the City of Wolfe City, Texas v. American Safety Casualty Insurance Company ( 2018 )


Menu:
  •                                                                             ACCEPTED
    06-17-00075-CV
    SIXTH COURT OF APPEALS
    TEXARKANA, TEXAS
    1/4/2018 3:36 PM
    DEBBIE AUTREY
    CLERK
    No. 06-17-00075-CV
    ––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
    FILED IN
    In the Sixth Court of Appeals
    6th COURT OF APPEALS
    TEXARKANA, TEXAS
    at Texarkana, Texas   1/5/2018 1:30:00 PM
    DEBBIE AUTREY
    ––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
    Clerk
    The City of Wolfe City, Texas, Appellant,
    v.
    American Safety Casualty Insurance Company, Appellee.
    Amended Reply Brief of Appellant
    the City of Wolfe City, Texas
    __________________________________________________________________
    Daniel W. Ray
    Texas Bar No. 24046685
    SCOTT, RAY & SULLIVAN,
    PLLC
    2608 Stonewall Street
    Post Office Box 1353
    Greenville, Texas 75403-1353
    Tel. (903) 454-0044
    Fax (903) 454-1514
    Daniel@scottraylaw.com
    ATTORNEY FOR APPELLANT,
    THE CITY OF WOLFE CITY,
    TEXAS
    TABLE OF CONTENTS
    Table of Contents ............................................................................ 2
    Index of Authorities ........................................................................ 4
    Arguments ....................................................................................... 5
    1. The City does not have the burden to prove ASCIC’s defense of
    “Design Defect” under the no-evidence MSJ standard. ............. 5
    A. The correct no-evidence MSJ standard. ................................. 5
    B. The City carried its burden under the correct standard. ...... 6
    C. ASCIC attempts to modify the no-evidence MSJ standard. .. 7
    2. ASCIC failed to prove the design-defect defense in its traditional
    MSJ. ............................................................................................. 9
    A. The standard of proof for a design-defect defense. .............. 10
    B. ASCIC’s evidence of a design-defect falls short of the
    standard..................................................................................... 10
    3. The terms of the bond, and the contract it secures, controls
    ASCIC’s liability. ...................................................................... 11
    A. The AMR system was not an acceptable punch list item. .. 11
    B. ASCIC was responsible as a surety for punch list items. .... 12
    C. Change Order No. 2 was not a confirmation of substantial
    completion. ................................................................................ 13
    4. The City could not have objected to the certificate of substantial
    completion within the contractual time-frame because Hayter
    acted fraudulently or in bad faith. ........................................... 14
    5. The Trial Court contemplated that additional evidence would be
    discovered after the hearing on ASCIC’s motions for summary
    judgment. .................................................................................. 16
    Appellant’s Amended Reply Brief                                                                    Page 2
    Conclusion ..................................................................................... 17
    Certificate of Compliance.............................................................. 19
    Certificate of Service ..................................................................... 19
    Appellant’s Amended Reply Brief                                                                 Page 3
    INDEX OF AUTHORITIES
    CASES
    Barraza v. Eureka Co., 
    25 S.W.3d 225
    (Tex. App.—El Paso 2000, pet.
    denied) ......................................................................................... 9
    Bayshore Constructors, Inc. v. S. Montgomery County Mun. Util.
    Dist.
    543 S.W.2d 898
    , 901 02 (Tex. Civ. App.—Beaumont 1976),
    writ ref'd n.r.e. (Mar. 30, 1977) ................................................. 12
    Blackard v. Fairview Farms Land Co., Ltd., 
    346 S.W.3d 861
    (Tex.
    App.—Dallas 2011, no pet.)......................................................... 5
    City of Hous. v. Clear Creek Basin Auth., 
    589 S.W.2d 671
    (Tex.1979)
    ..................................................................................................... 9
    Foreman v. Whitty, 
    392 S.W.3d 265
    (Tex. App.—San Antonio 2012,
    no pet.) ........................................................................................ 9
    Maguire Oil Co. v. City of Hous., 
    69 S.W.3d 350
    (Tex. App.—
    Texarkana 2002, pet. denied) .................................................... 6
    Montgomery v. Kennedy, 
    669 S.W.2d 309
    (Tex. 1984) .................. 9
    RULES
    Tex. R. Civ. P. 166a(i) ..................................................................... 5
    OTHER AUTHORITIES
    4A Bruner & O'Connor Construction Law § 12:46. .................. 8, 10
    Appellant’s Amended Reply Brief                                                                       Page 4
    Arguments
    To be as brief as possible, the City incorporates in this reply all the
    arguments put forth in the City’s Brief. The City further shows this Court
    the following:
    1.   The City does not have the burden to prove ASCIC’s defense of
    “Design-Defect” under the no-evidence MSJ standard.
