In re: Christopher Michael Cote ( 2015 )


Menu:
  •                                                               FILED
    JUL 27 2015
    1                         NOT FOR PUBLICATION
    SUSAN M. SPRAUL, CLERK
    2                                                           U.S. BKCY. APP. PANEL
    OF THE NINTH CIRCUIT
    3                  UNITED STATES BANKRUPTCY APPELLATE PANEL
    4                            OF THE NINTH CIRCUIT
    5   In re:                        )      BAP No. NC-14-1025-TaPaJu
    )
    6   CHRISTOPHER MICHAEL COTE,     )      Bk. No. 12-53464
    )
    7                  Debtor.        )      Adv. Pro. No. 12-05160
    ______________________________)
    8   CHRISTOPHER MICHAEL COTE,     )
    )
    9                  Appellant,     )
    )
    10   v.                            )      MEMORANDUM*
    )
    11   AL V., INC.,                  )
    )
    12                  Appellee.      )
    ______________________________)
    13
    Argued and Submitted on February 19, 2015
    14                     at San Francisco, California
    15                           Filed - July 27, 2015
    16            Appeal from the United States Bankruptcy Court
    for the Northern District of California
    17
    Honorable Stephen L. Johnson, Bankruptcy Judge, Presiding
    18                   ________________________________
    19   Appearances:     Charles Alex Naegele argued for Appellant
    Christopher Michael Cote; Mark B. Freschi argued
    20                    for Appellee Al V., Inc.
    __________________________________
    21
    Before: TAYLOR, PAPPAS, and JURY, Bankruptcy Judges.
    22
    23
    24
    25
    26
    *
    This disposition is not appropriate for publication.
    27   Although it may be cited for whatever persuasive value it may
    have (see Fed. R. App. P. 32.1), it has no precedential value.
    28   See 9th Cir. BAP Rule 8024-1(c)(2).
    1                               INTRODUCTION
    2        Chapter 71 debtor Christopher Cote appeals from the
    3   bankruptcy court’s judgment after trial awarding damages of
    4   $490,883.85 to appellee Al V., Inc. (“Contractor”) and declaring
    5   this debt excepted from discharge under § 523(a)(2)(A).
    6        Contractor sought a nondischargeable judgment based on
    7   alleged fraud relating to a construction contract between it and
    8   Cote.    Its alleged damages consisted primarily of amounts in
    9   excess of its right to recovery under the construction contract
    10   at its formation.
    11        The bankruptcy court found that Cote intentionally deceived
    12   Contractor by knowingly misrepresenting his ability to perform
    13   under the construction contract.    It then determined that this
    14   proximately caused damages to Contractor.    We determine that
    15   these findings were clearly erroneous.
    16        The record is inconsistent with a determination that Cote
    17   lacked necessary funding at initiation of the construction
    18   contract.    It also does not support the conclusion that the
    19   damages awarded were contemplated by the construction contract
    20   at formation or that they were completely recoverable under the
    21   construction contract as thereafter amended.    Therefore, we
    22   REVERSE.
    23                                  FACTS
    24        The Agreements Between Cote and Contractor.    Contractor, a
    25   licensed general contracting company owned by Al Valles and his
    26
    1
    Unless specified otherwise, all chapter and section
    27   references are to the Bankruptcy Code, 
    11 U.S.C. §§ 101-1532
    ,
    and all “Rule” references are to the Federal Rules of Bankruptcy
    28   Procedure, Rules 1001-9037.
    - 2 -
    1   wife,2 entered into a construction contract with Cote's
    2   development company3 to build 10 homes (“Phase I”) of a planned
    3   18-home solar-powered residential subdivision called Hanna
    4   Square in Gilroy, California.4
    5        At the beginning of the relationship, the parties signed a
    6   Letter of Understanding & Confidentiality Agreement dated
    7   June 4, 2007 (the “Confidentiality Agreement”).      Cote agreed to
    8   provide financial, technical, and management data to Contractor,
    9   which included bank construction loan approval letters and
    10   banking data.    Valles testified at trial that this
    11   Confidentiality Agreement somehow prohibited him from contact
    12   with Cote’s construction lender.
    13        The parties also entered into a Construction Services
    14   Contract (“Initial Contract”) along with an Addendum to and
    15   Modification of Construction Services Contract (“Addendum,” and
    16   together with the Initial Contract, the “Construction
    17   Contract”).5    Contractor later argued that he was fraudulently
    18
    19        2
    Valles had been in the contracting business more than
    20 years and had built over 150 custom homes and three
    20   commercial buildings; he primarily worked as an owner-builder
    and not as a third party contractor.
    21
    3
    Cote was the sole owner. At no point did Cote argue
    22   that he was not the proper defendant. For simplicity, we refer
    to the development company and Cote hereinafter as “Cote.”
    23
    4
    Cote’s schedules disclosed that his employment for
    24   21 years was as a Safari Guide and that he received $11,000.00
    per month in gross income. The record suggests, however, that
    25   he may have developed at least one prior project.
    26        5
    Each party admitted a copy of the Initial Contract into
    evidence at trial. Both copies contained identical text and
    27   contained signatures over the signature line for Valles and the
    initials “A.V.” on every page. The handwritten dates differ
    28                                                           (continued...)
    - 3 -
    1   induced to enter into and to perform under this contract.      The
    2   Construction Contract’s terms, thus, are critical to the
    3   analysis, and we highlight the most relevant terms (or lack
    4   thereof) as follows:
    5        1.    The Construction Contract made clear that it did not
    6   provide for the payment of the cost of building the homes in
    7   Phase II.    This necessarily excluded any of the Phase II “under
    8   roof” costs and certain site improvements.    Instead, the
    9   Construction Contract provided that the parties would proceed to
    10   build the eight homes in Phase II within one year of execution
    11   of the Construction Contract if the sales of homes in Phase I
    12   were sufficient.
    13        2.    Contractor agreed to construct the 10 homes in Phase I
    14   for a maximum “under roof” price of $120.756 per square foot or
    15   a total of $1,929,585 ($120.75 multiplied by 15,980 total square
    16   feet).    The Construction Contract, however, also contained
    17   numerous provisions that either required, under certain
    18   circumstances, or incentivized Contractor, in all events, to
    19
    20   (...continued)
    between the copies. At trial, Valles testified that the
    signature on his exhibit was not his signature. But, he did not
    21   dispute his signature on the Initial Contract introduced into
    evidence by Cote. Aside from speculation in Contractor’s
    22   closing argument, there was no further evidence or discussion
    regarding the disparity in signature.
