 37425
    ; Northrop Grumman Corp., 
    ASBCA No. 61771
    ,
    
    2019 WL 5089236
    ; Northrop Grumman Corp., 
    ASBCA No. 61345
    , 
    2019 WL 4908683
    ; L3 Communications Integrated Systems, L.P., 
    ASBCA No. 60431
    , 
    16-1 BCA ¶ 36362
    ; Sygnetics, Inc., 
    ASBCA No. 60357
    , 
    18-1 BCA ¶ 37160
    ;
    Flightsafety International Inc., 
    ASBCA No. 60415
    , 
    2018 WL 7200012
    ; Combat
    Support Associates, 
    ASBCA No. 58945
    , 
    16-1 BCA ¶ 36288
    ; Beechcraft Defense
    Co., 
    ASBCA No. 61550
    , 
    18-1 BCA ¶ 37069
    ; York International Corp.-York Navy
    Systems, 
    ASBCA No. 60561
    , 
    2016 WL 3565932
    ; Autonomous Solutions, Inc.,
    
    ASBCA No. 59131
    , 
    2014 WL 518988
    .
    21
    I start with the Supreme Court’s discussion of the exception to mootness in
    Weinstein v. Bradford, 
    96 S.Ct. 347
     (1975). In Weinstein v. Bradford the Supreme Court
    did not apply the exception to mootness doctrine but did discuss it in the process of
    reaching its decision:
    In Sosna v. Iowa, 
    419 U.S. 393
    , 
    95 S.Ct. 553
    , 
    42 L.Ed.2d 532
    (1975), we reviewed in some detail the historical
    developments of the mootness doctrine in this Court.
    Southern Pacific Terminal Co. v. ICC, 
    219 U.S. 498
    , 
    31 S.Ct. 279
    , 
    55 L.Ed. 310
     (1911), was the first case to enunciate the
    “capable of repetition, yet evading review” branch of the law
    of mootness. There it was held that because of the short
    duration of the Interstate Commerce Commission order
    challenged, it was virtually impossible to litigate the validity
    of the order prior to its expiration. Because of this fact, and
    the additional fact that the same party would in all probability
    be subject to the same kind of order in the future, review was
    allowed even though the order in question had expired by its
    own terms.
    Sosna decided that in the absence of a class action, the
    “capable of repetition, yet evading review” doctrine was
    limited to the situation where two elements combined: (1) the
    challenged action was in its duration too short to be fully
    litigated prior to its cessation or expiration, and (2) there was
    a reasonable expectation that the same complaining party
    would be subjected to the same action again.
    (Id. 348-49)
    I found no ASBCA decisions applying this exception to mootness, but I did find
    one decision acknowledging its existence. In Combat Support Associates, 
    ASBCA No. 58945
    , 
    16-1 BCA ¶ 36288
     we stated:
    We disagree with CSA that we are confronted with a dispute
    that is “capable of repetition, yet evading review.” A case is
    moot when the issues presented are no longer “live” or the
    parties lack a legally cognizable interest in the outcome.
    Humane Society of the United States v. Clinton, 
    236 F.3d 1320
    , 1331 (Fed. Cir. 2001). However, a claim is not moot if
    that action is capable of repetition, yet evading review. 
    Id.
    To qualify for this exception, the challenged action must meet
    two conditions. 
    Id.
     First, the action must in its duration be
    too short to be fully litigated prior to its cessation or
    expiration. 
    Id.
     Second, there must be a reasonable likelihood
    22
    that the party will again suffer the injury that gave rise to the
    suit. 
    Id.
    (Id. at 176,974) I conclude from Combat Support Associates that there is no impediment
    to the Board’s reliance on the mootness exception in the right circumstances. If there was
    ever the “right circumstance,” this is it.