    In its effort to skirt liability on the performance bond, the recurring
    theme of American Safety Casualty Insurance Company’s (“ASCIC” or
    “Appellee”) brief is to suggest that McKinney & McMillen (“M&M”), the
    general contractor, is not liable because of an alleged “Design-Defect” in
    the fixed-based automatic meter-reading collection system (“AMR
    system”). In doing so, ASCIC improperly shifts to the City the burden to
    prove ASCIC’s defense of a design defect.
    A.    The correct no-evidence MSJ standard.
    The no-evidence MSJ standard states that a “court must grant the
    motion unless the respondent produces summary judgment evidence
    raising a genuine issue of material fact.” Tex. R. Civ. P. 166a(i). Courts
    have interpreted this standard to require the nonmovant to produce only
    more than a ‘scintilla of evidence,” and the evidence must be read “in a
    light most favorable to the nonmovant”—here the City. See Blackard v.
    Appellant’s Amended Reply Brief                                     Page 5
    Fairview Farms Land Co., Ltd., 
    346 S.W.3d 861
    , 868 (Tex. App.—Dallas
    2011, no pet.). “More than a scintilla of evidence exists when the evidence
    would enable reasonable and fair-minded people to reach different
    conclusions.” 
    Id. Further, the
    nonmovant is only required to present
    evidence on the elements on the elements the movant challenges. See
    Maguire Oil Co. v. City of Hous., 
    69 S.W.3d 350
    , 357 (Tex. App.—
    Texarkana 2002, pet. denied). The only element ASCIC challenged in its
    no-evidence motion is whether M&M defaulted. (1CR327) (“an essential
    element of the City’s bond claim is that the City must show that the
    contractor, M&M, failed to fulfill its duty of performance under the
    construction contract”).
    B.    The City carried its burden under the correct standard.
    To survive the no-evidence MSJ, the City needed to provide only
    “more than a scintilla of evidence” that M&M defaulted on the
    Construction contract. The City met this requirement when it provided
    evidence of M&M’s responsibilities under the Contract and M&M’s
    failure to comply with those terms. (1CR668.) M&M failed to comply with
    the terms of the Contract when it did not deliver a fully functional system
    (1) as admitted by George McKinney, a representative of M&M, in his
    Appellant’s Amended Reply Brief                                     Page 6
    deposition (1CR697, 706); (2) as admitted to by M&M when it admitted
    it stopped work before this lawsuit was filed (1CR710-6); and (3) as
    admitted to by M&M in its response to Wolfe City’s Demand for Contract
    Performance when it refused to continue working on the project.
    (1CR724.) This put M&M in default of the construction contract, which
    makes ASCIC liable under the performance bond. Because there is more
    than a scintilla of evidence that M&M was in default, the no-evidence
    MSJ was erroneous. (See Appellant’s Br. at 27-30.)
    C.    ASCIC attempts to modify the no-evidence MSJ standard.
    Because the City provided sufficient evidence to surpass the “more
    than a scintilla” threshold when the evidence is viewed in a “light most
    favorable to the nonmovant,” ASCIC attempts to shift to the City the
    burden to prove that the City’s problems were NOT due to a design-
    defect. Thus, ASCIC attempts to modify the no-evidence MSJ standard.
    ASCIC asserts: “M&M’s responsibility is solely for construction or
    installation defects. If the City’s problems arose from a design defect in
    Zenner’s or Datamatic’s components, then M&M did not default on the
    construction contract.” (Appellee Br. at 16.) Further, “M&M could not
    have defaulted on the construction contract if the City’s problems
    Appellant’s Amended Reply Brief                                    Page 7
    resulted from a design defect rather than a construction or installation
    defect.” (Id. at 22.)
    After shifting the burden of proof for a no-evidence MSJ, ASCIC
    then claims that the City falls short: “[t]hus, for the City to raise a
    genuine fact issue on ASCIC’s ‘no evidence’ motion, it had to offer some
    evidence that the City’s failure to receive a fully functional system
    resulted from M&M’s default, and not from a defect in the Datamatic
    components that Hayter specified for the system.” (Id. at 25) (emphasis
    added.)