    23
    6
    Valles testified at trial that when he was presented
    24   with the Initial Contract for execution at the title company,
    Cote tried to reduce the agreed building costs from $120.75 per
    25   square foot to $115 per square foot. Their agreement to $120.75
    is contained in the Addendum. As later discussed, Contractor’s
    26   theory of the case does not turn on whether $115 might have been
    sufficiently funded, but $120.75 was not; and Cote never
    27   disputed that he agreed to $120.75 per square foot for the under
    roof building costs when he entered into the Construction
    28   Contract.
    - 4 -
    1   construct the 10 homes at a lower cost.7   Based on these
    2   provisions, Contractor was aware at the time that it entered
    3   into the Construction Contract of Cote's stated goal to have
    4   Phase I completed by January 1, 2008.   There is no evidence that
    5   Contractor advised Cote that his goal was unreasonable.
    6        3.   The Construction Contract also provided for the payment
    7   of certain costs for site improvements and established $589,930
    8   as the total maximum price for site improvements for both phases
    9   of Hanna Square.   Contractor agreed to later provide the
    10   allocated cost of Phase I site improvements; there is no
    11   evidence in the record that it did so or that the parties ever
    12   agreed to a specific number.   The bankruptcy court concluded
    13   that the agreed upon number for Phase I offsite improvements was
    14   $556,461; we disagree.   The Initial Contract stated that this
    15   was the maximum amount payable for both Phase I and Phase II
    16   site improvements.   The Addendum increased the site improvement
    17   budget for both phases to a maximum of $589,930.   The bankruptcy
    18
    7
    First, the Construction Contract required Contractor to
    19   reduce the maximum payable under the agreement if it obtained
    reductions in amounts payable to sub-contractors through
    20   negotiations. Contractor guaranteed in the Construction
    Contract that such negotiations were ongoing. The Addendum also
    21   required a downward adjustment if Cote provided a WRAP insurance
    policy covering Contractor and all sub-contractors at Cote’s
    22   expense. The record establishes that Cote provided insurance of
    some type.
    23        Second, the Construction Contract obligated or incentivized
    Contractor to build the homes in Phase I quickly and to complete
    24   Phase I at a total cost below budget. Contractor agreed to
    identify “the most efficient economic means of achieving
    25   Developer’s objective, which is to bring all homes to market and
    be sold before 1/1/08.” Pl.’s Trial Ex. 1 at 3. Cote agreed to
    26   pay Contractor a bonus payment of 50% of all construction cost
    savings if the project completed below budget and a $50,000
    27   bonus if the Contractor completed 8 of the 10 homes within four
    months of building permit issuance and the remaining 2 homes
    28   within five months of building permit issuance.
    - 5 -
    1   court’s use of $556,461, thus, is not logical or supported by
    2   the record.   In particular, this number was never mentioned by
    3   any party in testimony or in argument at the trial.
    4        The record, however, does support some assumptions as to
    5   what Cote must or should have known regarding Phase 1 site
    6   improvements at the time of the Construction Contract.8    The
    7   only other evidence regarding the site improvement cost for
    8   Phase I is a construction loan progress disbursement request
    9   including a cost allocation recap (“Disbursement Request”),
    10   identified as an exhibit to the construction loan, which
    11   budgeted $358,014 to bonded site improvements and $68,754 to
    12   non-bonded site improvements, for a total of $426,768 in
    13   budgeted site improvement costs.   There is no evidence in the
    14   record that any other amount for allocated Phase I site
    15   improvements was discussed by Contractor and Cote prior to
    16   execution of the Construction Contract, reasonably contemplated
    17
    8
    First, Cote had to assume that something, albeit less
    18   than $589,930, would be payable in relation to site
    improvements.
    19        Second, Cote could not assume that simple division would
    provide the answer. The loan documents in the record budgeted
    20   bonded site improvements of $358,014 and made clear that the
    bonded site improvements related to both phases of the Hanna
    21   Square project. The bankruptcy court correctly assumed that
    Cote was familiar with his lender’s assumptions and documents;
    22   he, thus, knew that he needed to pay the budgeted amount of the
    bonded site improvements when he entered into the Construction
    23   Contract.
    Third, as the bankruptcy court correctly found, the
    24   Construction Contract did not relate to both Phase I and
    Phase II. Thus, it would not be reasonable for Cote to assume
    25   that he needed to pay for all the remaining site improvement
    expense through Phase I financing; for example, it is impossible
    26   to properly landscape a home that is not yet built. The loan
    documents used a budgeted amount of $68,754 for non-bonded site
    27   improvements. The record, thus, establishes that Cote must have
    known that he needed to pay for $426,768 of site improvements in
    28   connection with Phase I.
    - 6 -
    1   by Cote prior to execution of the Construction Contract, or ever
    2   provided by Contractor either before or after the Construction
    3   Contract.
    4        4.   Contractor agreed to receive payment of $39,500 from
    5   the sale of each home if it required payment in excess of any
    6   amounts detailed in the schedule of payments from United
    7   American Bank (the “Bank”).    At trial, Contractor and Cote
    8   disagreed as to the intended meaning and effect of this
    9   provision.
    10        5.   Pursuant to the Addendum, Cote was responsible for
    11   certain expenses including those related to solar arrays and
    12   fill dirt.
    13        6.   The Construction Contract contained a confidentiality
    14   provision that repeated some paragraphs contained in the
    15   Confidentiality Agreement.    As with the Confidentiality
    16   Agreement, Valles contended that this provision prohibited him
    17   from contact with Cote’s construction lender.
    18        7.   The Construction Contract provided that Cote would pay
    19   Contractor in accordance with the Bank’s “Construction Loan draw
    20   system schedule as described in the United American Bank
    21   Construction Loan Document.”    Pl.’s Trial Ex. 1 at 15.    Further,
    22   Cote and Contractor agreed that all draw monies would be
    23   evaluated to confirm that the total monies paid corresponded
    24   with the total percentage of project completed as of the date
    25   the progress payment was requested and paid.
    26        8.   There was no provision for any award of attorney’s fees
    27   or interest.
    28        Funding for Phase I Construction.   Cote obtained a
    - 7 -
    1   construction loan in the total amount of $3.8 million (the
    2   “Construction Loan”) from the Bank.    After payment of existing
    3   liens and other closing costs, there was approximately
    4   $2.6 million in Construction Loan proceeds.     Contractor later
    5   argued that this amount was insufficient to pay amounts owed
    6   under the Construction Contract and, necessarily, that Cote knew
    7   it.   The bankruptcy court ultimately agreed.
    8         The record shows that the Bank also financed an additional
    9   $155,000.9    The bankruptcy court, however, did not address this
    10   additional loan.
