City of Mukilteo, Washington v. Usdot , 815 F.3d 632 ( 2016 )


Menu:
  •                     FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    CITY OF MUKILTEO, WASHINGTON, a                 No. 13-70385
    non-charter code city; CITY OF
    EDMONDS, WASHINGTON, a non-
    charter code city; SAVE OUR                       OPINION
    COMMUNITIES, a tax exempt
    organization; MICHAEL MOORE, an
    individual; VICTOR M. COUPEZ, an
    individual,
    Petitioners,
    v.
    U.S. DEPARTMENT OF
    TRANSPORTATION; ANTHONY FOXX,
    Secretary of Transportation;*
    FEDERAL AVIATION
    ADMINISTRATION; MICHAEL P.
    HUERTA, Acting Administrator,
    FAA; DAVID SUOMI, Regional
    Administrator, FAA Northwest
    Mountain Region,**
    Respondents.
    *
    Anthony Foxx is substituted for Ray LaHood as Secretary of
    Transportation. See Fed. R. App. P. 43(c)(2).
    **
    David Suomi is substituted for Kathryn Vernon as Acting Regional
    Administrator, FAA Northwest Mountain Region. See Fed. R. App. P.
    43(c)(2).
    2                CITY OF MUKILTEO V. USDOT
    On Petition for Review of an Order of the
    U.S. Department of Transportation
    Federal Aviation Administration
    Argued June 18, 2014
    Submitted October 9, 2015
    Seattle, Washington
    Filed March 4, 2016
    Before: Diarmuid F. O’Scannlain, Marsha S. Berzon,
    and Richard C. Tallman, Circuit Judges.
    Opinion by Judge Tallman
    SUMMARY***
    Federal Aviation Administration / Environmental Law
    The panel denied a petition for review challenging the
    Federal Aviation Administration’s (“FAA”) decision that no
    Environmental Impact Statement was necessary to commence
    operating commercial passenger service at Paine Field near
    Everett, Washington.
    Under the National Environmental Policy Act (“NEPA”),
    and its implementing regulations, the FAA was required to
    analyze all “reasonably foreseeable” environmental impacts
    ***
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    CITY OF MUKILTEO V. USDOT                    3
    of its decision to open Paine Field to commercial passenger
    traffic.
    The panel held that the scope of the FAA’s review was
    not arbitrary and capricious. The panel further held that the
    FAA’s demand-based flight operation projections for Paine
    Field were neither arbitrary nor capricious. The panel also
    rejected the petitioners’ contention that the FAA violated 40
    C.F.R. § 1508.25, which requires agencies to consider
    “connected actions” in NEPA documents, and held that it was
    not arbitrary for the FAA to have included no connected
    actions in the final Environmental Assessment. The panel
    rejected petitioners’ bias-based arguments, and held that: the
    FAA’s Finding of No Significant Impact was not
    predetermined by the creation of an optimistic schedule for
    completing the environmental review or statements favoring
    commercial service at Paine Field; and the FAA performed its
    NEPA obligations in good faith and did not prematurely
    commit resources to opening the terminal.
    COUNSEL
    Barbara E. Lichman (argued), Buchalter Nemer, Irvine,
    California, for Petitioners.
    Lane N. McFadden (argued), Attorney, Environment &
    Natural Resources Division; Robert G. Dreher, Acting
    Assistant Attorney General, United States Department of
    Justice, Washington, D.C.; Patricia A. Deem, Office of
    Regional Counsel, NW Mountain Region, Federal Aviation
    Administration, Seattle, Washington, for Respondents.
    4              CITY OF MUKILTEO V. USDOT
    OPINION
    TALLMAN, Circuit Judge:
    Paine Field, located in Snohomish County, Washington,
    near the city of Everett, was originally constructed in 1936
    when it was envisioned to become a major airport serving the
    communities located north of Seattle. Over the years, it has
    been used for military purposes (both during and after World
    War II), and for commercial and general aviation aircraft.
