Anis Avasta Construction Company ( 2020 )


Menu:
  •               ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of -                                   )
    )
    Anis Avasta Construction Company              ) ASBCA No. 61926
    )
    Under Contract No.     H92237-11-C-0830       )
    APPEARANCE FOR THE APPELLANT:                    Mr. Shujah Mowafaq
    President and CEO
    APPEARANCES FOR THE GOVERNMENT:                  Jeffrey P. Hildebrant, Esq.
    Air Force Deputy Chief Trial Attorney
    Isabelle P. Cutting, Esq.
    Trial Attorney
    OPINION BY ADMINISTRATIVE JUDGE WILSON
    ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT
    Anis Avasta Construction Company (appellant) brings this appeal alleging the
    United States Air Force (government) failed to pay appellant for work performed. The
    government moves for summary judgment, arguing that the claim is barred by the six
    year statute of limitations set forth in the Contract Dispute Act’s (CDA) 41 U.S.C.
    §§ 7101-7109, and also that the appeal is barred by the doctrine of laches. Appellant
    counters that there are material facts in dispute that preclude summary judgment. We
    grant the government’s motion.
    STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
    1. On July 27, 2011, the government awarded appellant a contract to construct a 200
    meter water well in Ahmed Kheyl, Afghanistan1 (app. supp. R4, signed contract at 1-3 2).
    2. FAR 52.232-5, PAYMENTS UNDER FIXED PRICE CONSTRUCTION
    CONTRACTS (SEPT 2002), was incorporated into the contract (app. supp. R4, signed
    contract at 14). FAR 52.232-5(h) requires that the government shall pay the amount due the
    1 Appellant submitted a copy of the signed contract (app. supp. R4, contract document).
    The government claims to not have any record of the contract (R4, tab 2). As the
    government is not contesting the existence of the contract in this motion, the
    Board accepts the existence of the executed contract at issue in this appeal.
    2 Appellant submitted several attachments to the Board with its complaint. Due to
    appellant’s pro se status and the difficulty of internet connectivity and mail
    coming from Afghanistan, the Board accepted the attachments as appellant’s
    supplemental Rule 4 file. As the attachments do not have a sufficient tabbing or
    numbering system, reference will be made to the document name and page.
    contractor under this contract after completion and acceptance of all work; presentation of a
    properly executed voucher; and, presentation of release of all claims against the government
    arising by virtue of the contract.
    3. Pursuant to the terms of the contract, on August 1, 2011, appellant signed a notice
    to proceed and had 30 calendar days to complete the contract work (app. supp. R4, contract
    document at 3; notice to proceed).
    4. On September 12, 2011, appellant contacted the contracting officer (CO) via
    email, stating that the water well construction was complete (app. supp. R4, email dtd.
    September 12, 2011). On September 24, 2011, the contracting officer’s representative
    (COR) replied, stating that the government would send the “paperwork to SOTF” (app.
    supp. R4, email dtd. September 24, 2011).
    5. The record contains no evidence of communication between September 24, 2011
    and September 5, 2012.3
    6. On September 5, 2012, email correspondence reflects that appellant reached out to
    the combined joint special operations task force – Afghanistan (CJSOTF-A) via email, and
    stated appellant still did not “have the COR and the person to sign and process the invoice”
    (app. supp. R4, email dtd. September 15, 2012).
    7. On September 10, 2012, appellant again reached out to the CJSOTF-A via email,
    asking “do you have any information of this contract from site” (app. supp. R4, email dtd.
    September 10, 2012).
    8. On September 13, 2012, a government official identified as Mr. Barden,
    responding from the CJSOFT-A email address, contacted appellant and stated, “I have
    discussed the issue with the COR and TSgt Ladd in our payment section. You are clear to
    submit for payment [to the payments email address].” (App. supp. R4, email dtd.
    September 13, 2012)
    9. On September 18, 2012, appellant emailed the CJSOTF-A payments email address,
    as directed by Mr. Barden in the September 13, 2012 email, regarding the invoice (app. supp.