    Existence of a design defect is a defense, which is ASCIC’s burden
    to prove. “[A] surety is entitled to the protection of the principal's
    ‘contract defenses.’ One such defense is the owner's control over
    preparation and issuance of detailed design documents with design
    inadequacies.” 4A Bruner & O'Connor Construction Law § 12:46. In
    short, existence of a design defect is a contract defense belonging to
    M&M. ASCIC can urge that defense, but also has the burden of proof on
    the defense.
    Because ASCIC carries the burden of proof for this defense, it
    cannot shift this burden to the City in a no-evidence MSJ. It is not proper
    Appellant’s Amended Reply Brief                                     Page 8
    in a no-evidence MSJ to raise a legal issue on which the movant has the
    burden of proof. A movant cannot file a no-evidence motion for summary
    judgment on a claim or defense on which he has the burden of proof at
    trial. Foreman v. Whitty, 
    392 S.W.3d 265
    , 279 (Tex. App.—San Antonio
    2012, no pet.); See also, e.g., Barraza v. Eureka Co., 
    25 S.W.3d 225
    , 231
    (Tex. App.—El Paso 2000, pet. denied) (party may not urge no-evidence
    summary judgment on claims or defenses on which it has burden of
    proof).
    In sum, the City met the actual no-evidence threshold and was not
    required to meet the threshold of providing evidence to disprove ASCIC’s
    design-defect defense.
    2.   ASCIC failed to prove the design-defect defense in its traditional
    MSJ.
    The burden that ASCIC attempts to require of the City in the no-
    evidence MSJ is a burden ASCIC itself does not meet in its traditional
    MSJ. “Defendants moving for summary judgment must expressly present
    and conclusively prove all essential elements of their defense as a matter
    of law; there can be no genuine issues of material fact.” Montgomery v.
    Kennedy, 
    669 S.W.2d 309
    , 310-11 (Tex. 1984) (citing City of Houston v.
    Clear Creek Basin Auth., 
    589 S.W.2d 671
    , 678 (Tex.1979)).
    Appellant’s Amended Reply Brief                                    Page 9
    A.    The standard of proof for a design-defect defense.
    Bruner & O’Connor’s treatise on Construction Law sets forth the
    standard ASCIC must prove for its design-defect defense:
    “[W]here the owner issues detailed design documents found to be
    defective, fails to disclose critical information to the contractor, or
    maintains control over the contractor's construction methods, the
    contractor's nonperformance will be excused.”
    4A Bruner & O'Connor Construction Law § 12:46 (emphasis added).
    ASCIC cites the same treatise in putting forth its design-defect defense.
    (Appellee Br. at 23.) For ASCIC to claim the design-defect defense, it had
    the burden to prove that detailed design documents provided by the City
    or its agent are defective and, thus, are the cause of the nonfunctioning
    AMR system.
    B.   ASCIC’s evidence of a design-defect falls short of the
    standard.
    ASCIC’s evidence of an alleged design defect amounts to the City
    selecting the type of water meter and requiring it to be supplied by an
    experienced qualified vendor—none of which comprise “detailed design
    documents that have been found to be defective.” ASCIC offered evidence
    that the Engineer specified the type of meters for the project. (1CR328.)
    The contractor could use one of five brands of water meters: Master
    Meter, Itron, Neptune, Badger, or Infinity. (Appellee Br. at 3, citing
    Appellant’s Amended Reply Brief                                   Page 10
    1CR135.) ASCIC further points to evidence that the engineer required
    the AMR system to be “supplied by an experienced, qualified, vendor.”
    (Id.) That is where the evidence stops. ASCIC did not present any
    evidence of “detailed design documents that were found to be defective.”
    Because ASCIC did not conclusively its design-defect defense, it was
    error to grant ASCIC’s traditional MSJ.
    3.     The terms of the bond, and the contract it secures, controls ASCIC’s
    liability.
    ASCIC attempts to convince this Court that freedom of contract
    does not exist and it is entitled to rely on a certificate of substantial
    completion, regardless of how it was obtained and regardless of the terms
    of the contract.
    A. The AMR system was not an acceptable punch list item.
    ASCIC’s erroneously argues that the AMR System was a punch list
    item. However, the Contract explicitly states that the punch list must not
    contain any major deficiencies. CR 411-12, 585. In this case, the entire
    purpose of the AMR System was so that the City could read the meters
    remotely, but this could not occur because the AMR System was not
    functional, as indicated on the punch list. See CR 412-13. Because the
    AMR System could not fulfil its intended purpose and was a major
    Appellant’s Amended Reply Brief                                   Page 11
    component of the overall project, it follows that the indication of the AMR
    System on the punch list as a deficiency was contrary to the explicit terms
    of the Contract and therefore not an actual punch list item pursuant to
    the terms of the Contract. Nevertheless, pursuant to the Contract, ASCIC
    was responsible for deficient items which were not corrected within 30
    days after being noted on the punch list.