    DCMA’s Position
    DCMA opposes the application of the “exception” to mootness as follows:
    There is no unlawful activity or wrongful behavior. Second,
    the exception applies when the wrongful behavior is capable
    of repetition. While it is clear that the Government will
    continue to determine the allowability of airfare costs in
    future incurred cost submissions for both L3 and other
    contractors and may continue to utilize statistical sampling in
    estimating the amount of those unallowable costs, the
    Government’s future practice will not affect L3’s entitlement
    to the costs originally questioned in the Government claims at
    issue in these appeals.[ 22]
    (Gov’t resp. at 6-7) I disagree with DCMA’s inference that the mootness exception
    requires “unlawful activity or wrongful behavior” or that DCMA’s “future practice will
    not affect L3’s entitlement to the costs originally questioned.” The cases highlighted
    below do not involve unlawful activity or wrongful behavior. DCMA’s arguments
    against the mootness exception are unpersuasive.
    Examples Where the Exception Applied
    L3 cited a number of Supreme Court and Federal Circuit cases and I selected
    three, in addition to Weinstein v. Bradford (Southern Pacific Terminal Co. v. ICC, 
    219 U.S. 498
    , 
    31 S.Ct. 279
    , 
    55 L.Ed. 310
     (1911)), to help us understand the exception. In
    Kingdomware Technologies v. United States, 
    136 S.Ct. 1969
     (2016) a veteran-owned
    small business brought a 2012 bid protest claim seeking declaratory and injunctive relief
    against Department of Veterans Affairs (VA) alleging that the Department failed to
    comply with the statutory Rule of Two generally requiring the Department to set aside
    contracts for veteran-owned small businesses. By 2014 the contracts in question had
    been fully completed and the cases were moot. After reciting the elements of the
    mootness exception discussed above in Weinstein v. Bradford (Southern Pacific Terminal
    Co.), the Supreme Court in Kingdomware held the exception applied:
    22   This may be true, but every time a contractor must go through this audit, final decision,
    appeal, dismissal fiasco it must incur litigation costs the government does not
    reimburse. Settlement is even worse because the contractor is required to pay.
    23
    Here, no live controversy in the ordinary sense remains
    because no court is now capable of granting the relief
    petitioner seeks. When Kingdomware filed this suit four
    years ago, it sought a permanent injunction and declaratory
    relief with respect to a particular procurement. The services
    at issue in that procurement were completed in May 2013.
    And the two earlier procurements, which Kingdomware had
    also protested, were complete in September 2012. See decl.
    of Corydon Ford Heard III ¶¶ 6–8. As a result, no court can
    enjoin further performance of those services or solicit new
    bids for the performance of those services. And declaratory
    relief would have no effect here with respect to the present
    procurements because the services have already been
    rendered.
    ....
    That exception applies to these short-term contracts. First,
    the procurements were fully performed in less than two years
    after they were awarded. We have previously held that a
    period of two years is too short to complete judicial review of
    the lawfulness of the procurement. See Southern Pacific
    Terminal Co. v. ICC, 
    219 U.S. 498
    , 514–516, 
    31 S.Ct. 279
    ,
    
    55 L.Ed. 310
     (1911). Second, it is reasonable to expect that
    the Department will refuse to apply the Rule of Two in a
    future procurement for the kind of services provided by
    Kingdomware. If Kingdomware's interpretation of § 8127(d)
    is correct, then the Department must use restricted
    competition rather than procure on the open market. And
    Kingdomware, which has been awarded many previous
    contracts, has shown a reasonable likelihood that it would be
    awarded a future contract if its interpretation of § 8127(d)
    prevails. See decl. of Corydon Ford Heard III ¶¶ 11–15
    (explaining that the company continues to bid on similar
    contracts). Thus, we have jurisdiction because the same legal
    issue in this case is likely to recur in future controversies
    between the same parties in circumstances where the period
    of contract performance is too short to allow full judicial
    review before performance is complete. Our interpretation of
    § 8127(d)'s requirements in this case will govern the
    Department's future contracting
    (Id. at 1975-76) In Humane Society v. Clinton, 
    236 F.3d 1320
     (Fed. Cir.),
    wildlife and animal protection organizations sued the President and
    24
    Secretary of Commerce seeking to compel them to renew action against
    Italy under High Seas Driftnet Fisheries Enforcement Act. At the time of
    the Federal Circuit’s decision Italy had stopped widespread driftnet fishing
    and the case was technically moot. However, the Federal circuit held that
    the exception to mootness applied because a claim is not moot if that action
    is capable of repetition, yet evading review:
    In a memorandum date-stamped April 28, 1997, concerning
    “Procedural steps under the High Seas Driftnet Fisheries
    Enforcement Act,” government attorneys recognized that the
    Driftnet Act did not explicitly address the situation if Italy
    was to continue or resume large-scale driftnet fishing after the
    Secretary's certification that driftnet fishing had ceased. The
    memorandum stated that it was possible to read the Act to
    require a new identification of Italy under § 1826a(b)(1)(B)
    and a second round of consultations under § 1826a(b)(2)
    before the Secretary could prohibit the importation of fish
    products from Italy. The memorandum also noted that such a
    process would appear to be incompatible with the purpose of
    the statute and could result in an annual cycle of agreements
    that appear to be adequate on paper but prove to be
    ineffectual in practice.