    R4, emails dtd. September 13, 2012, September 18, 2012). Later on September 18, 2012,
    TSgt Ladd responded from the CJSOTF-A payments email address stating that she would
    3   The record includes an email seemingly dated February 8, 2012 from the government
    representative. However, the email address is one clearly used by the personnel in
    that position and not the individual themselves and the date and context aligns
    more with the emails dated in 2011 and not 2012. As such, the Board finds that
    the next communication between the parties after the September 24, 2011 email
    from the government to appellant to be the September 5, 2012 email from
    appellant, requesting information on how to receive payment. (App. supp. R4,
    email dtd. February 8, 2012)
    2
    submit the payment and would copy appellant (app. supp. R4, email dtd. September 18,
    2012).
    10. On October 31, 2012, appellant reached back out to the government at the
    CJSOFT-A payments email address requesting a status of the payment as he had not yet
    received a copy (app. supp. R4, email dtd. October 31, 2012). On November 7, 2012,
    appellant again emailed the CJSOTF-A payments email address, specifically to TSgt Ladd,
    and stated that per their phone conversation the invoice was attached (app. supp. R4, email
    dtd. November 7, 2012). The record contains no evidence of the contents of the referenced
    phone conversation.
    11. On November 14, 2012, TSgt Ladd responded that a signed DD250 was
    necessary to process payment (app. supp. R4, email dtd. November 14, 2012). Later on
    November 14, 2012, appellant responded and stated that he could not “find the COR to sign
    the invoice” and to talk to “Mr. Barden he will tell you the status” (app. supp. R4, email dtd.
    November 14, 2012).
    12. The record contains no correspondence between November 14, 2012 and
    October 29, 2018.
    13. On October 29, 2018, appellant filed a claim dated October 28, 2018 in the
    amount of $72,000 with the current SOJTF-A CO, 1LT Maxwell Marsenison, via email, for
    payment for the Ahmed Kheyl water well project (R4, tab 14 at 3-4; app. supp. R4, email
    dtd. October 29, 2018).
    14. By email dated October 30, 2018, appellant requested that 1LT Marsenison
    confirm he had received appellant’s claim (app. supp. R4, email dtd. October 30, 2018). An
    email exchange on October 31, 2018 shows that appellant communicated with the Director of
    Contracting at SOJTF-A, MAJ Agyemang. MAJ Agyemang requested clarification as to
    whether appellant was referring to payment for the water well project or a pole barn project,
    as appellant submitted documentation for the pole barn project at the same time. Appellant
    stated he was seeking payment for the water well project but submitted the pole barn
    contracting officer’s final decision (COFD) because he had “received the pole barn invoice
    . . . and attached the COFD” for reference. On November 1, 2018, MAJ Agyemang replied
    that the government had no record of the water well contract or that it had been performed,
    which was required for payment. (App. supp. R4, emails dtd. October 31, 2018, November 1,
    2018)
    15. On November 2, 2018, appellant replied to MAJ Agyemang’s email, stating he
    was forwarding the email traffic from September 5, 2012 indicating that the work was
    complete, along with the email traffic from November 4 and 14, 2012, regarding appellant’s
    submission of the invoice (app. supp. R4, email dtd. November 2, 2018). Appellant
    referenced the statement in the November 14, 2012 email from TSgt Ladd indicating that he
    was “still waiting for the DD250 from the COR” (app. supp. R4, email dtd. November 2,
    2018).
    3
    16. On December 8, 2018, contract specialist Rebecca Raish replied to appellant’s
    email of November 2, 2018 and advised appellant that pursuant to 31 U.S.C. § 3702(b) and
    5 C.F.R. § 178.104, appellant could not file a claim against the government after six years
    had passed (app. supp. R4, email dtd. December 8, 2018).
    17. Appellant replied later on December 8, 2018 and stated he submitted a copy of
    the contract, the notice to proceed, and email traffic, which reflects that the contract was
    performed and completed. Appellant also asserted that he “continuously asked the issue
    and followed up with the contracting office until 2013” and never got a result. (App. supp.