    Today, the Boeing Company operates its 747 aircraft
    production factory at Paine Field. There are a host of related
    commercial businesses which repair and service large
    airplanes, providing jobs to more than 30,000 people. For
    that reason, the three existing runways are as long as 9,010
    feet.
    Paine Field has not, however, become the hub of
    commercial passenger traffic originally envisioned when it
    was first built. In 2012, authorization was given to
    commence service by commercial passenger carriers, starting
    with permission to build a small two-gate terminal. This case
    brings to our attention a longstanding public debate over the
    future of the airfield.
    Petitioners challenge the Federal Aviation
    Administration’s (FAA) decision that no Environmental
    Impact Statement (EIS) is necessary to commence operating
    commercial passenger service at Paine Field. The FAA made
    that decision after preparing a draft Environmental
    Assessment (EA), a less robust form of environmental
    review. See Earth Island Inst. v. U.S. Forest Serv., 
    697 F.3d 1010
    , 1021–22 (9th Cir. 2012). Two and a half years and
    over 4,000 public comments later, the FAA published a final
    CITY OF MUKILTEO V. USDOT                           5
    EA in September 2012. It found no significant environmental
    impacts as a result of the FAA’s approval. Petitioners claim
    that the FAA unreasonably restricted the scope of the EA,
    failed to include connected actions as required, and
    predetermined an outcome before conducting its review.
    We heard argument on this appeal in June of 2014.
    Shortly thereafter, the parties requested that we stay this
    action because, for lack of funding, it appeared unlikely that
    development would proceed. Construction of the passenger
    terminal was indefinitely delayed after Snohomish County,
    which owns and operates Paine Field, decided it would not
    fund the three million dollars needed to construct a building
    that could handle passengers and their baggage. At the time,
    no one else was willing to step forward with the money, even
    though Alaska Airlines, through its subsidiary Horizon Air,
    and Allegiant Airlines had expressed an interest in providing
    service in and out of Paine Field if adequate facilities were
    made available.1
    After argument, we stayed the proceeding and requested
    interim status reports every six months. Based on the
    Respondents’ September 2015 undisputed assurances that
    construction is now imminent, we reinstated this case and
    now reach the merits of the petition.
    We have jurisdiction over this appeal under 49 U.S.C.
    § 46110(a). We have reviewed the record compiled by the
    1
    It appears Horizon Air and Allegiant Airlines may no longer be
    interested in providing service at Paine Field. The government has
    represented, however, that there is no reason to believe that the new
    commercial service proposed at Paine Field would involve a different
    number of flight operations than provided for in the original proposal.
    6              CITY OF MUKILTEO V. USDOT
    agency in support of its decision. We hold that the scope of
    the FAA’s analysis was not arbitrary and capricious; we
    recognize that under the enabling act that created it, the FAA
    is allowed to express a preference for a certain outcome; and
    we deny the petition for review and uphold the FAA’s
    decision to permit commercial passenger operations to begin
    at Paine Field once the terminal is built.
    I
    Petitioners make several arguments about the scope of the
    FAA’s review, essentially claiming that the FAA wrongly
    failed to analyze what would happen if more airlines followed
    the first two proposed airlines into Paine Field. Under the
    National Environmental Policy Act (NEPA), 42 U.S.C.
    §§ 4321-4370h, and its implementing regulations, the FAA
    was required to analyze all “reasonably foreseeable”
    environmental impacts of its decision to open Paine Field to
    commercial passenger traffic. See 40 C.F.R. § 1508.9
    (requiring EAs to analyze environmental impacts of the
    proposed action); 
    Id. at §
    1508.8(b) (equating “impact” with
    “effect” and defining “indirect effects” as those that are
    “reasonably foreseeable”); 
    Id. at §
    1508.7 (defining
    “cumulative impacts” as those which result from the addition
    of impacts from current and past actions to those of
    “reasonably foreseeable” future actions). Similarly, the Clean
    Air Act, 42 U.S.C. §§ 7401-7671, and related federal
    regulations also require the FAA to analyze “reasonably
    foreseeable” emissions resulting from its action. See 40
    C.F.R. § 93.153(b) (requiring agencies to analyze indirect and
    direct emissions); 
    Id. at §
    93.152 (defining “indirect
    emissions” as those that are, among other things, “reasonably
    foreseeable”).
