Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp. , 2022 Ohio 19 ( 2022 )


Menu:
  • [Cite as Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp., 
    2022-Ohio-19
    .]
    COURT OF APPEALS OF OHIO
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    BROADWAY CONCRETE                                    :
    INVESTMENTS, L.L.C.,
    :
    Plaintiff-Appellee,                                        No. 110420
    :
    v.
    :
    MASONRY CONTRACTING
    CORP., ET AL.,                                        :
    Defendants-Appellants.                :
    JOURNAL ENTRY AND OPINION
    JUDGMENT: AFFIRMED IN PART; REVERSED AND REMANDED
    IN PART
    RELEASED AND JOURNALIZED: January 6, 2022
    Civil Appeal from the Cuyahoga County Court of Common Pleas
    Case No. CV-18-903809
    Appearances:
    Stark & Knoll Co., L.P.A., Michael L. Fortney,
    Alexandra N. Nienaber, and Richard P. Schroeter, Jr., for
    appellee.
    The Law Offices of David M. Leneghan, David M.
    Leneghan, K. Scott Carter, and Catana Chrostowski, for
    appellants.
    KATHLEEN ANN KEOUGH, P.J.:
    Defendants-appellants, Mason Contracting Corp. (“MCC”) and
    Western Surety Company (“Western Surety”), appeal the trial court’s judgment,
    rendered after a bench trial, that found in favor of plaintiff-appellee, Broadway
    Concrete Investments L.L.C. d.b.a. Pompili Precast Concrete (“Pompili”) on Pompili’s
    claims for breach of contract and violation of Ohio’s Prompt Payment Act and
    awarded Pompili $82,388.51 in damages, plus $21,230.86 in interest and
    $101,945.05 in attorney fees. For the reasons that follow, we affirm in part and
    reverse and remand in part for further proceedings consistent with this opinion.
    I.   Background
    This case arises out of the Nord Family Greenway construction
    project on the Case Western Reserve University campus. The prime contractor for
    the project was Gilbane Building Company. Gilbane subcontracted with Platform
    Cements, Inc. d.b.a. Platform Contracting (“Platform”) for Platform to perform
    excavation, site concrete, and hard cast (including precast concrete) for the project.
    Platform subcontracted the precast concrete work to MCC, which in turn
    subcontracted the supply of the precast concrete to Pompili by way of a purchase
    order in the amount of $366,830.75 executed on October 26, 2016.
    The evidence at trial demonstrated that prior to receiving the
    purchase order from MCC, Pompili submitted a written quote for the precast work
    directly to Platform. A copy of Pompili’s quote, which included various contract
    terms, was attached to the signed purchase order between MCC and Pompili, and a
    handwritten note on the purchase order stated, “Note: see Broadway Concrete LLC
    Terms & Conditions – Attached as Information Only.” Likewise, the written terms of
    the purchase order stated, “Special Conditions: See attached Quotation #0209-001
    for reference only.” Each page of the attached quotation from Pompili was marked
    “INFORMATION ONLY.”
    With respect to payment of Pompili’s invoices by MCC, the purchase
    order required all invoices to be submitted to MCC by the 25th of the month “in order
    for the invoices to be put on the appropriate draws. Receiving invoices after the 25th
    will delay your payment.” The contract stated further that MCC “will issue checks
    within 5 banking days after we receive payment.”
    MCC submitted three pay applications to Platform in 2016: the first
    in September, another in November, and the third in December. Pompili had not yet
    submitted any invoices to MCC and accordingly, none of these pay applications
    included any Pompili invoices. Matthew Birch, owner and president of MCC, testified
    at trial that MCC’s first pay application to Platform, in the amount of $50,000, was
    the result of an agreement with Platform that he would reduce his quote by $50,000
    and Platform would give him an up front payment to help his start-up company.
    Birch testified that when he submitted his original bid to Platform, he met with Jason
    Klar, the owner of Platform, who told him that his bid was high. Birch told Jason that
    he could reduce his bid if Platform paid him $50,000 to help start his newly formed
    company. Birch testified that Jason agreed, paid him the agreed-upon $50,000, and
    told him to invoice Platform.