    We can assume that, if a plaintiff was to challenge the
    Secretary's certification that a nation had ceased driftnet
    fishing and brought forth adequate evidence of persistent
    proscribed driftnet fishing, the Secretary would likely identify
    that nation again. Because of that re-identification, the
    challenge to the Secretary's prior certification would almost
    always be moot under the Government's theory. Thus, the
    question of the propriety of the Secretary's certification would
    escape judicial review. Even the Government's attorneys
    recognized that an ineffectual cycle of repetitious events
    could occur. We conclude that the purpose of the Act is
    better effectuated by holding that the question, whether the
    Secretary's certification that a nation has ceased driftnet
    fishing is in accord with law, is not rendered moot by a later
    re-listing or re-identification of that nation.
    (Id. 1331-32) In Federal Election Commission v. Wisconsin Right to Life, Inc., 
    551 U.S. 449
     (2007) a nonprofit ideological advocacy corporation sued Federal Election
    Commission (FEC), seeking declaration that “electioneering communications” provisions
    of Bipartisan Campaign Reform Act (BCRA) violated First Amendment. Supreme Court
    ruled the dispute was not mooted by passing of the election cycle:
    25
    As the District Court concluded, however, these cases fit
    comfortably within the established exception to mootness for
    disputes capable of repetition, yet evading review. (Citations
    omitted). The exception applies where “(1) the challenged
    action is in its duration too short to be fully litigated prior to
    cessation or expiration, and (2) there is a reasonable
    expectation that the same complaining party will be subject to
    the same action again.” (Citations omitted). Both
    circumstances are present here.
    As the District Court found, it would be “entirely
    unreasonable ... to expect that [WRTL] could have obtained
    complete judicial review of its claims in time for it to air its
    ads” during the BCRA blackout periods. (Citation omitted)
    The FEC contends that the 2–year window between elections
    provides ample time for parties to litigate their rights before
    each BCRA blackout period. But groups like WRTL cannot
    predict what issues will be matters of public concern during a
    future blackout period. In these cases, WRTL had no way of
    knowing well in advance that it would want to run ads on
    judicial filibusters during the BCRA blackout period. In any
    event, despite BCRA's command that the cases be expedited
    “to the greatest possible extent,” § 403(a)(4), 
    116 Stat. 113
    ,
    note following (Citation omitted), two BCRA blackout
    periods have come and gone during the pendency of this
    action. “[A] decision allowing the desired expenditures
    would be an empty gesture unless it afforded appellants
    sufficient opportunity prior to the election date to
    communicate their views effectively.” (Citations omitted)
    3 The second prong of the “capable of repetition” exception
    requires a “ ‘reasonable expectation’ ” or a “ ‘demonstrated
    probability’ ” that “the same controversy will recur involving
    the same complaining party.” (Citation omitted) Our cases
    find the same controversy sufficiently likely to recur when a
    party has a reasonable expectation that it “will again be
    subjected to the alleged illegality,” (citation omitted) or “will
    be subject to the threat of prosecution” under the challenged
    law (citations omited). The FEC argues that in order to prove
    likely recurrence of the same controversy, WRTL must
    establish that it will run ads in the future sharing all “the
    characteristics that the district court deemed legally relevant.”
    Brief for Appellant FEC 23.
