Granger Construction Company, Inc. v. TJ, LLC , 21 N.Y.S.3d 491 ( 2015 )


Menu:
  •                            State of New York
    Supreme Court, Appellate Division
    Third Judicial Department
    Decided and Entered: December 17, 2015                    520624
    ________________________________
    GRANGER CONSTRUCTION COMPANY,
    INC.,
    Plaintiff,
    v
    TJ, LLC,
    Defendant
    and Third-
    Party                   MEMORANDUM AND ORDER
    Plaintiff-
    Appellant,
    et al.,
    Defendant;
    LIBERTY MUTUAL GROUP INC.,
    Doing Business as LIBERTY
    MUTUAL INSURANCE COMPANY,
    Third-Party
    Defendant-
    Respondent.
    ________________________________
    Calendar Date:    October 22, 2015
    Before:    Peters, P.J., Garry, Rose and Clark, JJ.
    __________
    Hinman, Howard & Kattell, LLP, East Greenbush (Michael
    Keenan of counsel), for defendant and third-party plaintiff-
    appellant.
    Alario & Fischer, PC, East Syracuse (Linda E. Alario of
    counsel), for third-party defendant-respondent.
    __________
    -2-                520624
    Clark, J.
    Appeal from an order of the Supreme Court (Lebous, J.),
    entered November 26, 2014 in Broome County, which, among other
    things, granted third-party defendant's motion for summary
    judgment dismissing the third-party complaint.
    In 2011, defendant TJ, LLC entered into a contract with
    plaintiff for the construction of a hotel in the Town of Vestal,
    Broome County. The contract was insured by a performance bond
    with third-party defendant, Liberty Mutual Group Inc., acting as
    surety. Although construction continued through early 2013, the
    hotel opened in April 2012. When the fire alarm system began to
    malfunction in January 2013, TJ was forced to temporarily close
    the hotel. TJ informed plaintiff of the need for repairs, but
    plaintiff refused to perform the repairs, citing TJ's alleged
    failure to keep its payments current. Upon undertaking the
    repairs itself, TJ discovered other problems with the
    construction of the hotel and, by April 2013, TJ had hired
    contractors other than plaintiff to complete all needed repairs.
    In June 2013, TJ sent Liberty Mutual a letter stating that it
    intended to file for contractor default under the terms of the
    performance bond and that it had fully complied with paragraph 3
    of the bond. Liberty Mutual then scheduled a conference between
    plaintiff and TJ in an attempt to resolve their issues pursuant
    to the terms of the bond. A resolution having not been achieved,
    TJ sent a formal notice of contractor default to Liberty Mutual
    in July 2013.1
    Plaintiff thereafter commenced this action against TJ and
    defendant Thomas Bedosky, TJ's owner, alleging breach of
    contract, among other things. TJ then commenced a third-party
    action against Liberty Mutual to compel it to perform under the
    bond. After answering, Liberty Mutual moved for summary judgment
    dismissing the third-party complaint. Supreme Court granted
    1
    Both Liberty Mutual and plaintiff, as well as counsel for
    plaintiff, claim that they did not receive this notice.
    -3-                520624
    Liberty Mutual's motion for summary judgment and TJ appeals.2
    We affirm. In determining whether a party is relieved of
    its duty to perform under a surety bond, courts interpret the
    bond, like any other contract, according to its terms (see Walter
    Concrete Constr. Corp. v Lederle Labs. 99 NY2d 603, 605 [2003];
    General Phoenix Corp. v Cabot, 300 NY 87, 92 [1949]). As
    relevant herein, "a contractual duty ordinarily will not be
    construed as a condition precedent absent clear language showing
    that the parties intended to make it a condition" (Mullany v
    Munchkin Enters., Ltd., 69 AD3d 1271, 1274 [2010] [internal
    quotation marks, brackets and citations omitted]; see Unigard
    Sec. Ins. Co. v North Riv. Ins. Co. 79 NY2d 576, 581 [1992]).
    "Notably, it is for the court to decide, as a matter of law,
    whether an express condition precedent to performance exists
    under the terms of a contract" (Rooney v Slomowitz, 11 AD3d 864,
    865 [2004] [citations omitted]).
    Liberty Mutual contends that TJ failed to meet one or more
    express conditions precedent under the bond, thus rendering the
    bond null and void. Pursuant to paragraph 3 of the bond, Liberty
    Mutual's obligation arose after three conditions were met, namely
    (1) TJ notified plaintiff and Liberty Mutual that it was
    considering declaring a contractor default and was requesting a
    conference with the parties, (2) TJ formally declared a
    contractor default and terminated plaintiff's right to complete
    the contract, which could not occur earlier than 20 days after
    the parties received notice under section 3.1, and (3) TJ agreed
    to pay the balance of the contract price to Liberty Mutual or to
    a contractor selected to perform the rest of the construction
    contract. As relevant here, sections 4.2 and 4.4 of the bond,