    11         Valles testified at trial that, at the formation of the
    12   Construction Contract, Cote stated that he had additional funds
    13   available to him outside the Construction Loan.     The record
    14   supports this statement as there was evidence that some
    15   construction costs were paid where the source of these payments,
    16   is unknown.    The bankruptcy court did not address this evidence.
    17         Cote obtained a bond insuring payment in relation to
    18   $358,014 of site improvements.    The bond was effective;
    19   Contractor sued the bonding company and apparently the bonding
    20   company paid.    The bankruptcy court did not address the bond.
    21         While the parties disagreed about the meaning of the
    22   provision requiring payment from home sale proceeds, there was
    23   no evidence presented establishing that it was unreasonable for
    24   Cote to believe, when he signed the Construction Contract, that
    25   home sales would be sufficient to pay Contractor in full.     The
    26
    9
    An unchallenged document admitted into evidence at trial
    27   (defendant’s trial exhibit N) reflects that with the line of
    credit Cote’s maximum credit from the Bank for costs payable
    28   during Phase I of the Hanna Square project was $3,955,000.
    - 8 -
    1   only evidence in the record was that the Bank valued the entire
    2   Hanna Square project at over $12 million, which left it with a
    3   healthy loan to value ratio of 31% at the time the parties
    4   entered into the Construction Contract.    The bankruptcy court
    5   did not address this evidence.10
    6        Construction Loan Funding.    Valles also executed an
    7   Acknowledgment of Assignment, part of a form bank document
    8   titled Assignment of Construction Contracts dated July 11, 2007
    9   (“Contract Assignment”).    The Contract Assignment recited that
    10   Cote requested a $3,800,000 construction loan from the Bank.
    11   Contractor expressly acknowledged that it was familiar with the
    12   disbursement provisions of the Bank’s loan documents, that the
    13   Bank’s disbursement provisions were satisfactory, and that a
    14   change to the Construction Contract would not be effective
    15   unless Bank approved it.
    16        Valles never disputed that he signed the Contract
    17   Assignment.    He described it, however, as the document Cote
    18   produced to intentionally mislead Valles into believing that
    19   there was a full $3.8 million loan to cover construction costs
    20   for the project.
    21        Phase I Construction.    Once started, construction of
    22   Phase I proceeded with no payment problems until the sixth
    23   month.    Contractor submitted monthly invoices to Cote.   Cote
    24   then submitted monthly progress payment requests to the Bank.
    25
    10
    There is no evidence or argument in the record that
    26   Cote, Valles, or Bank anticipated the rapidly approaching real
    estate recession at the time of the Construction Contract and
    27   Construction Loan Agreement; unfortunately as Phase I of the
    Hanna Square project neared completion, the recession had
    28   arrived.
    - 9 -
    1   The Bank’s construction auditor walked the project with
    2   Contractor’s project manager and discussed the work and
    3   percentage completed.   The Bank deposited the approved amounts
    4   drawn from the loan into Cote’s account at the Bank.   And,
    5   thereafter, Cote issued checks to Contractor, which paid its
    6   invoices in full.   Indeed, on some occasions, the Bank’s auditor
    7   did not approve the full amount requested by Contractor; when
    8   Cote paid these amounts in full, he did so with other funds.
    9        During this time, Cote also utilized Construction Loan
    10   proceeds to pay other related construction costs.   There is no
    11   evidence in the record, however, that he improperly utilized
    12   Construction Loan proceeds or received any payment for personal
    13   benefit.
    14        Cote and Contractor also agreed to a few changes to the
    15   Construction Contract and executed formal change orders in the
    16   total amount of $175,502.   Under these change orders, Cote
    17   agreed to pay Contractor on account of charges notwithstanding
    18   the maximums in the Construction Contract.
    19        Then, in the sixth month (at which point Phase I was
    20   approximately 94% complete), Cote paid only part of Contractor’s
    21   invoice, which brought total payments to Contractor up to
    22   $1,778,350.   This was the last payment made by Cote to
    23   Contractor;11 the relationship fell apart.   Cote advised
    24   Contractor that he was out of money.   His trial testimony and
    25
    11
    Valles testified at trial that Contractor continued work
    26   on the project and that its final invoice was dated February 28,
    2008. He did not testify regarding the party for whom
    27   Contractor continued the work, even after Cote allegedly told
    him he had no more money. But, there is no dispute that
    28   Contractor continued the work.
    - 10 -
    1   the documentary evidence established, however, that at the time
    2   there was $536,501.79 in available credit under the Construction
    3   Loan.     That the Bank later paid additional amounts to Contractor
    4   further evidenced that the Construction Loan was not then fully
    5   drawn.    It appears instead that Cote was not able to immediately
    6   access remaining loan proceeds at the time of default — not that
    7   they did not exist.
    8        The following month, Contractor issued a final invoice for
    9   over $1 million dollars, which included contract overages and
    10   profit thereon of over $447,879 – 19% more than the maximum
    11   amount stated in the Construction Contract.    The same month,
    12   Contractor also filed a mechanic’s lien and initiated a lawsuit
    13   against Cote, the Bank, the bonding company, and others; and, it
    14   filed a lis pendens against the Hanna Square property.
    15        Contractor eventually settled12 the litigation with the Bank
    16   and the bonding company; the settlement brought Contractor’s
    17   receipts just shy of the maximum amount stated in the
    18   Construction Contract for construction of the Phase I homes plus
    19   the entire amount allocated by the Bank for site improvements.
    20   But, it did not cover the 19% overage amount.    At trial,
    21   Contractor offered into evidence copies of authorized change
    22   orders to support only $175,502 of the overages.
    23
    24        12
    The settlement agreement was among the documents
    admitted into evidence by the bankruptcy court (“Settlement
    25   Agreement”). By its terms, it involved settlement of claims for
    construction work on both phases of Hanna Square. Neither the
    26   parties nor the bankruptcy court raised any issue on this point
    and we, therefore, mention it only in passing. There is no
    27   evidence in the record that Phase II homes were constructed; we
    assume the reference to Phase II is attributable to some
    28   Phase II site improvements.
    - 11 -
    1        The bankruptcy and adversary proceeding.    Nearly one year
    2   after the settlement, Cote filed his chapter 7 bankruptcy
    3   petition.   In August 2012, over five years after the parties
    4   entered into the Construction Contract, Contractor filed a
    5   complaint initiating the adversary proceeding seeking judgment
    6   and determination of nondischargeability under § 523(a)(2)(A)
    7   and (a)(2)(B).    The complaint alleged that Cote falsely
    8   represented that he had a $3.8 million Construction Loan because
    9   the loan was actually funded in the principal amount of
    10   $2.1 million.    It alleged that Cote knew the loan amount
    11   representation was false, knew the Construction Loan was
    12   insufficient, and knew the costs of construction were beyond
    13   Cote’s ability to pay.    The complaint alleged that Cote never
    14   intended to fully compensate Contractor as required under the
    15   Construction Contract but, rather, intended to deprive it of
    16   “money, property and services.”    Contractor asserted damages in
    17   the amount of $769,123.01 as a proximate result of Cote’s
    18   alleged misrepresentations regarding his intent to pay and the
    19   sufficiency of funding.