    Jeremy Kler, the project manager for Platform on the project, was
    called as a witness by Pompili. Kler testified that Jason negotiated Platform’s contract
    with MCC and agreed to pay MCC $50,000 up front for its first pay application. Kler
    testified that he reviewed the pay application and approved it, even though none of
    the billed items had been completed at that point.        Kler likewise confirmed that
    MCC’s initial quote to Platform was for $674,980, but the contract executed between
    Platform and MCC was for $624,980. Platform paid MCC’s first pay application of
    $50,000 on October 13, 2016 — the same day it executed its contract with MCC and
    13 days before MCC and Pompili executed their subcontract.
    Pompili submitted its first invoice in the amount of $3,500 to MCC
    on January 31, 2017. MCC included Pompili’s invoice on its fourth pay application to
    Platform on January 25, 2017.1 Platform paid MCC’s fourth pay application on May 4,
    2017; MCC paid Pompili’s invoice on April 20, 2017, 14 days before it received payment
    from Platform.
    Pompili submitted its second invoice in the amount of $20,000 on
    April 20, 2017. MCC included Pompili’s invoice on its seventh pay application to
    Platform on April 25, 2017.       MCC received a partial payment of its total pay
    application from Platform on June 17, 2017, and tendered the full amount of Pompili’s
    invoice to Pompili on June 21, 2017.
    1 Birch testified that he included money for Pompili in his fourth pay application
    before receiving Pompili’s invoice because he knew Pompili was working on shop drawings.
    Pompili’s third invoice, dated May 19, 2017, was for $30,000 and
    included on MCC’s eighth pay application to Platform on May 25, 2017. MCC received
    payment from Platform on August 1, 2017, and paid Pompili on August 3, 2017.
    Pompili’s fourth invoice, dated June 29, 2017, in the amount of
    $5,000, was included on MCC’s ninth pay application to Platform dated June 25,
    2017. MCC paid Pompili on August 31, 2017, even though it did not receive payment
    from Platform on this application until September 27, 2017.
    Pompili’s fifth invoice, dated August 15, 2017, in the amount of
    $70,000, was included on MCC’s 11th pay application submitted to Platform on
    August 25, 2017. MCC paid Pompili on November 27, 2017, 17 days before it received
    payment from Platform on December 4, 2017.
    Pompili’s sixth invoice, dated September 18, 2017, for $36,500, was
    included on MCC’s 12th pay application to Platform on September 25, 2017. MCC
    paid Pompili on November 27, 2017, 17 days before receiving payment from Platform
    on December 14, 2017.
    On October 14, 2017, Pompili submitted its seventh invoice for
    $110,000. MCC included the invoice on its 13th pay application to Platform. Platform
    rejected the application, however, and informed MCC the owner had decided it would
    no longer pay for material that was stored off-site and would pay only for material
    that was installed or on-site. Platform advised Birch to revise his pay application.
    Birch conducted an on-site survey and concluded that Pompili’s invoices were
    overstated as compared to what material was on-site or installed. Platform agreed
    with Birch’s conclusion. Birch then revised Pompili’s invoice downward to reflects its
    overbilling and submitted a revised 13th pay application to Platform. Platform paid
    this pay application on January 18, 2018, but MCC made no payment to Pompili
    because of its overbilling credit.
    In November 2017, Pompili issued MCC a credit in the amount of
    $56,102.31 for its overbilling.      Pompili did not submit any invoices to MCC for
    November 2017, December 2017, and January 2018. Birch testified that during these
    months, he resubmitted Pompili’s October invoice, as adjusted, to Platform on MCC’s
    14th, 15th, and 16th pay applications.     MCC included $12,500 for Pompili on pay
    application 14, which was submitted to Platform on November 25, 2017, and paid by
    Platform on January 18, 2018. MCC did not pay Pompili upon receipt of Platform’s
    payment because the $12,500 invoiced for Pompili on pay application 14 was offset
    by a $12,500 credit on pay application 13. MCC invoiced $5,000 for Pompili on pay
    application 15, which it submitted to Platform on December 25, 2017. MCC paid
    Pompili on January 31, 2018, before Platform paid the application on March 14, 2018.
    MCC included $30,122.60 for Pompili on pay application 16, which was submitted to
    Platform on January 25, 2018. Platform paid MCC on March 14, 2018; MCC had
    already paid Pompili on January 31, 2018.
    Pompili’s next invoice in the amount of $88,000 was submitted to
    MCC on February 28, 2018. MCC included the invoice on payment application 17 to
    Platform, who tendered payment to MCC on April 24, 2018. MCC sent a check to
    Pompili on April 30, 2018.
