Frohberg Elec. Co. v. Grossenburg Implement , 297 Neb. 356 ( 2017 )


Menu:
  • Nebraska Supreme Court Online Library
    www.nebraska.gov/apps-courts-epub/
    09/29/2017 12:11 AM CDT
    - 356 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    Frohberg Electric Company, Inc., a Nebraska corporation,
    appellee, v. Grossenburg I mplement, I nc., a Nebraska
    corporation, and K iehm Construction, I nc.,
    a M innesota corporation, appellants.
    ___ N.W.2d ___
    Filed July 28, 2017.    No. S-16-987.
    1.	 Contracts. The meaning of a contract and whether a contract is ambigu-
    ous are questions of law.
    2.	 Arbitration and Award. Arbitrability presents a question of law.
    3.	 Judgments: Appeal and Error. When reviewing questions of law,
    an appellate court resolves the questions independently of the lower
    court’s conclusions.
    4.	 Arbitration and Award: Contracts: Appeal and Error. Where an
    issue concerns the formation or existence of an arbitration agreement
    and not its validity, enforceability, or scope, an appellate court applies
    state law.
    5.	 Arbitration and Award: Federal Acts: Contracts. The Federal
    Arbitration Act’s application is triggered only if a contract involving
    interstate commerce actually contains an arbitration clause.
    6.	 Arbitration and Award: Federal Acts: Contracts: States. In a con-
    tract involving interstate commerce, the equal-treatment principle of the
    Federal Arbitration Act applies in determining whether a valid arbitra-
    tion agreement exists: States may not apply a state rule discriminating
    against arbitration and are required to place arbitration agreements on
    equal footing with all other contracts.
    7.	 Contracts. In interpreting a contract, a court must first determine, as a
    matter of law, whether the contract is ambiguous.
    8.	 ____. A contract written in clear and unambiguous language is not sub-
    ject to interpretation or construction and must be enforced according to
    its terms.
    9.	 Contracts: Words and Phrases. A contract is ambiguous when a word,
    phrase, or provision in the contract has, or is susceptible of, at least two
    reasonable but conflicting interpretations or meanings.
    - 357 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    10.	 Arbitration and Award: Federal Acts: Contracts. If a contract con-
    taining an arbitration clause involves interstate commerce, the Federal
    Arbitration Act governs the contract.
    11.	 Contracts: States: Words and Phrases. Contracts involving interstate
    commerce include contracts for services between parties of differ-
    ent states.
    12.	 Appeal and Error. An appellate court is not obligated to engage in an
    analysis that is not necessary to adjudicate the case and controversy
    before it.
    Appeal from the District Court for Wayne County: James G.
    Kube, Judge. Reversed and remanded with directions.
    Timothy Engler, of Rembolt Ludtke, L.L.P., for appellants.
    David E. Copple and Michelle M. Schlecht, of Copple,
    Rockey, McKeever & Schlecht, P.C., L.L.O., for appellee.
    Heavican, C.J., Wright, Miller-Lerman, Cassel, Stacy,
    K elch, and Funke, JJ.
    Cassel, J.
    INTRODUCTION
    This is an appeal from an order denying a motion to compel
    arbitration of a construction dispute. A subcontractor sued the
    project’s owner and general contractor, which in turn sought to
    compel arbitration. The appeal turns on whether the subcon-
    tract effectively incorporated a mandatory arbitration clause
    from the general contract, thereby mandating the subcontractor
    to arbitrate. Because we conclude that it did, we reverse, and
    remand with directions.
    BACKGROUND
    Parties and Governing
    Contracts
    Grossenburg Implement, Inc. (Owner), a Nebraska cor-
    poration, executed a standard form contract (the general
    - 358 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    contract) with Kiehm Construction, Inc. (Contractor), a
    Minnesota corporation, for the construction of several struc-
    tures on Owner’s property in Wayne County, Nebraska. The
    general contract included a mandatory arbitration clause for
    “any Claim . . . not resolved by mediation pursuant to [the
    general conditions].”
    Contractor then subcontracted with Frohberg Electric
    Company, Inc. (Subcontractor), a Nebraska corporation, to
    provide electrical services and materials in constructing the
    structures. The subcontract referenced the existence of the
    general contract and stated, “Contractor has made available
    to . . . Subcontractor all of the above documents, and . . . the
    above have been carefully examined by . . . Subcontractor.”
    The general contract was also referenced in several sec-
    tions of the subcontract, including one (Section 11) in which
    Subcontractor agreed “[t]o be bound to . . . Contractor by
    the terms of the General Contract” and “to conform to and to
    comply with the provisions of the General Contract.” Another
    section (Section E), under the heading “The Contractor Agrees
    as Follows,” provided: “If arbitration of disputes is provided
    for in the General Contract, any dispute arising between
    . . . Contractor and . . . Subcontractor under this Subcontract,
    including the breach thereof, shall be settled by arbitration in
    the manner provided for in the General Contract.”
    Lower Court Proceedings
    After Subcontractor provided services pursuant to the sub-
    contract, a dispute arose concerning the payment owed to
    Subcontractor. Subcontractor then obtained a construction lien
    against Owner’s property and later filed a complaint against
    Owner and Contractor to obtain a judgment and foreclose on
    the construction lien.
    Owner and Contractor jointly moved to dismiss the com-
    plaint or, in the alternative, to compel arbitration pursuant to
    the terms of the subcontract and the general contract. They
    - 359 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    alleged that the subcontract included specific provisions in
    Section 11 and Section E which incorporated the alternative
    dispute resolution clauses from the general contract and gen-
    eral conditions signed by Owner and Contractor. Thus, they
    argued that the matter should be settled by arbitration as pro-
    vided in those documents.
    The district court overruled the motion and specifically held
    that the terms of the subcontract did not bind Subcontractor to
    the dispute resolution provisions of the general contract or gen-
    eral conditions. The court noted that the only provision specifi-
    cally purporting to bind the parties to alternative dispute reso-
    lution was under the subcontract section titled “The Contractor
    Agrees as Follows” and not contained within the other sections,
    “The Subcontractor Agrees as Follows” or “The Contractors
    and Subcontractors Agree as Follows.” Accordingly, the court
    found that Subcontractor did not agree to that provision by the
    express terms of the subcontract.
    The court also found that the provision of Section 11 in
    which Subcontractor agreed “[t]o be bound to . . . Contractor
    by the terms of the General Contract” was vague as to whether
    it applied to disputes between Subcontractor and Owner or
    between Subcontractor and Contractor. Since the general con-
    tract spoke only to disputes between Owner and Contractor,
    the court found that the general contract language was incon-
    sistent with the subcontract and that the language of the
    subcontract should govern. Because it had already deter-
    mined that the express terms of the subcontract did not bind
    Subcontractor to the dispute resolution process within the
    general contract, the court concluded that there was no arbitra-
    tion agreement.
    Owner and Contractor appealed, and we moved the case to
    our docket.1
    1
    See Neb. Rev. Stat. § 24-1106(3) (Reissue 2016).
    - 360 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    ASSIGNMENTS OF ERROR
    Owner and Contractor assign, reordered, restated, and com-
    bined, that the district court erred in (1) construing the subcon-
    tract and the general contract incorporated by reference and (2)
    denying their motion to compel arbitration and stay the action
    pending arbitration.
    STANDARD OF REVIEW
    [1-3] The meaning of a contract and whether a contract is
    ambiguous are questions of law.2 Likewise, arbitrability pre­
    sents a question of law.3 When reviewing questions of law,
    an appellate court resolves the questions independently of the
    lower court’s conclusions.4
    ANALYSIS
    Owner and Contractor advance two main arguments on
    appeal. They argue that the subcontract incorporated the dis-
    pute resolution process outlined in the general contract and
    general conditions with clear and unambiguous language set
    forth in both Section E and Section 11 of the subcontract. They
    also argue that the Federal Arbitration Act (FAA)5 applied to
    the subcontract and general contract and that under the express
    provisions of the FAA, their motion to compel arbitration
    should have been sustained.
    [4-6] We first address whether the subcontract unambigu-
    ously incorporated the terms of the general contract such
    that the claims in the instant case were subject to a binding
    arbitration clause. Because this issue concerns the formation
    2
    Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist., 
    291 Neb. 642
    , 
    868 N.W.2d 67
    (2015).
    3
    Wilczewski v. Charter West Nat. Bank, 
    295 Neb. 254
    , 
    889 N.W.2d 63
          (2016).
    4
    Id.
    5
    9 U.S.C. § 1 et seq. (2012).
    - 361 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    or existence of an arbitration agreement and not its valid-
    ity, enforceability, or scope, we apply state law.6 The FAA’s
    application is triggered only if a contract involving inter-
    state commerce actually contains an arbitration clause.7 But,
    the FAA’s equal-treatment principle applies in determining
    whether a valid arbitration agreement exists: States may not
    apply a state rule discriminating against arbitration and are
    required to place arbitration agreements on equal footing with
    all other contracts.8
    6
    See David Fiala, Ltd. v. Harrison, 
    290 Neb. 418
    , 
    860 N.W.2d 391
    (2015).
    See, also, Southland Corp. v. Keating, 
    465 U.S. 1
    , 19-20, 
    104 S. Ct. 852
    ,
    
