Nova Express v. Postmaster General , 277 F. App'x 990 ( 2008 )


Menu:
  •                      NOTE: This disposition is nonprecedential.
    United States Court of Appeals for the Federal Circuit
    2008-1033
    NOVA EXPRESS
    Appellant,
    v.
    John E. Potter, POSTMASTER GENERAL,
    Appellee.
    Philip Emiabata, as Nova Express, of Austin, Texas, pro se.
    Joseph A. Pixley, Trial Attorney, Commercial Litigation Branch, Civil Division,
    United States Department of Justice, of Washington, DC, for respondent. With him on
    the brief were Jeffrey S. Bucholtz, Acting Assistant Attorney General, Jeanne E.
    Davidson, Director, and Steven J. Gillingham, Assistant Director.
    Appealed from: United States Postal Service Board of Contract Appeals
    Administrative Judge Norman O. Menegat
    NOTE: This disposition is nonprecedential.
    United States Court of Appeals for the Federal Circuit
    2008-1033
    NOVA EXPRESS
    Appellant,
    v.
    John E. Potter, POSTMASTER GENERAL,
    Appellee.
    Appeal from the United States Postal Service Board of Contract Appeals
    in nos. 5101, 5205 and 5268, Administrative Judge Norman O. Menegat
    ___________________________
    DECIDED: May 8, 2008
    ___________________________
    Before LOURIE, BRYSON, and GAJARSA, Circuit Judges.
    PER CURIAM.
    Appellant Nova Express (“Nova”) appeals a decision by the United States Postal
    Service Board of Contract Appeals (“the Board”), upholding the default termination of
    Nova’s contract with the United States Postal Service (“Postal Service”). Nova Express,
    P.S.B.C.A. Nos. 5101, 5205 and 5268 (P.S.B.C.A. Jun. 11, 2007). For the reasons
    stated, we affirm the Board's decision.
    BACKGROUND
    On October 30, 2001, the Postal Service awarded Nova contract No. HCR 78640
    for transportation of mail between two Postal Service facilities (“the contract”). The
    contract expressly provided that Nova must “establish and maintain continuously in
    effect” a policy or policies for liability insurance with a minimum Combined Single Limit
    (CSL) of $750,000 for any truck used in performance of the contract. The contract
    further required that Nova furnish the contracting officer with proof that it had the
    requisite insurance, including copies of the applicable policy or policies. The contract’s
    termination clause provided that the Postal Service could terminate the contract for
    default upon Nova’s failure to perform any provision of the contract, including “if the
    supplier fails to establish and maintain continuously in effect insurance as required by
    this contract, or fails to provide proof of insurance . . . as required by the contracting
    officer.” Under the contract, the Postal Service’s right to terminate the contract for such
    default could be exercised only if the Postal Service notified Nova of the specific failure
    and provided three days to cure the defect.
    Nova obtained insurance for the truck used in performing the contract from
    Fireman’s Fund County Mutual (“Fireman’s Fund”) in the required amount of $750,000
    CSL for the term from September 3, 2002 through September 3, 2003. It financed the
    insurance through Pronote, Inc. (“Pronote”), an insurance financing company, under an
    arrangement in which Nova made a $3,404 downpayment to Fireman’s Fund, and
    Pronote paid the balance of the over $11,000 annual premium. Under the financing
    agreement, Nova paid monthly installments to Pronote over the term of the policy, and
    Pronote was authorized to direct Fireman’s Fund to cancel the policy if Nova failed to
    2008-1033                                     2
    make the required payments. The Board found that Pronote asked Fireman’s Fund to
    cancel the insurance and Fireman’s Fund did so, effective April 7, 2003. Nova did not
    notify the Postal Service that the insurance contract had been canceled.
    The contracting officer’s staff noticed in September 2003 that Nova’s insurance
    policy had expired according to its original term. The Postal Service attempted to
    contact Nova on multiple occasions regarding updating its insurance information, but
    Nova failed to respond. The Postal Service then contacted Fireman’s Fund directly. The
    Fireman’s Fund insurance agent advised the Postal Service that Nova’s policy had been
    canceled in April 2003.
    By letter dated September 19, 2003, the contracting officer notified Nova that its
    review indicated that Nova’s insurance had expired, and that as a result of this as well
    as unsatisfactory service, Nova was temporarily suspended from performing the
    contract, pending investigation of the allegations. As part of the investigation, the letter
    asked Nova to provide the Postal Service copies of insurance policies, documenting
    proof of insurance without any lapse of coverage after September 2002 to the present.
    By letter dated September 23, 2003, the contracting officer again notified Nova
    that under the contract Nova was required to establish and continuously maintain
    insurance coverage on all vehicles used in performing the contract. The letter advised
    Nova that it must furnish proof of continuous coverage by September 26, 2003 or its
    rights to perform under the contract would be terminated for default.
    In response to the letters, Nova submitted to the contracting officer copies of its
    Fireman’s Fund policy purporting to cover the period September 3, 2002 to September
    2008-1033                                    3
    3, 2003, and copies of various truck rental agreements in which some insurance or
    damage waivers had been purchased for the rented vehicle.
    On September 30, 2003, the contracting officer issued a final decision
    terminating Nova’s contract for default and withholding payment for the pay period
    leading up to the termination. On September 3, 2004, the contracting officer denied
    Nova’s claims for damages relating to the allegedly improper termination. And on
    January 31, 2005, the contracting officer issued a final decision claiming $2,706.20 in
    excess reprocurement costs resulting from the termination.