    R4, email dtd. December 8, 2018) The record reflects that prior to October 2018, the last
    communication between appellant and the government, was on November 14, 2012, with
    TSgt Ladd, the CJSOFT-A payments contact. In that communication, TSgt Ladd replied
    that a signed DD250 was required to issue payment for the contract and appellant responded
    that he was unable to “find the COR to sign the invoice.” (App. supp. R4, email dtd.
    November 14, 2012)
    18. Appellant filed a notice of appeal at the Board on January 2, 2019 and on
    January 3, 2019 it was docketed as ASBCA No. 61926.
    19. The government filed a notice of appearance in this appeal on January 7, 2019 4
    and on February 7, 2019 the government issued a COFD in this matter and denied
    appellant’s claim, asserting “[t]he government does not have any official evidence to
    support a completion of such contract and as such makes no admission that an enforceable
    contract exists” (R4, tab 16 at 2).
    20. The current CO at SOJTF-A, MAJ Kwame Agyemang, submitted a signed
    declaration dated January 28, 2019. MAG Agyemang declared, in pertinent part:
    a. That after extensive search he has found no record of the appellant
    contractor before January 24, 2017;
    b. That there is no record of the contract work being completed or accepted
    by that office;
    c. The security situation at the site of alleged contract performance makes it
    impossible for the government to verify the existence of the water well.
    (R4, tab 2)
    4   The notice of appearance in the record is dated “7 January 2018”, but was received by
    the Board on January 7, 2019.
    4
    DECISION
    The government moves for summary judgment, contending that appellant’s claim
    is barred by the statute of limitations established by the CDA, and also that appellant’s
    claim has lain dormant for so long that it is barred by the doctrine of laches (gov’t mot.
    at 2).
    A party is entitled to summary judgment if it, as the moving party, has shown that
    there are no genuine issues of material fact and it is entitled to judgment as a matter of
    law. Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986); Mingus Constructors, Inc. v.
    United States, 
    812 F.2d 1387
    , 1390 (Fed. Cir. 1987). Irrespective of the type of claim
    being raised, the applicable substantive law identifies which facts are material and might
    affect the outcome of the appeal, thus precluding the entry of summary judgment.
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986). A dispute is genuine only if,
    on the entirety of the record, a reasonable factfinder could resolve a factual matter in
    favor of the non-movant. In other words, the burden on the movant is not to produce
    evidence showing the absence of a genuine issue of material fact, but to point out that
    there is an absence of evidence to support the nonmoving party’s case. Sweats Fashions,
    Inc. v. Pannill Knitting Co., 
    833 F.2d 1560
    , 1562-63 (Fed. Cir. 1987).
    We view such facts in the light most favorable to the non-moving party, accepting
    its version of facts as true and drawing all reasonable factual inferences in its favor.
    Liberty 
    Lobby, 477 U.S. at 255
    ; C. Sanchez and Son, Inc. v. United States, 
    6 F.3d 1539
    ,
    1541 (Fed. Cir. 1993). However, the non-moving party must set forth specific facts
    showing the existence of a genuine factual dispute; conclusory statements and bare
    assertions are not sufficient. 
    Mingus, 812 F.2d at 1390-91
    ; Pure Gold, Inc. v. Syntex
    (U.S.A.), Inc., 
    739 F.2d 624
    , 626 (Fed. Cir. 1984). Our job is not “‘to weigh the evidence
    and determine the truth of the matter,’ but rather to ascertain whether material facts are
    disputed and whether there exists any genuine issue for trial.” Holmes & Narver
    Constructors, Inc., ASBCA Nos. 52429, 52551, 02-1 BCA ¶ 31,849 at 157,393 (quoting
    Liberty 
    Lobby, 477 U.S. at 249
    ).
