Levine/Schwab Partnership v. FCC ( 2023 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 1, 2022              Decided March 3, 2023
    No. 22-1016
    LEVINE/SCHWAB PARTNERSHIP,
    D/B/A SCHWAB MULTIMEDIA LLC,
    APPELLANT
    v.
    FEDERAL COMMUNICATIONS COMMISSION,
    APPELLEE
    On Appeal from an Order of the
    Federal Communications Commission
    Keenan P. Adamchak argued the cause for appellant. With
    him on the briefs was Davina S. Sashkin.
    Rachel Proctor May, Counsel, Federal Communications
    Commission, argued the cause for appellee. With her on the
    brief was Sarah E. Citrin, Deputy Associate General Counsel.
    Jacob M. Lewis, Associate General Counsel, entered an ap-
    pearance.
    Before: MILLETT, WILKINS, and WALKER, Circuit Judges.
    Opinion for the Court filed by Circuit Judge WALKER.
    2
    WALKER, Circuit Judge: To build a radio station, a broad-
    caster must obtain a construction permit from the Federal Com-
    munications Commission. Those permits have time limits.
    Absent an extension from the FCC, a broadcaster must build
    the station within three years.
    Here, Schwab Multimedia received a construction permit
    from the FCC. But Schwab never built its station. Though the
    FCC granted Schwab’s first three requests for more time, it de-
    nied Schwab’s fourth.
    Schwab appealed the FCC’s decision, claiming that it was
    arbitrary and capricious. Because the agency’s decision was
    reasonable and reasonably explained, we affirm.
    I
    In 2016, Schwab obtained an FCC permit to build a radio
    station in Culver City, California. An FCC rule gave Schwab
    three years to complete construction. 
    47 C.F.R. § 73.3598
    (a).
    But the FCC does not apply that rule inflexibly. When certain
    events “not under the control of the permittee” prevent con-
    struction, the FCC will toll (pause) the three-year clock, giving
    the permittee more time. 
    Id.
     § 73.3598(b).
    Schwab requested, and the FCC’s Media Bureau granted,
    three such tolling requests. But it denied Schwab’s fourth.
    Schwab asked the Bureau to reconsider. It claimed that the
    landlord of its original site had withdrawn permission to build.
    It also submitted an application to modify its construction per-
    mit so it could build at a new site at the Culver City Mall. The
    Media Bureau denied Schwab’s petition for reconsideration.
    3
    Schwab then filed an Application for Review before the full
    FCC. The FCC affirmed the Bureau. It found that site loss was
    the “cause of Schwab’s inability to construct.” JA 288. And
    site loss is not a reason for tolling recognized in FCC regula-
    tions. It also dismissed as moot Schwab’s application to mod-
    ify its construction permit because, without tolling, the permit
    had expired.
    Schwab appealed.
    II
    Before we consider the merits, we briefly explain why we
    reject the FCC’s argument that Schwab lacks standing.
    To have standing, Schwab must show that it was injured by
    the FCC’s order and that “a favorable decision” from this court
    would redress that injury. See Lujan v. Defenders of Wildlife,
    
    504 U.S. 555
    , 560-61 (1992) (cleaned up).
    Schwab meets that test. It suffered an injury caused by the
    FCC: The agency’s refusal to give Schwab more time meant
    that it lost its chance to build a radio station. And an order from
    this court could redress that injury: Reversing the FCC’s deci-
    sion would reinstate Schwab’s construction permit and give it
    more time to build.
    True, Schwab told the FCC that it cannot build at its origi-
    nal site. But when it submitted its tolling request, it also asked
    the FCC to modify its permit to let it build at a new site, the
    Culver City Mall. And it has a lease for that site ready to be
    executed. So if it won on tolling here — giving it six months
    and twenty-two days to build — and the FCC approved
    Schwab’s modification request, Schwab could still complete
    construction of its radio station.
    4
    To be clear, even if Schwab won here, we aren’t certain
    that it could build its radio station. Perhaps the new site
    wouldn’t pan out. But a showing of certainty is not required; a
    “mere likelihood will do.” National Wildlife Federation v. Ho-
    del, 
    839 F.2d 694
    , 705 (D.C. Cir. 1988).
    III
    We now turn to the merits.
    The FCC denied Schwab’s Application for Review because
    site loss is not a legitimate reason for tolling under the FCC’s
    rules. It also refused to grant Schwab a waiver of the FCC’s
    three-year deadline on construction permits.
    Those decisions were not arbitrary and capricious.
    
    5 U.S.C. § 706
    (2)(A). They were “reasonable and reasonably
    explained,” and the FCC’s factual findings are supported by
    substantial evidence. FCC v. Prometheus Radio Project, 
    141 S. Ct. 1150
    , 1158 (2021).
    A
    The FCC based its denial of Schwab’s tolling request on
    three underlying determinations. All three were reasonable.
    First, the FCC reasonably found that Schwab had no con-
    struction site. Indeed, Schwab admitted as much. It told the
    Media Bureau that the landlord of the original site had “re-
    scinded [its] verbal agreement . . . to use the site.” JA 131.