    On March 30, 2018, Pompili invoiced MCC $15,000. On April 23,
    2018, it invoiced MCC $8,867.81, and on May 24, 2018, it invoiced MCC $2,500 as
    its final billing on the project.
    Birch testified that the last invoice he submitted to Platform for
    Pompili was its March 30th invoice because Pompili had already invoiced $303,000
    and been paid $260,000 on its contract, so it was a good time to “hold off on payment
    and invoicing” to close out the contract — meaning to finalize what changes had been
    made to the contract requirements due to change orders or work authorizations that
    would affect the contract price. However, on April 30, 2018, the same day Birch sent
    Pompili a check for its February 28, 2018 invoice, Pompili filed a mechanic’s lien on
    the project. MCC stopped payment on the check and escrowed the money with
    Platform, who ultimately paid Pompili $80,000.
    Pompili filed suit against MCC, Platform, Case Western Reserve
    University, and Travelers Casualty and Surety Company of America.            Pompili
    subsequently amended its complaint, which omitted Case Western Reserve
    University but added Western Surety as a defendant. Pompili later dismissed all its
    claims against Platform and Travelers. MCC later substituted a bond with Western
    Surety for the mechanic’s lien.
    In its amended complaint, Pompili asserted a breach-of-contract
    claim against MCC, contending that MCC had breached the contract by failing to pay
    it $82,388.51 still owing pursuant to the terms of the contract. Pompili also asserted
    a claim against MCC for violation of Ohio’s Prompt Payment Act, alleging that MCC
    did not pay its invoices within ten days of receiving payment from Platform, as
    required by the Act. Pompili alleged that it was entitled to interest and attorney fees
    as a result of MCC’s violation of the Act.
    MCC filed an answer and two counterclaims: one alleging Pompili’s
    breach of contract for its failure to perform timely product deliveries, resulting in
    delays and additional work in the amount of $37,537.09 incurred by MCC; and
    tortious interference with MCC and Platform’s contract relating to Pompili’s failure
    to timely deliver the precast material to MCC, causing project delays, and its conduct
    during the project in entering into a direct contract with Platform to provide certain
    precast material for the project not specified in its contract with MCC.         MCC
    dismissed the tortious interference claim at trial.
    A bench trial commenced against MCC and Western Surety in August
    2019. In its subsequent opinion and order, the trial court rendered judgment in favor
    of Pompili on its breach-of-contract claim, finding that MCC breached the contract
    by failing to pay Pompili $82,388.51, which the court concluded was the amount due
    on the contract according to Pompili’s invoices less the $80,000 paid to Pompili by
    Platform and the $180,110.34 paid to Pompili by MCC. The court rendered judgment
    against MCC on its breach-of-contract claim.
    With respect to the alleged Prompt Pay Act violation, the court found
    that MCC did not pay any of Pompili’s invoices within the ten-day payment period
    required by the Act. The court awarded $21,230.86 to Pompili in interest for MCC’s
    late payments, and ordered that interest would accrue at $26.64 per day until paid in
    full, which the court calculated to represent $82,388.51 at 18 percent interest over
    365 days. After a hearing, the court also awarded Pompili $101,945.05 in attorney
    fees.
    This court dismissed MCC’s first appeal for lack of a final appealable
    order because the trial court’s judgment did not resolve Pompili’s claim against
    Western Surety. Broadway Concrete Invest., L.L.C. v. Masonry Contr. Corp., 8th
    Dist. Cuyahoga No. 109839, 
    2021-Ohio-1813
    . The trial court subsequently entered
    an order that Western Surety was obligated to satisfy MCC’s judgment up to the
    amount of the bond, and this appeal followed.
    II. Law and Analysis
    A. Ohio’s Prompt Payment Act
    In its first assignment of error, MCC contends that the trial court
    erred in finding that it violated Ohio’s Prompt Payment Act, which is set forth in R.C.
    4113.61.
    The interpretation of a statute involves a purely legal question. Thus,
    an appellate court conducts a de novo review of the trial court’s judgment interpreting
    a statute without according any deference to the trial court’s interpretation.
    Worldwide Asset Purchasing L.L.C. v. Easterly, 
    186 Ohio App.3d 478
    , 2009-Ohio-
    6196, 
    928 N.E.2d 1148
    , ¶ 48 (10th Dist.).