    Statute of Limitations
    The government first asserts that appellant’s claim is precluded as a matter of law
    because appellant waited “seven years, one month and 18 days” after the claim accrued in
    order to enforce its right to payment (gov’t mot. at 5). The CDA provides that “[e]ach
    claim by . . . the Federal Government against a contractor relating to a contract shall be
    submitted within 6 years after the accrual of the claim.” 41 U.S.C. § 7103(a)(4)(A). A
    claim accrues “when all events, that fix the alleged liability of . . . the contractor and
    permit assertion of the claim, were known or should have been known.” FAR 33.201.
    The events fixing liability “should have been known” when they occurred unless they
    were either concealed or inherently unknowable at the time. Alion Science and Tech.
    Corp., ASBCA No. 58992, 15-1 BCA ¶ 36,168 at 176,489 (citing Raytheon Missile Sys.,
    ASBCA No. 58011, 13 BCA ¶ 35,241 at 173,017). Only facts that could not reasonably
    5
    be known by the claimant postpone claim accrual.
    Id. (citing United States
    v.
    Commodities Export Co., 
    972 F.2d 1266
    , 1272 (Fed. Cir. 1992)). Failure to meet a
    statute of limitations is an affirmative defense, for which appellant bears the burden of
    proof. Kellogg Brown & Root Servs., Inc., ASBCA No. 58175, 15-1 BCA ¶ 35,988
    at 175,823 (citing FED. R. CIV. P. 8(c); Bridgestone/Firestone Research, Inc. v.
    Automobile Club de L ‘Quest de la France, 
    245 F.3d 1359
    , 1361 (Fed. Cir. 2001)).
    For the purposes of this motion, the Board accepts that the contract existed and the
    work was complete on September 12, 2011, the date appellant contacted the government
    and stated that the work was finished (SOF ¶ 4). On that date, the facts leading to
    appellant’s claim for payment for work completed were objectively and reasonably
    knowable by the parties. Alion Science and Tech. Corp., 15-1 BCA ¶ 36,168 at 176,489
    (citing Raytheon, 13 BCA ¶ 35,241 at 173,017).
    Therefore, September 12, 2011 is the date on which the clock starts in order to
    calculate the statute of limitations. 41 U.S.C. § 7103(a)(4)(A). The record reflects that
    following appellant’s email of September 12, 2011, the government responded on
    September 24, 2011 and then appellant sent a follow up over a year later, on September 5,
    2012 (SOF ¶¶ 5-6). The parties then engaged in a consistent flow of emails between
    September 2012 and November 2012 (SOF ¶¶ 6-11). On November 14, 2012, the
    government representative indicated that appellant would need to submit a completed
    DD250 for payment to be issued (SOF ¶ 11).
    Later on that same date, appellant directed the government to speak with
    “Mr. Barden” and that appellant could not “find the COR to sign the invoice” (SOF ¶ 11).
    The record contains no additional communication, or paperwork as requested by the
    government, from appellant on this matter until October 29, 2018, when appellant
    submitted a certified claim to the government (SOF ¶¶ 12-13). On February 7, 2019, the
    government denied the claim (SOF ¶ 19).
    Based upon the evidence of record, 7 years and 54 days passed from the date the
    claim accrued to the date appellant filed its claim with the current CO. Appellant first
    argues that it has only been 5 years, 10 months, and 16 days and as such, the claim is not
    barred by the CDA statute of limitations (app. resp. at 4). Appellant asserts that
    November 14, 2012, the date of the last email correspondence with the government
    payments contact, wherein he was directed to submit the DD250, is the date when the
    statute of limitations clock starts ticking (SOF ¶¶ 11, 15; see also app. resp. at 4).
    We established above that the contract was completed on the date appellant
    emailed the government representative and stated the project was complete,
    September 12, 2011, and therefore that is the date the claim accrued (SOF ¶ 4; see also
    FAR 33.201). Appellant implies that the date of accrual is the date of the last
    communication with the government payments representative on November 14, 2012
    (SOF ¶¶ 11, 15). However, appellant offers no further explanation as to why accrual
    should be November 14, 2012 instead of September 5, 2011. The contents of the
    6
    November 14, 2012 email requests that appellant submit a DD250 to prove completion
    and acceptance of the government at the contract site (SOF ¶ 11). The undisputed facts
    are that the contract was complete on September 12, 2011 (SOF ¶ 4). Therefore,
    appellant’s passive assertion that the date of the email requesting the DD250 –
    November 14, 2012 – is the date of accrual is no more than a bare assertion of a disputed
    fact. 