    Nova appealed all three determinations to the Board.        The Board affirmed,
    concluding that Nova had knowingly breached its contract obligations. The Board found
    that Nova’s liability insurance policy with Fireman’s Fund was cancelled effective April 7,
    2003 and that Nova had not shown that it had liability insurance in the amount required
    by the contract at any time after that date. The Board also rejected Nova’s contention
    that the Postal Service acted in bad faith and found that the evidence provided by the
    Postal Service was sufficient to establish Nova’s liability for $2,706.20 in reprocurement
    costs.
    We have jurisdiction pursuant to 
    28 U.S.C. § 1295
    (a)(10).
    DISCUSSION
    The express terms of the contract allow for termination for default upon three
    days notice for failure to continuously maintain the required insurance. Whether or not
    Nova continuously maintained the required insurance and whether the Postal Service
    provided Nova with the requisite three days notice are questions of fact.             See
    McDonnell Douglas Corp. v. United States, 
    323 F.3d 1006
    , 1014 (Fed. Cir. 2003) (“In
    2008-1033                                    4
    determining whether a default termination was justified, a court must review the
    evidence and circumstances surrounding the termination, and that assessment involves
    a consideration of factual and evidentiary issues.”). This Court cannot set aside the
    Board’s factual determinations unless they are “fraudulent, or arbitrary, or capricious, or
    so grossly erroneous as to necessarily imply bad faith, or if such decision is not
    supported by substantial evidence.” 
    41 U.S.C. § 609
    (b); see also West Coast Gen.
    Corp. v. Dalton, 
    39 F.3d 312
    , 314 (Fed. Cir. 1994).
    We find no basis for overturning the Board’s findings. In a thorough opinion, the
    Board carefully reviewed the testimony and exhibits before it. 1 Substantial evidence
    supports the Board’s determination that Nova’s Fireman’s Fund insurance policy had
    been canceled effective April 7, 2003, and that none of the truck rental agreements
    provided the required level of insurance. As the Board found, the cancellation of the
    Fireman’s Fund policy was documented in a letter from Pronote, and the truck rental
    agreements Nova provided either showed that no liability insurance was purchased or
    that the liability insurance provided was much less than the required $750,000.
    Substantial evidence also supports the Board’s determination that the Postal
    Service provided Nova with adequate notice of its failure to meet the terms of the
    1
    Nova argues that the Board failed to discuss various pieces of evidence in
    its opinion. Nova has not established the relevance of any of the evidence it believes
    was wrongfully neglected, however, and we conclude that there was nothing arbitrary
    and capricious in the Board’s consideration of the evidence. We also find no abuse of
    discretion in the Board’s acceptance into evidence of Postal Service Exhibits which
    Nova argues were first provided to it at trial. See Johnson Mgmt. Group CFC, Inc. v.
    Martinez, 
    308 F.3d 1245
    , 1252 (Fed. Cir. 2002) (“[A] discovery or evidentiary ruling of
    the Board will not be overturned unless ‘an abuse of discretion is clear and is harmful.’”)
    (quoting Curtin v. Office of Pers. Mgmt., 
    846 F.2d 1373
    , 1378 (Fed. Cir. 1988))). The
    Board was entitled to find credible the government’s representation that the Exhibits in
    question had been repeatedly sent to Nova prior to trial.
    2008-1033                                   5
    contract and gave Nova three days to cure this breach prior to terminating the contract.
    Nova’s reliance on the September 19, 2003 letter to show that no notice had been given
    is misplaced. The September 19, 2003 letter did not terminate the contract but merely
    suspended Nova’s performance of the contract pending investigation. As the Board
    found, it was the September 23, 2003 letter which provided Nova with notification that
    the contract would terminate if Nova did not furnish proof of continuous insurance, and
    this letter gave Nova three days to furnish such proof. The contract was only terminated
    on September 30, after this three day period had expired.
    There is also no reversible error in the Board’s determination that the Postal
    Service did not act with bad faith in terminating the contract. See Am-Pro Protective
    Agency, Inc. v. United States, 
    281 F.3d 1234
    , 1241 (Fed. Cir. 2002) (holding that clear
    and convincing evidence is required to overcome the presumption that the government
    acted in good faith). The Board found that Nova’s allegations of bad faith were not
    supported in the record, and it concluded that witnesses for the Postal Service denying
    the allegations were credible. Nova has provided no convincing basis for overturning
    these findings. See Charles G. Williams Constr., Inc. v. White, 
    326 F.3d 1376
    , 1381
    (Fed. Cir. 2003) (“Board credibility determinations . . . are ‘virtually unassailable.’”).
    Accordingly, we affirm the Board’s finding that the Postal Service’s termination of
    the contract was justified.
    We also affirm the Board’s determination that the Postal Service was entitled to
    recover its reprocurement costs. Nova argues here, as it did before the Board, that the
    government should have produced the “bid sheets” reflecting the various emergency
    service offers.    The Board found that despite the absence of the bid sheets the
    2008-1033                                      6
    testimony of the Postal Service’s contract specialist was “credible and sufficient to
    establish that the Postal Service acted properly and made reasonable efforts to
    minimize the reprocurement costs.” We find no basis to disturb the Board’s finding.
    The judgment of the Board is affirmed.
    Costs to Appellee.
    2008-1033                                  7