    79 L. Ed. 2d 1
    (1984) (noting “lower courts generally look to state law
    regarding questions of formation of the arbitration agreement under [9
    U.S.C.] § 2 [(1976)], . . . which is entirely appropriate so long as the
    state rule does not conflict with the policy of § 2”) (citations omitted);
    Washington Mut. Finance Group, LLC v. Bailey, 
    364 F.3d 260
    , 264 (5th
    Cir. 2004) (holding “in determining whether the parties agreed to arbitrate
    a certain matter, courts apply the contract law of the particular state that
    governs the agreement”); ISC Holding AG v. Nobel Biocare Investments
    N.V., 351 Fed. Appx. 480 (2d Cir. 2009) (applying state contract law
    where contract was ambiguous as to whether agreement to arbitrate
    existed).
    7
    See 
    id. See, also,
    CardioNet, Inc. v. CIGNA Health Corp., 
    751 F.3d 165
    ,
    173 (3d Cir. 2014) (“while the FAA ‘embodies a strong federal policy
    in favor of arbitration, . . . the duty to arbitrate remains one assumed by
    contract.’ . . . Thus, the presumption of arbitrability applies only where
    an arbitration agreement is ambiguous about whether it covers the dispute
    at hand. . . . Otherwise, the plain language of the contract controls”)
    (citations omitted); Dasher v. RBC Bank (USA), 
    745 F.3d 1111
    , 1116 (11th
    Cir. 2014) (determining that presumption of arbitrability does not apply
    “before it is determined whether there is a ‘validly formed and enforceable
    arbitration agreement’”); Paul Revere Variable Annuity Ins. v. Kirschhofer,
    
