LoRoad, LLC v. Global Expedition Vehicles LLC , 787 F.3d 923 ( 2015 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 14-2636
    ___________________________
    LoRoad, LLC
    lllllllllllllllllllll Plaintiff - Appellant
    v.
    Global Expedition Vehicles, LLC
    lllllllllllllllllllll Defendant - Appellee
    ____________
    Appeal from United States District Court
    for the Western District of Missouri - Springfield
    ____________
    Submitted: February 11, 2015
    Filed: June 1, 2015
    ____________
    Before LOKEN, SMITH, and COLLOTON, Circuit Judges.
    ____________
    LOKEN, Circuit Judge.
    LoRoad, L.L.C., based in Oregon, negotiated to have Global Expedition
    Vehicles, L.L.C. (GXV), based in Missouri, build a custom expedition vehicle. With
    the project underway, the relationship broke down. LoRoad filed this diversity action
    to compel arbitration of the dispute, invoking the arbitration provision in a written
    Assembly Agreement allegedly entered into by the parties. GXV denied a valid,
    enforceable agreement to arbitrate. Ruling on cross-motions for summary judgment,
    the district court1 held that LoRoad failed to accept the Assembly Agreement signed
    by GXV; therefore, the court could not enforce the arbitration provision in that
    Agreement. LoRoad appeals the resulting adverse summary judgment. We affirm.
    I.
    In September 2012, wilderness photographer Rodney Lough on behalf of
    LoRoad began negotiations with GXV for construction of a custom expedition
    vehicle to be used by LoRoad for Lough’s off-road photography expeditions. On
    October 1, GXV sent a proposed Assembly Agreement for Lough’s review. The
    Agreement contained terms sufficiently definite and complete that, had LoRoad
    accepted, it would have been a binding contract. The terms included a
    “nonrefundable deposit of $120,000 to be paid at contract signing,” and an arbitration
    clause. GXV also emailed Lough that it would purchase a 2001 BAE 6x6 truck for
    $110,000 to serve as the base for Lough’s custom vehicle. Each subsequent version
    of the Assembly Agreement included this specific truck in calculating the total cost
    to build.
    Rather than accept the October 1 proposed Agreement, Lough returned a
    marked-up copy on October 9. GXV sent a revised Agreement on October 22, and
    after further negotiations, another revised Agreement on October 31. On November
    2, LoRoad wired $120,000 to GXV, which René Van Pelt of GXV acknowledged on
    November 5. On November 16, Lough faxed GXV the October 31 draft Agreement
    with relatively minor handwritten notations and changes. In the space for LoRoad’s
    signature at the end of the Agreement, Lough wrote “LeeAnna Lough” (his wife and
    also a LoRoad principal) above the LoRoad signature line, and “By:” below that line.
    1
    The Honorable Sarah W. Hays, United States Magistrate Judge for the
    Western District of Missouri.
    -2-
    On November 28, Lough emailed, “We still have unfinished business.” Van
    Pelt responded with answers to “notes and questions that we received by fax on
    November 16th.” On December 6, GXV sent a receipt for the $120,000 with the
    subject line, “Contract Deposit,” and emailed a status report on acquiring the base
    vehicle. On December 11, after further communications, Van Pelt sent LoRoad a
    revised Build List, which was “Exhibit A” to the Assembly Agreement and listed
    specifications for the vehicle. Van Pelt noted, “Once I get a thumbs up on the Build
    List, I will revise the contract and email to you as a complete document set.” On
    December 15, Lough emailed Van Pelt, “I am still not feeling comfortable with how
    things are at the moment . . . We are very seriously looking at pulling out, at which
    point will [] want our money returned.”
    On January 30, 2013, Van Pelt emailed Rodney Lough, “Your BAE 6x6 in
    transit,” explaining GXV’s delay in getting the truck and predicting it would arrive
    at GXV on Friday. On Friday, February 1, Van Pelt emailed Lough a picture of the
    truck. On February 11, Lough emailed Van Pelt asking for a status report. Van Pelt
    responded that GXV’s engineering team had started work on the truck, would send
    it to be painted when they were done, and asked Lough to “respond via email that the
    color is staying per Build List: White.”
