Precision Metals Corp. ( 2018 )


Menu:
  •                ARMED SERVICES BOARD OF CONTRACT APPEALS
    Appeal of --                                   )
    )
    Precision Metals Corp.                         )      ASBCA No. 61422
    )
    Under Contract No. SPE7Ll-15-M-2140            )
    APPEARANCE FOR THE APPELLANT:                         Mr. Tony Figlozzi
    Vice President
    APPEARANCES FOR THE GOVERNMENT:                       Daniel K. Poling, Esq.
    DLA Chief Trial Attorney
    Matthew 0. Geary, Esq.
    Trial Attorney
    DLA Land and Maritime
    Columbus, OH
    OPINION BY ADMINISTRATIVE JUDGE YOUNGER
    ON THE GOVERNMENT'S MOTION TO DISMISS
    DLA Land and Maritime Land Supply Chain (the government) moves to dismiss
    this appeal, arguing that appellant, Precision Metals Corp. (Precision or appellant), failed
    to submit a timely appeal as required by the Contract Disputes Act, 41 U.S.C. § 7104(a).
    Appellant opposes the motion. We grant the government's motion and dismiss the appeal
    for lack of jurisdiction.
    STA TEMENT OF FACTS FOR PURPOSES OF THE MOTION
    1. On 16 July 2015, the government awarded Contract No. SPE7Ll-15-M-2140 to
    Precision for the purchase of "leg, machine gun bipod, left hand" parts. The total award
    amount of the contract was $22,440.00. (Gov't mot., ex. 1)
    2. The contract contained various standard clauses, including Federal Acquisition
    Regulation (FAR) 52.209-3, FIRST ARTICLE APPROVAL - CONTRACTOR TESTING
    (SEP 1989), which provided, in paragraph (b ), that the contractor "shall submit the first
    article test report within 280 calendar days from the date of this contract," a date elsewhere
    specified as 21 April 2016; FAR 52.233-1, DISPUTES (MAY 2014); and FAR 52.249-8,
    DEFAULT(FIXED-PRICE SUPPLY AND SERVICE) (APR 1984) (R4, tab 1 at 11, 17, 20-21).
    3. The contract was modified twice during performance, including once by
    Modification No. POOOO 1, dated 12 May 2016, to extend the first article test delivery date
    to 12 August 2016 (gov't mot., exs. 2-3).
    4. By letter dated 13 March 2017, the government issued a show cause notice to
    Precision, asserting that the first article test had not been delivered by the modified
    delivery date (incorrectly stated to be 2 August 2016), and Precision had not requested a
    new delivery date (gov't mot., ex. 4).
    5. By letter dated 22 March 2017, Precision indicated that it would deliver the
    materials by 10 May 2017 (gov't mot., ex. 5 at 2).
    6. In a letter to Precision dated 3 April 2017, the contracting officer stated that he
    would forbear from terminating the contract until IO May 2017, to allow delivery of the
    first article test report (gov't mot., ex. 6 at 2). The contracting officer warned, however,
    that if the first article test report were not delivered by that date, "the [contract] may be
    terminated in accordance with the default clause" (id.).
    7. By final decision dated 12 May 2017, the contracting officer terminated the
    contract for default following Precision's failure to deliver the first article test report by
    IO May 2017 (gov't mot., ex. 8 at 3-4). The final decision included an advice of rights (id.
    at 4). The contracting officer emailed the final decision to Amy Pitarra, contracts
    administrator at Precision, the same day, and included a read receipt. The read receipt stated
    that the email was read by Ms. Pitarra on 12 May 2017 at 3:24 pm. (Gov't mot., exs. 8-9)
    8. By email dated 15 May 2017, Precision requested reconsideration of the final
    decision (gov't mot., ex. 10 at 1-2). We find no evidence of any subsequent
    communication between the parties until Precision filed its notice of appeal.
    9. Precision filed a notice of appeal with the Board by email dated 21 November
    2017, and the Board thereafter docketed the appeal as ASBCA No. 61422.
    DECISION
    The government's core argument in its motion to dismiss is that the Board lacks
    jurisdiction over this appeal because Precision did not file its notice of appeal within the
    90-day statutory period from receipt of the termination notification (Respondent's Motion
    to Dismiss (motion) at 2-3). For its part, Precision asserts that the government terminated
    the contract despite the fact that the parts were ready for inspection (Bd. corr. ltrs. dtd.
    12 December 2017, 22 January 2018). Precision also requests a no-cost cancellation in
    lieu of the termination for default at issue here and marshals equitable considerations in
    support of its position (id.).
    2
    We conclude that we lack jurisdiction over this appeal. It is familiar that, under the
    Contract Disputes Act (Act), a contracting officer's final decision "is not subject to review
    by any ... tribunal...unless an appeal...is timely commenced." 41 U.S.C. § 7103(g). In tum,