    We apply a manifest weight standard, however, to the trial court’s
    findings of fact. Sonis v. Rasner, 8th Dist. Cuyahoga No. 101929, 
    2015-Ohio-3028
    ,
    ¶ 52. In assessing whether a verdict in a civil bench trial is against the manifest
    weight of the evidence, we examine the entire record, weigh the evidence and all
    reasonable inferences, consider the witnesses’ credibility, and determine whether, in
    resolving conflicts in the evidence, the trier of fact clearly lost its way and created such
    a manifest miscarriage of justice that the verdict must be overturned and a new trial
    ordered. Sonis at ¶ 53, citing State v. Martin, 
    20 Ohio App.3d 172
    , 175, 
    485 N.E.2d 717
     (1st Dist.1983). In weighing the evidence, we are guided by a presumption that
    the findings of the trier of fact are correct. Sonis at ¶ 54, citing Seasons Coal v.
    Cleveland, 
    10 Ohio St.3d 77
    , 
    461 N.E.2d 1273
     (1984). Every reasonable presumption
    must be made in favor of the judgment and the findings of fact. 
    Id.,
     citing Seasons
    Coal at 80, fn. 3.
    Ohio’s Prompt Payment Act is set forth in R.C. 4113.61, captioned
    “Procedure when subcontractor or material supplier submits request for payment to
    contractor or intermediate subcontractor in time for inclusion in pay request to owner
    or contractor.” As relevant to this case, R.C. 4113.61(A)(2)(b) provides:
    (2) If a * * * lower tier material supplier submits an application or
    request for payment or an invoice for materials to a subcontractor * * *
    in sufficient time to allow the subcontractor * * * to include the
    application, request, or invoice in the subcontractor’s * * * own pay
    request submitted to a contractor * * * the subcontractor * * * within
    ten calendar days after receipt of payment from the subcontractor * * *
    shall pay to the:
    ***
    (b) Lower tier material supplier, an amount that is equal to all or that
    portion of the invoice for materials which represents the material
    furnished by the lower tier material supplier.
    The Prompt Payment Act “is a penal statute and must be strictly
    construed.” Intercargo Ins. Co. v. Mun. Pipe Contrs., Inc., 
    127 Ohio Misc.2d 48
    ,
    
    2003-Ohio-7363
    , 
    805 N.E.2d 606
    , ¶ 24 (C.P.) (The Act is penal in nature because it
    imposes an 18 percent fine, which is well over the market rate, for failing to perform
    a required act, and allows the trial court to impose a sanction of attorney fees.);
    Wright v. State, 
    69 Ohio App.3d 775
    , 779, 
    591 N.E.2d 1279
     (10th Dist.1990) (a penal
    statute is one that imposes a penalty).
    A penal statute “should be construed according to its exact and
    technical meaning, recognizing nothing that is not expressed, and limiting its
    application to cases clearly described within the words used.” Commercial Credit Co.
    v. Schreyer, 
    120 Ohio St. 568
    , 575, 
    166 N.E. 808
     (1929). Penal statutes “‘may not be
    extended by implication to cases not falling within their terms.’” Macedonia v. Burns,
    9th Dist. Summit No. 20404, 
    2001 Ohio App. LEXIS 2288
    , 8 (May 23 2001), quoting
    Cleveland v. Jorski, 
    142 Ohio St. 529
    , 
    53 N.E.2d 513
     (1944), paragraph one of the
    syllabus. When strictly construing a statute, “a court cannot introduce an exception
    to the statute which the legislature has not authorized.” Pearl v. Koch, 
    5 Ohio Dec. 5
    ,
    8, 
    1894 Ohio Misc. LEXIS 192
     (1894). The “statute must be read without expansion
    beyond its letter [and] is to be confined to such subjects or applications as are
    obviously within its terms and purpose.” Mathers v. Bull, 
    9 Ohio Dec. 408
    , 410, 
    1898 Ohio Misc. LEXIS 187
     (Nov.1898). When construing a statute, courts must give the
    words therein “their usual, normal, and/or customary meanings.” Washington Cty.
    Home v. Ohio Dept. of Health, 
    178 Ohio App.3d 78
    , 
    2008-Ohio-4342
    , 
    896 N.E.2d 1011
    , ¶ 28 (4th Dist.).