    Mingus, 812 F.2d at 1390-91
    ; Pure 
    Gold, 739 F.2d at 626
    . As such, there are no
    material facts in dispute regarding the accrual date of the claim or when appellant
    submitted said claim to the government.
    Appellant also submits that it “regularly followed up” and that the CO already had
    “confirmed the invoice” (app. resp. at 3 ¶ 11). However, this assertion does not negate that
    appellant had six years from the date the claim accrued to file the claim with the
    government for payment. Only facts that could not reasonably be known by the claimant
    postpone claim accrual. Alion Science and Tech. Corp., 15-1 BCA ¶ 36,168 at 176,489
    (citing United States v. Commodities Export 
    Co., 972 F.2d at 1272
    ). Appellant presents no
    facts or argument that would support the notion that appellant could not have reasonably
    known that its claim had accrued. While the Board views the facts in the light most
    favorable to the non-moving party, the non-movant must set forth specific facts showing
    the existence of a genuine dispute, not a conclusory or bare assertion. Liberty 
    Lobby, 477 U.S. at 255
    ; C. Sanchez and 
    Son, 6 F.3d at 1541
    ; 
    Mingus, 812 F.2d at 1390-91
    ; Pure 
    Gold, 739 F.2d at 626
    .
    The parties agree that appellant and the government had a gap in communication
    between September 2011 and September 2012 and then again from November 2012 to
    October 2018. The Board does not consider this to be consistent or continuous
    communication, but most pertinently, appellant’s argument is nothing more than a bare
    assertion that the government failed to respond to appellant’s request for payment without
    providing facts to support that allegation. 
    Mingus, 812 F.2d at 1390-91
    ; Pure 
    Gold, 739 F.2d at 626
    .
    Finally, appellant also argues that the government had enough documentation to
    prove the existence of the contract and the completed work, as provided by appellant
    (app. resp. at 3 ¶¶ 8-12). However, the undisputed facts reflect that the last
    communication in November 2012 from the government requested a document from
    appellant, who, in response, told the government to “talk with Mr. Barden” (SOF ¶ 11).
    Appellant did not present the signed document as requested and did not follow up on this
    matter again until October 2018 (SOF ¶ 13). Appellant has not provided any additional
    facts to dispute this or to support its allegations that it was the government’s
    responsibility to still issue payment without submitting the requested documents. This
    argument is also no more than a bare assertion of a disputed fact and is not sufficient to
    prohibit summary judgment. 
    Mingus, 812 F.2d at 1390-91
    ; Pure 
    Gold, 739 F.2d at 626
    .
    As such, on the government’s motion that appellant’s claim is barred by the statute
    of limitations, the Board finds that summary judgment is warranted. Because we find
    7
    that the government is entitled to summary judgment based upon the CDA’s six-year
    statute of limitations, we do not need to consider the government’s laches argument.
    CONCLUSION
    The government’s motion for summary judgment is granted and the appeal is
    denied.
    Dated: November 18, 2020
    OWEN C. WILSON
    Administrative Judge
    Vice Chairman
    Armed Services Board
    of Contract Appeals
    I concur                                           I concur
    RICHARD SHACKLEFORD                                MICHAEL T. PAUL
    Administrative Judge                               Administrative Judge
    Acting Chairman                                    Armed Services Board
    Armed Services Board                               of Contract Appeals
    of Contract Appeals
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61926, Appeal of Anis
    Avasta Construction Company, rendered in conformance with the Board’s Charter.
    Dated: November 18, 2020
    PAULLA K. GATES-LEWIS
    Recorder, Armed Services
    Board of Contract Appeals
    8