    CITY OF MUKILTEO V. USDOT                              7
    The Supreme Court has emphasized that NEPA only
    “guarantees a particular procedure, not a particular result”
    and “a person with standing who is injured by a failure to
    comply with the NEPA procedure may complain of that
    failure at the time the failure takes place, for the claim can
    never get riper.” Ohio Forestry Ass’n, Inc. v. Sierra Club,
    
    523 U.S. 726
    , 737 (1998). Accordingly, when reviewing
    agency decisions under NEPA, the starting point is the
    administrative record. Animal Def. Council v. Hodel,
    
    840 F.2d 1432
    , 1436 (9th Cir. 1988), amended, 
    867 F.2d 1244
    (9th Cir. 1989). Our task is to determine whether the
    agency made an arbitrary and capricious decision based on
    that record. 
    Id. Here, the
    FAA based its flight operation projections on
    demand and determined that the only additional, and
    reasonably foreseeable, flights were those initially proposed
    by two airlines, amounting to approximately twenty-two
    operations2 per day. Those airlines proposed to employ
    smaller aircraft with a capacity of up to 150 passengers. In
    contrast, the projections touted by petitioners were based
    solely on the airport’s maximum capacity and do not take into
    account actual historical demand. While it is true that we do
    not have the most current projections before us, that data is
    not necessary to determine whether the FAA based its 2012
    decision on reasonable grounds. Further, the ongoing validity
    of that 2012 decision is unchallenged. The FAA claims that
    2
    An “[a]ir carrier operation” is defined as a single takeoff or landing.
    See 14 C.F.R. § 139.5. Historical data shows that Paine Field peaked in
    air carrier operations around the year 2000. That year, Paine saw a total
    of 213,291 “operations.” More recently, operations declined to 117,104
    operations per year in 2011. Thus, adding by 2018 approximately 8,340
    operations per year from commercial passenger operators will leave the
    overall airport operations within the level of historic variation.
    8                 CITY OF MUKILTEO V. USDOT
    the 2012 finding of no significant impact (FONSI) is still
    valid because Propeller Air, Inc., the new outside investor,
    now plans to build “a terminal facility consistent with that
    evaluated in the Final EA,” and that the number of operations
    will be similar. Petitioners submitted nothing to challenge
    that statement.
    The final EA evaluated four proposed FAA actions.3 The
    FAA must still take at least one of those original four
    actions—amending Paine Field’s Part 139 Certificate—to
    allow commercial passenger operations. Given that the major
    action4 analyzed in the original EA is now likely to occur, and
    the FAA maintains that it will occur “consistent” with the
    original plan, we evaluate the 2012 FONSI based on the
    existing administrative record.
    Petitioners do not contest the FAA’s claim that the
    projections regarding the number of air carrier operations in
    the FONSI are still consistent with the current terminal
    construction efforts, despite being given the opportunity to do
    3
    The four actions were: (1) amending Paine Field’s Part 139 Certificate
    to allow it to host commercial passenger service; (2) amending the Part
    119 Specifications for Horizon to allow flights in and out of Paine;
    (3) amending the Part 119 Specifications for Allegiant to allow flights in
    and out of Paine; and (4) determining whether Snohomish County was
    eligible to receive a federal grant to defray the cost of expanding and
    updating the existing terminal. Only action (1) is challenged here.
