Kellogg Brown & Root Services v. Army , 823 F.3d 622 ( 2016 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    KELLOGG BROWN & ROOT SERVICES, INC.,
    Appellant
    v.
    PATRICK J. MURPHY,
    ACTING SECRETARY OF THE ARMY,
    Appellee
    ______________________
    2015-1148
    ______________________
    Appeal from the Armed Services Board of Contract
    Appeals in No. 58492, Administrative Judge Alexander
    Younger, Administrative Judge Mark N. Stempler, Ad-
    ministrative Judge Richard Shackleford.
    ______________________
    Decided: May 18, 2016
    ______________________
    THOMAS PARKER MCLISH, Akin, Gump, Strauss,
    Hauer & Feld, LLP, Washington, DC, argued for appel-
    lant. Also represented by SCOTT MICHAEL HEIMBERG;
    TIRZAH S. LOLLAR, Vinson & Elkins LLP, Washington,
    DC; JOHN M. FAUST, Law Office of John M. Faust, PLLC,
    Washington, DC.
    ELLEN MARY LYNCH, Commercial Litigation Branch,
    Civil Division, United States Department of Justice
    Washington, DC, argued for appellee. Also represented by
    2                  KELLOGG BROWN & ROOT SERVICES    v. ARMY
    BENJAMIN C. MIZER, ROBERT E. KIRSCHMAN, JR., BRYANT
    G. SNEE.
    ______________________
    Before NEWMAN, O’MALLEY, and CHEN, Circuit Judges.
    NEWMAN, Circuit Judge.
    The only issue on this appeal is whether the six-year
    statute of limitations of the Contract Disputes Act had
    run for this claim. The claim was filed by Kellogg Brown
    & Root Services, Inc. (KBR) for costs incurred by KBR for
    work done by its subcontractor in performing a contract
    with the Army to construct dining facilities and to provide
    meal and related services for troops in Iraq. On the
    Army’s motion, the Armed Services Board of Contract
    Appeals (ASBCA or Board) dismissed KBR’s claim for
    lack of subject matter jurisdiction, holding that the period
    of limitations had run before KBR filed this claim. 1 The
    claim was filed on May 2, 2012; thus, the critical date of
    accrual for limitations purposes is May 2, 2006.
    On review of the premises and the applicable law, we
    conclude that the Board erred in law and on the applica-
    tion of law to the undisputed facts. We conclude that the
    KBR claim had not accrued, for limitation purposes,
    before May 2, 2006. The Board’s dismissal is reversed; we
    remand for determination of the merits of the claim.
    BACKGROUND
    In summary: on December 14, 2001, the Army and
    KBR entered into a cost-plus-award-fee contract under
    the Logistics Civil Augmentation Program. KBR subcon-
    1 Kellogg Brown & Root Servs., Inc. v. Dep’t of the
    Army, ASBCA No. 58492, 14-1 BCA ¶35,713 (“Board
    Op.”).
    KELLOGG BROWN & ROOT SERVICES   v. ARMY                  3
    tracted with a joint venture between The Kuwait Compa-
    ny for Process Plant Construction & Contracting K.S.C.
    and Morris Corporation (AUST) PTY Ltd. (KCPC/Morris),
    to implement certain work release orders for construction
    of dining facilities and provision of food services at two
    locations in Iraq. On July 31, 2003, KBR terminated the
    subcontract for “fail[ure] to bring conditions to full con-
    tract performance as of 31 July, 2003,” as required by the
    subcontract. Army Br. at 4. KCPC/Morris disputed the
    termination, and, at KBR’s request, also continued per-
    formance until transition to a new subcontractor on
    September 12, 2003.
    The ensuing determination of reimbursable costs and
    termination conditions included a suit filed in 2004 by
    KCPC/Morris against KBR in the United States District
    Court for the Eastern District of Virginia, in which
    KCPC/Morris stated (and KBR disputed) that an oral
    settlement had been reached and sought its enforcement.
