Leveen v. United States ( 2021 )


Menu:
  •              In the United States Court of Federal Claims
    No. 21-1658
    (Filed: October 29, 2021)
    NOT TO BE PUBLISHED
    )
    LINDSAY LEVEEN,                               )
    )
    Plaintiff,             )
    )
    v.                                     )
    )
    UNITED STATES,                                )
    )
    Defendant.             )
    )
    Lindsay Leveen, pro se, Sausalito, CA.
    John M. McAdams III, Trial Attorney, Commercial Litigation Branch, Civil Division,
    United States Department of Justice, Washington, D.C. for defendant. With him on the brief
    were Brian M. Boynton, Acting Assistant Attorney General, Civil Division, Martin F. Hockey,
    Jr., Acting Director, and Reginald T. Blades, Jr., Assistant Director, Commercial Litigation
    Branch, Civil Division, United States Department of Justice, Washington, D.C.
    OPINION AND ORDER
    LETTOW, Senior Judge.
    Plaintiff, Lindsay Leveen, has brought suit in this court alleging that he is entitled to a
    whistleblower award from the Environmental Protection Agency (“EPA”) for information that he
    provided concerning alleged improper handling of hazardous materials. He claims that his tips
    triggered an EPA investigation into an energy company that resulted in a substantial fine,
    respecting which Mr. Leveen asserts that he is entitled to a whistleblower award. See Compl. ¶
    1, ECF No. 1. The United States as defendant (“the government”) has responded with a motion
    to dismiss (“Def.’s Mot.”) for lack of subject-matter jurisdiction under Rule 12(b)(1) and for
    failure to state a claim under Rule 12(b)(6) of the Rules of the Court of Federal Claims
    (“RCFC”). See ECF No. 13. Mr. Leveen has filed a response to that motion (“Pl.’s Resp.”), see
    ECF No. 8, and supplemental briefs including Pl.’s Supp. Br., ECF No. 17. He has also
    submitted an amended complaint.1 The government has filed a reply brief. See ECF No. 19. A
    hearing was held on October 28, 2021.
    Because this court lacks subject-matter jurisdiction, Mr. Leveen’s claim is DISMISSED.
    BACKGROUND2
    Mr. Leveen’s original complaint was filed on August 3, 2021 and alleges that he “was the
    tipster to the EPA regarding hazardous solid waste (HAZMAT) that Bloom Energy mishandled”
    and that he “provided the EPA hundred[s] of documents and spent hundreds of hours showing
    the [agency] evidence of the mishandling of HAZMAT by Bloom Energy.” Compl. ¶ 1.3
    Plaintiff also asserts that the information purportedly provided to the government resulted in a
    six-year investigation and a fine of $1,360,000. Compl. ¶ 1. Mr. Leveen claims that he is
    entitled to 30% of this fee, totaling $411,000. Compl. ¶ 1. He avers that the government has
    ignored and failed to act on his claim. Am. Compl. ¶ 1.4
    The government’s motion to dismiss Mr. Leveen’s claim argues that “Mr. Leveen has
    failed to demonstrate that his claim falls within the subject-matter jurisdiction of the [c]ourt
    because it does not appear to be based upon an express or implied-in-fact contract with the
    United States, or a money-mandating provision of law, as required to invoke Tucker Act
    jurisdiction.” Def.’s Mot. at 2. It further contends that Mr. Leveen’s failure to indicate a
    substantive source of law entitling him to a whistleblower award would justify dismissal for
    failure to state a claim. Id. at 3.
    Mr. Leveen responded to the government’s motion but did not identify any source of law
    to rebut the government’s assertions. Pl.’s Resp. at 1-2. Instead, plaintiff, a chemical engineer,
    asserted his belief that he is entitled to a whistleblower award based on thermodynamic
    1
    The amended complaint, see ECF No. 31, supersedes the original complaint, but it in
    essence does not materially revise the allegations in the original complaint, except that he
    additionally requests an award of punitive damages from the United States.
    2
    The recitations that follow do not constitute findings of fact by the court. Instead, the
    recited factual elements are taken from the complaint, the motion to dismiss, and plaintiff’s
    responses. No factual disputes are involved.
    3
    Mr. Leveen’s original complaint identifies the EPA only; however, his Response and
    Supplemental Brief identify additional federal government agencies. See, e.g., Pl.’s Resp. at 1
    (“Plaintiff is the tipster to the [d]efendant including [d]efendant’s FTC, DOE, EPA, DOT, FERC
    and SEC on the Bloom Energy hazmat.”); Pl.’s Supp. Br. at 2-3 (including a letter from the
    Federal Trade Commission). Plaintiff’s invocation of additional government agencies in these
    later filings is not fundamental to his claim.