    4
    According to Petitioners, this, and the construction of a new terminal,
    are the FAA actions that they really seek to challenge. In a letter
    submitted to us on May 20, 2014, the Petitioners said the “cause of the
    harm that Petitioners allege and from which they require relief” is the
    FAA’s “plans to turn Paine Field into a commercial airport, and expand
    its facilities to accommodate commercial service,” rather than the change
    in Horizon’s and Allegiant’s Part 119 Specifications.
    CITY OF MUKILTEO V. USDOT                         9
    so. Given that we are to defer to the FAA “especially in areas
    of agency expertise such as aviation forecasting,” the FAA’s
    demand-based projections of approximately 8,340 operations
    per year in 2018, were not arbitrary and capricious.5 Nat’l
    Parks & Conservation Ass’n v. U.S. Dep’t of Transp.,
    
    222 F.3d 677
    , 682 (9th Cir. 2000). We decline to apply the
    less deferential standard advanced by Petitioners because this
    is a factual determination dependent on agency expertise
    rather than a legal determination. See San Luis Obispo
    Mothers for Peace v. Nuclear Regulatory Comm’n, 
    449 F.3d 1016
    , 1028 (9th Cir. 2006).
    We also reject Petitioners’ argument that amending Paine
    Field’s Part 139 Certificate to allow commercial passenger
    operations means that Paine Field “must allow access by all
    aircraft so requesting” in the future. Petitioners have
    provided no support for this come one, come all theory and
    instead rely on statutory provisions that limit the ability to
    take away airport access once access has been granted to a
    particular airline. See 49 U.S.C. § 47524(c)(1) (providing
    limits on new airport access restrictions); 49 U.S.C.
    § 41713(b)(1) (preempting state restrictions on access). The
    statutes cited by the Petitioners only go into effect after
    access has been authorized—meaning that the airport is open
    to commercial operations generally (via the airport’s Part 139
    Certificate) and the airline specifically has authority to
    conduct operations at that airport (via the airline’s Part 119
    Specifications). Thus, our decision today does not open the
    floodgates because any future airline must still get an
    amendment to its Part 119 Specifications in order to operate
    5
    These demand-based projections were actually quite close to the
    maximum terminal capacity projections advanced by Petitioners, which
    predicted 8,760 operations per year by 2018.
    10             CITY OF MUKILTEO V. USDOT
    out of Paine Field. The FAA, therefore, reasonably based the
    EA on the number of operations Horizon and Allegiant
    intended to carry out, not on the speculative number of
    operations that could someday be carried out at Paine Field if
    other airlines also seek an amendment to their Part 119
    Specifications.
    Given the existing administrative record, we hold that the
    FAA’s demand-based projections were neither arbitrary nor
    capricious.
    II
    Petitioners next argue that the FAA violated 40 C.F.R.
    § 1508.25, which requires agencies to consider “connected
    actions” in NEPA documents. Connected actions are those
    that are interdependent or automatically triggered by the
    proposed action. See 40 C.F.R. § 1508.25. The FAA
    determined that there were no connected actions for this
    project, and Petitioners have failed to provide anything more
    than mere speculation that the FAA’s actions now will lead
    to more aircraft activity at Paine Field in the future than
    covered in the EA. Thus, it was not arbitrary for the FAA to
    have included no connected actions in the final EA.
    III
    Petitioners also argue that the FAA decided what the
    result would be before performing the EA for two reasons:
    (1) the FAA made statements favoring passenger service at
    Paine Field; and (2) the FAA gave a schedule to the
    consulting firm that prepared the EA which included the date
    on which a FONSI could issue. Petitioners argue this
    schedule and the FAA’s statements show that the FAA
    CITY OF MUKILTEO V. USDOT                    11
    decided to issue a FONSI before even starting the
    environmental review process. We reject both of these bias-
    based arguments.
    Petitioners’ first argument, that the FAA favored
    commercial service, is easily rejected because NEPA does not
    prohibit agencies from having or expressing a favored
    outcome. Metcalf v. Daley, 
    214 F.3d 1135
    , 1142 (9th Cir.