    226 F.3d 15
    (1st Cir. 2000) (determining that federal preference for
    arbitration does not come into play where right to arbitrate is unclear or
    ambiguous).
    8
    See Kindred Nursing Centers Ltd. v. Clark, ___ U.S. ___, 
    137 S. Ct. 1421
    ,
    
    197 L. Ed. 2d 806
    (2017).
    - 362 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    [7,8] In interpreting a contract, a court must first deter-
    mine, as a matter of law, whether the contract is ambiguous.9
    A contract written in clear and unambiguous language is not
    subject to interpretation or construction and must be enforced
    according to its terms.10
    Section E
    Owner and Contractor argue that the district court improp-
    erly focused on the assigned headings of the subcontract when
    it construed Section E as agreed to only by Contractor. Owner
    and Contractor allege that Section E unambiguously incorpo-
    rated the dispute resolution process provided for in the general
    contract and that it was binding upon both Contractor and
    Subcontractor. We agree.
    As stated above, Section E provided, “If arbitration of
    disputes is provided for in the General Contract, any dispute
    arising between . . . Contractor and . . . Subcontractor under
    this Subcontract, including the breach thereof, shall be settled
    by arbitration in the manner provided for in the General
    Contract.” But, because the provision was included under
    the section heading “The Contractor Agrees as Follows” and
    not under either the heading “The Subcontractor Agrees as
    Follows” or the heading “The Contractors and Subcontractors
    Agree as Follows,” the district court determined that
    Subcontractor’s claims were not subject to arbitration. By
    purportedly enforcing the express terms of the contract, the
    court concluded that Section E was binding on Contractor
    only. In doing so, the district court adopted a restrictive inter-
    pretation of the section.
    [9] While two conflicting interpretations of Section E can
    be advanced, only one of them is reasonable. The district
    court’s restrictive interpretation disregards Section E’s broad
    language and effectively rewrites the section by limiting its
    9
    Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist., supra note 2.
    10
    
    Id. - 363
    -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    applicability to those disputes complained of by Contractor
    and not Subcontractor. A contract is ambiguous when a word,
    phrase, or provision in the contract has, or is susceptible of, at
    least two reasonable but conflicting interpretations or mean-
    ings.11 Because the restrictive interpretation of Section E was
    unreasonable, Section E was unambiguous and should have
    been enforced by its express terms.
    Consequently, both Contractor and Subcontractor agreed
    to Section E despite the section heading. For two reasons,
    we read that heading as suggesting a mutual promise rather
    than a unilateral commitment. First, the plain meaning of
    the term “agrees” contemplates a mutual understanding with
    ­another.12 And because Subcontractor was the only other party
    to the subcontract, it was the only one with which Contractor
    could agree. Second, because other provisions under the same
    heading, including an integration clause, are ones that are
    clearly intended to apply to both parties, the heading implicitly
    declares that “Contractor Agrees” with Subcontractor.
    Even under the heading “The Contractor Agrees as
    Follows,” the express terms of Section E included a recipro-
    cal agreement to arbitrate all disputes between Contractor
    and Subcontractor arising from the subcontract pursuant to
    the terms of the general contract. Because Subcontractor’s
    claims arose from the subcontract, they were subject to this
    agreement.
    Incorporated A rbitration
    Agreement
    Section E expressly provided for the settlement of disputes
    between Contractor and Subcontractor by “arbitration in the
    11
    