    20        The bankruptcy court held a one-day 6-hour timed trial13 on
    21   December 3, 2013.    The parties objected to virtually none of the
    22   documentary evidence, and the bankruptcy court admitted the
    23   numerous documents into evidence for all purposes; this included
    24   documents submitted without any explanatory testimony and
    25
    26        13
    We have exercised our discretion to review documents
    filed on the bankruptcy court’s electronic docket in the
    27   Adversary Proceeding and in the main case. See O’Rourke v.
    Seaboard Sur. Co. (In re E.R. Fegert, Inc.), 
    887 F.2d 955
    ,
    28   957–58 (9th Cir. 1989).
    - 12 -
    1   documents that appear incomplete or include unexplained
    2   notations.    After trial, the bankruptcy court took the matter
    3   under submission and did not receive further briefing.
    4        The bankruptcy court entered its Order Following Trial on
    5   First Amended Complaint Objecting to Discharge of Debtor (“Order
    6   After Trial”) on January 3, 2014, as its findings of fact and
    7   conclusions of law.    It found that Valles was not sophisticated
    8   in business.   It found that “Cote misrepresented the amount of
    9   funds at his disposal to complete the Hanna Square project[]”;
    10   he did not have $3.8 million in the loan, as he told Contractor,
    11   because nearly $1 million was paid to holders of first and
    12   second deeds of trust; and he told the Bank maximum costs would
    13   be $2,041,636.55 – an amount less than the amount required by
    14   Contractor under the Construction Contract.    Order After Trial
    15   at 11.    The bankruptcy court found that “[d]ue to these
    16   differences, it appears the project ran out of money in January
    17   2008, leaving [Contractor] unpaid.”     
    Id.
    18        Cote timely appealed.14
    19                               JURISDICTION
    20        The bankruptcy court had jurisdiction pursuant to 28 U.S.C.
    21   §§ 1334 and 157(b)(2)(I).    We have jurisdiction under 28 U.S.C.
    22   § 158.
    23                                  ISSUE
    24        Whether the bankruptcy court erred in determining that a
    25   debt owed by Cote to Contractor was excepted from discharge
    26
    27        14
    Cote filed the notice of appeal after entry of the Order
    After Trial, but before the Judgment. Nonetheless, the appeal
    28   was timely. See Fed. R. Bankr. P. 8002(a)(2).
    - 13 -
    1   pursuant to § 523(a)(2)(A).
    2                            STANDARD OF REVIEW
    3        Whether a claim is nondischargeable presents mixed issues
    4   of law and fact.    Deitz v. Ford (In re Deitz), 
    760 F.3d 1038
    ,
    5   1042 (9th Cir. 2014).    Mixed questions of law and fact are
    6   generally reviewed de novo.    See Mathews v. Chevron Corp.,
    7   
    362 F.3d 1172
    , 1180 (9th Cir. 2004); In re Deitz, 760 F.3d at
    8   1043.    In the context of a dischargeability analysis, however,
    9   the bankruptcy court’s factual findings are reviewed under the
    10   clearly erroneous standard.    Candland v. Ins. Co. of N. Am.
    11   (In re Candland), 
    90 F.3d 1466
    , 1469 (9th Cir. 1996).    Thus,
    12   whether a creditor proved an essential element under
    13   § 523(a)(2)(A) is a factual determination reviewed for clear
    14   error.    Am. Express Travel Related Servs. Co., Inc. v. Vee
    15   Vinhnee (In re Vee Vinhnee), 
    336 B.R. 437
    , 443 (9th Cir. BAP
    16   2005).
    17        “Clearly erroneous review is significantly deferential,
    18   requiring that the appellate court accept the [trial] court’s
    19   findings absent a definite and firm conviction that a mistake
    20   has been made.”    United States v. Syrax, 
    235 F.3d 422
    , 427 (9th
    21   Cir. 2000).    The bankruptcy court’s choice among multiple
    22   plausible views of the evidence cannot be clear error.    United
    23   States v. Elliott, 
    322 F.3d 710
    , 714 (9th Cir. 2003).    The
    24   deference owed to the bankruptcy court is heightened where its
    25   choice is based on the credibility of live witnesses.
    26   Rule 8013.    A factual finding is clearly erroneous, however, if,
    27   after examining the evidence, the reviewing court “is left with
    28   the definite and firm conviction that a mistake has been
    - 14 -
    1   committed.”    Anderson v. City of Bessemer City, NC, 
    470 U.S. 2
       564, 573 (1985) (internal citation omitted).
    3        In general, contract interpretation is a question of law
    4   reviewed on a de novo basis.    “This is particularly true where
    5   the intent of the parties is easily ascertainable from the clear
    6   and explicit language of the contract.”     U.S. v. 1.377 Acres of
    7   Land, 
    352 F.3d 1259
    , 1265 (9th Cir. 2003).     If the bankruptcy
    8   court relies on extrinsic evidence in rendering its decision,
    9   however, its findings of fact are reviewed for clear error.      See
    10   
    id. at 1264
    .
    11                                 DISCUSSION
    12   A.   Exception to discharge
    13        A claim for denial of a discharge under § 523 is construed
    14   liberally in favor of the discharge and strictly against a
    15   person objecting to the discharge.      Inst. of Imaginal Studies v.
    16   Christoff (In re Christoff), 
    527 B.R. 624
    , 629 (9th Cir. BAP
    17   2015).   A creditor objecting to the dischargeability of its
    18   claim bears the burden of proving, by a preponderance of the
    19   evidence, that the particular debt falls within one of the
    20   exceptions to discharge enumerated in section 523(a).     Grogan v.
    21   Garner, 
    498 U.S. 279
    , 286-91 (1991).
    22        To prevail on a claim under § 523(a)(2)(A), a creditor must
    23   establish the existence of five distinct elements: (1) the
    24   debtor made representations; (2) debtor knew the representations
    25   were false at the time he made them; (3) debtor made the
    26   representations with the intention and purpose of deceiving the
    27   creditor; (4) the creditor justifiably relied on the
    28   representations; and (5) the creditor sustained the alleged loss
    - 15 -
    1   and damage as the proximate result of the representations having
    2   been made.   Ghomesh v. Sabban (In re Sabban), 
    600 F.3d 1219
    ,
    3   1221 (9th Cir. 2010); Britton v. Price (In re Britton), 
    950 F.2d 4
       602, 604 (9th Cir. 1991).