    On January 24, 2005, KBR and KCPC/Morris entered into
    a written agreement, described by the Board as follows:
    [T]he parties divided KCPC/Morris’ costs into two
    groups: (a) the “Settlement Amount” of
    $17,400,000; and (b) KCPC/Morris’ costs incurred
    and profit related to its performance under the
    Master Agreement and the termination of the
    Work Releases . . . including overhead, G&A, prof-
    it and certain costs incurred in preparing requests
    for payment to the U.S. Government.
    Board Op. at 3. This agreement also converted the de-
    fault termination into a termination for convenience. 
    Id. The group
    (a) “Settlement Amount” of $17,400,000
    was paid, and is not at issue. This CDA action concerns
    only the group (b) component. For the group (b) costs, the
    agreement stated that KBR and KCPC/Morris would
    cooperate “to prepare a well-supported invoice or invoices
    to the U.S. Government,” the agreement also stating that
    4                  KELLOGG BROWN & ROOT SERVICES   v. ARMY
    “[i]n no event shall KBR submit an invoice to the Gov-
    ernment for any portion of the JOINT VENTURE’s costs
    that KBR does not believe is supportable.” 2005 Settle-
    ment Agreement at 4.
    On August 26, 2006, KCPC/Morris submitted to KBR
    a certified claim for the “outstanding payments, costs and
    lost profit associated with the termination for convenience
    by [KBR] of the [] contract.” Army Br. at 5. On November
    3, 2006, KBR forwarded KCPC/Morris’ claim to the Army,
    with a letter stating that KBR “does not certify or com-
    ment to the validity of these costs and does not have any
    other supporting documentation for validation.” Letter
    from Senior Manager, Contracts, KBR, to Chief, LOGCAP
    Branch, Department of the Army (Nov. 3, 2006) (“KBR
    Letter”).
    The Army responded to KBR on May 30, 2007, stating
    that “it is KBR’s management responsibility to negotiate
    or discuss claims with its subcontractors and the Army
    does not comment in advance as to whether a claim or
    certain costs are appropriate. Therefore, the Army will
    not meet with, or correspond directly with KBR’s subcon-
    tractors.” See Board Op. at 5 (quoting Army Sustainment
    Command Letter to KBR (May 30, 2007)). The Army
    refused to consider the submitted information, and di-
    rected KBR to “settle a claim by its sub with the sub, then
    bill the government.” E-mail from Chief, Contracting
    Division, Logistics Civil Augmentation Program, Army
    Sustainment Command, to Senior Manager, Contracts,
    Kellogg Brown and Root, “RE: Request for additional
    information regarding draft settlement” (July 19, 2007)
    (“Army Email”).
    On October 10, 2007, KBR “sponsored” the
    KCPC/Morris claim, followed by certification of the claim
    by letter dated January 10, 2008. On September 8, 2010,
    KBR withdrew the claim, stating that “[u]pon further
    review of the data provided by KCPC/Morris, KBR has
    KELLOGG BROWN & ROOT SERVICES    v. ARMY                  5
    determined that this constitutes a business dispute
    between KBR and KCPC/Morris and should be resolved in
    accordance with KBR’s subcontract with KCPC/Morris.”
    Letter from Senior Manager, Contracts, Kellogg Brown
    and Root, to Army Contracting Command, “Subject:
    DAAA09-02-D-0007: Subcontractor Claim KCPC/Morris.”
    The record before us does not provide details, but KBR
    states that the asserted costs were eventually reduced by
    about $2.1 million. KBR Br. 20.
    On August 4, 2011, KCPC/Morris filed suit against
    KBR in the United States District Court for the Eastern
    District of Virginia, stating in its complaint that “KBR
    allowed [KCPC/Morris’ claim] to languish with the Gov-
    ernment, . . . and then inexplicably withdrew the entire
    claim       in September      2010     without    consulting
    KCPC/Morris. . . . KBR has failed to submit and pursue
    the portions of the claim it concedes are well support-
    ed . . . .” Compl. at 2, Kuwait Co. for Process Plant Const.