    the Act defines timely commencement to be bringing an appeal to the Board "within 90
    days from the date of receipt of a contracting officer's decision." 41 U.S.C. § 7104(a).
    Numerous decisions give effect to this time limitation, treating it as jurisdictional. E.g.,
    Cosmic Construction Co. v. United States, 
    697 F.2d 1389
    , 1390-91 (Fed. Cir. 1982)
    (holding that the 90-day deadline "is thus part of a statute waiving sovereign immunity,
    which must be strictly construed" and "which defines the jurisdiction" of the Board);
    Decker & Co. v. West, 
    76 F.3d 1573
    , 1578 (Fed. Cir. 1996) (citing Cosmic where appeal
    was filed almost two years after the notice of termination for default and holding that the
    "90-day appeal deadline is jurisdictional and cannot be waived"); Bushra Co., ASBCA
    No. 59918, 16-1 BCA, 36,355 at 177,238 (holding that timeliness of appeal "is a matter
    of the Board's jurisdiction" and "must be brought before the Board within 90 days of that
    decision being received by the contractor"); Mansoor International Development Services,
    ASBCA No. 58423, 14-1 BCA, 35,742 at 174,925 (reciting that Board "may only
    exercise jurisdiction over an appeal filed 'within 90 days from the date of receipt of a
    contracting officer's decision"' under 41 U.S.C. § 7104(a)).
    The evidence shows that the contracting officer sent Precision the termination
    notice by email on 12 May 2017, and the evidence also shows that Ms. Pitarra opened the
    email the same day (statement 7). Taking 12 May 2017 as the receipt date, Precision
    would have been required to file a timely appeal 90 days later, or by 10 August 2017.
    Appellant did not file this appeal until 21 November 2017, well outside the 90-day
    statutory period set forth in the Act for appeals to the Board.
    We also conclude that the contracting officer did not reconsider the decision. It is
    familiar that the finality of a contracting officer's decision may be vitiated by subsequent
    action that lead the contractor reasonably to conclude that the decision was being
    reconsidered. E.g., Sach Sinha and Associates, Inc., ASBCA No. 46916, 95-1 BCA
    , 27,499 at 137,041-42 (holding finality of default termination was vitiated where, after
    issuing decision, contracting officer met with contractor, discussed termination, and
    requested written settlement alternatives). The test is "whether the contractor has
    presented evidence showing it reasonably or objectively could have concluded that the
    [contracting officer's] decision was being reconsidered." 
    Id. at 137,042.
    As we have
    found, there is no evidence of communication, much less discussion of reconsideration,
    after Precision submitted its 15 May 2017 request (statement 8). That leaves only the
    request itself, but a request is not tantamount to reconsideration tolling the 90-day
    deadline. E.g., Propulsion Controls Engineering, ASBCA No. 53307, 01-2 BCA
    , 31,494 at 155,508 (holding it "unreasonable to conclude that a contracting officer is
    reconsidering a final decision simply as a result of a request to do so").
    3
    In opposing the motion, Precision stresses equitable considerations relating chiefly to
    family difficulties and other considerations to justify setting aside the default. But the
    Federal Circuit has held that such considerations are irrelevant to compliance with the
    90-day deadline for appealing to the Board. Cosmic, 
    697 F.2d 1390-91
    . The government's
    motion is granted and the appeal is dismissed for lack of jurisdiction. Appellant's attention
    is directed to the deadline for filing appeals in the Court of Federal Claims.
    CONCLUSION
    The government's motion is granted and the appeal is dismissed for lack of
    jurisdiction.
    Dated: 16 April 2018
    ALEXANDER YOUNGER
    Administrative Judge
    Armed Services Board
    of Contract Appeals
    I concur                                          I concur
    J\J>s_
    RICHARD SHACKLEFORD                               J. REifi PROUTY
    Administrative Judge                              Administrative Judge
    Acting Chairman                                   Vice Chairman
    Armed Services Board                              Armed Services Board
    of Contract Appeals                               of Contract Appeals
    4
    I certify that the foregoing is a true copy of the Opinion and Decision of the
    Armed Services Board of Contract Appeals in ASBCA No. 61422, Appeal of Precision
    Metals Corp., rendered in conformance with the Board's Charter.
    Dated:
    JEFFREY D. GARDIN
    Recorder, Armed Services
    Board of Contract Appeals
    5
    

Document Info

Docket Number: ASBCA No. 61422

Judges: Younger

Filed Date: 4/16/2018

Precedential Status: Precedential

Modified Date: 4/30/2018