    4
    At the hearing, Mr. Leveen explained that earlier this year, he submitted a request to
    EPA for a whistleblower award after learning that Bloom Energy had been fined late last year.
    2
    principles and common sense. Id. at 1. Mr. Leveen’s supplemental brief urges “the court to
    proceed with this case as fast as possible and without delay.” Pl.’s Supp. Br. at 1.
    STANDARDS FOR DECISION
    The Tucker Act provides this court with jurisdiction over “any claim against the United
    States founded either upon the Constitution, or any Act of Congress or any regulation of an
    executive department, or upon any express or implied contract with the United States, or for
    liquidated or unliquidated damages in cases not sounding in tort.” 
    28 U.S.C. § 1491
    (a)(1). To
    invoke this court’s Tucker Act jurisdiction, “a plaintiff must identify a separate source of
    substantive law that creates the right to money damages.” Fisher v. United States, 
    402 F.3d 1167
    , 1172 (Fed. Cir. 2005) (en banc in relevant part) (citing United States v. Mitchell, 
    463 U.S. 206
    , 216 (1983); United States v. Testan, 
    424 U.S. 392
    , 398 (1976)). If a plaintiff fails to do so,
    this court “should [dismiss] for lack of subject matter jurisdiction.” Jan’s Helicopter Serv., Inc.
    v. Federal Aviation Admin., 
    525 F.3d 1299
    , 1308 (Fed. Cir. 2008) (quoting Greenlee Cty. v.
    United States, 
    487 F.3d 871
    , 876 (Fed. Cir. 2007)).
    Mr. Leveen, as plaintiff, must establish jurisdiction by a preponderance of the evidence.
    Trusted Integration, Inc. v. United States, 
    659 F.3d 1159
    , 1163 (Fed. Cir. 2011) (citing Reynolds
    v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988)).5 “If a court lacks
    jurisdiction to decide the merits of a case, dismissal is required as a matter of law.” Gray v.
    United States, 
    69 Fed. Cl. 95
    , 98 (2005) (citing Ex parte McCardle, 74 U.S. (7 Wall.) 506, 514
    (1868); Thoen v. United States, 
    765 F.2d 1110
    , 1116 (Fed. Cir. 1985)); see also RCFC 12(h)(3)
    (“If the court determines at any time that it lacks subject-matter jurisdiction, the court must
    dismiss the action.”).
    5
    A court may “grant the pro se litigant leeway on procedural matters, such as pleading
    requirements.” McZeal v. Sprint Nextel Corp., 
    501 F.3d 1354
    , 1356 (Fed. Cir. 2007) (citing
    Hughes v. Rowe, 
    449 U.S. 5
    , 15 (1980) (“An unrepresented litigant should not be punished for
    his failure to recognize subtle factual or legal deficiencies in his claims.”)). But this leniency
    cannot extend to lessening jurisdictional requirements. See Kelley v. Secretary, United States
    Dep’t of Labor, 
    812 F.2d 1378
    , 1380 (Fed. Cir. 1987) (“[A] court may not . . . take a liberal view
    of . . . jurisdictional requirement[s] and set a different rule for pro se litigants only.”).
    3
    ANALYSIS
    Mr. Leveen does not recite or rely on any statute or law that would authorize or require in
    these circumstances a whistleblower award for tipping off the EPA to mishandling of hazardous
    materials. Nor does he argue that his tipoff created an express or implied-in-fact contract with
    the agency so as to entitle him to such an award. See, e.g., Meidinger v. United States, 
    146 Fed. Cl. 491
    , 494 (“Mr. Meidinger contends, however, that the basis for this court’s jurisdiction is . . .
    the existence of an implied contract, which implicates this court’s Tucker Act jurisdiction.”).
    These deficiencies are fatal to Mr. Leveen’s claim. See Lewis v. United States, 
    114 Fed. Cl. 682
    ,
    685 (“Although constituting a grant of jurisdiction, the Tucker Act does not create substantive
    legal rights. To state a viable cause of action, claimants must also identify a separate source of
    substantive law creating a right to money damages.” (internal citations omitted)). Mr. Leveen
    has failed to identify such a source of substantive law, nor has the court independently done so.
    The court is therefore obligated to dismiss the present case for lack of subject-matter jurisdiction.
    CONCLUSION
    For the reasons stated, the government’s motion to dismiss is GRANTED. Mr. Leveen’s
    action shall be DISMISSED without prejudice for lack of subject-matter jurisdiction. The clerk
    shall enter judgment accordingly.
    No costs.
    It is so ORDERED.
    s/ Charles F. Lettow
    Charles F. Lettow
    Senior Judge
    4