    26
    The FEC asks for too much. We have recognized that the “
    ‘capable of repetition, yet evading review’ doctrine, in the
    context of election cases, is appropriate when there are ‘as
    applied’ challenges as well as in the more typical case
    involving only facial attacks.” (Citation omitted) Requiring
    repetition of every “legally relevant” characteristic of an as-
    applied challenge—down to the last detail—would effectively
    overrule this statement by making this exception unavailable
    for virtually all as-applied challenges. History repeats itself,
    but not at the level of specificity demanded by the FEC.
    Here, WRTL credibly claimed that it planned on running “
    ‘materially similar’ ” future targeted broadcast ads
    mentioning a candidate within the blackout period, (citation
    omitted) and there is no reason to believe that the FEC will
    “refrain from prosecuting violations” of BCRA, (citation
    omitted). Under the circumstances, particularly where WRTL
    sought another preliminary injunction based on an ad it
    planned to run during the 2006 blackout period, (citation
    omitted) we hold that there exists a reasonable expectation
    that the same controversy involving the same party will recur.
    We have jurisdiction to decide these cases.
    (Id. at 462-64)
    Each of these cases apply the elements needed to establish the “capable of
    repetition, yet evading review” doctrine which are (1) the challenged action was in its
    duration too short to be fully litigated prior to its cessation or expiration, and (2) there
    was a reasonable expectation that the same complaining party would be subjected to the
    same action again.” Weinstein v. Bradford, 
    96 S.Ct. 347
    , 348-349. I studied the Supreme
    Court’s and Federal Circuit’s application of the exception to mootness in these four
    situations. Southern Pacific Terminal (cited in Weinstein v. Bradford) is the first case in
    which the Supreme Court applied the mootness exception because of “the short duration
    of the Interstate Commerce Commission order challenged, it was virtually impossible to
    litigate the validity of the order prior to its expiration.” In Kingdomware Technologies it
    was the short terms of the contracts meaning they were complete before the courts could
    resolve the case; in Humane Society it was the “Secretary's certification that a nation has
    ceased driftnet fishing”; in Wisconsin Right to Life it was the short duration of BCRA
    [Bipartisan Campaign Reform Act] blackout periods. I want to highlight a significant
    difference between these cases and L3’s situation. In the cases cited above the “short
    duration” element of the exception was satisfied by something outside the control of
    government entity arguing that the case was moot and the exception did not apply. Just
    the opposite in L3’s case. It was DCMA that withdrew the final decisions cutting short
    the appeals. It was DCMA that set up the “capable of repetition, yet evading review”
    situation. DCMA withdraws the COFDs to moot the appeals and then argues that the
    exception does not apply. This is unfair and makes for an even more compelling reason
    27
    to apply the exception. As the Federal Circuit wrote in Humane Society, finding the case
    moot would lead to an “ineffectual cycle of repetitious events. . . .” The same is true in
    L3, dismissal of these appeals as moot perpetuates the “ineffectual cycle” already seen
    between 2006 and 2018 of DCAA audits finding unallowable costs prompting DCMA
    final decisions demanding repayment, L3 appealing to the ASBCA and ultimately
    DCMA abandoning the DCAA audits leaving L3 without resolution of its defenses. I
    conclude from the above that the first element of the mootness exception, “the challenged
    action was in its duration too short to be fully litigated prior to its cessation or expiration”
    is satisfied.
    The record establishes that L3 has endured this cycle of audit, final decision,
    appeal and dismissal for at least twelve years with no end in sight (SOF ¶¶ 12-13).
    Therefore, the second element of the mootness exception “a reasonable expectation that
    the same complaining party would be subjected to the same action again” is satisfied.
    The Mootness Exception Applies in ASBCA Nos. 61811, 61813 and 61814
    I would apply the mootness exception and this case would continue. L3 is entitled
    to present its arguments to the Board. DCAA/DCMA are likewise entitled to defend the
    audits. This does not mean that L3 will prevail, it just gives L3 a chance to make its case.
    I move on to L3’s motion for summary judgment.