    The next documentary exchange frames the contract issue on appeal. On
    February 11, Lough emailed Van Pelt saying LoRoad “had no record of the parties’
    creating and executing a final set of documents.” Lough asked GXV to send “a final
    set [of documents] incorporating everything we’ve come to agreement on” “for final
    review and then signatures, so we can get this thing moving.” Van Pelt responded
    that GXV received a signed contract from LoRoad on November 16.2 Lough replied
    he had no record of that, and asked Van Pelt to “send me a copy of what you have,
    2
    GXV interpreted the handwritten “LeeAnna Lough” on the marked-up
    Agreement LoRoad sent on November 16 as an authorized LoRoad signature.
    -3-
    because we do not have one here nor do we have an executed copy from you either.”
    In response, Van Pelt returned a copy of the Agreement received from LoRoad on
    November 16, with Lough’s handwritten changes and with the addition of Michael
    Van Pelt’s signature on the GXV signature line, but without the critical Build List.
    In a February 14 reply, Lough asked for the entire Agreement, stated he did not
    know where the document came from, and asserted, “That is NOT LeeAnna’s
    signature . . . I would never have authorized LeeAnna to sign a document that was not
    ready for signature and this document isn’t there and therefore we would not have
    signed it. I have emails from you going through and into December where the two
    of us continue finalizing the documents as they have not been completed.” Lough
    further stated, “We do want you guys to create this vehicle however we are no where
    near having the documents done . . . and while you have our commitment in the form
    of a $120k deposit, that in no way means that you have an agreement with us until the
    final documents are signed, sealed and delivered properly.”
    On February 22, Van Pelt sent a document titled “Assembly Agreement
    Addendum” dated February 2013, and a Build List dated December 11, 2012 (neither
    document is in the record on appeal). Lough responded: “Sending us an Addendum
    for a non-executed Assembly Agreement is not what you said you would do.” Lough
    “officially disputed your assertion that the Assembly Agreement is a signed and
    executed document.” On February 25, Lough reiterated LoRoad had not executed an
    agreement and described the $120,000 as a “good faith deposit,” not a payment under
    the Assembly Agreement. GXV then ceased work on the custom vehicle.
    In March, LoRoad’s attorney began communicating with GXV. His first letter
    stated, “Lo Road is committed to purchasing the Expedition Vehicle” but “there is no
    final, executed contract in place.” The letter stated that, “according to all drafts of the
    Assembly Agreement, signed or not, GXV’s commencement of work was to begin 15
    days after receipt of the deposit,” expressed concern about the delays, and asked for
    -4-
    certain action items to be completed, including a revised Build List. An attachment
    detailed eleven reasons why there was “No Executed Contract in Place.”
    On March 15, LoRoad’s attorney sent another letter, invoking the Adequate
    Assurances provision of the Uniform Commercial Code. GXV responded on March
    16, “Global Expedition Vehicles contends that we do have an executed contract with
    the Lo Road, LLC. We have expended a great deal of money and engineering
    payroll, based on this contract.” Van Pelt sent an email on March 27 expressing
    surprise that Lough wanted to change the Build List because Lough advised on
    February 22 he wanted to proceed with the December 11, 2012 Build List. On April
    19, LoRoad’s attorney sent a letter stating that GXV had failed to provide adequate
    assurances and was in material breach of the contract, and that LoRoad intended to
    institute arbitration pursuant to the Assembly Agreement. This petition to compel
    arbitration followed.
    II.