    The language of the Prompt Payment Act is clear and unambiguous.
    If a lower tier material supplier submits an invoice to a subcontractor in time for that
    subcontractor to include the invoice in its pay application to the contractor, the
    subcontractor must pay the lower tier material supplier within ten days after the
    subcontractor receives payment from the contractor. Thus, as applicable to this case,
    if Pompili submitted an invoice to MCC in time for MCC to include the invoice in its
    pay application to Platform, MCC was required to pay Pompili within ten days after
    receiving payment from Platform. MCC would be in violation of the Act if it did not
    do so.
    The trial court concluded that MCC violated the Act because it
    submitted a pay application for $50,000 to Platform before Pompili had completed
    any work and was paid for this invoice on October 13, 2016. The court found that
    Pompili submitted its first invoice for shop drawings in the amount of $3,500 on
    January 31, 2017, and even though MCC had previously been paid by Platform for
    that work, MCC did not pay Pompili for this invoice until May 3, 2017. The court
    further concluded that MCC submitted its second and third pay applications to
    Platform prior to receiving invoices from Pompili and was paid on those pay
    applications. Accordingly, the court concluded that each of Pompili’s invoices had
    been “prepaid” by Platform to MCC before Pompili submitted the invoice to MCC,
    and therefore, MCC was late with each payment it made to Pompili and, thus, in
    violation of the Prompt Payment Act.
    However, the trial court’s interpretation of the law and its application
    of the law to the facts of this case was incorrect. The Prompt Payment Act provides
    that a subcontractor will be liable for a prompt payment violation if: (1) a material
    supplier submits an invoice to the subcontractor in time for the subcontractor to
    include the invoice on its pay application; (2) the subcontractor receives payment on
    the application; and (3) the subcontractor fails to pay the material supplier’s invoice
    within ten days of receiving payment on the application. It is clear from the statute
    that the ten-day prompt payment clock begins to run on the date the upstream
    contractor tenders payment to a lower tier subcontractor on the subcontractor’s pay
    application containing an invoice from a material supplier.
    Here, however, the trial court read into the Act a requirement that
    MCC was required to pay Pompili from funds it received on pay applications that did
    not include any Pompili invoices. The trial court concluded that even though MCC
    received funds from Platform on a pay application it submitted before MCC and
    Pompili executed their contract, and months before Pompili submitted its first
    invoice, because MCC had received what the court concluded were “project funds,” it
    was obligated to pay Pompili throughout the project within ten days of its receipt of
    Pompili’s invoices. That is not the law. The ten-day clock clearly and unambiguously
    begins to run upon payment by the contractor of the subcontractor’s pay application
    that contained the material supplier’s invoice; it does not start running when the
    lower tier material supplier submits its invoice.
    The trial court included a chart with its findings of fact and
    conclusions of law that set forth the dates of Pompili’s invoices, the amount of each
    invoice, and the due date for payment by MCC. But the trial court’s due dates for the
    invoices are inconsistent. The court found that MCC was required to pay Pompili’s
    first four invoices within ten days of MCC’s receipt of the invoice. But then, without
    explanation, the court found that Pompili’s fifth invoice, which was dated August 15,
    2017, had a due date of October 8, 2017. The court concluded that Pompili’s sixth
    invoice, dated September 18, 2017, had a due date of October 28, 2017; its seventh
    invoice, dated October 14, 2017, had a payment due date of January 20, 2018; and its
    eighth invoice, dated February 23, 2018, was due March 5, 2018. The court gave no
    explanation or reason for why some invoices were due in 10 days from receipt of the
    invoice but others were not due for nearly 30 days. Further, and most importantly,
    the chart did not include any reference to when MCC submitted a pay application to
    Platform, which Pompili invoices were included in those pay applications, when MCC
    was paid on the pay applications, and the amount of the payment. Thus, the trial
    court’s ruling the MCC had violated the Act was not premised on the conditions
    required by the Act to find a violation.