    B. ASCIC was responsible as a surety for punch list items.
    A surety can be responsible for punch list items. Indeed, in
    Bayshore Constructors, the contract specified that “[t]he Contractor shall
    remedy any defects in the work and pay for any damage to other work
    resulting therefrom, which shall appear within a period of one (1) year
    from the date of final acceptance of the work unless a longer period is
    specified.” Bayshore Constructors, Inc. v. S. Montgomery County Mun.
    Util. Dist., 
    543 S.W.2d 898
    , 902 (Tex. Civ. App.—Beaumont 1976, writ
    ref'd n.r.e.). The Court interpreted the contract, and the bond, to include
    the one year warranty period. 
    Id. In this
    case, the Contract specified that all punch list items shall be
    remedied within 30 days from the date of the certificate of substantial
    completion. CR 418-19. Even though completion of the punch list items
    Appellant’s Amended Reply Brief                                     Page 12
    did not occur, ASCIC argues that it should not be responsible for punch
    list items because the City is provided a remedy through warranty.
    ASCIC’s argument is in opposition with Bayshore Constructors, which
    held a performance bond open under a one year warranty period.
    Furthermore, in this case, the contract reinstituted liquidated damages
    in the event the punch list items were not remedied within the allotted
    time-frame. CR 418-19. In other words, there was no warranty period if
    the punch list items were not remedied within 30 days, and it follows that
    ASCIC contemplated liability under the terms of the contract beyond the
    issuance of substantial completion when it issued the bond. Therefore,
    because liquidated damages were reinstituted after the issuance of
    substantial completion, ASCIC argument, that punch list items should
    be covered under warranty, fails.
    C. Change Order No. 2 was not a confirmation of substantial
    completion.
    ASCIC also erroneously argues that the City confirmed substantial
    completion through Change Order No. 2. ASCIC’s argument is erroneous
    because the date contained on Change Order No. 2 was an estimated
    completion date. Change orders are a routine practice in the construction
    industry because the scope of any given project typically changes over the
    Appellant’s Amended Reply Brief                                  Page 13
    life of the project. It follows that if a project is to change in scope, the time
    of completion will also change, hence the necessity to input a date of
    substantial completion (time of performance) on the change order. For
    instance, in this case, Change Order No. 1 contained the date of October
    13, 2012. Change Order No. 1 did not confirm that the project was
    completed on October 13, 2012, it merely adjusted the time of
    performance based on the change of scope. See CR 1464-65. If the date
    on Change Order No. 1 was merely a time of performance, then it follows
    that Change Order No. 2, which contained a different date, merely
    adjusted the time of performance from October 13, 2012 to March 21,
    2013 to account for the change of scope in the project. Even if Change
    Order No. 2 constitutes an agreement that confirmed substantial
    completion, the City is excused because it was obtain fraudulently or in
    bad faith.
    4.   The City could not have objected to the certificate of substantial
    completion within the contractual time-frame because Hayter acted
    fraudulently or in bad faith.
    ASCIC argues that the City did not comply with the requirements
    to contest Hayter’s certificate of substantial completion. ASCIC further
    argues that the City offered no summary judgment evidence that Hayter
    Appellant’s Amended Reply Brief                                         Page 14
    acted fraudulently or in bad faith. Simply, the former fails because of the
    latter fails. The evidence was very clear from the engineer’s deposition
    that he acted intentionally in opposition with the terms of the Contract
    and in opposition with his duties as a professional engineer to the
    detriment of the City. CR 415-17, 531, 537-40. ASCIC attempts to
    downplay his actions as mere negligent acts within an engineer’s
    discretion. However, as noted by the City’s expert, Hayter’s actions were
    contrary to that of a licensed professional engineer in Texas. See CR
    1462-64. Even if the testimony of the City’s expert is not admissible as
    newly discovered evidence, ASCIC cannot deny that Hayter’s actions
    were intentional conduct to the detriment of the City, which meets the
    requirements for gross negligence, gross mistake, and/or bad faith.