    5        A debtor’s silence or omission of a material fact can
    6   constitute a false representation that is actionable under
    7   § 523(a)(2)(A).   Citibank (South Dakota), N.A. v. Eashai
    8   (In re Eashai), 
    87 F.3d 1082
    , 1088-89 (9th Cir. 1996).   However,
    9   in order to find liability for fraud based upon omission or
    10   silence, there must also be a duty to disclose.    
    Id.
    11        In this appeal, Cote challenges the bankruptcy court’s
    12   factual findings supporting its determination of
    13   nondischargeability under § 523(a)(2)(A).15   He argues that the
    14   bankruptcy court’s own math reveals its error in finding that
    15   Cote had insufficient funds and that the evidence supports
    16   neither a determination that Cote intended to deceive Contractor
    17   nor a determination that Contractor justifiably relied on the
    18   existence of $3.8 million in construction financing.
    19        This was essentially a fraudulent inducement or fraud at
    20   contract initiation case.   Accordingly, a finding of fraud was
    21   appropriate only if Cote knew that he could not pay Contractor
    22   as required under the Construction Contract at its formation;
    23
    24        15
    Cote also challenges the § 523(a)(2)(A)
    nondischargeability determination on the grounds that his
    25   alleged misrepresentation was an oral “statement respecting the
    debtor’s or an insider’s financial condition,” which is
    26   specifically not excepted from discharge. We disagree entirely.
    Assuming Cote adequately preserved the issue, which the
    27   bankruptcy court failed to address in its written decision,
    because we reverse on other grounds, we need not further address
    28   this argument.
    - 16 -
    1   among other things, this would require that Cote knew that the
    2   Contractor would not complete the project as agreed upon, but
    3   instead would come in significantly over budget and after the
    4   target date for completion.    There is no such evidence in this
    5   record.
    6        While we acknowledge the post-trial deference owed to the
    7   bankruptcy court, we conclude that it grounded its
    8   determinations on three factual findings that are clearly
    9   erroneous.    First, it overestimated the amount Cote agreed to
    10   pay to Contractor under the Construction Contract in connection
    11   with Phase I of the Hanna Square project.    Second, it
    12   underestimated the funds and sources of funds available to Cote
    13   to meet the agreed upon expenses under the Construction
    14   Contract.    And, third, its award of damages exceeded anything
    15   owed under the Construction Contract both as it was initially
    16   drafted and even as modified by the change orders.
    17        The trial testimony record is minimal, especially
    18   considering the amount of debt Contractor sought to have
    19   determined nondischargeable.    We defer to the bankruptcy court’s
    20   credibility assessments as to specific testimony,16 as we must;
    21   but, despite the bankruptcy court’s generalized finding that
    22   Cote was not a credible witness, we conclude that in critical
    23   areas Cote’s undisputed testimony, when corroborated by
    24   documentary evidence, could not be disregarded.
    25        The documents taken into evidence, many of which involved
    26
    16
    The bankruptcy court, again, specifically found that
    27   Valles was not sophisticated in business; nothing in the record
    shows otherwise. Contractor built many homes previously but not
    28   as a third party general contractor.
    - 17 -
    1   no explanatory testimony, were substantial.   The bankruptcy
    2   court undertook to review the record, and we assume it reviewed
    3   all the admitted documents.   See Tevis v. Wilke, Fleury,
    4   Hoffelt, Gould & Birney, LLP (In re Tevis), 
    347 B.R. 679
    , 695
    5   (9th Cir. BAP 2006)(“It is the bankruptcy court’s responsibility
    6   to evaluate the evidence presented . . . [for] [it] has an
    7   obligation to consider all of the evidence properly presented
    8   and to give it the weight that it deserves.”).   Based on our
    9   review of the record, Contractor failed to establish all the
    10   elements of its § 523(a)(2)(A) claim, and, thus, it failed to
    11   carry its burden.
    12   B.   What was the misrepresentation?
    13        Contractor’s complaint alleged that Cote made three
    14   distinct misrepresentations; the bankruptcy court found a
    15   misrepresentation based on a variation of the third.
    16        1.   Alleged false promise to pay
    17        Contractor alleged that Cote induced it to enter into the
    18   Construction Contract without any intention of paying.     The
    19   bankruptcy court did not base its nondischargeability decision
    20   on this theory, therefore, we do not address it in detail here.17
    21        2.   Alleged false representations to the Bank
    22        Contractor also alleged that Cote made misrepresentations
    23   to the Bank regarding the agreed upon price under the
    24   Construction Contract.   The bankruptcy court considered
    25
    17
    In any event, Contractor’s first theory is inconsistent
    26   with the undisputed fact that Cote paid Contractor over
    $1.7 million prior to default and that Contractor, eventually,
    27   received payment of substantially all amounts owed under the
    Construction Contract other than cost overruns and profit
    28   thereon from Cote, Cote's lender, and the bond Cote obtained.
    - 18 -
    1   important the difference between the numbers in the (limited and
    2   largely incomplete) bank documents in evidence and the
    3   Construction Contract cost numbers; but, it did not base its
    4   decision on any alleged misrepresentation made to the Bank.18
    5        3.     False representations regarding the Construction Loan
    6               and the sufficiency of funds to pay Contractor
    7        Contractor alleged that Cote misrepresented19 that the full
    8   $3.8 million of Construction Loan proceeds was available to pay
    9   construction costs and that he failed to disclose that
    10   approximately $1 million of the proceeds was to be used to pay
    11   off existing liens on the property.    It, thus, asserted a claim
    12   of omission in the face of duty to disclose.    Contractor also
    13   implicitly argued that the lesser amount available under the
    14   Construction Loan proved that Cote had insufficient funding to
    15   pay Contractor the full price agreed to under the Construction
    16   Contract.    The bankruptcy court did not entirely reject this
    17   argument; instead, it found fraud on a slightly different basis.
    18        The bankruptcy court found that Cote misrepresented the
    19   amount of funds at his disposal to complete the project.     In
    20   connection with this finding, the bankruptcy court correctly
    21   found that only a maximum of approximately $2.6 million was
    22   available from the $3.8 million Construction Loan to complete
    23
    24
    25
    18
    Nor did the Bank assert a fraud claim against Cote.
    26
    19
    At trial, Valles provided no details as to when, where,
    27   or what Cote actually said to allegedly make Valles believe that
    the Construction Loan did not require loan fees, loan and title
    28   costs, interest reserves, or other common financing costs.