    Pompili claims there was no error in the trial court’s judgment,
    however, because there is no requirement in the Act that the material supplier’s
    invoice be included on the subcontractor’s next invoice in order to be paid; rather, the
    only requirement is that the material supplier submit its invoice in time for the
    invoice to be included in the subcontractor’s pay application to the contractor. It
    contends that MCC was prepaid for all of Pompili’s work, beginning with the $50,000
    payment to MCC from Platform after MCC’s first pay application, and was afforded
    sufficient time to include all of Pompili’s invoices in its pay applications. This
    argument fails. There is no language in the Act that requires a subcontractor to pay a
    lower tier material supplier from sums received on pay applications submitted before
    the material supplier submits an invoice or before the subcontractor and material
    supplier even entered into a contract. Because no invoices from Pompili were
    included in MCC’s first, second, or third pay applications, MCC had no prompt
    payment obligations to Pompili under the Act regarding those applications.
    Pompili contends that we should nonetheless affirm the trial court
    because adopting an interpretation of the Act that allows a subcontractor to submit
    pay applications before the lower tier subcontractor or material supplier submits an
    invoice would allow the subcontractor to avoid its obligations under the Prompt
    Payment Act by being prepaid for the lower tier subcontractor or material supplier’s
    work. The Prompt Payment Act does not address this situation and under rules of
    strict construction, we cannot read anything into the Act that is not there. The Act
    clearly conditions prompt payment on the receipt of payment on the pay application
    that contained the material supplier’s invoice. For the trial court to read anything
    else into the Act was an error of law.
    Moreover, it does not appear that MCC was trying to avoid its
    payment obligations to Pompili. The evidence at trial demonstrated that MCC
    consistently submitted Pompili’s invoices on its pay applications to Platform and,
    after receiving payment from Platform, paid Pompili.
    To summarize, because none of Pompili’s invoices were included with
    MCC’s first three payment applications to Platform, MCC had no prompt payment
    obligation to pay Pompili’s first invoice, dated January 31, 2017, or succeeding
    invoices, out of funds Platform paid MCC for these pay applications. The trial court’s
    finding that MCC was late with every payment to Pompili because it was prepaid for
    Pompili’s work is contrary to the Act, which clearly provides that the ten-day prompt
    payment obligation begins to run only after the subcontractor receives payment on a
    pay application that included the material supplier’s invoice. Accordingly, the trial
    court’s judgment finding that MCC violated the Prompt Payment Act is reversed.
    Likewise, the trial court’s judgment that MCC owes Pompili interest
    for its violation of the Act is reversed. The trial court erroneously determined that
    interest was due on the paid invoices because it concluded, under its flawed
    interpretation of the Prompt Payment Act, that MCC had been prepaid for Pompili’s
    work and was therefore required to pay Pompili within ten days of receiving its
    invoices. Similarly, the trial court erroneously concluded that MCC owed interest on
    the disputed unpaid invoices, even though under R.C. 4113.61(A)(2)(b), “the
    subcontractor * * * may withhold amounts that may be necessary to resolve disputed
    liens or claims involving the work or labor performed or material furnished by the
    lower tier subcontractor or lower tier material supplier.” Our review of the record
    demonstrates there were ongoing disputes relating to the amount and quality of
    materials that Pompili delivered to the project.        Furthermore, MCC obviously
    disputed Pompili’s mechanic’s lien, which Pompili filed on April 30, 2018.
    Finally, the trial court’s judgment ordering MCC to pay Pompili’s
    attorney fees as a result of its alleged violation of the Prompt Payment Act is reversed.
    R.C. 4113.61(B)(2) provides that in making a determination to award attorney fees for
    a violation of the Prompt Payment Act, the trial court should consider all relevant
    factors, including (1) the presence or absence of good faith allegations or defenses
    asserted by the parties; (2) the proportion of the amount of recovery as it relates to
    the amount demanded; and (3) the nature of the services rendered and the time
    expended in rendering the services.
    The trial court obviously erred in awarding attorney fees for invoices
    that MCC timely paid under a strict construction of R.C. 4113.61. Regarding disputed
    invoices, the trial court found that MCC did not have a good-faith defense for
    withholding payment to Pompili on any of Pompili’s invoices because it was prepaid
    for Pompili’s work under its first payment application. However, as discussed above,
    MCC’s first payment application to Platform is wholly irrelevant to an analysis of
    whether MCC violated the Prompt Payment Act because no Pompili invoice was
    included with the payment application. Accordingly, MCC’s good faith in withholding
    monies from Pompili on any disputed invoices is in no way related to its receipt of
    payment on its first pay application. Furthermore, as noted above, the record reflects
    a good-faith dispute regarding Pompili’s mechanic’s lien. Accordingly, the trial
    court’s determination that MCC had no good-faith defense to paying the disputed
    invoices is in error.