    Id. 12 “Agree,”
    Oxford English Dictionary Online, http://www.oed.com/view/
    Entry/4146 (last visited July 20, 2017) (defining term as “[t]o accede,
    consent; to come to an agreement with another”).
    - 364 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    manner provided for in the General Contract.” Therefore, we
    must clarify what the general contract provides regarding the
    “manner” of arbitration.
    The general contract provides, “For any Claim subject to,
    but not resolved by mediation pursuant to Section 15.3 of [the
    general conditions], the method of binding dispute resolution
    shall be . . . Arbitration pursuant to Section 15.4 of [the general
    conditions].” And, § 15.3.1 of the general conditions provides,
    “Claims, disputes, or other matters in controversy arising out of
    or related to the Contract except those waived as provided for
    in Sections 9.10.4, 9.10.5, and 15.1.6 shall be subject to media-
    tion as a condition precedent to binding dispute resolution.”
    Thus, a claim must be subject to mediation and the mediation
    of the dispute must be unsuccessful before the claim is subject
    to binding arbitration.
    The sweeping language of § 15.3.1 subjects all claims
    arising out of the contract, except those waived pursuant to
    the general conditions, to mediation as a condition precedent
    to binding dispute resolution. Section 9.10.4 waived certain
    claims by Owner after it made final payment. Section 9.10.5
    similarly waived those claims by Contractor and subcontractors
    after their acceptance of final payment. Finally, Section 15.1.6
    waived all claims for consequential damages.
    Here, Owner did not make a final payment and, necessarily,
    Subcontractor did not accept a final payment. Subcontractor’s
    claims arose out of a perceived breach of the contract, and
    Subcontractor did not seek consequential damages. Therefore,
    Subcontractor’s claims did not fall within one of the categories
    of claims waiving mediation pursuant to the general conditions.
    Because Subcontractor’s claims all arose out of the contract,
    the claims were subject to the dispute resolution process man-
    dated by § 15.3.1.
    - 365 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    A pplicability of FAA
    [10] If a contract containing an arbitration clause involves
    interstate commerce, the FAA governs the contract.13 We have
    already determined that the subcontract unambiguously incor-
    porated the arbitration agreement, with its requirement for
    mediation as a condition precedent, from the general contract
    and general conditions. Accordingly, we now consider whether
    the subcontract involved interstate commerce, thereby trigger-
    ing the applicability of the FAA.
    [11] Contracts involving interstate commerce include con-
    tracts for services between parties of different states.14 Here,
    the subcontract undeniably met this definition. The subcontract
    was for the provision and installation of electrical services and
    materials in the buildings constructed pursuant to the general
    contract. Thus, it was a contract for services. And it was clearly
    between parties of different states: Contractor is a Minnesota
    corporation, and Subcontractor is a Nebraska corporation.
    Therefore, the FAA applied and the agreement is presumed
    valid, irrevocable, and enforceable.15
    Because the subcontract’s arbitration clause is governed
    by the FAA, the action should have been stayed until arbitra-
    tion was had in accordance with the terms of the agreement.16
    Section 15.3.1 mandated mediation as a condition precedent
    to binding arbitration. At oral argument, it was conceded that
    mediation had not been attempted. Therefore, we must reverse
    the district court’s decision and remand the cause with direc-
    tions that the court enter an order compelling arbitration in the
    manner provided for in the general contract. That is, the parties
    must attempt to resolve their dispute in mediation and then
    13
    David Fiala, Ltd. v. Harrison, supra note 6.
    14
    
    Id. 15 See
    9 U.S.C. § 2 (2012).
    16
    See 9 U.S.C. § 3 (2012).
    - 366 -
    Nebraska Supreme Court A dvance Sheets
    297 Nebraska R eports
    FROHBERG ELEC. CO. v. GROSSENBURG IMPLEMENT
    Cite as 
    297 Neb. 356
    submit their dispute to arbitration in the event that mediation
    is unsuccessful.
    [12] Having found reversible error, we do not address Owner
    and Contractor’s remaining arguments. An appellate court is
    not obligated to engage in an analysis that is not necessary to
    adjudicate the case and controversy before it.17
    CONCLUSION
    Because the subcontract included a mutually agreed-to
    arbitration clause governed by the FAA and Subcontractor’s
    claims were subject to the clause, we conclude that the motion
    to compel arbitration in the manner provided for in the gen-
    eral contract should have been sustained. In other words, the
    parties should have been required to attempt mediation and,
    if that failed, to proceed to arbitration. We reverse the district
    court’s order and remand the cause with directions that the
    court enter an order staying the action and compelling arbitra-
    tion pursuant to the agreement.
    R eversed and remanded with directions.
    17
    Flores v. Flores-Guerrero, 
    290 Neb. 248
    , 
    859 N.W.2d 578
    (2015).