    LoRoad argues that the terms of the Assembly Agreement that GXV signed and
    faxed to LoRoad on February 13, 2013, included an agreement to arbitrate that is
    enforceable against GXV. If enforceable, the Assembly Agreement is “a contract
    evidencing a transaction involving commerce” subject to the Federal Arbitration Act,
    9 U.S.C. § 2. However, the parties agree that Missouri contract law governs the issue
    on appeal. Under both the Federal Arbitration Act and Missouri law, “[a] party who
    has not agreed to arbitrate a dispute cannot be forced to do so. Accordingly, the court
    must determine whether there is an agreement between those parties which commits
    the subject matter of the dispute to arbitration.” PCS Nitrogen Fertilizer, L.P. v.
    Christy Refractories, L.L.C., 
    225 F.3d 974
    , 977-78 (8th Cir. 2000) (quotations
    omitted); see Arrowhead Contracting, Inc. v. M.H. Wash., LLC, 
    243 S.W.3d 532
    , 535
    (Mo. App. 2008). The party seeking to compel arbitration has the burden to prove a
    -5-
    valid and enforceable arbitration agreement. Baier v. Darden Restaurants, 
    420 S.W.3d 733
    , 737 (Mo. App. 2014).
    As the Assembly Agreement concerned the sale of “goods,” it is governed by
    Article 2 of Missouri’s Uniform Commercial Code. See Mo. Rev. Stat. § 400.2-
    105(1). General principles of contract law apply unless “displaced by the particular
    provisions” of the UCC. Mo. Rev. Stat. § 400.1-103. Under the UCC, “[a] contract
    for sale of goods may be made in any manner sufficient to show agreement, including
    conduct by both parties which recognizes the existence of such a contract.” Mo. Rev.
    Stat. § 400.2-204(1). Without question, the writing on which LoRoad relies was
    sufficiently definite to form a contract enforceable against GXV, including its
    arbitration provision. See Mo. Rev. Stat. § 400.2-201(1). But a writing alone is
    insufficient if it does not establish that an agreement was reached between the parties;
    the document must “indicate the consummation of a contract, not mere negotiations.”
    Howard Constr. Co. v. Jeff-Cole Quarries, Inc., 
    669 S.W.2d 221
    , 227 (Mo. App.
    1983). Therefore, LoRoad must show an agreement between the parties. The district
    court concluded that the undisputed facts establish that LoRoad never accepted the
    Assembly Agreement. We agree.
    The UCC “expands the traditional concept of a contract,” but it “continues the
    common-law principle that the intent of the parties to make a contract must be
    manifested.” Computer Network, Ltd. v. Purcell Tire & Rubber Co., 
    747 S.W.2d 669
    ,
    674 (Mo. App. 1988). Thus, the “core issue” is whether both LoRoad and GXV
    intended to form a legally binding contract:
    If the parties intended no binding agreement or contract, the rules of
    construction and interpretation will not establish one. If no intent is
    found, the inquiry is put to an end. If the expressions in the agreement
    are clear, the court determines the intent from a reading of the writing.
    If the intent is not clearly expressed, then surrounding circumstances
    -6-
    may be considered -- the subsequent actions of the parties and the
    practical construction of the contract.
    
    Id. (emphasis added).
    The intent which we are concerned with is the parties’
    objective intent and what a reasonably prudent person would have been led to believe
    from the actions or words of the parties. See 
    id. at 675.
    Here, if an authorized representative had signed the Assembly Agreement that
    LoRoad faxed to GXV on November 16, 2012, then the document was an offer,3 and
    both sides manifested the intent to form a binding contract when GXV signed that
    document and returned it to LoRoad on February 13, 2013. This was GXV’s
    contemporaneous interpretation of the effect of its action on February 13. But
    LoRoad immediately objected and countered with strong, indeed persuasive reasons
    why the marked-up document it faxed on November 16 was not a binding offer that
    GXV could accept, pointing out it was not LeeAnna Lough’s signature on the
    document, and she was not authorized to sign a contract binding LoRoad . Thus, this
    document did not clearly manifest LoRoad’s intent to form a binding contract.
    Rather, it appears to be merely another mark-up of an Assembly Agreement that GXV
    had initially proposed and which the parties had been negotiating for over a month.