    respectively, state that when TJ has satisfied the conditions of
    paragraph 3, Liberty Mutual shall promptly, and at its own
    2
    TJ also cross-moved to strike Liberty Mutual's second
    affirmative defense. Such motion was denied by Supreme Court.
    To the extent that TJ does not take issue with this portion of
    Supreme Court's order, any argument with respect thereto has been
    abandoned (see Salzer v Benderson Dev. Co., LLC, 130 AD3d 1226,
    1229 n 1 [2015]).
    -4-                520624
    expense, undertake performance of the construction contract
    through independent contractors or, alternatively, waive this
    right and either tender payment to TJ or deny liability.
    Paragraph 5 states that, should Liberty Mutual have failed to
    proceed under paragraph 4 within a reasonable time, it would be
    deemed to be in default on the bond 15 days after receiving
    additional written notice from TJ demanding performance.
    However, if Liberty Mutual tendered payment and then TJ refused
    the payment, or if Liberty Mutual denied liability, then TJ was
    entitled to enforce any remedy available to it against Liberty
    Mutual without providing further notice.
    Inasmuch as paragraph 3 clearly states that Liberty
    Mutual's obligation under the bond "shall arise" only after TJ
    had performed the three conditions detailed in sections 3.1 to
    3.3, this language unambiguously created conditions precedent to
    be performed in the order that they are listed (see Archstone v
    Tocci Bldg. Corp. of N.J., Inc., 119 AD3d 497, 498 [2014], lv
    dismissed 24 NY3d 1037 [2014]; see also 120 Greenwich Dev.
    Assocs., LLC v Reliance Ins. Co., 
    2004 WL 1277998
    , *11-12, 2004
    US Dist LEXIS 10514, *34-37 [SD NY, June 8, 2004, No. 01 Civ 8219
    (PKL)]). Therefore, TJ must have strictly complied with each
    condition precedent before Liberty Mutual could be held liable
    under the bond.
    Viewing the facts in the light most favorable to TJ, as the
    nonmovant (see U.W. Marx, Inc. v Koko Contr., Inc., 97 AD3d 893,
    894 [2012]), Liberty Mutual met its burden of demonstrating the
    absence of a material question of fact (see JMD Holding Corp. v
    Congress Fin. Corp., 4 NY3d 373, 384 [2005]).3 The record before
    us demonstrates that TJ failed to comply with at least one of the
    express conditions precedent in paragraph 3 of the bond.
    Specifically, plaintiff affirms that it never received the notice
    from TJ, allegedly sent in June 2013, saying that TJ was
    considering declaring a contractor default, as required by
    section 3.1. This, by itself, would preclude Liberty Mutual's
    liability under the express terms of the performance bond (see
    3
    We note that Supreme Court issued a bench decision
    immediately following oral argument on Liberty Mutual's motion.
    -5-                 520624
    153 Hudson Dev., LLC v DiNunno, 8 AD3d 77, 78 [2004]). Further,
    the evidence establishes that TJ paid outside contractors under
    section 3.3 prior to sending notice to plaintiff and Liberty
    Mutual pursuant to section 3.1 or 3.2, which also would serve to
    preclude Liberty Mutual's liability. Finally, TJ also admits
    that it failed to provide additional notice demanding performance
    before bringing suit as set forth in paragraph 5, which also
    operates to release Liberty Mutual of its obligations under the
    bond to the extent that the conditions precedent set forth in
    paragraph 3 had not been complied with. Thus, inasmuch as the
    record demonstrates that TJ failed to comply with the conditions
    precedent of paragraph 3, Liberty Mutual adequately shifted the
    burden to TJ to demonstrate a material question of fact (see
    Alvarez v Prospect Hosp., 68 NY2d 320, 324 [1986]).
    In this regard, we are unpersuaded by TJ's contentions that
    the loss of profits and economic hardship of temporarily closing
    the hotel in order to comply with the terms set forth in
    paragraph 3 of the bond rise to the level to warrant excusing
    performance of the bond's conditions under the rarely imposed
    theory of impossibility of performance (see Kel Kim Corp. v
    Central Mkts., 70 NY2d 900, 902 [1987]; 407 E. 61st Garage v
    Savoy Fifth Ave. Corp., 23 NY2d 275, 281 [1968]; Lagarenne v
    Ingber, 273 AD2d 735, 737 [2000]). Nor are we persuaded that the
    plain language of the bond should be construed so as to reflect
    the "commercial reality" facing TJ. Accordingly, TJ failed to
    meet its shifted burden and summary judgment was properly granted
    to Liberty Mutual (see Roel Partnership v Amwest Sur. Ins. Co.,
    258 AD2d 780, 781-782 [1999]).
    TJ's remaining contentions are found to be lacking in
    merit.
    Peters, P.J., Garry and Rose, JJ., concur.
    -6-                  520624
    ORDERED that the order is affirmed, with costs.
    ENTER:
    Robert D. Mayberger
    Clerk of the Court
    

Document Info

Docket Number: 520624

Citation Numbers: 134 A.D.3d 1329, 21 N.Y.S.3d 491

Filed Date: 12/17/2015

Precedential Status: Precedential

Modified Date: 1/12/2023