    & Contr. v. Kellogg, Brown & Root Servs., Inc., 1:11-cv-
    824-CMH/TRJ, (E.D. Va. August 4, 2011). This suit was
    withdrawn after KBR and KCPC/Morris entered into an
    agreement dated February 17, 2012, for payment to
    KCPC/Morris of $10,464,493, which the Board summa-
    rized as for “construction costs, equipment, expenses such
    as medical care and travel, meals served, overhead and
    G&A, profit, and termination settlement costs.” Board
    Op. at 4–5. On May 2, 2012, KBR filed a certified claim
    with the Army for this amount. The contracting officer
    did not act on the claim, thereby placing it in “deemed
    denied” status. KBR then appealed to the Board.
    The Army moved to dismiss, stating that the six-year
    CDA statute of limitations had run. The Board granted
    the motion, finding alternative dates for the accrual of the
    claim, both dates before the critical limitations date of
    May 2, 2006. The Board found, first, that the claim
    accrued on September 12, 2003, the date when
    KCPC/Morris ended its work under the subcontract; and
    6                  KELLOGG BROWN & ROOT SERVICES    v. ARMY
    alternatively on January 24, 2005, when KBR and
    KCPC/Morris agreed to cooperate to present an invoice to
    the Army for costs above the “Settlement Amount” of
    $17.4 million. The Board held that there was no basis for
    equitable tolling of the limitations period. Board Op. at
    10–11 (“With a record that reflects such lengthy time gaps
    as this . . . , we cannot say that KBR has actively pursued
    its remedies. In addition, [the record] does not support
    any conclusion of trickery or other misconduct.”) (internal
    quotations marks omitted). This appeal followed.
    DISCUSSION
    The limitations period is determined in accordance
    with the Contract Disputes Act (CDA), which provides
    that a claim “shall be submitted within 6 years after the
    accrual of the claim.” 41 U.S.C. § 7103(a)(4)(A). We start
    with the Board’s ruling that the claim accrued on the date
    the subcontractor ended its work.
    “Accrual” When Subcontractor Work Ended On
    September 12, 2003
    The FAR defines “accrual” of a contract claim as:
    the date when all events, that fix the alleged lia-
    bility of either the Government or the contractor
    and permit assertion of the claim, were known or
    should have been known. For liability to be fixed,
    some injury must have occurred. However, mone-
    tary damages need not have been incurred.
    48 C.F.R. § 33.201. Precedent elaborates that whether
    and when a CDA claim accrued is determined in accord-
    ance with the FAR, the conditions of the contract, and the
    facts of the particular case. Parsons Global Servs. v.
    McHugh, 
    677 F.3d 1166
    , 1170 (Fed. Cir. 2012) (“we evalu-
    ate whether a particular request for payment amounts to
    a claim based on the FAR implementing the CDA, the
    language of the contract in dispute, and the facts of each
    case.”); James M. Ellett Constr. Co. v. United States, 93
    KELLOGG BROWN & ROOT SERVICES    v. ARMY                   
    7 F.3d 1537
    , 1542 (Fed. Cir. 1996) (the existence of a CDA
    claim “is based on the FAR definition of a claim, the
    contract language, and the facts of the case”); Reflectone,
    Inc. v. Dalton, 
    60 F.3d 1572
    , 1575 (Fed. Cir. 1995) (en
    banc) (“we must assess whether a particular demand for
    payment constitutes a claim, based on the FAR imple-
    menting the CDA, the language of the contract in dispute,
    and the facts of the case.”).
    The Board reasoned that “liability was fixed” on Sep-
    tember 12, 2003, because the claim was for the “alleged
    entitlement to the net costs of performance of the termi-
    nated KCPC/Morris subcontract, including costs for
    construction of sites C-1 and C-2, meals served, overhead,
    G&A and profit (statement 19).” Board Op. at 7. KBR
    responds that until the amount of payment to be request-
    ed of the Army was determined, the claim had not come
    into existence and thus could not accrue. KBR points to
    the Army’s requirement that KBR resolve all subcontrac-
    tor issues in order to “permit assertion of the claim.” FAR
    § 33.201. “Claim” is defined as:
    “Claim” means a written demand or written as-
    sertion by one of the contracting parties seeking,
    as a matter of right, the payment of money in a
    sum certain, the adjustment or interpretation of
    contract terms, or other relief arising under or re-
    lating to the contract. However, a written de-
    mand or written assertion by the contractor
    seeking the payment of money exceeding $100,000
    is not a claim under 41 U.S.C. chapter 71, Con-
    tract Disputes, until certified as required by the
    statute. . . .