    Legal Standard for Summary Judgment
    Summary judgment is properly granted only where there is no genuine issue of
    material fact and the movant is entitled to judgment as a matter of law. The moving party
    bears the burden of establishing the absence of any genuine issue of material fact and all
    significant doubt over factual issues must be resolved in favor of the party opposing
    summary judgment. Mingus Constructors, Inc. v. United States, 
    812 F.2d 1387
    , 1390
    (Fed. Cir. 1987) (citations omitted). In the course of the Board's evaluation of a motion
    for summary judgment, our role is not “‘to weigh the evidence and determine the truth of
    the matter,’ but rather to ascertain whether material facts are disputed and whether there
    exists any genuine issue for trial.” Holmes & Narver Constructors, Inc., ASBCA
    Nos. 52429, 52551, 
    02-1 BCA ¶ 31,849
     at 157,393 (quoting Anderson v. Liberty Lobby,
    Inc., 
    477 U.S. 242
    , 249 (1986)). A material fact is one which may make a difference in
    the outcome of the case. Liberty Lobby, 
    477 U.S. at 249
    . The opposing party must assert
    facts sufficient to show a dispute as to a material fact of an element of the argument for
    reformation or breach. New Iraq Ahd Co., 
    ASBCA No. 59304
    , 
    15-1 BCA ¶ 35,849
    at 175,291-92 (citing Mingus, 
    812 F.2d at 1390-91
    ) (“To ward off summary judgment,
    the non-moving party must do more than make mere allegations; it must assert facts
    sufficient to show a dispute of material fact.”); see Lee's Ford Dock. Inc., 
    ASBCA No. 59041
    . 
    16-1 BCA ¶ 36
    .298 at 177,010.
    28
    L3’s Articulation of the Burden of Proof
    L3 discusses burden of proof several times:
    A decision sustaining these appeals is appropriate in
    accordance with Board Rule 17 (or in the alternative, Board
    Rule 7(c)) and binding precedent of the Board because the
    Government has plainly indicated an intention not to continue
    the defense of the appeals and has failed to meet its burden of
    proving the costs disallowed by the COFDs are unallowable.
    (App. opp’n at 3) L3 repeats this argument later in its opposition:
    A decision sustaining these appeals is appropriate in
    accordance with Board Rule 17, or in the alternative Board
    Rule 7(c), and binding precedent of the Board because the
    Government has plainly indicated an intention not to continue
    the prosecution or defense of the appeals and has not met its
    burden of proving the costs disallowed in the COFDs are
    unallowable.
    (Id. at 34) And:
    The facts in these appeals are analogous to those in Centron.
    The Government has essentially conceded that it cannot—or
    at least has no intent of trying to—meet its burden of proving
    the Government’s cost disallowance claims asserted in the
    COFDs.
    (Id. at 35) And:
    To the extent the Board considers a default judgment
    sustaining the appeals a “sanction” under Rule 16—rather
    than the natural result of failing to defend the appeals or meet
    the Government’s burden of proving the cost disallowance
    claims asserted in the COFDs—it is one that is “necessary to
    the just and expeditious conduct of the appeal” under Rule 16
    and an entirely “appropriate action” under Rule 17.
    (Id. at 36)
    FAR 31.201-3, Allocates the Burden of Proof to L3
    It is true that these are government claims and the government bears an initial
    burden but that burden is not as claimed by L3. As I explain below the government’s
    29
    burden is to challenge specific costs claimed by the contractor. In their briefs, neither L3
    nor DCMA consider FAR 31.201-3, Determining reasonableness and how it operates to
    place the burden of proof on L3. Our interpretation is consistent with that of DCMA’s
    COFDs (SOF ¶¶ 7-9).
    FAR Part 31, Contract Cost Principles and Procedures, defines what costs are and
    are not allowable providing the standards applied by DCAA in its audits (SOF ¶¶ 4-5)
    and DCMA in its final decisions (SOF ¶¶ 7-9). As explained in Boeing North American,
    Inc. v. Roche, 
    298 F.3d 1274
     (Fed. Cir. 2002), this Board is also obligated to follow
    FAR Part 31:
    Although a cost may be allocable to a contract, the cost is not
    necessarily allowable. We have agreed with the general
    proposition that “costs may be assignable and allocable under
    CAS, but not allowable under [FAR].” United States v.