    The first assignment of error is sustained. The trial court’s judgment
    finding MCC in violation of the Prompt Payment Act and liable for interest and
    attorney fees is reversed.
    III. Breach of Contract
    The trial court found that Pompili “fully performed its scope of work
    under the contract” with MCC and that MCC breached the contract by failing to pay
    Pompili $82,388.51, which the trial court concluded was the amount due on Pompili’s
    invoices after subtracting the $80,000 paid to Pompili by Platform and the
    $180,110.34 paid by MCC.2 In its second assignment of error, MCC contends that the
    trial court erred in finding that it had breached the contract.3
    2 This amount is inconsistent with a statement by Pompili’s counsel contained in a
    May 11, 2018 memorandum to Case Western Reserve University advising the university of
    Pompili’s mechanic’s lien. Counsel stated therein: “As a result of MCC’s failure to pay
    Pompili amounts due pursuant to the contract, Pompili filed the attached Affidavit for
    Mechanic’s Lien. At the time of the filing of the Lien, Pompili was owed $157,272.51 for
    materials supplied to the project, and Pompili filed a lien in the amount of $113,217.81.
    Since the filing of the Lien, Platform paid Pompili $80,000, thereby reducing the amount
    owed to Pompili on the project to $77,272.51.”
    3 MCC contends that because the contract terms were ambiguous, the trial court
    had an obligation to construe the contract terms before finding it had breached the
    contract, and because it did not do so, its judgment should be reversed. Pompili contends
    that MCC waived this argument because it did not raise it in the trial court. We need not
    consider MCC’s argument nor determine whether it was waived because under our de novo
    review of Pompili’s breach-of-contract claim, we conclude that the trial court incorrectly
    determined the contract terms and then utilized those incorrect terms to find that Pompili
    performed its duties under the contract.
    Contract interpretation is a question of law that is reviewed de novo
    on appeal. Delta Fuels, Inc. v. Ohio DOT, 10th Dist. Franklin Nos. 15AP-28 and 15AP-
    206, 
    2015-Ohio-5545
    , ¶ 39. “To prove a breach of contract, a plaintiff must prove the
    existence and terms of a contract, the plaintiff’s performance of the contract, the
    defendant’s breach of the contract, and damages or loss to the plaintiff.” (Emphasis
    added.) 
    Id.
    Upon our de novo review, we find that although the trial court
    correctly determined there was a contract between the parties, it incorrectly
    determined the terms of that contract. The purchase order from MCC to Pompili was
    signed by Birch, on behalf of MCC, on October 25, 2016, and by Mark Melvin, on
    behalf of Pompili, on October 26, 2016. A handwritten notation on the purchase
    order noted that Pompili’s original proposal to Platform was attached to the purchase
    order “as information only,” and each page of the proposal was marked
    “INFORMATION ONLY.” Neither Pompili’s proposal nor the proposed joint check
    agreement (which Jeremy Kler testified was never signed by Platform), were
    incorporated into the purchase order. Thus, the terms of the contract between MCC
    and Pompili are contained only in the purchase order.
    It appears, however, that the trial court found that various terms of
    Pompili’s attached quotation were part of the contract between MCC and Pompili,
    and relied upon those terms to conclude that Pompili “performed its duties under the
    contract.” For example, in its opinion and order, the trial court stated that “Plaintiff’s
    contract terms specifically exempted all field work including field measuring.” But
    that term is not contained in the purchase order between MCC and Pompili; it is
    contained in Pompili’s quotation attached to the purchase order, which stated: “All
    field measuring and verification of dimensions on submitted erection drawings shall
    be the responsibility of the contractor.”
    Likewise, the trial court concluded that Pompili “was merely required
    to produce pieces pursuant to approved shop drawings,” and that “[Pompili] required
    that production would only occur upon final approval of shop drawing[s] by the
    Project architect.” But that is not a term contained in the purchase order between
    MCC and Pompili; it is found in Item 5 of the General Contract Terms of Pompili’s
    quotation to Platform, which states, “No production shall take place until approved
    shop drawings are received.”      As explained above, Pompili’s quotation was for
    information only; its terms were never incorporated into the contract between MCC
    and Pompili. However, in reliance on this alleged contract term, the court concluded
    that any “delays in the project were not caused by [Pompili].”