    - 19 -
    1   Phase I of the project.20    It found, in effect, that at the time
    2   of the Construction Contract, Cote knowingly misrepresented that
    3   he had sufficient funds to pay Contractor the amounts owed
    4   pursuant to the Construction Contract.    The bankruptcy court
    5   reasoned that if Cote “had sufficient funding, he would have
    6   paid [Contractor].”    Order After Trial at 13.    The record does
    7   not support this finding.
    8   C.   The record does not support a finding that Cote knowingly
    9        misrepresented that he had sufficient funds to pay
    10        Contractor
    11        1.   The bankruptcy court underestimated Cote’s sources of
    12             funding at the time of contract formation
    13             a)      The Construction Loan proceeds
    14        The bankruptcy court commenced its analysis of the
    15   sufficiency of funds by deducting the payoffs of existing
    16   secured debt ($1,147,199) from the $3.8 million loan amount.
    17   The difference, approximately $2.6 million, is supported by
    18   Cote’s trial exhibit, an estimated closing statement from
    19   Alliance Title Company, “Est. Undisbursed Funds,” which shows
    20   $2,604,463 ("Net Loan Proceeds") remained after the payoffs and
    21   all costs and charges for the loan.
    22
    20
    The bankruptcy court also found that Cote told the Bank
    23   that the project would cost a maximum of $2,041,636.55. We
    question this finding; there was no express testimony in this
    24   regard, and the Bank obtained an assignment of the Construction
    Contract. The bankruptcy court’s finding was based on its
    25   review of the Disbursement Request. A representative of the
    Bank's construction auditor testified that this document was a
    26   progress disbursement request; Valles had no personal knowledge
    of who prepared the document that he received in discovery; and
    27   Cote testified he did not think it was the budget he submitted
    to the Bank. No one testified from the Bank at trial. And the
    28   loan officer involved is now deceased.
    - 20 -
    1        But, rather than analyzing whether the Net Loan Proceeds
    2   were sufficient to pay the Construction Contract at the time of
    3   formation, the bankruptcy court instead analyzed whether a cost
    4   allocation totaling $2,014,636 (roughly identified in the
    5   Disbursement Request) was sufficient to pay the Construction
    6   Contract.   It never further considered whether Cote intended
    7   that any of the approximate $500,000 of loan proceeds
    8   ($2.6 million less $2.014 million) cover any portion of the
    9   costs incurred for Contractor’s services under the Construction
    10   Contract.   This failure was not harmless.   There is no evidence
    11   in the record from which the bankruptcy court could logically or
    12   plausibly infer that the approximately $500,000 ("Excess Loan
    13   Proceeds"), or some part thereof, was not available for payment
    14   to Contractor.21
    15        Obviously, there is a mathematical problem with the
    16   bankruptcy court’s summary conclusion in regard to the Net Loan
    17   Proceeds.   The maximum under roof cost of Phase I, $1,929,585,
    18   plus the maximum site improvement cost for both Phase I and
    19   Phase II, $589,930, is only $2,519,515 — an amount less than the
    20   Net Loan Proceeds.    And, there is no evidence in the record that
    21   supports the bankruptcy court’s finding that Cote knew the
    22   Phase I site improvements would be more than the Bank's budgeted
    23   amount of $426,768.   On a facial review, the Net Loan Proceeds
    24   were sufficient for payment of the maximum obligations under the
    25   Construction Contract reasonably assumed to be payable at the
    26
    27
    21
    At trial Cote testified that the loan contained amounts
    28   for retainage and contingencies, among other costs.
    - 21 -
    1   time of its signing: $2,356,353;22 indeed, there was
    2   approximately $250,000 in Construction Loan proceeds in excess
    3   of this amount.
    4        The bankruptcy court reached a different conclusion by
    5   focusing on the undisputed facts that: (1) the limited bank loan
    6   documents in evidence used $101.06 per square foot (and not
    7   $120.75) as the cost of construction for the homes in Phase I
    8   (totaling $1,614,868) and $426,768, not the bankruptcy court's
    9   erroneously identified $556,461, as the site improvement number.
    10   The bankruptcy court then concluded, in the face of contrary,
    11   undisputed evidence, that only $2,041,636.55 was available for
    12   payment of Construction Contract expenses and that Cote knew it.
    13   These findings were clearly erroneous.
    14        The record is at odds with a conclusion that all Excess
    15   Loan Proceeds were available for construction.   The Construction
    16   Loan documentation, incomplete as it is, indicates that, as is
    17   not uncommon with construction loans, there were interest
    18   reserves built into the anticipated uses of funds.     The evidence
    19   in the record references an interest reserve and interest paid
    20   from the initiation of the Construction Loan of $63,850.65.
    21   Although the record is less than precise, nothing suggests that
    22   Cote reasonably anticipated or should have reasonably
    23   anticipated that interest reserves would exhaust the Excess Loan
    24   Proceeds.   Indeed, as Cote's stated goal was completion of
    25   Phase I and sale of the homes by January 1, 2008, this would
    26   have been close to the maximum in interest carry reasonably
    27
    28        22
    $1,929,585 + $426,768 = $2,356,353.
    - 22 -
    1   anticipated at loan initiation.
    2        The Construction Contract also provided that Cote was
    3   responsible for costs related to certain components of Phase I,
    4   including the solar arrays.     Cote apparently paid some of these
    5   expenses from Construction Loan proceeds.     This payment was
    6   appropriate; Phase I could not be completed without such
    7   advances, but they were draws against the $2.6 million that
    8   further reduced its availability to Contractor.
    9        Cote testified, however, there was also a contingency
    10   budget built into the Construction Loan.     The bankruptcy court
    11   never addressed this testimony, notwithstanding that the limited
    12   loan documents in the record evidence that a contingency line
    13   item existed and was utilized.     Based on the documentary
    14   evidence in the record, the bankruptcy court’s limited view of
    15   the amount of Construction Loan proceeds available to pay costs
    16   under the Construction Contract was clearly erroneous.
    17        The record, instead, supports that as of the formation of
    18   the Construction Contract, Cote had access to sufficient funds
    19   or significant funds to cover the known costs reasonably
    20   anticipated to be incurred under the Construction Contract in
    21   Phase I from Construction Loan proceeds.     The bankruptcy court’s
    22   disregard of the Net Loan Proceeds as a source of payment is
    23   clear error.
    24               b)   The additional $155,000 line of credit
    25        In addition to the $3.8 million in Construction Loan
    26   proceeds, Cote testified that he had a separate line of credit.
    27   The record supports his testimony and there was no contrary
    28   evidence.    The bankruptcy court never addressed this source of
    - 23 -
    1   funding.   On this record, its failure to consider these funds as
    2   a source of repayment was not harmless error.