    2000). Agencies are required only to conduct the required
    environmental review “objectively and in good faith,” rather
    than as “subterfuge to rationalize a decision already made.”
    
    Id. at 1142.
    Indeed, the enabling legislation that created the
    FAA includes an express congressional directive that the
    agency shall promote and encourage the development of
    commercial aviation throughout the United States. See
    Federal Aviation Act of 1958, Pub. L. No. 85-726, §§ 102-
    103, 72 Stat. 731, 740 (later recodified and repealed)
    (explaining that the FAA is charged with “[t]he promotion,
    encouragement, and development of civil aeronautics”). The
    FAA acted well within the bounds of NEPA by advocating
    for commercial service at Paine Field.
    Petitioners’ second argument, based on the FAA giving
    the EA contractor a schedule which included the date a
    FONSI could issue, is also without merit. As the FAA points
    out, approving a schedule which included the date a FONSI
    could issue did not obligate the FAA to reach a Finding of No
    Significant Impact. The FAA simply identified its preferred
    outcome and laid out an optimistic timetable for achieving
    that outcome. This is consistent with regulations that actually
    encourage the FAA to identify a preferred alternative and
    encourage the FAA to set time limits during the
    environmental review process. See 40 C.F.R. § 1501.8
    12             CITY OF MUKILTEO V. USDOT
    (encouraging time limits); 40 C.F.R. § 1502.14(e)
    (encouraging listing a preferred alternative).
    As the FONSI at issue in this case states, the FAA did a
    “careful and thorough” review of the final EA before issuing
    its finding. Because the FAA reserved the “absolute right” to
    determine whether a FONSI would issue or not, creating this
    tentative schedule did not violate NEPA. See Friends of
    Southeast’s Future v. Morrison, 
    153 F.3d 1059
    , 1063–65 (9th
    Cir. 1998) (holding that tentative timber cutting schedule
    released before EIS did not violate NEPA).
    In short, the FAA’s Finding of No Significant Impact was
    not predetermined by the creation of an optimistic schedule
    for completing the environmental review or statements
    favoring commercial service at Paine Field. The FAA
    performed its NEPA obligations in good faith and did not
    prematurely commit resources to opening the terminal. The
    Petitioners’ bias arguments fail.
    IV
    We emphasize that we base our decision today on the
    current administrative record. So far as that record shows, the
    only changes in the status quo since the FAA issued its 2012
    decision is that a private entity, Propeller Air, Inc., has now
    stepped forward to pay for building the small passenger
    terminal which the FAA has previously approved, and that
    the airlines likely to use the terminal may change. These
    changes are not enough to warrant a supplemental EA, as
    neither of these changes, in themselves, will necessarily alter
    the environmental impact. See Great Old Broads for
    Wilderness v. Kimbell, 
    709 F.3d 836
    , 854 (9th Cir. 2013)
    (holding that supplementation is not required when the final
    CITY OF MUKILTEO V. USDOT                   13
    project is a “minor variation” of one of the alternatives
    discussed in the NEPA document); see also FAA Order
    1050.1E (Change One) ¶ 402b(1) (requiring the FAA to
    supplement an EA only if “significant changes” have been
    made to the project).
    Practical concerns also weigh against requiring the FAA
    to reevaluate or supplement the EA at this time. As
    previously discussed, any airline wishing to fly out of Paine
    Field, besides Horizon or Allegiant, needs to request access
    from the FAA and an amendment to their Part 119
    Specifications, potentially triggering another round of
    environmental assessment subject to scrutiny under NEPA.
    We do not prejudice Petitioners by deciding this case on the
    current record because if they want post-2012 facts reviewed,
    the Petitioners can simply challenge the FAA’s future actions
    when further expansion is sought. But on this record we
    cannot say the FAA’s decision to permit limited commercial
    passenger operations to begin at Paine Field without a full
    environmental impact statement was arbitrary and capricious.
    PETITION FOR REVIEW DENIED.