    48 C.F.R. § 2.101; see also 
    id. § 52.233-1(c)(same).
        Fixing the date of accrual of a claim requires first that
    there is a “claim” as defined in the Contract Disputes Act
    and associated Regulations. KBR states that “a sum
    certain” could not have been demanded or asserted on
    8                  KELLOGG BROWN & ROOT SERVICES   v. ARMY
    September 12, 2003, because the reimbursable costs and
    profit entitlements were not then known, and in view of
    disputes including termination conditions, could not
    reasonably have been known. KBR states that until
    KCPC/Morris sent KBR its documented and certified
    claim on August 26, 2006 (after the critical date of May 2,
    2006), there was not a basis for determining the “sum
    certain” that is required for a CDA claim. KBR points out
    that the Army refused to consider the KCPC/Morris
    certified claim when forwarded by KBR, and that the
    Army required KBR to resolve all issues with the subcon-
    tractor: “KBR is required to settle a claim with the sub-
    contractor, then bill the government.” See Army Email.
    The Army does not state that the amount of the claim
    was reasonably known in 2003 or 2005; the Army’s argu-
    ment is that liability was “fixed” by KBR’s cost-reimbursal
    contract with the Army, although the amount of the
    liability was not established. Army Br. at 12–15 (“Even
    though the exact amount of money that KBR owed
    KCPC/Morris had not yet been established . . .[,] KBR’s
    liability to KCPC/Morris was fixed because KBR knew
    that      it   owed     KCPC/Morris       money. . . . When
    KCPC/Morris’ claim accrued against KBR, so too did
    KBR’s claim accrue against the government.”). However,
    by FAR definition, a “claim” for “the payment of money”
    does not “accrue” until the amount of the claim, “a sum
    certain,” FAR § 2.101, is “known or should have been
    known,” 
    id. § 33.201.
        In Parsons Global, this court observed that determi-
    nation of whether a claim accrued is based on the particu-
    lar 
    circumstances. 677 F.3d at 1170
    (“we evaluate
    whether a particular request for payment amounts to a
    claim based on . . . the facts of each case.”). KBR states
    that it did not have sufficient information to request a
    sum certain until KCPC/Morris first presented its claim
    to KBR on August 26, 2006, after the critical date. The
    KELLOGG BROWN & ROOT SERVICES   v. ARMY                  9
    Board did not find otherwise, and the Army does not
    argue otherwise.
    Instead, the Board adopted the theory, presented by
    the Army, that the payment of the remaining subcontrac-
    tor costs was a “non-routine” request for payment, and
    thus accrued as of the date the subcontractor ended its
    work, on September 12, 2003. Reflectone, explains the
    distinction between routine and non-routine requests for
    payment in CDA matters: “A routine request for payment
    is made under the contract, not outside 
    it,” 60 F.3d at 1575
    , while a non-routine request seeks “compensation
    because of unforeseen or unintended circumstances,” 
    id. at 1577.
    The Board held that any termination of a sub-
    contract is unforeseen or unintended, and therefore
    produces the immediate accrual of any compensation
    owed. Board Op. at 10.
    The Board’s holding is a misapplication of so-called
    “non-routine” requests. The origin of this rule, as ex-
    plained in James M. 
    Ellett, 93 F.3d at 1543
    , is to permit a
    contractor that has been injured by “some unexpected or
    unforeseen action on the government’s part that ties it to
    the demanded costs,” in the words of Parsons 
    Global, 677 F.3d at 1171
    , to seek immediate payment of any damages
    flowing from the government’s action. Termination of a
    subcontractor by the prime contractor is not a per se
    “unexpected or unforeseen government action” that per-
    mits and requires an immediate claim by the prime
    contractor. The Army does not argue otherwise.