    3              c)   The bond for site costs
    4        Cote also obtained a bond for site costs.23   Of the $426,768
    5   in budgeted site costs, Contractor’s trial exhibit reflects the
    6   amount of bonded site costs as $358,014.24
    7        The bankruptcy court never considered this insurance of
    8   funding in its analysis.    Contractor presented no evidence that
    9   it was at risk for nonpayment for bonded site improvements
    10   despite the fact that payment was substantially assured via the
    11   bond obtained by Cote; indeed, the only evidence was that it
    12   received post-default payment from the bond.    The bankruptcy
    13   court’s failure to consider this evidence is not harmless error.
    14              d)   Deferred funding: $39,500 contract provision
    15        At trial the parties disagreed on the meaning and import of
    16
    23
    A recital in the Settlement Agreement states that
    17   American Contractors Indemnity Company, as surety for Cote,
    “issued certain performance and labor and materials bonds in
    18   connection with the project, including without limitation,
    Subdivision Public Improvement Payment Bond No. 1000756422 in
    19   the amount of . . . ($393,816.00), dated of (sic) July 10 2007
    (the “Bond”). It appears that the Bond likely covered both
    20   Phase I and II, as “Project” is defined in the Settlement
    Agreement to include all phases of Hanna Square, and the amount
    21   of the Bond is higher than the amount set forth in the
    Disbursement Request for Phase I only. Contractor’s reference
    22   to “project” and “Project” in its various pleadings
    inconsistently varied as to whether it was referring to one or
    23   both phases of Hanna Square. And at trial, Contractor’s counsel
    attempted to impeach Cote by reading Cote’s deposition testimony
    24   taken in the state court action wherein he stated that he knew
    the Bank did not lend enough to complete the entire project.
    25   Read in context, Cote was referring to the undisputed fact that
    the Bank made its loan only for Phase I of Hanna Square except
    26   as to certain bonded site improvements.
    27        24
    Bonds generally provide a separate source of payment of
    site costs in the event funding is unavailable and are
    28   frequently required by construction lenders.
    - 24 -
    1   the provision in the Construction Contract for Contractor’s
    2   deferral of payment for up to $39,500 per home until the close
    3   of escrow on the homes.    Cote testified that he relied on this
    4   provision as a source for payment of costs up to $395,000 to the
    5   extent Contractor’s costs exceeded the amount provided by the
    6   Bank under its progress payment process.    Again, there was no
    7   evidence presented establishing that it was unreasonable for
    8   Cote to believe, when he singed the Construction Contract, that
    9   home sales would be sufficient to pay Contractor in full.
    10        The bankruptcy court, with no discussion or analysis, found
    11   that this contract provision applied only if the Contractor
    12   “required” the changes that resulted in the overages.    As shown
    13   in Contractor’s February 2008 invoice, Contractor requested
    14   judgment for costs and profits thereon that were incurred in
    15   excess of the maximum amount reasonably viewed as payable under
    16   the Construction Contract.    This overage equals $447,879 - 19%
    17   over the maximum price agreed upon by the parties in the
    18   Construction Contract.    Even under Contractor’s and the
    19   bankruptcy court's interpretation of the $39,500 provision,
    20   Contractor agreed to defer receipt of payment of $395,000 of
    21   this amount until close of escrow on the homes.    Close of escrow
    22   never occurred.
    23        Thus, the bankruptcy court’s finding that the $39,500
    24   provision applied to none of the amounts for which Contractor
    25   sought payment is clearly erroneous.    This error is not
    26   harmless, as the record supports Cote’s testimony that he
    27   thought that if problems arose he had up to $395,000 with which
    28   to complete construction of the project based upon Contractor’s
    - 25 -
    1   agreement to defer payment on such required amounts until close
    2   of escrow.   The only evidence in the record is that at the time
    3   the loan was made and the Construction Contract was executed,
    4   the Bank valued the Hanna Square project at $12 million, which
    5   left it with a healthy loan to value ration of 31%.
    6              e)   Other funding sources
    7        The record is thin on this point, but there is evidence of
    8   payments from sources other than the Bank's loan proceeds.     The
    9   bankruptcy court also ignored this documentary evidence.
    10        In sum, the record shows that Cote had funding sources that
    11   the bankruptcy court did not consider.
    12        2.    The bankruptcy court overestimated the reasonably
    13              assumed site costs for Phase I
    14        It is undisputed that Cote agreed to pay Contractor a total
    15   of $589,930 for all site improvement (non-building) costs for
    16   Phases I and II together.    But, nothing in the record shows what
    17   amount, if any, the parties agreed to for the Phase I site
    18   costs.    The only admitted evidence for Phase I site costs
    19   consisted of the site cost number reflected in the Disbursement
    20   Request, $426,748.     Therefore, the bankruptcy court erred when
    21   it assigned $556,461, the amount in the Initial Contract for
    22   both phases, to the Phase I site costs; there is no support in
    23   the record for this determination.      This error was not harmless.
    24        3.    The bankruptcy court's determination of falsity, thus,
    25              was based improperly on findings that were clearly
    26              erroneous
    27        The errors detailed above led the bankruptcy court to the
    28   conclusion of material falsity through statement, omission, or
    - 26 -
    1   action.    Its determination was clearly erroneous.   The record is
    2   clear that Cote had sources of payment not acknowledged by the
    3   bankruptcy court.    Further, the record makes clear that the
    4   bankruptcy court erroneously inflated the maximum amount due
    5   under the Construction Contract at its initiation by including
    6   overstated site improvement costs and erroneously concluded that
    7   Cote knew that he lacked sufficient funds.
    8        Contractor argues on appeal that Cote should have known
    9   that the project would go over budget, because all projects go
    10   over budget.    We disagree.   Contractor presented neither
    11   evidence supporting its argument that all projects go over
    12   budget nor evidence that Cote knew Contractor would go over
    13   budget.    Rather, the record shows that Cote built in monetary
    14   incentives to try to encourage quick construction and cost
    15   savings efforts - to bring the project in early and below
    16   budget.    The record also shows that the amounts in the
    17   Construction Contract were maximums and that Contractor was
    18   obligated to provide reductions upon certain circumstances.
    19   There is nothing in the Construction Contract that allowed
    20   Contractor to charge anything in excess of the amounts set forth
    21   therein.