    It follows that since the evidentiary standard for summary
    judgment indicates that Hayter acted in bad faith to the City’s detriment,
    the City would have never known whether to contest Hayter’s certificate
    of substantial completion within the contractual time frame. Hayter’s
    admission of its actions certainly were not volunteered within 30 days
    after substantial completion. Indeed, only through the deposition of Mike
    Tibbets did the City confirm the scope of the engineer’s betrayal. See CR
    Appellant’s Amended Reply Brief                                   Page 15
    760-61. Further, it is pointless for ASCIC to argue that the City did not
    contest Hayter’s issuance of the certificate of substantial completion. If
    this Court holds the substantial completion valid, there is no need to
    consider this point, and if this Court holds the certificate invalid due to
    fraud, gross mistake, or bad faith, as the City contends, then ASCIC’s
    argument collapses because there would have been no valid certificate for
    the City to contest.
    5.    The Trial Court contemplated that additional evidence would be
    discovered after the hearing on ASCIC’s motions for summary judgment.
    Although the issue of newly discovered evidence has been debated
    at great length between Appellant and Appellee, when considering
    whether the Trial Court abused its discretion in denying the City’s
    Motion for Reconsideration, it is important to note that the Trail Court
    contemplated that there would be newly discovered evidence after
    ASCIC’s hearing on its motions for summary judgment. The morning of
    and prior to the hearing, the Trial Court signed an agreed order, which
    extended the discovery deadline. CR 780-81. The principle reason for this
    order was to extend deadlines due to the addition of Hayter as a named
    defendant only 11 days prior to ASCIC’s hearing.
    Appellant’s Amended Reply Brief                                   Page 16
    Conclusion
    In its no-evidence MSJ, ASCIC improperly attempted to increase
    the no-evidence MSJ threshold (which the City met) by shifting to the
    City the burden to prove ASCIC’s “Design-Defect” defense and then
    claiming that the City falls short of the shifted burden. In its traditional
    MSJ, ASCIC fell short of the standard to conclusively prove its “Design-
    Defect” defense.
    Further, ASCIC should be held accountable to the terms of its bond
    and the contract that it secured. Even though the AMR System was not
    a contractual punch list item, the Contract explicitly required contract
    damages to be reinstated if any deficiency on the punch list was not
    corrected within 30 days. In addition, ASCIC’s argument that Change
    Order No. 2 confirmed substantial completion is erroneous and against
    industry practice because the change in date simply noted a change in
    time of performance. The City did not agree to actual substantial
    completion via Change Order No. 2, and it could not have contested
    Hayter’s certificate of substantial completion because it had no
    knowledge of Hayter’s bad faith and/or fraudulent actions until the
    deposition of its engineer. Because bad faith or fraudulent actions are
    Appellant’s Amended Reply Brief                                    Page 17
    frequently denied until the bitter end, the Trial Court should have
    contemplated that newly discovered evidence would be forthcoming,
    especially since it signed an order extending the discovery period the very
    morning of ASCIC’s hearing on its motions for summary judgment.
    Respectfully Submitted,
    /s/ Daniel W. Ray_____________
    Daniel W. Ray
    Texas Bar No. 24046685
    Daniel@scottraylaw.com
    Scott, Ray & Sullivan, PLLC
    P.O. Box 1353
    2608 Stonewall Street
    Greenville, Texas 75403
    Tel: (903) 454-0044
    Fax: (903) 454-1514
    ATTORNEY FOR APPELLANT THE
    CITY OF WOLFE CITY, TEXAS
    Appellant’s Amended Reply Brief                                   Page 18
    CERTIFICATE OF COMPLIANCE
    This brief was prepared using Microsoft Word in Century font with
    14-point type. This brief contains 2,717 words, not counting the sections
    excluded by Tex. R. App. P. 9.4(i)(1).
    /s/ Daniel W. Ray_____________
    Daniel W. Ray
    CERTIFICATE OF SERVICE
    On January 4, 2018, a copy of this brief was served through
    efileTexas.gov on all counsel, as indicated below:
    James D. Cupples
    Texas Bar No. 05252300
    CUPPLES & ASSOCIATES, PLLC
    700 Gemini Street #200
    Houston, Texas 77058
    Tel. (281) 218-8888
    Fax (281) 218-8788
    Cupplesjd@comcast.net
    Byron C. Keeling
    State Bar No. 11157980
    KEELING & DOWNES, P.C.
    bck@keelingdownes.com
    1500 McGowen, Suite 220
    Houston, Texas 77004
    Tel (832) 214-9900
    Fax (832) 214-9908
    /s/ Daniel W. Ray_____________
    Daniel W. Ray
    Appellant’s Amended Reply Brief                                  Page 19