    Whether a request for payment is deemed routine or
    non-routine in the context of accrual of a CDA claim
    against the government is “dependent on the circum-
    stances in which the requested costs arose.” 
    Id. at 1170.
    KBR states that the group (b) costs for which payment is
    requested are the routine costs of performance and termi-
    nation, and did not arise from unexpected government
    10                  KELLOGG BROWN & ROOT SERVICES     v. ARMY
    action, but from subcontractor inadequacy in performance
    of its obligations under the subcontract.
    The Army argues that KBR’s November 3, 2006 letter
    to the Army (after the critical date) was a “non-routine”
    request for payment, for this letter states that KBR “does
    not certify or comment to the validity of these costs and
    does not have any other supporting documentation for
    validation.” See KBR Letter. However, the Army refused
    to accept this letter as a “claim,” either routine or non-
    routine.
    KBR states that whether its November 3, 2006, letter
    forwarding the KCPC/Morris claim is viewed as a “rou-
    tine” or “non-routine” request is irrelevant to the limita-
    tions issue, for it occurred after the critical date of May 2,
    2006. We agree that this letter did not retrospectively
    convert the termination date of September 12, 2003, into
    the “accrual” of a “claim” that was not even arguably
    presented until after the critical limitations date.
    In other, related situations, precedent illustrates that
    the limitations period does not begin to run if a claim
    cannot be filed because mandatory pre-claim procedures
    have not been completed. See Crown Coat Front Co. v.
    United States, 
    386 U.S. 503
    , 510-12 (1967) (pre-CDA case,
    finding that the government contractor’s claim “first
    accrued . . . upon the completion of the administrative
    proceedings contemplated and required by the provisions
    of the contract”). Here, the Army required that KBR
    resolve disputed costs with the subcontractor before KBR
    could present a claim for reimbursement of those costs.
    See Bay Area Laundry and Dry Cleaning Pension Trust
    Fund v. Ferbar Corp. of Calf., Inc., 
    522 U.S. 192
    , 200–01
    (1997) (rejecting as “inconsistent with basic limitations
    principles” the position that a limitations period can
    commence when the claimant’s suit would be premature
    because required pre-suit procedures had not taken
    place).
    KELLOGG BROWN & ROOT SERVICES   v. ARMY                 11
    The Army also states that the Severin Doctrine re-
    quires that this claim accrued on September 12, 2003.
    That is not an apt application of Severin v. United States,
    
    99 Ct. Cl. 435
    (1943), where the court held that “if plain-
    tiffs had proved that they, in performance of their con-
    tract with the government[,] become liable to their
    subcontractor for damages which the latter suffered, that
    liability, though not yet satisfied by payment, might well
    constitute actual damages to plaintiffs and sustain their
    suit.” 
    Id. at 443.
    The Army states that “Severin describes
    precisely the situation that we have here—KBR became
    liable to its subcontractor for damages that the subcon-
    tractor suffered because of KBR’s default termination
    decision.” Army Br. 13.
    The Army argues, “When KCPC/Morris’ claim accrued
    against KBR, so too did KBR’s claim accrue against the
    government.” 
    Id. at 14.
    Severin does not so hold. The
    prime contractor may indeed be liable for damages that
    the prime inflicts on the subcontractor. However, Severin
    does not hold that the date of “accrual” of the prime’s
    claim against the government is the date of termination of
    the subcontractor. Accrual in accordance with FAR
    § 33.201 does not occur until KBR requests, or reasonably
    could have requested, a sum certain from the government.
    As the Army repeatedly told KBR here, it would not
    consider any of KBR’s submissions until after resolution
    of the subcontractor issues.