    22   D.   The record does not support the bankruptcy court's
    23        determination of proximate cause and justifiable reliance
    24        The bankruptcy court found that Contractor sustained
    25   damages, although it did not articulate whether the damages were
    26   the proximate result of the misrepresentation on which it based
    27   its § 523(a)(2)(A) judgment.     It awarded the damages as
    28   calculated by Contractor in its final February 2008 invoice,
    - 27 -
    1   subtracted the $535,000 settlement amount received and awarded
    2   Contractor $490,883.85.
    3        On this record, the bankruptcy court clearly erred in
    4   implicitly determining that pre-Construction Contract statement
    5   or omission proximately caused the damages that it ultimately
    6   awarded.    Contractor received payment of all but $47,353 of the
    7   maximum under roof cost in the Construction Contract, plus 100%
    8   of the site improvement costs included in the Bank's budget.
    9   The vast majority of the damages awarded by the bankruptcy
    10   court, thus, were amounts that resulted from cost overruns
    11   beyond the scope of the Construction Contract.
    12        There is no evidence in the record that Cote ever agreed to
    13   pay all these requested cost overruns as he executed only
    14   $175,000 in change orders.    Again, Contractor agreed in the
    15   Construction Contract to build the Phase I homes and related
    16   site improvements for a maximum amount.    It thus requested – and
    17   received – damages greater than either the original contract
    18   amount or the increased contract amount given the limited change
    19   orders.    The damages awarded by the bankruptcy court exceed
    20   those available even under a breach of contract theory.
    21        In sum, it was illogical and implausible for the bankruptcy
    22   court to find that Contractor was proximately damaged by being
    23   induced to enter into a contract under which Contractor received
    24   payment of almost all but the amounts that exceeded the
    25   contractual maximums.
    26        The bankruptcy court also found that Valles and, thus,
    27   Contractor relied on Cote’s representation about the sufficiency
    28   of funds at Cote’s disposal.    Valles testified that Cote told
    - 28 -
    1   him he had a $3.8 million loan; as stated, this was true.
    2        Contractor, however, presented no evidence that the full
    3   $3.8 million amount was necessary to pay Contractor.   Both
    4   Valles and Frietas testified that when Cote changed the rate of
    5   compensation to $115, they insisted it be revised to $120.75.
    6   The bankruptcy court did not find Cote believable when he
    7   testified that he only agreed to the increase because he was in
    8   a hurry to close the loan even though Valles and Frietas were
    9   taking advantage of him.25   We do not question this finding, but
    10   note that the difference between the two amounts is $5.75 per
    11   square foot, a total of $91,885.   Based on Contractor’s alleged
    12   damages, the insufficiency of funds issue cannot turn on this
    13   rate differential.
    14        The bankruptcy court did not find that Contractor’s
    15   reliance was justifiable, although, again, it found that Valles
    16   “did not appear to be particularly sophisticated in business
    17   transactions.”   Order Following Trial at 9.
    18   E.   The record does not support unequivocally the bankruptcy
    19        court’s inference that Cote intended to deceive Contractor
    20        The bankruptcy court found that Cote’s intent to deceive
    21   Contractor was clear.   The record does not support its finding
    22   unequivocally.
    23         The bankruptcy court relied on Valles’ testimony that he
    24   was kept in the dark on the loan and construction funding
    25   process and that he had restricted access to both the Bank and
    26
    25
    Although the bankruptcy court made a general finding
    27   that Cote was not a credible witness, this was the only
    testimony that the bankruptcy court specifically identified as
    28   not credible.
    - 29 -
    1   its auditor.   The record, however, was inconsistent on these
    2   points.
    3        The bankruptcy court appears implicitly to have concluded
    4   that Cote intentionally did not provide Valles any bank
    5   documents.   But the record is devoid of any testimony to this
    6   effect and, in fact, is inconsistent with Valles’ execution of
    7   the Contract Assignment wherein he acknowledged and accepted the
    8   disbursement provisions in the Bank’s loan documents.     Further,
    9   at trial, Valles testified that Cote provided him other
    10   documentation regarding the funding for the project, although
    11   Valles did not recall any other specific documents.26     Thus, the
    12   record is unclear as to what loan documentation Valles reviewed.
    13        Valles also testified that he was prevented from contacting
    14   the Bank’s auditor, but this testimony is inconsistent with
    15   testimony by Contractor’s project manager and agent, Frietas.
    16   Frietas testified that with each invoice submitted by
    17   Contractor, Frietas walked the project with the Bank's auditor
    18   and discussed billings and percentage completion.   The
    19   bankruptcy court found both Valles and Frietas to be credible
    20   witnesses.   It, however, failed to address or reconcile the
    21   inconsistencies in their testimony.
    22        The bankruptcy court also found the method of disbursing
    23   loan proceeds, the requirement that Contractor acknowledge
    24   assignment of the Construction Contract, the fact that the Bank
    25
    26
    The Contract Assignment was the only bank loan document
    26   admitted in its entirely into evidence. Contractor’s exhibit
    list included a document titled “United American Bank Loan
    27   Agreement (Loan #171571)” as exhibit 30, but it, along with
    documents numbered 31 through 44, was crossed off the list and
    28   never discussed or offered at trial.
    - 30 -
    1   dealt exclusively with Cote, and other aspects of the lending
    2   process supported its determination of intent to defraud.    We
    3   note that there was no expert testimony or secondary sources
    4   discussing construction lending introduced into evidence at
    5   trial.   Nor was there any testimony that Cote, as opposed to the
    6   Bank, dictated the terms of the construction loan and decided
    7   how to disburse loan proceeds; one would logically assume that
    8   the Bank would make these decisions.   The only testimony
    9   suggesting concern on these points was from Valles, who, as
    10   previously discussed, was found to be unsophisticated in
    11   business.
    12        Finally, the bankruptcy court found evidence of intent to
    13   defraud from what it described as alterations Cote made to the
    14   amounts requested by Contractor when he sought payments from the
    15   Bank.    Nothing in the record, however, shows that Cote made any
    16   such alterations.   The record evidences that he requested
    17   payment consistent with Contractor’s requests, but also sought
    18   advances on account of other project costs not covered under the
    19   Construction Contract, such as $157,400 for solar arrays and
    20   $100,000 for insurance.   The Construction Contract made clear
    21   that Cote was responsible for these portions of the Phase I
    22   construction; nothing in the agreements prohibited him from
    23   using some of the Construction Loan proceeds to pay these
    24   required costs.   Again, there was neither testimony nor evidence
    25   presented establishing that this use was inconsistent with the
    26   discussions of the parties prior to execution of the
    27   Construction Contract or at any point in time.
    28
    - 31 -
    1                         CONCLUSION
    2   Based on the foregoing, we REVERSE.
    3
    4
    5
    6
    7
    8
    9
    10
    11
    12
    13
    14
    15
    16
    17
    18
    19
    20
    21
    22
    23
    24
    25
    26
    27
    28
    - 32 -