    Boeing Co., 
    802 F.2d 1390
    , 1394 (Fed.Cir.1986). [Footnote
    omitted] And the FAR makes clear that “[w]hile the total cost
    of a contract includes all costs properly allocable to the
    contract, the allowable costs to the Government are limited to
    those allocable costs which are allowable pursuant to [FAR]
    Part 31 and applicable agency supplements.” FAR § 31.201–
    1(b) (2001).
    (Id. at 1280)
    FAR 31.201-2, Determining allowability lists five elements required to determine
    if a cost is allowable (SOF ¶ 1). One of the five elements is reasonableness defined by
    FAR 31.201-3 Determining reasonableness, which includes the following language in
    FAR 31.201-3(a):
    No presumption of reasonableness shall be attached to the
    incurrence of costs by a contractor. If an initial review of the
    facts results in a challenge of a specific cost by the
    contracting officer or the contracting officer’s representative,
    the burden of proof shall be upon the contractor to establish
    that such cost is reasonable.
    (SOF ¶ 1) (Emphasis added)
    When interpreting a procurement regulation, “we seek an interpretation consistent
    with the plain terms provided; it is not our prerogative to insert additional words or
    phrases to alter an otherwise plain and clear meaning.” Raytheon Company, 
    ASBCA No. 57576
     et al., 
    15-1 BCA ¶36,043
     at 176,050. The language to be interpreted, quoted
    and italicized above, is, “If an initial review of the facts results in a challenge of a
    specific cost by the contracting officer or the contracting officer's representative, the
    30
    burden of proof shall be upon the contractor to establish that such cost is reasonable.”
    This language is unambiguous and has only one reasonable interpretation. It requires two
    actions by the government: (1) it must perform an “initial review of the facts,” and (2)
    that review results in a “challenge” to “specific cost[s]” by a contracting officer or
    contracting officer’s representative. If the government meets this initial burden, “the
    burden of proof shall be upon the contractor to establish that such cost is reasonable.”
    DCMA employed this interpretation in its COFDs (SOF ¶¶ 7-9).
    We interpreted FAR 31.201-3(a) in Kellogg Brown & Root, ASBCA, No. 58081,
    
    17-1 BCA ¶ 36,595
    , where we recognized that contesting reasonableness “is significant
    because it shifts the burden of proof” to the contractor (id. at 178,240). We went on to
    hold that a general (blanket) assertion that all costs are unreasonable is insufficient to
    require the contractor to do more to prove reasonableness (id. at 178,250). I do not have
    such a blanket objection before me in these appeals. We have DCAA audits that
    challenge specific costs identified as unallowable and DCMA COFDs demanding
    repayment of those unallowable costs (SOF ¶¶ 7-9).
    In North American Landscaping, Construction and Dredge, Co. (NALCO)
    
    ASBCA No. 60235
    , 
    18-1 BCA ¶ 37116
     a separate concurring decision included the
    following footnote No. 29:
    The Federal Acquisition Regulation (FAR) has, on other
    occasions, permitted a CO's suspicions to trigger a
    requirement that a contractor provide more substantiation for
    certain costs. For example, in FAR 31.201-3, all that is
    necessary to impose upon a contractor the burden of proof of
    demonstrating a particular cost to be reasonable is the CO's
    “challenge” of that cost after “an initial review of the facts.”
    FAR 31.201-3(a). Like the DFARS clause we have discussed
    above, this FAR provision does not go into detail about what
    is sufficient for the CO to bring such a challenge.
    NALCO, 
    18-1 BCA ¶ 37116
     at 180,659 n.29 (emphasis added). This footnote, although
    dicta, presents the interpretation of FAR 31.201-3(a) I followed in this case.
    In Parsons Evergreene, LLC, 
    ASBCA No. 58634
    , 
    18-1 BCA ¶ 37137
    , the trial
    judge employed the same interpretation of FAR 31.201-3(a) I discussed above that was
    applied in Kellogg Brown & Root, 
    17-1 BCA ¶ 36,595
    . Parsons, 
    18-1 BCA ¶ 37137
    at 180,790. A concurring opinion took issue with the trial judge’s conclusion that a
    blanket challenge to costs that failed to challenge specific costs was insufficient to
    require the contractor to do more to prove reasonableness. The concurring opinion
    concluded, “There was no requirement nor need to follow FAR 31.201 to evaluate this
    claim and thus, we concur in the result but not the analysis” Parsons, 
    18-1 BCA ¶ 37137
    at 180,821. Again, I am not faced with such a blanket challenge in this case.