    The Army also argues that the government’s exposure
    in “pass-through” suits for subcontractor claims is limited
    to the amount of the prime contractor’s liability for the
    subcontractor’s costs. Accepting this position for this
    case, it does not follow that KBR’s claim against the
    government accrued before the subcontractor submitted
    its certified claim to KBR. Severin is concerned with
    liability among government, contractor, and subcontrac-
    tor, 
    see 99 Ct. Cl. at 443
    , not with dates of “accrual” of
    “claims” as defined by the FAR. And the Severin Doctrine
    12                 KELLOGG BROWN & ROOT SERVICES   v. ARMY
    is directed to liability resulting from government action
    harming the subcontractor.
    KBR criticizes the Army’s position that prime contrac-
    tors have ripe CDA claims against the government at the
    moment that dispute arises with a subcontractor, even if
    the government is not involved in the dispute; even if, as
    here, the Army required KBR to resolve its subcontractor
    issues before the Army would consider the claim. KBR
    states that the Board’s ruling and the Army’s position
    would require cost-reimbursement contractors to request
    payment of subcontractor costs while those costs are
    under dispute, lest the prime contractor lose the right to
    recover those costs. KBR correctly observes that the CDA
    does not require the filing of protective claims related to
    subcontractors while those claims are being resolved
    between the prime and sub.
    We conclude that the Board erred in holding that be-
    cause subcontract activity by KCPC/Morris ended on
    September 12, 2003, the KBR claim for group (b) costs
    accrued on that date.
    Alternate Accrual in January 2005
    The Board held alternatively that KBR’s claim ac-
    crued when, “in January 2005, KBR had sufficient actual
    knowledge to enter into a written settlement agreement
    segregating subcontract costs into a ‘Settlement Amount’
    and other costs above that amount.” Board Op. at 8.
    This appeal relates only to the “other costs” above the
    Settlement Amount. The January 2005 agreement also
    established conversion from termination for default to
    termination for convenience, adding the need for KBR and
    the subcontractor to resolve the issue of lost profits.
    Indeed, the Army does not argue that “a sum certain” was
    known at the time the January 2005 agreement was
    entered.
    KELLOGG BROWN & ROOT SERVICES    v. ARMY                  13
    In accordance with the FAR, KBR’s claim for the “oth-
    er costs” did not alternatively accrue when KBR and the
    subcontractor agreed to resolve these costs and cooperate
    to present a claim when the costs were resolved. We
    conclude that the Board erred in holding that KBR’s claim
    accrued with the January 24, 2005 agreement.
    Other Arguments
    We have considered the other issues and arguments.
    We agree with the Board that KBR’s withdrawn 2008
    claim did not toll the limitations period, although this is
    irrelevant in view of our holding that this claim did not
    accrue before the critical date.
    We take note of the Board’s concern for the lengthy
    pendency of this claim, and the Board’s suggestion that a
    contractor could indefinitely delay the accrual of its claim.
    KBR responds that the Allowable Cost and Payment
    clause of the Contract Disputes Act limits the time in
    which a contractor may seek reimbursement after a
    “physically complete contract” has been performed, citing
    48 C.F.R. § 52.216-7(d)(5). KBR states that the FAR
    requires it to submit a “completion invoice or voucher,”
    including “settled subcontract amounts,” within 120 days
    after indirect cost rates are determined for all years of the
    contract, 
    id., and KBR
    must then release the government
    from further liabilities and claims under the contract,
    except for specified claims and unknown claims,
    
    id. § 52.216-7(h).
    KBR points out that a contractor cannot
    postpone a request for payment either unilaterally or
    indefinitely. The Army does not argue otherwise. Nor
    does the Army argue that the cost-plus-award-fee contract
    between KBR and the government became a physically
    complete contract at any time prior to the filing of the
    claim.
    The court has confirmed that the limitations period of
    the Contract Disputes Act is not jurisdictional. See Sikor-
    sky Aircraft Corp. v. United States, 
    773 F.3d 1315
    (Fed.
    14                KELLOGG BROWN & ROOT SERVICES   v. ARMY
    Cir. 2014). However, in view of our decision that the
    statute of limitations does not bar this claim, equitable
    tolling need not be considered.
    CONCLUSION
    The Board’s dismissal on statute of limitations
    grounds is reversed. The case is remanded to the Board
    for determination of the merits of the claim.
    REVERSED AND REMANDED