    And it offered no evidence to suggest that it had since secured
    the landlord’s permission. See PSSI Global Services, LLC v.
    FCC, 
    983 F.3d 1
    , 7 (D.C. Cir. 2020) (we “accept the [FCC’s]
    5
    findings of fact so long as they are supported by substantial ev-
    idence on the record as a whole” (cleaned up)).
    True, Schwab claimed that it had found a “new home” at
    the Culver City Mall. JA 131. But when the FCC considered
    Schwab’s tolling request, Schwab had not secured the FCC’s
    permission to build at that new site.
    Second, it was reasonable for the FCC to conclude that site
    loss was the real reason Schwab could not build. Pointing to
    wildfires and COVID-19, Schwab claimed that “act[s] of God”
    prevented construction. 
    47 C.F.R. § 73.3598
    (b)(1). But even
    absent those obstacles, construction was impossible. You can’t
    build a radio station without a place to put it. See BDPCS, Inc.
    v. FCC, 
    351 F.3d 1177
    , 1183 (D.C. Cir. 2003) (“When an
    agency offers multiple grounds for a decision, we will affirm
    the agency so long as any one of the grounds is valid.”).
    Third, the FCC reasonably held that site loss is not a legit-
    imate basis for tolling. See 
    47 C.F.R. § 73.3598
    (b). FCC rules
    say: “The period of construction for an original construction
    permit shall toll when construction is prevented by the follow-
    ing causes not under the control of the permittee.” 
    Id.
     The
    provision goes on to specify five causes. They are: (1) acts of
    God; (2) administrative or judicial review; (3-4) certain unan-
    swered requests to Canada or Mexico for international coordi-
    nation; and (5) failure of a condition imposed by the FCC. Id.;
    see also In re JNE Investments, Inc., 23 FCC Rcd. 623, 631
    (2008) (“tolling is inapplicable outside of the circumstances
    identified in Section 73.3598(b)”).
    Those causes do not include site loss. Rather, the FCC
    views site selection as an “independent business decision
    within a permittee’s control.” In re Royce International Broad-
    casting Co., 23 FCC Rcd. 9010, 9016 (2008). So it has
    6
    declined to add “site-related difficulties” to its list of criteria
    for tolling. Id.; see also In re Birach Broadcasting Corp., 18
    FCC Rcd. 1414, 1415 (2003) (affirming a finding that site loss
    and high land prices, which slowed the process of securing a
    new site, do not qualify for tolling).
    B
    Finally, Schwab claims the FCC erred because it did not
    waive its three-year deadline on construction permits. See 47
    C.F.R. § l.3.
    The FCC may waive its rules “where particular facts would
    make strict compliance [with a rule] inconsistent with the pub-
    lic interest.” Northeast Cellular Telephone Co. v. FCC, 
    897 F.2d 1164
    , 1166 (D.C. Cir. 1990) (cleaned up); see also 
    47 C.F.R. § 1.3
     (FCC may “waive[ ]” its rules for “good cause
    shown”).
    But Schwab never urged the FCC to hold that site loss jus-
    tified a waiver of the three-year construction deadline. That
    failure prevents us from considering waiver now. The FCC
    must be “ ‘afforded [an] opportunity to pass’ on all arguments
    made to a court.” NTCH, Inc. v. FCC, 
    841 F.3d 497
    , 508 (D.C.
    Cir. 2016) (quoting 
    47 U.S.C. § 405
    (a)). So parties must first
    “reasonably flag[ ]” their arguments “for the agency’s consid-
    eration.” 
    Id.
     (cleaned up). Schwab did not. 1
    1
    Because the exhaustion requirement is not jurisdictional, we may
    overlook a failure to exhaust. NTCH, 
    841 F.3d at 508
    . But here,
    “none of the traditional exceptions” apply. Action for Children’s
    Television v. FCC, 
    906 F.2d 752
    , 755 (D.C. Cir. 1990) (cleaned up)
    (listing exceptions).
    7
    And even if the issue was before us, Schwab produced no
    evidence to show that good cause would support a waiver. See
    In re Birach Broadcasting Corp., 18 FCC Rcd. at 1415 (“The
    Commission will not waive its rules absent good cause.”).
    *    *    *
    We affirm the FCC’s order. 2
    So ordered.
    2
    The FCC dismissed as moot Schwab’s application to modify its per-
    mit to let it build at a new site. The FCC reasoned that Schwab’s
    permit had expired and that the agency could not modify an expired
    permit. See In re JNE Investments Inc., 23 FCC Rcd. at 632. That
    may have been a mistake. Schwab filed its modification application
    “four days before the end of the . . . construction period,” while the
    permit was still valid. JA 286. And at oral argument, the FCC said
    it would pause the construction clock while it reviewed Schwab’s
    modification application. If that is true, then the clock could not have
    expired, as the FCC claimed, mooting Schwab’s modification appli-
    cation. But even if the FCC erred, Schwab did not mention that error
    in its appellate briefing. So it forfeited any objection. See United
    States v. All Assets Held at Credit Suisse (Guernsey) Ltd., 
    45 F.4th 426
    , 434 (D.C. Cir. 2022) (arguments not raised in an “opening
    brief” are “forfeited”).