    Accordingly, we find that the trial court erred by incorporating terms
    from Pompili’s quotation into the contract between MCC and Pompili and then
    applying the evidence presented at trial to those terms. In short, the trial court failed
    to apply the evidence to the proper contract. The second assignment of error is
    sustained, and the trial court’s judgment is therefore reversed.
    IV. Mechanic’s Lien Bond
    On October 17, 2018, the trial court in Cuyahoga C.P. No. CV-18-
    900764 issued an order approving the stipulation of Pompili and MCC to Western
    Surety’s bond and rider in the amount of $123,583, and rescinding the mechanic’s
    lien that Pompili had filed on the property. In its third assignment of error, Western
    Surety argues that the trial court erred in finding that it is liable for a portion of the
    judgment against MCC.
    Under R.C. 1311.11(C), a mechanic’s lien may be replaced by a surety
    bond. The bond serves as a substitute for the lien and is based upon the prior
    existence of the lien. A&J Plumbing, Inc. v. Huntington Natl. Bank, 11th Dist. Lake
    No. 2014-L-023, 
    2014-Ohio-5707
    , ¶ 18. Therefore, a valid claim cannot be brought
    against a bond unless there is a valid existing mechanic’s lien. Id. at ¶ 24.
    One of the statutory requirements to establish a valid mechanic’s lien
    is serving a notice of furnishing on the project owner if the owner has recorded a
    notice of commencement. See R.C. 1311.05 and 1311.05. Western Surety argues that
    Pompili failed to establish at trial that it timely served a notice of furnishing and,
    therefore, failed to establish that its lien was valid. Western Surety has waived this
    argument for purposes of appeal, however.
    First, failure to timely serve a notice of furnishing is an affirmative
    defense to a mechanic’s lien. But neither Western Surety nor MCC raised the
    affirmative defense of failure to timely serve a notice of furnishing in their answers to
    Pompili’s first amended complaint. Failure to raise an affirmative defense is a waiver
    of the defense. Bell v. Teasley, 10th Dist. Franklin No. 10AP-850, 
    2011-Ohio-2744
    , ¶
    13 (affirmative defenses not raised in the pleadings or an amendment to the pleadings
    are waived).
    Moreover, it is well settled that a party cannot raise new arguments
    and legal issues for the first time on appeal, and the failure to raise an issue in the trial
    court waives that issue for appellate purpose. Miller v. Cardinal Care Mgmt., 8th
    Dist. Cuyahoga No. 107730, 
    2019-Ohio-2826
    , ¶ 23. Neither MCC nor Western Surety
    presented any evidence or argument at trial that Pompili failed to timely serve the
    notice of furnishing, nor did they challenge the validity of Pompili’s lien in any
    manner. Although Western Surety cites the testimony of David Schaefer as support
    for its argument that Pompili failed to serve a notice of furnishing, Schaefer did not
    testify at trial; he testified in a post-judgment hearing regarding the award of attorney
    fees. Schaefer’s involvement in the case was limited to his expert opinion on the
    reasonableness of the hourly rate and fees of Pompili’s counsel for determining
    attorney fees and thus, is insufficient to establish that MCC or Western Surety
    challenged the validity of Pompili’s lien at trial.
    Under R.C. 1311.06, to file a valid mechanic’s lien, a person shall
    “make and file for record in the office of the county recorder in the counties in which
    the improved property is located, an affidavit.” Once it is recorded, a copy of the
    affidavit must be served on the owner of the property. R.C. 1311.07. Pompili
    presented evidence at trial through the testimony of Mark Melvin, co-owner of
    Pompili, that it had taken the necessary steps to properly file its mechanic’s lien.
    Neither MCC nor Western Surety challenged the validity of Pompili’s lien at trial and
    thus, they cannot do so now on appeal. The third assignment of error is overruled.
    Affirmed in part; reversed and remanded in part.
    It is ordered that the parties share costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate be sent to said court to carry this judgment
    into execution.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27
    of the Rules of Appellate Procedure.
    KATHLEEN ANN KEOUGH, PRESDING JUDGE
    MICHELLE J. SHEEHAN, J., and
    EMANUELLA D. GROVES, J., CONCUR