    31
    In BAE Systems San Francisco Ship Repair, 
    ASBCA No. 58809
    , 
    14-1 BCA ¶ 35642
    , citing the Federal Circuit, we held that where the government has challenged
    specific costs, the contractor has the burden of proof to prove the costs it claims are
    reasonable:
    Interpreting FAR 31.201 -3(a), the Federal Circuit recently
    affirmed that the contractor has the burden of proof, unaided
    by a presumption of reasonableness, to establish that the costs
    it incurred were reasonable. Kellogg Brown & Root Services,
    Inc. v. United States, 
    728 F.3d 1348
    , 1363 (Fed. Cir. 2013)
    (“It seems that KBR seeks a presumption that it is entitled to
    reimbursement simply because it incurred facilities costs. It
    is not.”). This Board has long so held. See Northrop
    Worldwide Aircraft Services, Inc., ASBCA Nos. 45216,
    45877, 
    98-1 BCA ¶ 29,654
     at 146,934 (citing Northrop
    Worldwide Aircraft Services, Inc., 
    ASBCA No. 47442
    , 
    97-1 BCA ¶ 28,885
    ).
    (Id. at 174,534)
    L3’s repeated contention that the government has the burden to prove the costs
    challenged by DCAA and DCMA are unallowable is simply wrong. DCAA’s audits and
    DCMA’s COFDs satisfy the government’s initial burden to conduct an initial review and
    contracting officer challenge of specific costs. Accordingly, pursuant to FAR 31.201-3(a),
    “the burden of proof shall be upon the contractor [L3] to establish that such cost is
    reasonable” (SOF ¶ 1).
    Disputed Material Facts Exist
    Thus far I have spent all of my time on the mootness exception and interpreting
    FAR 31.201-3(a) as it relates to the burden of proof. Such interpretation is a question of
    law. States Roofing Corp. v. Winter, 
    587 F.3d 1364
     at 1368 (Fed. Cir. 2009). Questions
    of law are susceptible of resolution by summary judgment. Dixie Construction Company,
    Inc., 
    ASBCA No. 56880
    , 
    10-1 BCA ¶ 34,422
     at 169,917. Although I resolved the
    interpretation / burden of proof questions of law issues, I cannot resolve L3’s motion.
    Placing the burden of proof of allowability on L3 just clears the way for the parties to
    litigate the underlying factual matters in view of the proper allocation of burden of proof.
    DCAA and DCMA contend that the audit challenged costs are unallowable. L3 contends
    that the statistical analysis used in the DCAA audits is flawed 23 and the audit challenged
    costs are allowable. Whether costs are allowable is a question of fact. Martin Marietta
    23   I note that DCMA’s expert, Mr. Arab, identified an error in DCAA’s statistical analysis
    (sample size) that DCAA agreed with and implemented a change (SOF ¶¶ 16-18).
    I do not know if that cured the problem complained of by L3 or not, but L3 is
    entitled to proceed.
    32
    Corp., 
    ASBCA No. 15313
    , 
    71-1 BCA ¶ 8644
     (Disputes as to whether certain kinds of
    incurred costs (e.g. interest, donations, independent R&D, etc.) are allowable under the
    contract are disputes concerning a question of fact arising under the contract provisions . .
    . .). Accordingly, I have disputed material facts that cannot be resolved by summary
    judgment.
    L3 is not Entitled to Summary Judgment that its Challenged Costs are Allowable
    Because the question of allowability of discrete costs involves disputed material
    facts, I would deny L3’s motion and allow the litigation to proceed.
    CONCLUSION
    Based on the above, I would deny DCMA’s motion to dismiss for mootness and
    L3’s motion asking the Board to decide that its challenged costs are allowable. I would
    allow the appeals to proceed.
    Dated: March 1, 2021
    CRAIG S. CLARKE
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA Nos. 61811, 61813, 61814,
    Appeals of L3 Technologies, Inc., rendered in conformance with the Board’s Charter.
    Dated: March 2, 2021
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    33