    See FutureFuel Chem. Co. v. Lonza, Inc., 
    756 F.3d 641
    , 647 (8th Cir. 2014)
    (“ongoing negotiations between the parties over these terms demonstrates that there
    was no mutual assent”).
    Looking beyond the contract document on which LoRoad relies, the undisputed
    facts establish clear, immediate, unequivocal rejection by LoRoad and its attorney
    3
    An offer is “the manifestation of willingness to enter into a bargain, so made
    as to justify another person in understanding that his assent to that bargain is invited
    and will conclude it.” See Brown Mach., Div. of John Brown, Inc. v. Hercules, Inc.,
    
    770 S.W.2d 416
    , 419 (Mo. App. 1989), citing Restatement (Second) of Contracts § 24
    (1981).
    -7-
    when GXV claimed in February 2013 that a binding contract had been formed. While
    such subsequent action would not revoke or nullify a contract already formed, it is
    relevant in resolving the ambiguity as to whether LoRoad intended to be bound to the
    terms of the marked-up form of contract it sent to GXV on November 16. This is
    precisely the analysis that this court and Missouri courts have conducted in resolving
    disputes over whether ongoing negotiations that included the exchange of multiple
    draft agreements resulted in a binding contract. See 
    Arrowhead, 243 S.W.3d at 535
    -
    36 (no contract to arbitrate formed); Computer 
    Network, 747 S.W.2d at 675
    (contract
    formed); 
    Howard, 669 S.W.2d at 228-29
    (no contract); Shapleigh Inv. Co. v. Miller,
    
    193 S.W.2d 931
    , 937 (Mo. App. 1946) (contract formed); 
    FutureFuel, 756 F.3d at 647
    (no contract); Conolly v. Clark, 
    457 F.3d 872
    , 876 (8th Cir. 2006) (e-mail
    correspondence following alleged hand-shake agreement showed continuing
    negotiations); Moses.com Securities, Inc. v. Comp. Software Sys., Inc., 
    263 F.3d 783
    ,
    784 (8th Cir. 2001) (no contract).
    LoRoad further argues that the requisite intent to form a binding Assembly
    Agreement was proved by “conduct by both parties which recognize[d] the existence
    of such a contract.” Mo. Rev. Stat. § 400.2-204(1); see § 400.2-207(3). We agree
    GXV’s conduct was consistent with recognition of a binding contract. But the issue
    is LoRoad’s intent, and the only “conduct” asserted on the part of LoRoad was its
    payment of $120,000 on November 2, before it sent the November 16 marked-up
    contract to GXV. The Assembly Agreement called for payment of a nonrefundable
    deposit of $120,000 “at contract signing.” On February 25, after GXV asserted that
    a final contract was in place, Lough emailed that “the Assembly Agreement is NOT
    yet executed,” describing his November 16 version as a “change document,” and the
    $120,000 as “a good faith deposit . . . to demonstrate our seriousness about moving
    forward on this project.” On this record, we agree with the district court that there
    was simply no conduct by LoRoad that recognized the existence of a binding
    contract. See 
    FutureFuel, 756 F.3d at 647
    (“the parties did not conduct their business
    in recognition of a valid contractual arrangement”).
    -8-
    Finally, LoRoad argues that an enforceable agreement to arbitrate was formed
    because, “[w]hile there are numerous changes between and among the six versions
    [of the Assembly Agreement], not a single word of the arbitration provision changed
    from the first version sent by GXV to LoRoad on October 1, 2012, to the November
    16 version executed by GXV.” This contention is without merit. While the parties
    could have executed a free-standing agreement to arbitrate disputes that arose under
    whatever Assembly Agreement was ultimately signed, there is not a shred of evidence
    of their intent to do so. Thus, there was an enforceable agreement to arbitrate if, and
    only if, LoRoad proved there was a final, enforceable Assembly Agreement. As the
    undisputed evidence showed no such contract was formed, the district court properly
    granted summary judgment in favor of GXV.
    The judgment of the district court is affirmed.
    ______________________________
    -9-